ITEM DESCRIPCION UND NOVIEMBRE DICIEMBRE PARCIAL


01 TRABAJOS PRELIMINARES 2,410.49
01.01 CASETA DE ALMACEN Y GUARDIANIA m2 S/. 740.10 740.10
01.02 CARTEL DE IDENTIFICACION DE OBRA DE 3.6X2.4M und S/. 470.39 470.39
01.03 MOVILIZACION Y DESMOVILIZACION glb S/. 600.00 S/. 600.00 1,200.00
02 CERCO PERIMETRICO 50,510.52
02.01 OBRAS PRELIMINARES 167.79
02.01.01 TRAZO Y REPLANTEO m2 S/. 167.79 167.79
02.02 MOVIMIENTO DE TIERRAS 1,317.93
02.02.01 EXCAVACION DE ZANJAS HASTA 1.40 M m3 S/. 909.90 909.90
02.02.02 ELIMINACION DE TIERRA EXCEDENTE HASTA 30 M m3 S/. 408.03 408.03
02.03 OBRAS DE CONCRETO SIMPLE 12,771.38
02.03.01 CONCRETO 1:10+30% P.G. PARA CIMIENTOS CORRIDOS m3 S/. 7,640.66 7,640.66
02.03.02 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS m3 S/. 1,920.46 1,920.46
02.03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS m2 S/. 1,696.14 1,696.14
02.03.04 TARRAJEO EN EXTERIORES E INTERIORES MORTERO 1:5 SOBRECIMIENTO m2 S/. 1,514.12 1,514.12
02.04 CARPINTERIA METALICA 35,370.22
02.04.01 MARCO C/MALLA METALICA m2 S/. 26,204.14 26,204.14
02.04.02 POSTE DE FN DE 3" und S/. 504.25 S/. 5,546.75 6,051.00
02.04.03 PINTURA EN CARPINTERIA METALICA (ESMALTE Y ANTIC.) m2 S/. 3,115.08 3,115.08
02.05 PUERTA 883.20
02.05.01 PUERTA METALICA SEGÚN DISEÑO glb S/. 840.00 840.00
02.05.02 PINTURA EN CARPINTERI A METALICA (ESMALTE Y ANTIC.) m2 S/. 43.20 43.20
03 FLETE TERRESTRE 5,589.85
3.01 FLETE TERRESTRE 5,589.85
03.01.01 FLETE TERRESTRE glb S/. 2,375.69 S/. 3,214.16 5,589.85

COSTO DIRECTO: 17,025.38 41,485.48 S/. 58,510.86

GASTOS GENERALES (18.934727%) 3,223.71 7,855.16 S/. 11,078.87

UTILIDAD (10%) 1,702.54 4,148.55 5,851.09

SUB TOTAL 21,951.63 53,489.19 75,440.82

IGV (18%) 3,951.29 9,628.05 S/. 13,579.35

PRESUPUESTO PARCIAL 25,902.93 63,117.24 S/. 89,020.17

PORCENTAJE MENSUAL 29.10% 70.90% 100.00%

PORCENTAJE ACUMULADO 29.10% 100.00%