July 31 Location Description Activity WHO Due Date REMARKS MATERIALS MANPOWER STATUS
Date
190731: On-going siding installation
Walking Beam Siding and Gate
Walking Beam Paolo Aug-3 190808: Done with siding installation NONAT DONE
Installation
Gate installation on going
Concreting and CHB laying for Flood 190731: Drawing to be submitted on AUG 05
Walking Beam Paolo Aug-5 DONE
Proctection 190902:
190731: On-going installation of trusses and
purlins Cement - 10 bags
Extension of Powerhouse
190807: Column concrete pouring 6" CHB - 330 pcs
Powerhouse Roofing, CHB Laying, Column Paolo Aug-11 PAYAGAN DONE
On-going installation of roofing and Additional Cement
Concreting, Pavement Concreting
CHB laying for wall finishing
190902: On-going framing for wall on top
190731: Drawing to be submitted on AUG 05
190902: Unable to start (Payagan doing the After QA Construction: Target
IM1 Zocalo for Flood Protection Paolo Oct 15 NONAT Completion Date Oct 12
construction of Powerhouse)
190915: Priority Zone 1B Stair Foundation
1. Roughing 2. QC 3. Billet Charging
190731: For inspection on AUG 2 Priority billet charging siding
Siding 4. IM1 Oil Tank 5. Kaesser 6.
RM2 Roofing Paolo October 5 190915: Joint inspection done, need to Payagan working on Zone 1B
Electrical Warehouse 7. Skylight stair landing foundation
schedule date of construction
Replacement
Billet Charging Concreting, 190731: Drawing to be submitted on AUG 05
RM2 Pavement Paolo October 15 PAYAGAN
Storeroom 190902: To be concreted on SEPT 6 (storeroom) DONE
RM2 AM1 Foundation Concreting Paolo Sept - 6 190902: To be concreted on SEPT 6 DONE
Finish
July 31 Location Description Activity WHO Due Date REMARKS MATERIALS MANPOWER STATUS
Date
Finish
July 31 Location Description Activity WHO Due Date REMARKS MATERIALS MANPOWER STATUS
Date
Finish
July 31 Location Description Activity WHO Due Date REMARKS MATERIALS MANPOWER STATUS
Date
Finish
July 31 Location Description Activity WHO Due Date REMARKS MATERIALS MANPOWER STATUS
Date
Description Finish
July 31 Location WHO Due Date REMARKS MATERIALS MANPOWER STATUS
Activity Date
Fence up
Zone 1B from
the Park using
Blue Polysack
or Scrap
o Zone 1B Paolo Aug-2 190731: Coordinated with s9 Done
Roofing
sheets.
Lock the 2
cocnrete
room doors
Gas has to be
empty.
Excavation to
intercept the
pipes.
See me with
Lexter so can
dsicuss with
Contractor -
PRESAM & MJL, PRESAM,
MLC. Presam and Carag
Diesel pumps Paolo Gas Pump w/
Zone 1B Jul-25 190722: MJL submitted their
relocation 3 nozzles proposal for
Need final Carag
relocation site MXC evaluation
190730: Has
Presam
submitted the
quotation?
190806:
PRESAM
submitted
their
quotation
Finalized As
Built Drawing
for Balon Bato For
Balon Bato Paolo Jun-28 Done
(Civil Works - presentation
Ok, Electrical-
on progress)
190716:
Follow-up on
when it will
Foundations be
for ATAD constructed. Payagan started
Zone 1B Paolo Jul-25 Sep 30 Payagan
stairs line D 190719: Plan 09/23/2019
columns 0-1 approved by
S2, MXCCC
will ask
second offer
ATAD must
send us the
offer. CSC-
Mechanical
ATAD l RM1 l
Shop Crane
59: Survey of
Beam. Ask
Zone 1b,
Atad to quote
Recommenda
for the
tion of
columns
misalignment,
Zone 1B modification Jul-17
Paolo Cost Proposal
& crane
(July 5)
beams on top
of cooling bed
190722:
by column 6
Catherine will
to column 8,
email to ffup
as an option.
since no
result with
MXC
Gate Tension
Inlcuded in the
Balon Bato rod & Grease Paolo Aug-2 McCrann
punchlist
Fitting
Flood Flight
Balon Bato Paolo Aug-2 CLARO floodlight is delivered
Installation
Grease Tank
installation &
Canteen
drain piping to
canal