"CREACION DEL CERCO PERIMETRICO DE LA LOSA DEPORTIVA EN EL CENTRO POBLADO

DE CHANGA DEL DISTRITO DE POMABAMBA-PROVINCIA DE POMABAMBA-


DEPARTAMENTO DE ANCASH"

CRONOGRAMA FISICO - FINANCIERO


CREACION DEL CERCO PERIMETRICO DE LA LOSA DEPORTIVA EN EL CENTRO
POBLADO DE CHANGA DEL DISTRITO DE POMABAMBA-PROVINCIA DE POMABAMBA- 45 DIAS
PROYECTO
DEPARTAMENTO DE ANCASH" CALENDARIO

ITEM DESCRIPCION UND NOVIEMBRE DICIEMBRE PARCIAL


01 CREACIÓN DE TROCHA

CREACION DEL CERCO PERIMETRICO DE LA LOSA DEPORTIVA EN EL CENTRO POBLADO DE


CHANGA DEL DISTRITO DE POMABAMBA-PROVINCIA DE POMABAMBA-DEPARTAMENTO DE
01.01 Und 17,025.38 41,485.48 S/. 58,510.86
ANCASH"

CD COSTO DIRECTO 17,025.38 41,485.48 58,510.86


GG GASTOS GENERALES 18.93% 3,223.71 7,855.16 S/. 11,078.87
UTI UTILIDAD 10.00% 1,702.54 4,148.55 S/. 5,851.09
ST SUB TOTAL 21,951.63 53,489.19 75,440.82
IGV IGV 18.00% 3,951.29 9,628.05 S/. 13,579.35
CTE COSTO TOTAL DE EJECUCION DEL PROYECTO 25,902.93 63,117.24 89,020.17

PORCENTAJE DE AVANCE (%) 29.10% 70.90%


PORCENTAJE DE AVANCE ACUMULADO (% ) 29.10% 100.00% ok