Documente Academic
Documente Profesional
Documente Cultură
Table of Contents
Contents
101 DEFINITIONS AND TERMS .......................................................................................................... 101-1
101.1 DESCRIPTION............................................................................................................................ 101-1
101.2 TERMS AND DEFINITIONS ........................................................................................................... 101-1
B
Back Fill
Excavated material, which is placed and compacted in trenches and around footings.
Base
A layer of material constructed on top of the sub base, or in the absence thereof, the selected layer. A base
may extend to outside the travelled way.
Batter Board
A board of timber fixed to posts at the top of cuttings or the bottom of embankments, which indicates the
slope at which the cutting or embankment is to be constructed.
Binder
A material such as bitumen, cement or lime, which is added to and mixed into aggregate, granular materials
or soils to bind the mixture together.
Bitumen
A class of black or dark-coloured (solid, semisolid, or viscous) cementitious substances, natural or
manufactured, composed principally of high molecular weight hydrocarbons, of which asphalts, tars, pitches,
and asphaltites are typical.
Bond Stone
A bond stone is an elongated primordial stone incorporated with the longest dimension at right angles to the
face of a masonry structure to provide structural integrity.
Borrow Area/Borrow Pit
An area, within designated boundaries, outside the Permanent Works, approved for the purpose of obtaining
fill or pavement materials. A borrow pit is the excavated pit in a borrow area.
Borrow Material
Borrow material is a general term used to describe material obtained from a borrow pit.
Boulder
A boulder is a fragment of rock, usually rounded by weathering or abrasion, with a minimum dimension of
20 mm or more.
Bridge
A bridge is a structure erected over a depression, river, watercourse, railway line, road or other obstacle for
carrying motor, railway, pedestrian or other traffic or services and having a length, measured between
abutment faces along the centreline of the superstructure, of 6 m or more.
C
California Bearing Ratio (CBR)
The California Bearing Ratio (CBR) of an untreated soil or gravel as determined by means of AACRA Test S-
12 (ref: Division 802 and AACRA Soils and Materials Manual; Section 5.12) is the load in Newtons,
expressed as a percentage of California Standard Values, required to allow a circular piston of 1 935 mm2 to
penetrate the surface of a compacted material at a rate of 1.27 mm per minute to depths of 2.54, 5.08 and
7.62 mm. The California standard values for these depths are 13.344, 20.016 and 25.354 kN respectively.
Capping Layer
A layer of selected fill material placed on the top of the topmost embankment layer or the bottom of
excavation.
Carriageway
That portion of the roadway including the various traffic lanes and auxiliary lanes but excluding shoulders.
Catch water Drain or Bank
A longitudinal drain or bank outside the road prism for diverting water that would otherwise flow into the road
prism.
Cemented Material
Cemented Material is material in an existing pavement, which cannot be broken up with the tines of a type
1400 Caterpillar or similar road grader.
Cemented crushed stone is cemented material constructed with crushed stone.
An existing stabilized pavement layer will not necessarily be classified as cemented material.
Channel
A Channel is a natural or artificial water course.
Characteristic Strength of Concrete
The characteristic strength of concrete is that strength below which only a pre-selected proportion of test
results (i.e. 1%, 2% or 5%) are expected to fall.
Chippings
Chippings are single sized particles of crushed rock, crushed boulders, crushed cobbles or crushed gravel
used for surface dressing.
Coarse Aggregate
Coarse aggregate is material retained on the 4.75 mm sieve.
Cobble
A Cobble is a fragment of rock, usually rounded by weathering or abrasion, with a minimum dimension of 60
mm. and a maximum dimension of 200 mm.
Coefficient of Uniformity
The coefficient of uniformity is the ratio of the sieve size through which 60% by mass of the material passes
to the sieve size through which 10% by mass passes.
Compliance Testing
Compliance Testing is the testing of the completed works to ascertain compliance of the requirements of the
Specification.
Crushed Particle
A Crushed Particle is a particle of coarse aggregate, which has at least three fractured faces when obtained
by crushing rock and boulders, and at least two fractured faces when obtained by crushing gravel.
Crushed Ratio
The Crushed Ratio is the percentage of crushed particles of coarse aggregate to the total number of
particles in coarse aggregate.
Culvert
A Culvert is a drainage structure, which provides an opening under the carriageway or median for the
passage of water.
Curing Compound
A Curing Compound is a liquid which is applied as a surface coating to (newly placed) concrete and hardens
to form a membrane that inhibits the evaporation of moisture from the concrete.
Cut
Cut shall mean all excavated material from the road prism including side drains.
Cutting
Cutting is that portion of the road prism from where material is excavated to sub-grade or road bed level.
D
Detour
A Detour is a diversion of traffic on existing roadways because of obstruction of the existing roadway is
required to facilitate safe construction of the works.
Delineation Barrier
A Delineation Barrier is a barrier used to define hazards and guide traffic through the work site.
Standard Specification for AACRA Road & Bridge Works
Definitions and Terms
Final November 2004
Page 101-3
SECTION 100 GENERAL
DIVISION 101 DEFINITIONS AND TERMS
Delineator
A Delineator is the small retro-reflectors or panels of retro-reflective sheeting that are attached to guideposts,
or in the case of traffic barriers to a mounting plate to provide a coherent pattern of delineation of the edges
of the carriageway as an aid to night driving.
Departure Terminal
A Departure Terminal is a safety barrier system of a type which is used only at the departure end with
respect to the direction of flow of traffic.
Device
Device is a generic term used to refer to a safety barrier, a terminal or a transition. In this context a device is
usually part of a safety barrier system.
Durability
Durability is the term used to indicate the presence (degree of wear) and longevity of the markings
E
Earthworks
Earthworks is the excavation of material from cuttings and/or the construction of embankments.
Embankment
An Embankment is that portion of the road prism composed of approved fill material, which lies above the
original ground and is bounded by the side slopes, described in the Contract, extending downwards and
outwards from the outer shoulder breakpoints and on which the pavement is constructed.
Equipment
Equipment is all machinery, together with the necessary supplies for upkeep and maintenance, and also all
tools and apparatus necessary for the proper construction and acceptable completion of the work.
Excess Overburden
Excess Overburden is the surplus material within a borrow area which is not required or otherwise is
unsuitable for use in construction.
F
False work
False work is the support for concrete formwork.
Fill
Fill is material, which is used for the construction of embankments.
Filler
Filler, is either processed or naturally occurring material passing the 75 µm sieve which is principally used to
improve the combined aggregate grading and thus reduce the air voids content of bituminous mixtures.
Fine Aggregate
Fine aggregate is crushed or naturally occurring material passing the 4.75 mm sieve.
Flexible Guide Post
A Flexible Guide Post is one that deflects when impacted by a vehicle and then returns to the vertical
position, without maintenance intervention.
Footway
A Footway is an area normally adjacent to the carriageway provided for the use by pedestrians.
Formwork
Formwork is temporary boarding or sheeting erected to contain concrete during placing, compacting and
initial hardening.
Furrow Ditch
A Furrow Ditch is a longitudinal drain or bank outside the road prism provided for diverting water that would
otherwise flow onto the road prism.
G
Gabions
Gabions consist of woven steel mesh boxes or mattresses filled with stone.
Grade line
The Grade line is a reference line in the drawings of the longitudinal sections of the road indicating, at
regular intervals, the elevations according to which the road is to be constructed. The grade line may refer to
the level of the completed road, base or any other layer and may indicate the elevations either along the
carriageway centre line or along any designated position on the road cross-section.
Grading Modulus(GM)
The Grading Modulus is the cumulative percentages by mass of material in a representative sample of
aggregate, gravel or soil retained on the 2.00 mm, 0.425 mm and 75 µm sieves, divided by 100.
Gravel
Gravel is a naturally occurring, rounded, granular material with a particle size between 2 mm and 60 mm. (it
does not apply to Gravel Wearing Courses).
Grout Check
A Grout Check is a recess formed at concrete construction joints, which may be filled with grout; to mask,
and ensure a straight line to, the joint.
Guide Post
Guide Posts are used to mark the edge of the road carriageway. They assist the road user by indicating the
alignment of the road ahead, especially at horizontal and vertical curves, and under some circumstances, by
providing a gauge with which to assess available sight distance.
H
Highway
A Highway is the general term denoting a public way for purposes of vehicular travel, including the entire area within the
right -of - way.
I
Inlet and Outlet Drainage Channels
Inlet and Outlet Channels lead into or discharge from culverts, storm-water drains and minor bridges.
Inspector
An Inspector is the authorised representative of the Engineer assigned to make detailed inspections of
materials or contract performance.
K
Kicker
A Kicker is a concrete plinth at least 70 mm high above the concrete floor, forming the start of a concrete
wall or column.
L
Lane
A Lane is part of a travelled way intended for a single stream of traffic in one direction, which has normally
been demarked as such by road markings.
Lateral Distance
Lateral Distance is the distance from the edge of a sign blade to the centre of the edge line of a roadway,
kerb face or other measurement point designated on the sign inventory form.
Leading Terminal
The Leading Edge is the approach end of a safety barrier system with respect to the direction of flow of
traffic.
Levelling Course(s)
A Levelling Course(s) is one or more layers of asphalt or granular material, of varying thickness, which are
applied to improve the regularity of an existing road surface.
Longitudinal Line Marking
Longitudinal Line Marking comprises all lines that are generally parallel to the traffic flow i.e. - Separation,
Barrier, Lane, Merge and Edge lines, as shown in the standard drawings.
Lot
A Lot is a sizable portion of work or quantity of material which is assessed as a unit for the purpose of quality
control and selected to represent material or work produced by essentially the same process and materials.
Luminance Factor
The Luminance Factor is the ratio of light reflected from a surface to that of an ideal white diffusing surface
when illuminated and viewed under the same conditions and viewing geometry. It is expressed as a decimal
point in the range of 0 to 1 where the surface has a matt finish. The values can also be expressed as a
percentage.
M
Manufacturer’s Recommendations
The Manufacturer’s Recommendations are the methods and procedures for the installation of components,
systems or devices.
Masonry
Masonry is stonework constructed with interlocking stones more than one stone thick.
Median
The Median is the area between the two carriageways of a dual carriageway road.
Median Drain
A Median Drain is a longitudinal drain situated in the median of a dual carriageway road.
Milling
Milling is the excavating and removing a layer of material exceeding 10 mm in thickness from an existing
pavement by means of an approved milling machine. Milling is normally used only on asphalt and cemented
layers.
Mitre Drain/Mitre Bank
A Mitre Drain is a drain constructed at an angle to the centreline of the road to divert water from the side
drains. Mitre drains will include mitre banks placed across side drains.
Mortar
Mortar is a mixture of fine aggregate, cement and/or hydrated lime usually in predetermined proportions, with
water, to create a fine grained cementious material suitable for the bedding of bricks and masonry etc.
Multi-Panel Sign
A Multi-Panel Sign is a sign with a blade manufactured from more than one sheet of aluminium but erected
as one section
Multi-Section Sign
A Multi-Sector Sign is a sign with a large blade manufactured from more than one section-allowing field
bolting together. Individual sections may be of single panel or multi-panel construction.
N
Nested Rails
Nestled Rails are two or more steel rails erected together (one inside the other) to increase stiffness. Nested
rails share bolts.
Non Retro-reflective Raised Pavement Markers
Non Retro-reflective Raised Pavement Markers are road markers applied directly to the pavement surface or
installed by means of a suitable adhesive which reflect ambient light during daylight hours and to a limited
degree when illuminated by vehicle headlights or roadway lighting at night.
O
Obstruction
An Obstruction is any works, or otherwise, on or adjacent to an existing carriageway that requires
modification to the existing traffic control arrangements.
Other Markings
“Other Markings” comprise all diagonal and chevron markings, messages on the pavement including words,
numerals, arrows and symbols, kerb markings, markings for parking control and any other markings not
covered under longitudinal line markings and transverse lines.
Optimum Moisture Content for Compaction
The Optimum Moisture Content for Compaction is the moisture content of a soil calculated on the basis of
dry weight of soil at which the soil can be compacted to the approximate maximum density under a specified
standard method of compaction.
Overburden
Overburden is unsuitable material which overlies suitable material within a borrow pit or quarry.
Overhaul
Overhaul distance is that distance in excess of the free-haul distance.
Overlay
An additional pavement layer applied on top of an existing road for strengthening the pavement and/or for
improving the riding quality.
P
Parking Lane
A Parking Lane is an auxiliary lane adjoining the travelled way for the purpose of vehicular parking.
Pavement
Pavement is a multi-layered horizontal structure, which is constructed for the purpose of carrying traffic.
Pavement Layers
Pavement Layers are the layers of different materials, which comprise the pavement structure.
Pavement Markers
Pavement Markers is the term used to include non retro-reflective raised pavement markers and retro-
reflective raised pavement markers.
Pavement Marking
Pavement Marking comprises all longitudinal line marking, transverse lines, other markings and raised
pavement markers used on the road pavement and kerbs for the purposes of guiding traffic.
Pavement Planing
Pavement Planing is the alteration of an existing road surface by the removal of a layer of material by means
of a milling machine or other equipment.
Performance Requirement
Performance Requirements are objective values of reflectivity, skid resistance and durability measured to
ensure that the pavement marking meets the requirements of this specification under day and night as well
as wet and dry conditions.
Physical Barrier
A Physical Barrier is a temporary safety barrier required to provide a strong physical barrier between the
travelled way and the work area.
Pioneer Layer
A Pioneer Layer is the initial layer constructed over a weak roadbed where selected material is used to
provide a stable platform for the construction of subsequent layers.
Pre-stressing
Pre-stressing is the inducement of compressive stress into a structural concrete element either by pre-
tensioning or post-tensioning tendons comprising of cables, wires or bars incorporated into the element.
Prime Coat
Prime Coat is a bituminous treatment applied to the surface of a newly constructed unbound road base prior
to the construction of a bituminous layer or surface treatment.
Project Specifications
The Project Specifications are the specifications relating to a specific project, which form part of the contract
documents for the project, which contain supplementary and/or amending specifications to the standard
specifications.
Q
Quality Control
Quality Control is the procedures, and/or testing, carried out prior to, or during, the construction of the Works
for the purpose of ensuring compliance with the requirements of the Specification.
Quarry
A quarry is an area within designated boundaries, approved for the purpose of obtaining rock.
R
Recycling
Recycling is the processing of salvaged material in a plant for re-use.
Regulatory Traffic Control Device
A Regulatory Traffic Control Device is any sign, signal, marking, or installation indicating an obligation to
comply with a legally enforceable instruction.
Rehabilitation
Rehabilitation is work undertaken to significantly extend service life and improve the condition or riding
comfort of an existing road.
Reinforcement for Asphalt
Reinforcement for Asphalt is the provision of a cloth or grid of synthetic material placed underneath or
between asphalt layers for strengthening the asphalt.
Reproducibility of Equipment
Reproducibility is the ability of a device to produce identical readings at relatively the same point.
Reverse Cut
Reverse Cut is a sign manufacturing process whereby a white retro-reflective background is overlaid with a
coloured, translucent, electronically cutable film (ECF), from which the legend has been cut to expose the
white background
Retexturing
Retexturing is the treatment of an existing road surface to restore the texture to a specified depth of texture
or skid resistance.
Retro-reflective Raised Pavement Marker
Retro-reflective Raised Pavement Markers are markers applied directly to the pavement surface or installed
by means of a suitable adhesive which provide a point source of reflected or internal light when illuminated
by vehicle headlights when viewed at normal night time viewing angles by vehicle drivers. There may be
some delineation during daylight hours due to their contrasting colour, reflection and profile with respect to
the pavement surface.
Retro-reflectivity
Retro-reflectivity is the term is used to indicate the reflectivity provided by solid glass beads and is expressed
in millicandelas per lux per square metre (mcd/lux/m2) as measured by a retro-reflectometer approved by the
Engineer.
Right-of - Way
Right of Way is the land secured and reserved by the Department for the construction and maintenance of
highway.
S
Safety Barrier
A Safety Barrier is a longitudinal structure, excluding terminals, whose prime purpose is to restrain and/or
redirect, in a controlled manner, vehicles which are out of control.
Safety Barrier System
A Safety Barrier System comprises one or more safety barriers with associated terminals and transitions.
Scabbling
Scabbling is the use of a hand-held or self supporting percussion machine to remove the surface of
hardened concrete without damaging the structure.
Scarify
Scarify is the process of loosening and breaking-up soil or existing pavement layers by means of a machine
fitted with tines.
Screed
A Screed is a layer of fine-graded asphalt or slurry placed to fill in cracks in existing seals and to improve the
riding quality of the road.
Seal
A Seal is the application of one or more layers of bituminous binder with or without layers of crushed stone,
sand or slurry in successive layers on the carriageway, shoulders or on any other compacted layer on which
movement of traffic takes place.
Selected Layer
Selected Layer is the lower layer or layers of the pavement, which is constructed, direct onto the fill, or in
some cases the roadbed. It may include roadbed material compacted in- situ.
Services
Services comprise cables, pipes or other structures to provide, inter alia, conduits for electricity, telephone
and telegraph connections, water, sewage, etc.
Semi-Flexible Guide Post
A Semi-Flexible Guidepost is a guidepost which fails by bending when impacted by a vehicle, but can be
straightened with maintenance intervention.
Shoulder
(a) When referring to Shoulder as a surface, it is the area between the outside edge of the travelled way and
the shoulder breakpoint.
(b) When referring to Shoulder as a pavement layer, it is the upper pavement layer lying between the
outside edge of the base and the shoulder breakpoint.
Shoulder Breakpoint
Shoulder Breakpoint is the point on a cross section at which the extended flat planes of the surface of the
shoulder and the outside slope of the fill and pavement intersect.
Side Drain
A Side Drain is a longitudinal drain offset from, and parallel to, the carriageway.
Side Fill
Side Fill is either surplus or additional fill which is used to extend and flatten the slope of an embankment
and which is often compacted to a lower standard than the embankment.
Side Track
A Side Track is a length of temporary pavement constructed for the detour of traffic to allow safe construction
of the works.
Sidewalk
The Sidewalk is the portion of the roadway primarily constructed for the use of pedestrians.
Sign Blank
A Sign Blank is an aluminium plate or extruded section substrate forming support for sign face materials.
Sign Blade
A Sign Blade is a sign blank complete with background and legend.
Slip Base
A Slip Base is a signpost base which incorporates special mating flanges bolted or otherwise fixed together
to provide tension and compression capacity but which allows controlled shear failure to occur in the event of
vehicular impact.
Skew or Skew Angle
The Skew or Skew Angle is the acute angle formed by the intersection of a line normal to the centreline of
the roadway with a line parallel to the centreline of bents, piers or abutments of a bridge, or in the case of a
culvert, with the centreline of the culvert barrels.
Skid Resistance
Skid Resistance is an estimation of adherence quality on a wet pavement surface as measured by friction
between the surface and the friction equipment. The abbreviation SRN (Skid Resistance Number) is used to
describe the value.
Slope
Unless otherwise stated, Slope is given in terms of the ratio of the vertical difference in elevation between
any two points and the horizontal distance between them. The ratio may also be expressed as a percentage.
Spalls
Spalls comprise chipped or splintered fragments of stone.
Specifications
Specifications is the general term comprising all the directions, provisions and requirements contained
herein, entitled “Standard Specifications for AACRA Urban Infrastructure Works” together with such other
documents as may be added or adopted as supplemental specifications or as special provisions,, and all
further documents of any description, including notes on plans, pertaining to the method and manner of
performing the work or to the quantities and qualities of materials to be furnished under the contract.
Spoil (Material)
Spoil is surplus material originating from construction operations.
Stabilisation
Stabilisation is the treatment of pavement materials by the addition of lime or Portland cement.
Stone Pitching
Stone Pitching is a single course of stones placed on edge with spalls rammed into the spaces between the
stones.
Stripe
Stripe is that part of longitudinal line marking comprising pavement marking material.
Structures
Structures comprise bridges, culverts, catch basins, drop inlets, manholes, retaining walls, cribbing, end
walls, buildings, sewers, service pipes, under drains, foundation drains, and other miscellaneous items,
which may be encountered in the work, and which are not classified herein.
Sub-base
Sub-base is the pavement layer of material of specified dimensions on top of the sub-grade and below the
road base.
Sub-contractor
A Sub-contractor is any individual, firm or corporation to whom the Contractor sublets any part of the
contract.
Sub-grade
Sub-grade is the surface upon which the pavement structure and shoulders are constructed.
Sub-structure
The Sub-structure is all of that part of the structure below the bridge seats or bellow the spring lines of
concrete arches. Back walls and wing walls of abutments shall be considered as parts of the substructure.
Sub-surface Drain (Sub-soil Drains)
A Sub-surface Drain is a covered drain constructed to intercept and remove sub-soil water. It includes all
pipes and filter material in the drain.
Surface Dressing
Surface Dressing is the sealing or resealing of the surface of the carriageway or shoulders by means of one
or more successive applications of bituminous binder and chippings.
T
Tack Coat
Tack Coat is a bituminous treatment applied to the surface of an existing bituminous layer prior to the
construction of a new bituminous layer.
Tendon
A Tendon is a cable, wire or steel bar used to apply a pre-stress to structural concrete elements (see pre-
stressing).
Terminal
A Terminal is a device to protect vehicle occupants from injury in an impact with the end of a safety barrier
and includes the end section of a safety barrier system. Terminals may be leading terminals or departure
terminals.
Texture Treatment
Texture Treatment is the treatment of an existing road surface to obtain a uniform texture.
Triple Beam:
Triple Beam is the triple corrugated beam component of a non rigid road safety barrier system.
Topsoil
Topsoil is a surface layer of soil, which contains organic matter and is capable of supporting the growth of
vegetation.
Traffic
Traffic includes vehicles, pedestrians and animals travelling along a route.
Traffic Lane
A Traffic Lane is the part of a carriageway intended for a single stream of traffic in one direction. It is
normally marked as such by road markings.
Transition:
Transition is a connecting device to provide effective continuity of the protection offered by a safety barrier
between safety barriers of different properties or dimensions. The part of a safety barrier system with
varying properties such as stiffness and dimensions, between and linking safety barriers with different
properties or dimensions. A transition may be also link or connect a safety barrier to a fixture.
Standard Specification for AACRA Road & Bridge Works
Definitions and Terms
Final November 2004
Page 101-13
SECTION 100 GENERAL
DIVISION 101 DEFINITIONS AND TERMS
Transverse Lines
Transverse Lines comprise all lines that are marked at angles, including right angles, to the general traffic
flow i.e. - Cross Walk, Stop, Hold and Transverse plus continuity lines as shown in the standard drawings.
Travelled Way
Travelled Way is that portion of the carriageway which includes the various traffic lanes and auxiliary lanes
but exclude the shoulders.
U
Unbound Material
Unbound Material is naturally occurring or processed material which is not bound together by the addition of
a binder such as cement, lime or bitumen.
V
Verge
The Verge is the area between the outer edge of the road prism and the boundary of the road reserve.
W
Wheel Track
The Wheel Track is the path followed by the wheel of a vehicle during normal riding movements. The wheel
tracks cover approximately the outer metre width on both sides of a traffic lane.
Work Area
The Work Area is the specific area where work is being done.
Working Drawings
Working Drawings comprise stress sheets, shop drawings, erection plans, false work plans, cofferdam plans,
bending diagrams for reinforcing steel, or any other supplementary plans or similar data which the Contractor
is required to submit to the Engineer for approval.
Work in restricted areas
No additional or extra over payment will be made for work in restricted areas, unless the items of work to
which it will apply and the pay items under which payment will be effected, are explicitly specified in these
standard specifications or in the project specifications and listed in the schedule of quantities.
Work Site
The Work Site is an area that includes the work area(s) and any additional length of road required for
advance signing, tapers, sidetracks or other areas needed for associated purposes.
102.2 Services
(a) This Contract may include certain work relating to the moving and reinstating of existing services
that may be affected by the construction of the works.
(b) The Employer will, in the contract documents, provide information regarding the location of existing
utility services, but the Employer does not accept responsibility for the accuracy of this information.
(c) The Contractor shall check and determine on the site the positions of any services shown on the
drawings.
(d) This shall be done by visual inspections, using detecting apparatus, and by making excavations to
expose the position of the services at critical points. This shall also be done where no services are
shown on the drawings but where such services are nevertheless believed to be present.
(e) The positions of all services so detected shall be marked carefully and then drawn in on the
drawings. These services will then be defined as known services. The Contractor shall take all
reasonable precautions not to damage the services during the search, where the onus shall rest
with him to prove that, in the event of damage being done to such services during the search, it
was not his fault that they had been damaged.
(f) The Contractor will be held responsible for any damage caused by him to known services, unless
he can prove that he has taken all the above precautions and that the damage has nevertheless
been caused because the position of the known service had deviated by more than one metre from
the position as may reasonably have been deduced from the investigation made by him.
(g) The Contractor shall take all reasonable precautions to protect existing services during construction
and during the relocation of such services. Where protective measures involve the construction of
permanent work, the Contractor shall execute the work in accordance with the Engineer's
instructions, and payment shall be made as provided in the project specifications.
(h) All pipes, cables, conduits or other known services of any nature whatsoever damaged as a result
of the Contractor's operations shall be repaired and reinstated forthwith by the Contractor or by the
authority concerned, all at the expense of the Contractor and to the satisfaction of the Engineer.
(i) It shall be clearly understood that, in certain instances, existing services can be relocated only after
the Contractor has advanced sufficiently on or has completed certain sections of earthworks or
certain structures.
(j) Whenever services are encountered which interfere with the execution of the works and which
require to be moved and relocated, the Contractor shall advise the Engineer, who will determine
the extent of the work, if any, to be undertaken by the Contractor in moving, relocating and
reinstating or protecting such services.
(k) Any work required to be undertaken by the Contractor in protecting, moving and relocating the
services for which no provision has been made in the contract documents, or for which there are no
appropriate tender rates, will be classed as a variation, as provided in the General Conditions of
Contract.
(l) The Contractor shall work in close co-operation with private owners or public authorities controlling
services, which have to be protected, moved or relocated. Details regarding the state of
negotiations concluded between the Employer and the owner at the time of tendering in respect of
the time when either the owner is prepared to start moving such services or when the Contractor is
required to or will be allowed to start moving the services, and the duration of such operations, will
either be stated in the tender documents or be made available to tenderers. Should the owners of
services refuse to co-operate with the Contractor in a reasonable manner in connection with the
protection or moving of services belonging to them, the Contractor shall refer the matter to the
Engineer.
(m) When the Contractor details his programme of work, he shall, in consultation with the Engineer,
clearly indicate as to when he proposes to start with and conclude the moving of each service or
when he will require the owner to start with and conclude the moving of each service. Should it
thereafter, through delays on the part of the Employer or the owner of the service to be moved, be
impossible to adhere to the programme of work, such programme shall be suitably amended by the
Contractor in consultation with the Engineer so as to limit, in so far as is possible, the extent of any
damages or delays. Should it be impossible to limit entirely the damages or delays resulting from
the amendments necessary to the programme of work, the Contractor shall be reimbursed for any
additional costs incurred or damages suffered by him.
(b) The Contractor shall check the condition of all reference and level beacons and shall satisfy himself
that they have not been displaced and are true in regard to position and level. If beacons have
been destroyed, displaced or damaged before the site is handed over to the Contractor, the
Engineer will arrange to have new beacons installed. A beacon which has been displaced shall not
be used unless its true position and level have been re-established and the new values verified by
the Engineer.
(c) Where a beacon is likely to be displaced during construction operations, the Contractor shall
establish suitable reference beacons at locations where they will not be displaced during
construction. No beacon shall be covered over, displaced or destroyed before accurate reference
beacons have been established and details of the position and levels of such beacons have been
submitted to and approved by the Engineer. The Contractor's reference beacons shall be of at
least the same quality and durability as the existing beacons.
(d) The Contractor shall submit to the Engineer the method of setting-out he proposes to employ. To
ensure beyond all doubt that the complex elements of the road, such as traffic interchanges,
structures and other important features are located truly and correctly, the Contractor shall check
all setting-out by a second method. The Engineer may at any time request the Contractor to submit
proof that his setting-out has been satisfactorily checked.
(e) In cases where the displacement of or damage to property beacons or trigonometrical-survey
beacons is unavoidable, the Contractor shall notify the Engineer in good time so that he may
arrange to have such beacons suitably referenced and later on reinstated. The cost of such work, if
paid for by the Contractor, shall be reimbursable as extra work, as provided in the Conditions of
Contract.
(f) For the purposes of this clause, any beacon made from a metal peg cast in concrete and any
boundary beacon, whether or not cast in concrete, shall be regarded as a beacon. Centre-line pegs
shall not be classified as beacons.
(g) To protect beacons, the boundary fences of the road reserve shall be splayed at corners so as to
avoid the use of corner posts in the same position as property or trigonometrical-survey beacons,
all as shown on the drawings.
(h) Accurate control of line and level shall be provided by the Contractor at all stages of construction.
In respect of the road itself, control shall be at 20 m intervals or such closer intervals as may be
directed for horizontal and vertical curves. Wherever necessary, but particularly on completion of
the fill and the base, the Contractor shall re- establish stake-line pegs at sufficiently close intervals
to determine accurately the position of the edges of the base, surfacing and especially kerbing,
guardrails and other permanently visible road elements.
(i) The setting-out of work will not be measured and paid for directly, and compensation for the work
involved in setting- out will be deemed to be covered by the rates tendered and paid for the various
items of work included in this contract.
(f) The Engineer shall have the right to have any sign, notice or advertisement moved to a better
position or to have it removed from the site of the works if it should in any way prove unsatisfactory,
inconvenient or dangerous to the general public.
(g) All advertisements, notices and temporary signs shall be removed by the Contractor upon
completion of the works.
102.8 Measurements
102.8.1 Units of Measurements
All work shall be measured in accordance with the SI System of metric units.
102.9 Payment
102.9.1 Contract Rates
(a) In computing the final contract amount, payment shall be based on the actual quantity of authorized
work done in accordance with the specifications and drawings. The tendered rates shall apply,
subject to the provisions of the General Conditions of Contract, irrespective of whether the actual
quantities are more or less than the scheduled quantities.
(b) Where no rate or price has been entered against a pay item in the schedule of quantities by a
tenderer, it shall be understood that he does not require any compensation for such work. Where,
however, a pay item described in these specifications or in the project specifications does not
appear in the schedule of quantities, the Contractor will receive reasonable compensation for such
work if required, unless anything to the contrary has been determined elsewhere.
work as specified, for procuring, furnishing, placing and installing all materials, for procuring and
providing labour, supervision, constructional plant, tools and equipment, for wastage, transport,
loading and off-loading, handling, maintenance, temporary work, testing, quality control including
process control, overheads, profit, risk and other obligations and for all other incidentals necessary
for the completion of the work and maintenance during the period of maintenance.
(b) The Contractor shall note that the cost of all works and materials for minor construction details at
bridges, for example small quantities of caulking compound and joint filler (other than expansion
joints), anchor-bar covers, etc, not shown in the schedule of quantities, shall be included in the
tendered rates for concrete.
(c) This clause shall apply in full to all pay items except where these requirements may be specifically
amended in each case.
not been purchased but has been produced on the site, at 80% of a fair evaluation of the
value of such material.
(ii) The Engineer may, at his sole discretion, allow payment under "materials on the site" in
respect of articles such as precast beams manufactured and stored off site, subject to
their having been completed, to proof of their ownership as being that of the Contractor,
and to the articles being clearly marked with the Contractor's name, the contract number
and other particulars in accordance with the Engineer's instructions,
(e) Rate-only items
(i) Against an item in the schedule of quantities where no quantity is given but a rate only is
required, the Contractor shall fill in a rate or amount which will constitute payment for
work which may be done in terms of this item, Such rate-only item is used where it is
estimated that little or no work will be required under the item, or where the item is to be
considered as an alternative for another item where a quantity is given, or for variations in
rates of application or mix proportions in terms of Clause 102.13 of this section.
(ii) Work under rate-only items will be paid for only if it has been executed in terms of a
written instruction by the Engineer,
102.12.1 Tenders
(a) An alternative offer or design will be considered only if the tender for the original items has been
fully priced and completed.
(b) Unless the alternative offer stipulates to the contrary, it shall be assumed that the period for
completion of the works shall be the same as for the original design.
(c) An alternative offer or design shall be submitted together with the tender for the original items or
design, otherwise it will not be considered when tenders are adjudicated.
(d) Calculations, drawings and a modified schedule of quantities in respect of each alternative offer or
design shall accompany the alternative tender offer.
102.12.5 Quantities
Each alternative offer shall be accompanied by a modified priced schedule of quantities compiled in
accordance with the Standard Specifications, in so far as it is applicable, which clearly shows the manner in
which the price for the original schedule of quantities which fall away or are being changed. In addition to the
schedule of quantities, a set of calculations shall be supplied to show how the quantities have been
determined. All assumptions in regard to foundation conditions or other factors which will determine
quantities shall be clearly and conspicuously marked by underlining or colouring, and shall indicate whether
or not the assumptions have been based on information furnished in the contract documents (with the
necessary references).
102.12.9 Final Drawings and Calculations and the Priced Schedule of Quantities
(a) Where a tender with an alternative design has been accepted, the Contractor shall, not less than
three months before he intends starting with the construction of such design, submit to the
Engineer a complete set of working drawings, detailed calculations and a complete schedule of
quantities, for approval.
(b) The schedule of quantities shall be based on the preliminary schedule of quantities, but with the
necessary adjustments in quantities and prices and with the tendered price for the alternative
design being retained.
(c) Within six weeks of having received the above, the Engineer will indicate which drawings,
calculations, quantities, prices and other particulars are acceptable to him and which not, with
reasons furnished.
(d) The Contractor shall then submit to the Engineer in good time any modified drawings and other
particulars for approval, for which he will require two weeks. Any delay arising from the fact that the
amended particulars do not meet the requirements shall be the responsibility of the Contractor.
(e) No work which will be affected by an alternative design may be commenced, unless the drawings,
schedule of quantities and prices for such alternative design have been approved.
(f) Should the Contractor fail to modify any drawings, calculations, quantities, prices or any other
particulars to the satisfaction of the Engineer, the alternative design will be rejected and the original
design shall be constructed for the same amount as has been tendered for the alternative design.
(a) foundation conditions which differ from foundation conditions shown in the contract documents, or
in regard to assumptions regarding foundation conditions stated in his tender by the Contractor and
accepted by the Engineer; and/or
(b) changes not arising from any failure or fault of the Contractor, but from modifications requested by
the Engineer.
to reject work which has not been constructed in accordance with the specifications or the rates of
application or mix proportions prescribed by him.
(h) The Employer shall be refunded for any decrease in the specified rates of application or mix
proportions at the same rate per unit of measurement as that tendered by the Contractor for
additional materials required by an increase in the rates of application or mix proportions.
(e) Should the Contractor wish to use land outside the area provided by the Employer for storing or
keeping material or equipment required for the construction of the permanent works, it will be
subject to the following:
(a) That the Engineer approves any area selected for this purpose.
(b) That such land be physically separated from any production plant or activities and suitably
fenced in.
(c) That the area used for the aforesaid purpose be surveyed, and, where the land does not
belong to the Contractor, he shall enter into a contract of lease with the owner of such land
in respect of the full period for which such land shall be used for such purpose, which
contract shall stipulate that the owner shall not have any right whatsoever to any material
stockpiled on such land during the currency of the contract of lease.
(d) That suitable, permanent reference beacons, approved by the Engineer, be placed next to
the area, at the cost of the Contractor, for use by the Engineer with a view to, if applicable,
taking cross-sections for determining quantities.
102.15.1 Earthworks
(a) Where a cut slope has been over-excavated or undercut, backfilling will not normally be allowed
and the entire slope may have to be re-trimmed to obtain a uniform slope.
(b) Where the floor of a cutting has been taken too deep, it will normally require backfilling and re-
compaction with selected gravel in the case of soil or gravel excavation, and with crushed stone or
suitably sized rock in the case of hard excavations. All necessary measures shall be taken to drain
away groundwater that may accumulate in backfilled sections.
(c) Excess width of fills will have to be trimmed down.
(d) Where erosion has damaged the surface of cuts or fills, the damage shall be made good by
backfilling with suitable material and re-trimming. In more serious cases, the slopes may have to be
cut back by benching, backfilled and compacted to the required standard of compaction with
suitable light equipment, and then re-trimmed.
102.15.2 Stabilising
Any sections failing to meet the requirements specified or damaged to the extent that they require breaking-
up and re-compaction will have to be re-stabilised with the type and quantity of stabilising agent ordered by
the Engineer. The Engineer may also order that the layer be removed entirely and replaced with fresh
material to be stabilised.
102.15.4 Concrete
Concrete work will normally require the cutting-back and complete removal of any weak or honeycombed
sections and making good by using special epoxy adhesives to bind fresh concrete to old concrete. Cracks,
when permitted to remain, shall be injected with suitable epoxy compounds, and test cores shall then be
drilled for testing the efficacy of the injection process.
102.16 Water
(a) The Contractor himself shall make arrangements for procuring, transporting, storing, distributing
and applying the water needed for construction and other purposes, except where otherwise
specified. No direct payment will be made for providing water, the cost of which shall be included in
the rates tendered for the various items of work for which water is needed.
(b) Only clean water, free from undesirable concentrations of deleterious salts and other materials,
shall be used. All water sources used shall be subject to the Engineer's approval.
(a) Shall measure the sediment content of bodies of water adjacent to the work area that will receive
drainage from the work area before developing a material source.
(b) Shall control all erosion so the sediment levels in the bodies of water within the drainage area of
the work area do not increase.
(c) Shall strip and stockpile the overburden. After operations are complete, shall move all waste back
into the source. Shall neatly trim and flatten the side slopes to the extent practicable.
(d) Shall spread the stockpiled overburden uniformly over the sides and bottom of the mined area.
(e) Shall establish a vegetative cover to blend the site into the surrounding area.
102.23.3 Certification
(a) For material manufactured off-site, a manufacturer with an ISO 9000 certification or an effective
testing and inspection system shall be used. Require the manufacturer to clearly mark the material
or packaging with a unique product identification or specification standard to which it is produced.
(b) Material accepted by certification may be sampled and tested at any time. If found not in
conformance with the contract, the material will be rejected whether in place or not.
(iii) not excavate, remove, damage, alter, or deface any archaeological or paleontological
remains or specimens. Control the actions of employees and subcontractors on the
project to ensure that protected sites are not disturbed or damaged. Should any of these
items be encountered, suspend operations at the discovery site, notify the Engineer, and
continue operations in other areas. The Engineer shall inform the Contractor when
operations may resume at the discovery site.
(iv) When utilities are to be relocated or adjusted, the AACRA will notify the owners of utilities
affected by the relocations or adjustments. The relocations or adjustments will be required
to be performed by others within the time frames specified or otherwise as soon as
practicable.
(v) Before beginning work in an area, the Contractor shall arrange with all owners of utilities
to:
- Locate their utilities;
- Protect their utilities from construction operations.
The Contractor shall cooperate with owners of utilities to expedite the relocation or adjustment of
the utilities so as to minimize interruption of service and duplication of work.
(vi) If utility services are interrupted as a result of damage by the construction, the Contractor
shall immediately notify the owner and other proper authorities and shall cooperate assist
them until service is restored.
(vii) Not work around the location of fire hydrants until provisions for continued service are
made and approved by the local fire authority.
(viii) If utility adjustment work, not included in the contract, is required, compensation for the
work will be provided under applicable Clauses of the contract.
(ix) Satisfactorily repair damage, due to the fault or negligence of the Contractor, at no cost to
the Employer.
(x) Repair of damage to underground utilities that were not shown on the plans or identified
before construction and not caused by the fault or negligence of the Contractor will be
paid for by the Employer.
(c) Railroad Protection.
(i) The AACRA will obtain the necessary permits and agreements from the Rail Authorities
for specified contract work for relocating railroads or for work at railroad crossings and
make arrangements for all other work that, due to the method of operation, may also
impact the railroad.
(ii) The Contract shall furnish copies of all permits and agreements.
(iii) The Contractor shall conduct the work covered by the railroad permit or agreement in a
manner satisfactory to the Rail Authorities
(iv) The Contractor shall not interfere with railroad operations.
(v) If the construction damages Rail Authorities’ property, the Contractor shall reimburse the
Rail Authorities for all damages or, at the railroad's option, repair the damage at no cost to
the AACRA.
(vi) The Contractor shall not cross railroad tracks, with vehicles or equipment, except at
existing and open public grade crossings or railroad approved temporary grade crossings.
(vii) If there is a need for a temporary grade crossing, the Contractor shall make the
necessary arrangements with the Rail Authorities for its construction, protection, and
eventual removal.
(viii) The Contractor shall reimburse the Rail Authorities for all temporary grade crossing work
or, at the Rail Authorities option, perform the work.
(d) Responsibility for Damage Claims
(i) The Contractor shall indemnify and hold harmless the AACRA, its employees, and its
consultants from suits, actions, or claims brought for injuries or damage received or
sustained by any person, persons, or property resulting from the construction operations
or arising out of the negligent performance of the contract.
(ii) The Contractor shall procure and maintain until final acceptance of the contract, liability
insurance of the types and limits specified in the Contract. The Contractor shall obtain
insurance from companies authorised to carry out such business. The insurance shall
cover all operations under the contract whether performed by the Contractor or by their
Sub-Contractors.
(iii) The Contractor shall furnish "certificates of insurance" certifying that the policies will not
be changed or cancelled until 30 days written notice has been given to the AACRA,
before work begins. Insurance coverage in the minimum amounts set forth in the Contract
shall not relieve the Contractor of liability in excess of the coverage.
(e) Legal Relationship of the Parties
(i) In the performance of the contract, the Contractor is independent and neither the
Contractor nor anyone used or employed by the Contractor shall act in the capacity of
agent, employee, servant, or representative of the Employer.
(ii) The Contractor's independent status does not limit the Employer's general rights under
the contract including inspection of work, specification of safety measures and equipment,
and ability to stop work.
(a) Setting up and maintaining his organization, personnel, camps, accommodation, ablution and other
facilities, offices, stores, workshops, other temporary structures, fencing testing facilities and
constructional plant on the site and their removal on completion of the contract.
(b) Complying with the requirements of the General Conditions of Contract and the specifications,
including the effecting of insurances and providing the sureties required.
(c) All general site and office overheads, profit, financing costs, risks, legal and contractual responsibilities
and other costs and obligations of a preliminary or general nature which are not specifically
measured for payment under any other items of payment.
The lump sum tendered under pay item 103P1(a) above shall represent full compensation for the fixed part
of the Contractor's general obligations, i.e. that part which is substantially fixed and is not a function of the
time required for the completion of the contract or of the value of the work.
Should the final value of the work (excluding any payments in terms of clause 11 of the General Conditions
of Contract for Construction,) increase or decrease by twenty (20) per cent or less in relation to the tendered
amount (less any allowances, if any, in the tender for price adjustments in terms of Clause 11 of the General
Conditions of Contract for Construction), the lump sum tendered for pay item 103P1(a) shall not be subject to
any variation whatsoever.
Payment of the lump sum tendered under pay item 103P1(a) will be made in three instalments, as follows:
(a) The first instalment, 50% of the lump sum, will be paid in the first payment certificate after the
contractor has met all his obligations under this section and has made a substantial start with
construction in accordance with the approved programme.
(b) The second instalment, 35% of the lump sum, will be paid when the value of the work done reaches
one half of the tendered amount, excluding contingencies and price adjustments in terms of clause
49 of the general conditions of contract.
(c) The third and final instalment, 15% of the lump sum, will be paid when the works have been
completed and the Contractor has fulfilled all the requirements of this section.
(d) Before any payment is made under this pay item, the Contractor shall satisfy the engineer that he has
provided camps and construction plant of good quality on the site, the value of which exceeds that of
the first instalment.
The Contractor may also be required to furnish documentary proof that he owns the camps and construction
plant on the site, the value of which shall exceed that of the first instalment.
In the event of the Contractor not being able to satisfy the Engineer as to the ownership of the camps and
construction plant, the Engineer shall have the right to withhold parts of any payments to be made under this
pay item, until the works have been completed.
The lump sum tendered under pay item 103P1(b) shall represent full compensation for that part of the
Contractor's general obligations, which is a function of only the value of the work, but not of the period of
completion. The lump sum tendered for pay item 103P1(b) will be increased or decreased pro rata in full
settlement of any difference in value-related general obligations resulting from an increased or decreased
value of the work.
The lump sum tendered in pay Item 103P1(b) will be payable monthly in instalments in relation to the value
of work done (excluding the value of any price adjustments in terms of the general conditions of contract).
The tendered rate per month for pay Item 103P1(c) represents full compensation for that part of the
Contractor's general obligations, which are mainly a function of construction time. The tendered rate will be
paid monthly, pro rata for parts of a month, from the date on which the Contractor has received the letter of
acceptance in terms of the conditions of contract, until the end of the period for completion of the works, plus
any extension thereof as provided in the Conditions of Contract, provided that -
(a) should the works be certified as having been completed before the contractual date for completion of
the works, the Contractor will then be entitled to payments in regard to the unexpired period for
completion;
(b) should the progress of the Contractor in terms of the value of work done be in arrear in regard to his
approved original programme, payments in respect of this item may be limited to payments for this
period, which, in his original programme (after suitable adjustments in respect of the extension of
time granted) agree with the actual value of work done.
Any payment made under pay item 103P1 will not be taken into account when determining whether the value
of a certificate complies with the 'minimum amount of interim certificate", as laid down in the Appendix to
Tender. The adjustments specified in pay items 103P1 (a), (b) and (c) will be made only if the value of the
work or the period for completion were to change and it is agreed that such adjustments will be in full
settlement of the changed compensation for amended general obligations.
104.2 General
1. The offices and laboratory will be erected by the Contractor on the Site or on land that has been
provided by the Employer adjacent to the Site for this purpose and are to be in close proximity to the
Contractor's offices and laboratories. If the Contractor should decide to move his own offices and/or
laboratories to a new site, the offices, laboratory and other buildings erected for the use of the
Engineer shall be rebuilt by the Contractor at the new site if required, at no additional charge.
2. The Contractor shall locate and arrange to lease or rent suitable houses for the exclusive use of
supervisory staff. Rental agreement shall not be finalised until the accommodation has been approved
as suitable by the Engineer.
3. The Contractor may not proceed with the permanent works before he has provided the required
equipment. If the offices for the Engineer and his staff are not ready for occupation when the
permanent works is commenced, the Contractor shall provide suitable temporary offices acceptable to
the Engineer at no cost to the Employer.
4. The Contractor shall take all reasonable precautions to ensure the general security and to prevent
unauthorised entry to the offices and laboratories of the Engineer. A security fence shall be erected by
the Contractor around the offices and laboratory of the Engineer.
5. The layout, siting and orientation of the offices and laboratory or other accommodation shall be to the
Engineer's approval and shall be decided upon in consultation with him. Laboratories and office
accommodation complete with their contents, access roads and hard standings shall be ready for
occupation and the use of the Engineer within 120 days of the date for commencement of the Works
unless otherwise approved in the Contract.
6. All offices, testing laboratories and residential accommodation shall be regularly cleaned for so long as
they are in use and suitable arrangements shall be made for the disposal of waste arising from the
offices, testing laboratories and residential accommodation.
7. All offices, testing laboratories and residential accommodation equipment shall be of a quality and
precision appropriate to its use and shall be delivered in a serviceable condition to the Engineer. The
Contractor shall keep all equipment in good order and shall repair or replace, as instructed by the
Engineer, any equipment that becomes unserviceable. The Contractor shall ensure that any
equipment needing periodic calibration shall be calibrated on delivery, annually and at other times as
and when required the nature of its duty and by the Engineer.
8. When major components of the Works are manufactured off the site the Contractor shall arrange to
make available adequate and secure accommodation at or adjacent to the place of, and during the
period of, manufacture and testing.
9. Ownership of the Engineer’s offices, laboratory building and sanitary facilities will transfer to the
Employer on completion of the project. Also, the ownership of the Engineer’s office furniture and
equipment will also transfer to the Employer on completion of the project. The ownership of the
mobile radios and laboratory equipment remains with the Contractor.
104.3.2 Offices
(a) The Engineer’s Offices shall be contained in a single building unit and shall consist of separate
accommodation within the building.
(b) The fittings, furniture and equipment provided shall conform to the requirements listed in the
Contract.
(c) The various sizes of offices required shall be as shown in Table 104.03-1, and schedules of supplies
and equipment to be provided as listed in the Contract.
(d) Areas around Offices
Sufficient all weather access and other roads around the offices shall be provided by the Contractor.
He shall keep them free of mud and dust either by using crushed stone, suitable dust laying oils,
bituminous surfacing or other approved means. They shall be well-drained and kept trafficable at all
times. Footpaths shall be similarly treated to provide convenient access to all buildings, between the
car park, offices, and laboratory for the Engineer.
Table 4.1
Minimum floor area for Engineer’s Office
Item Description Area (m2)
1 Resident Engineer's Office 12
4 Secretary's Office 8
5 Conference Room 15
6 Computer Room 8
7 Kitchen Unit 6
8 Ablution Unit 2
104.3.4 Laboratories
(a) The laboratory shall consist of a single building adjacent to the Engineer's offices, and shall consist
of separate accommodation within the building (minimum internal area indicated m2) as indicated in
Table 104.1 unless otherwise directed by the Engineer.
(b) The various sizes of the laboratories required shall be as shown in Table 104.2, and schedules of
equipment to be provided as listed in the Contract as per the type of pavement construction.
(c) The laboratories, fittings, furniture to be provided as listed in the Contract.
Table 4.2
Minimum floor area for Laboratory
Item Description Area (m2)
1 Soils Laboratory 40
2 Oven and soaking room 20
3 Sample storage 15
4 Office 10
Table 4.3
Minimum floor area for Housing Accommodation for the Engineer
Room Type Minimum Floor Area (m2)
Residence
Lounge 20
Dining Area 12
Kitchen 8
Bedroom 15
Toilet Area 9
104.4.2 Description
(a) The buildings shall be constructed from hollow blocks or bricks or of an approved equivalent
material. The construction material to be used shall be strong, durable and of an acceptable quality.
(b) The accommodation to be provided under this item shall be provided on a location to be approved by
the Engineer.
(c) Furnishings and equipment shall be as selected by the Engineer.
(d) The buildings shall be fully air-conditioned unless specified otherwise. All areas except kitchen and
bathrooms shall have ceiling fans.
(e) The facilities shall be fully wired and connected to a 220/250 V AC power source, with at least two
power points in each room and five points in the kitchen.
(f) The living/dining rooms shall have reverse cycle air conditioning / heating units of at least 1.2 kW.
(g) The furniture and equipment for the facilities are to be supplied new unless otherwise approved by
the Engineer in writing and after the completion of the contract all items shall become the property of
the Employer.
(h) There shall be a waterproof protection below concrete floors and waterproof layer (damp course) at
the same level within the brick walls. The quality and thickness of the waterproofing material to be
used shall be subject to approval of the Engineer.
(i) All buildings/ facilities shall have hot and cold running water.
(j) Where the water supply is not connected to the water main, an external elevated cold water storage
tank with a capacity of 5000 litres shall be provided in order to obtain a minimum head of 3 m of
water at the taps, together with the pipes leading to the supply tank.
(k) The living quarters, at the Contractor’s option if they are designed to be moved and re-erected on
another site on completion of Works, shall be made of timber, fibre cement or other approved
material and shall have double walls fitted with insulating material. Walls and ceilings shall be lined
on the inside with timber or other approved material.
(l) Floors shall be of timber or alternatively of concrete covered with suitable carpeting or vinyl tiles.
(m) The living quarters shall have a minimum clear height from floor to ceiling of 3.0 m.
(n) The total area of windows shall be at least 20% of the exterior floor area and all windows shall be of
an approved type that open and close readily. All exterior doors and windows shall be provided with
insect screens and the windows and doors shall be provided with suitable curtains.
(o) Each facility shall be properly painted inside and outside with an approved paint and the paintwork
shall be maintained during the Contract period.
104.4.3 Maintenance
(a) The Contractor shall arrange to maintain the residential accommodation until the issue of the Taking-
Over Certificate for the complete Works.
(b) Maintenance includes attending to repairs to various parts of the building, fittings etc. and the
connecting services as and when necessary, including the annual interior and exterior paint work
and periodic painting of wood and steel work; replacing the broken window/door, maintenance of
internal roads and other repairs as directed by the Engineer.
(c) The Contractor shall arrange to provide an uninterrupted supply of electricity and water for the
facilities. In case of failure of mains water or power supply, suitable arrangements shall have been
made for providing uninterrupted supply.
(d) All sources/tapings and connected equipment and fittings, piping, tanks, wiring and all other
accessories of the main and alternate power/water supply for the residential accommodation shall be
the property of the Employer.
104.5 Services
104.5.1 Sanitary Arrangements
(a) The Contractor shall be responsible for the maintenance of all sanitary services necessary to keep
latrines in a clean, neat and hygienic condition.
(b) The Contractor shall also provide for the removal of all rubbish.
104.6 Vehicles
(a) The Contractor shall provide vehicles for the sole use of the Engineer and his staff. The vehicles
shall be new. The vehicles must be comprehensively insured to cover any driver. The vehicles shall
be replaced after 150,000 km. Ownership of vehicles reverts to the Employer at the end of the
Contract.
(b) The Contractor shall provide the type of vehicles listed in the Contract. The vehicles shall be
provided with drivers, fuel and lubricants as required and shall be serviced, maintained and repaired
so as to be in a reliable and roadworthy condition at all times.
(c) All vehicles shall be available to the Engineer prior to commencement of the permanent works and in
accordance with the Engineer’s supervisory requirements or, in default, the Contractor shall make
other arrangements to cover the cost of alternative transport.
(d) The Contractor shall be responsible for replacement whether temporary or permanent of any vehicle
through repair or accident where such vehicle is unavailable to the Engineer for a period of more
than 24 hours.
104.7 Attendance
(a) The Contractor shall provide the Engineer with and maintain continuity of technicians equal to the
task and capable of performing the functions described in the Contract. Surveying technicians shall
be capable of assisting Surveyors in manual tasks. Laboratory assistants shall be capable of
assisting the Engineer’s laboratory staff in manual tasks. Drivers provided for the Engineer’s site
vehicles shall have a valid driving license and driving experience suitable for the vehicles supplied.
Cleaning staff shall be capable of carrying out duties to the satisfaction of the Engineer.
(b) The Contractor shall provide soap and towels in the offices and laboratories of the Engineer, the
services of cleaners and sanitary staff, together with cleaning equipment, and day and night
watchmen.
Standard Specification for AACRA Road & Bridge Works
Engineers Establishment on Site
Final November 2004
Page 104-7
SECTION 100 GENERAL
DIVISION 105 PROVISION FOR TRAFFIC
(c) The Contractor shall provide all assistance such as labourers, all tools and protective clothing,
wooden pegs, iron picks and pickets, water, cement and aggregate for concreting, transport for
labourers and materials, as may be required by the Engineer and his staff for checking, setting out,
surveying, measuring or testing the work.
(d) The Contractor shall include in his rates in the Bill of Quantities, the cost of all attendance upon the
Engineer and his staff.
Pay Item 104 P8.2: Percentage on-cost to be invoiced in amounts for equipment supplied under
Pay Item 104 P8.1
Payment for Pay Item 104 P8.1 shall be the sum of the invoiced amounts for any additional equipment ordered
by the Engineer under this item.
Payment for Pay Item 104 P8.2 shall be the tendered percentage on-cost of the amount paid under Pay Item
104 P8.1
Pay Item 104 P9: Building, House Type, Complete Including Fixtures
Pay Item 104 P10: Building, Apartment Type, Complete Including Fixtures
Pay Item 104 P11: Motel Style Accommodation Complete Including Fixtures
The measurement of the residential accommodation shall be on the number of units leased or rented. Except
for items detailed elsewhere in the contract, the payment includes that of providing the necessary fittings,
installations and the furniture, equipment and supplies in accordance with the details given in the contract.
The work provided in this item shall be as shown in the Bill of Quantities. The Contract unit rate for leasing or
renting residential accommodation for Engineer/Employer supervisory staff shall include all the expenses for
the work described, supply of furniture and equipment, including provision of uninterrupted supply of water
and power.
Pay Item 104 P 12 Items measured by number
The unit of measurement shall be the authorised number of units supplied and installed, complete and in
accordance with the Specifications and Drawings together with all minor fittings, brackets, connections, leads,
mountings, etc.
(i) Air conditioning unit in (No.)
(ii) Heater in (No.)
(iii) Gas burners (including provision of gas installation) in (No.)
Pay Item 104 P 13 Services
Provision of water, electricity, LP gas, tanks, sewage and rubbish removal, cleaning services, all as specified in
this section and including the construction and maintenance of the access roads, footpaths, fencing, car parks
etc:
Pay Item 104 P13.1 Services for residential accommodation(s) in per month
Payment of the lump sum tendered items shall be in full compensation for providing the services specified
For lump sum items 80% of the amount shall be paid when the item is provided and fitted or installed to the
Engineer's satisfaction. A further 20% shall be paid when the accommodation(s) are accepted by the Engineer
and any and all minor works have been completed.
Payment for services provided under Pay Item 104 P3 and 104 P13 shall be made in four equal instalments,
when the value of the permanent work done has reached 25%, 50% and 75% of the Contract Amount. Final
payment will be made when all accommodation has been returned to the owner or otherwise has been
dismantled cleared or removed to the Engineers satisfaction.
Payment at bid unit rates for the various items of payment scheduled in this Division, shall be in full
compensation for providing, procuring, erecting or leasing, installing and/or fitting the item or service as may be
required or specified, for the use of the item or service including replacements when defective and all transport,
handling and other costs.
Payment for Pay Item 104 P 3 and 104 P13 shall be increased pro rata for the time it is required during any
extended time of construction for which extension of time has been granted.
Payment under Pay Item 104 P 5 shall be made in full in the payment certificate following the date of
handover of the vehicles to the Engineer.
105.2 General
DEFINITIONS
APPROVED An arrangement of temporary signs and devices to warn traffic and guide
TEMPORARY TRAFFIC it through or past a work area or temporary hazard that has been
MANAGEMENT approved for use by the Engineer and the Employer
PLAN(S):
REGULATORY Any sign, signal, marking, or installation indicating an obligation to comply
TRAFFIC CONTROL with a legally enforceable instruction.
DEVICE:
WORK AREA: The specific area where work is being done.
WORK SITE: An area which includes the work area(s) and any additional length of road
required for advance signing, tapers, side tracks or other areas needed
for associated purposes.
OBSTRUCTION: Any works or otherwise on or adjacent to an existing carriageway that
requires modification to the existing traffic control arrangements.
SIDE TRACK: A length of temporary pavement constructed for detour of traffic to allow
safe construction of the works.
DETOUR: Diversion of traffic on existing roadways because of obstruction of the
existing roadway required to facilitate safe construction of the works.
DELINEATION A barrier used to define hazards and guide traffic through the work site.
BARRIER:
PHYSICAL BARRIER: A temporary safety barrier required to provide a strong physical barrier
between the travelled way and the work area.
(a) Install and maintain temporary traffic control devices adjacent to and within the project as required by
the traffic control plan, Clause 105.03, and the Engineer.
Install and maintain the traffic control devices as follows:
(i) Furnish and install traffic control devices before the start of construction operations;
(ii) Install only those traffic control devices needed for each stage or phase;
(iii) Relocate temporary traffic control devices as necessary;
(iv) Remove devices that no longer apply to the existing conditions;
(v) Immediately replace any device that is lost, stolen, destroyed, or inoperative;
(vi) Keep temporary traffic control devices clean; and
(vii) Remove all temporary traffic control devices upon contract completion or when
approved.
(b) Traffic safety officer
The safety of the travelling public is of utmost importance and every effort must be made to ensure
that all road signs, barricades, delineators, flagmen and speed controls are maintained and effective
and that courtesy is extended to the public at all times.
The Contractor shall nominate a knowledgeable member of his staff on site who shall be the
responsible person for the arrangements and maintenance of all accommodation of traffic measures
required for the duration of the contract. The responsible person shall liaise daily with the Resident
Engineer in order to maintain proper traffic arrangements.
The traffic safety officer will be required to perform the following duties and this list shall not be
deemed to be comprehensive. He shall:
(i) be responsible for keeping the temporary traffic accommodation requirements up to
specification 24 hours a day 7 days a week;
(ii) compile and maintain a complete daily record of traffic signs installed and the traffic signs
sequence at each location during the execution of the contract;.
(iii) inspect and report to the Engineer on the state of all required road signs as often as the
Engineer may require but in any event not less than once a day or at such other intervals as
may be specified;
(iv) exercise control in terms of traffic safety over the safe movement of personnel, visitors
and plant on site including the wearing of high visibility clothing, the operation of amber
flicker lights, and the display and cleanliness of "construction vehicle" signs, all as
specified;
(v) be responsible for keeping all road signs and traffic cones clean and visible at all times.
The Contractor shall remove all bituminous and other foreign matter from road signs and
traffic cones or provide new road signs and traffic cones all at the Contractor's own cost,
and all as directed by and to the satisfaction of the Engineer;
(vi) compile complete records of traffic accident scenes which are in any way connected with
construction activities, and draw up accident reports (including amongst others
photographs);
(vii) attend to the training and performance of flagmen and all other personnel involved in the
control of traffic; and
(viii) attend to all complaints and claims from the public with regard to traffic safety and report
on such matters to the Engineer.
(c) Provision of Side Tracks
The Contractor shall be responsible for the safe and easy passage of public traffic past and/or over
sections of roads that he has occupied. The Contractor shall take the necessary care at all times in
his operations and use of his equipment to protect the public and to facilitate the flow of traffic.
Where the Engineer determines that the existing road cannot remain in use by through traffic, the
Contractor shall provide details of a proposal for a bypass, to be included in a Temporary Traffic
Management Plan, for the approval of the Engineer before the construction Commences
(d) Minimum vertical clearance
The minimum vertical clearance over any portion of a bypass shall be 5.3 m
If the minimum clearance available is less than 5.3 m, the minimum clearance shall be indicated on
approved signs at approved locations on and in advance of the obstruction.
Submission Details: At least two (2) working days prior to proposed traffic control utilising
traffic controllers provide to the Engineer names of the proposed traffic
controllers and the training undertaken.
Release of Hold Point: The Engineer will consider the submitted document prior to authorising
the release of the Hold Point.
Where possible, side tracks shall be constructed so as not to damage or displace property markers,
or original points, lines and levels of reference. In cases where this is not possible the Contractor
shall notify the Engineer in good time so that he may arrange to have these suitably referenced
before they are displaced.
(f) Avoidance of Interference
The Contractor shall not interfere unnecessarily or improperly with the convenience of the public, or,
the access and use and occupation of all roads and footpaths, irrespective of whether they are public
or in the possession of the Employer or of others.
This shall include the safe and convenient passage for pedestrians and vehicles to and from
entrances and buildings at all times as detailed on the approved Temporary Traffic Management
Plan(s). Temporary connections to intersecting roadways shall be provided and maintained as
necessary. Any areas of excavation adjacent to pedestrian and vehicular accesses shall be suitably
fenced and sign posted.
Prior to the commencement of construction the Contractor shall provide written notice to all traders
and occupants of adjacent properties where access to or from those properties is affected by the
works to be undertaken.
Short term incidental works which affect the use of side roads, vehicular and pedestrian access shall
not be undertaken without providing adequate alternative provisions in accordance with this
specification.
No separate payment shall be made for the provision and maintenance of such access and facilities.
Where the approved Temporary Traffic Management Plan(s) involve regulatory traffic control devices, the
Contractor shall forward copies of the approved plans to the local traffic police so that such traffic regulations
may be enforced.
The Temporary Traffic Management Plan(s) shall include:
(a) Design drawings for any temporary roadways and sidetracks in accordance with Clause 105.11
showing pavement, wearing surface and drainage details;
(b) Details of arrangements for construction under traffic; and
(c) A signpost layout plan showing:
(i) location, size and legend of all temporary signs;
(ii) temporary regulatory signs and temporary speed zones; and
(iii) all traffic control devices such as temporary traffic signals, road marking, pavement
reflectors, guideposts, safety barrier systems, barrier boards etc.
Special consideration shall be given in the preparation of the Temporary Traffic Management Plan(s)
to the safety of pedestrians, cyclists and workers. Particular care shall be taken when requiring
reversal of traffic flows or the separation of unidirectional flow by medians or other physical
separation.
Where Temporary Traffic Management Plans are included as part of the drawings, they shall be
used as the basis for preparation of Temporary Traffic Management Plans
No extension of time will be granted or allowed relative to any delay associated with the obtaining of
the necessary approvals unless it is shown to the satisfaction of the Engineer that all necessary
steps have been taken by the Contractor within the specified timeframe.
Process Held: Work which would involve any obstruction whatsoever to traffic.
Submission Details: At least 5 working days prior to undertaking any work which would
involve any obstruction whatsoever to traffic, the Contractor shall
prepare and submit Temporary Traffic Management Plan(s) to the
Engineer for endorsement.
Release of Hold Point: On return by the Engineer to the Contractor of a copy of the Temporary
Traffic Management Plan(s) authorising the release of the Hold Point.
Where an arrangement for a side track, detour or obstruction is specified or shown on the drawings,
and the Contractor chooses to utilise that arrangement, this in no way relieves the responsibility of
the Contractor with respect to the adequacy in all respects of the design, construction and operation
of any side track, detour or obstruction.
Table 105.3
Unless otherwise approved, pavements shall be at least 6 4m wide with appropriate shoulders and widening
as necessary at horizontal curves. The minimum design speed of 40 km/h shall be adopted unless
otherwise approved.
Process Held: Construction of temporary side tracks not detailed on the approved
Temporary Traffic Management Plan(s).
Submission Details: At least ten (10) working days prior to the proposed construction of the
side track, the Contractor shall submit the design of the temporary side
track for assessment by the Engineer.
Release of Hold Point: The Engineer will review the design for compliance with the relevant
standards prior to authorising the release of the Hold Point.
(ii) Surfacing
Provide a wearing surface of a standard suitable for the traffic using the road being side
tracked.
The wearing surface type and pavement design shall be in accordance with the drawings
or approved Traffic management Plan. It shall be firm, even and skid resistant under all
weather conditions and shall be designed to remain sound for the duration of its use.
The wearing surface widths shall extend across the full width of the traffic lanes and
shoulders.
The wearing surface shall be carried onto any existing connecting roadway so as to finish
square to the existing roadway centreline.
For deviations expected to operate for less than forty-eight (48) hours, the requirement for
sealing may be waived subject to the employment of dust control measures.
Provide line marking, delineation and safety barriers in accordance with the approved
Traffic Management Plan
- Install only those traffic control devices needed for each stage or phase;
- Relocate temporary traffic control devices as necessary; and
- Remove devices that no longer apply to the existing conditions.
(iii) Immediately replace any device that is lost, stolen, destroyed, or inoperative.
(iv) Keep temporary traffic control devices clean.
(v) Furnish and maintain traffic control devices that meet an appropriate Quality Standard for
Work Zone Traffic Control Devices and are approved by the Engineer as such.
(vi) Repair or remove and replace "marginal" devices within 48 hours.
(vii) Repair or remove and replace "unacceptable" devices immediately.
(viii) Remove all temporary traffic control devices upon contract completion or when approved
to do so.
(b) Delineation Barriers
Barricades shall comply with all statutorily required road signage requirements and shall be
constructed of lightweight commercial quality materials as approved by the Engineer.
Trestles supporting barrier boards shall be constructed of metal, sawn timber or other suitable
materials and shall be yellow. Trestles shall serve as firm support for the barrier board but the bases
of the trestles shall not protrude beyond the ends of the boards. The trestles shall be kept in place by
sandbags or other suitable means.
Tapes, mesh fencing, interconnected lightweight units and bollard fences may all be used as
delineation barriers.
Furnish temporary concrete barriers. Used barriers may be used provided they are not
badly damaged. Lifting holes no larger than 100 mm or lifting loops are permitted.
Individual sections may vary in length. Connect sections so they do not separate when
struck by a vehicle. Mount 80 mm minimum dimension white or yellow retro reflectors, as
applicable, to the top or side of the barrier on 7.6 metre centers. Mount the retro reflectors
at a uniform height at least 600 mm above the pavement surface.
(ii) Channelisation Devices and Barricades
Channelisation devices shall include delineators, cones, barricades, guardrails, barriers,
road studs or road markings, or any appropriate combination of these devices.
(d) Traffic Signals
Traffic Signals for the control of traffic, either portable or temporary, may be used as described
below:
Portable traffic signals may be used for shuttle control where a single lane has to be used
alternately by traffic from opposite directions or at road crossings or intersections. They
are intended for relatively short-term applications.
(ii) Temporary Fixed Traffic Signals
Temporary fixed traffic signals may be used for long-term shuttle operations or for non-
shuttle control of intersecting traffic flows.
(e) Warning Lamps
Warning lamps shall be of robust construction and shall be capable complying with a reasonable
level of Photometric performance for the intended application.
When steady-burn warning lights are installed on barricades or drums and used in a series for
delineation, use flashing warning lights on the first 2 barricades or drums in the series. Mount
batteries for warning lights a maximum of 300 mm from ground or roadway surface as measured to
top of the battery casing.
(f) Traffic Guidance Flaps and Cones
Cones or flaps shall not be used as a substitute for barriers and signs at any location within the work
site.
Traffic guidance cones shall not be left in position at night unless there is a watchman in attendance
who can reposition cones dislodged by traffic. Otherwise they shall be removed and replaced with
flaps or barriers. Flaps fixed to the pavement may be left in position at night.
Traffic guidance cones to be used at night shall be reflectorised.
The Contractor shall shape and grade the earthworks for the traffic diversion so as to make full use of all
material that can be obtained from alongside the diversion, from the side cuts or from the immediate vicinity
of the works.
If sufficient material cannot be obtained in this manner he shall import material from other sources.
Where necessary, cuttings shall be carried out in such a manner as to obtain a satisfactory vertical alignment.
Where the sub grade is not sufficiently dense in its natural state, it shall be scarified to a depth of 200 mm,
mixed, watered, and compacted to 90% density according to ACCRA Test S-11 (ref: Division 802 and AACRA
Soils and Materials Manual; Section 5.11) .
Any fills which may be necessary for any reason, eg for the construction of fords, shall be constructed and
compacted by the Contractor as described above. Wherever possible, fords shall be constructed from rock
fill or coarse material so as to limit, in so far as is possible, damage caused by floodwaters. The Contractor
shall construct cuttings where required. When the earthworks for temporary deviations as described in
clause 105.07 have been completed, those sections of the temporary deviations and of existing gravel roads
used as temporary diversions, as indicated by the Engineer, shall be provided with a wearing course of
suitable gravel approved by the Engineer.
The Contractor shall provide, spread, water, mix and compact such material to 93% of AACRA Test S-11
(ref: Division 802 and AACRA Soils and Materials Manual; Section 5.11) density.
If gravel shoulders are to be used for the accommodation of traffic and if the existing shoulders are unsafe
for traffic, the shoulders shall be reconstructed as specified. All grass and other superfluous vegetation shall
be bladed from the surface. Approved gravel material shall be imported from the road reserve or from borrow
pits. The material shall be spread, watered, mixed and compacted to 93% of AACRA Test S-11 (ref: Division
802 and AACRA Soils and Materials Manual; Section 5.11) density in layers of the specified thickness.
The Engineer may also instruct the Contractor to water the temporary diversions to keep down dust
or to facilitate the proper blading of the surface. All drainage works shall be maintained in a good
working order.
The blading of surfaces of temporary diversions and the application of gravel and water shall be
measured and paid for separately, but all other maintenance shall be - deemed to be included in the
rate tendered for item 105P1: Accommodating traffic and maintaining temporary - diversions.
(b) Maintenance of Bituminous Surfaced Temporary Diversions
All temporary diversions with bituminous surfacing and existing gravel roads with bituminous surfacing
used by public traffic bypassing construction shall be maintained in a good and - safe trafficable
condition for the entire period during which such roads are used. Maintenance shall include:
(i) patching and repair of the bituminous surfacing and the clearing of shoulders;
(ii) clearing of all drains, including culvert inlet and outlet drains, and other incidentals and,
unless otherwise specified in the project specifications; and
(iii) care and maintenance of all road markings, road signs, delineators and guardrails.
The cost of all maintenance to temporary diversions with bituminous surfacing shall be included under the
provision sum – tendered in pay item 105P1. Accommodating traffic and maintaining temporary deviations,
except for the cost of repairs to the bituminous surfacing and pavement, shall be paid for separately under
pay item 105P10
Table 105.4
Process Held: Opening of side tracks to traffic (including portable or temporary traffic
signals sites)
Submission Details: At least 2 working days prior to proposed opening of the side track
provide notice that work is conforming and ready for inspection.
Release of Hold Point: The Engineer will inspect the site for compliance with the specification
prior to authorising the release of the Hold Point.
All permanent sign posting, pavement markings, safety barriers and traffic signals where required
under the Contract shall be completed or reinstated prior to opening completed work to traffic.
The Contractor may apply by notice to the Engineer for a Taking-Over Certificate
(Certificate of Completion) not earlier than fourteen days before the Works will, in the
Contractor’s opinion, be complete and ready for taking over. If the Works are divided into
sections, the Contractor may similarly apply for a Taking Over Certificate for each section.
The Contractor shall then complete this work before issuing a further notice to the Engineer.
dispose of any unauthorised or defective work or material or from recovering damages for any such
work or material.
Failure of the Contractor to perform all the obligations under the contract shall not bar the Employer
from unilaterally accepting the contract however failure to perform any of the obligations under the
contract by the Contractor may be held by the Engineer to be adequate reason for recommending
the withholding of payments until compliance is achieved.
106.3.3 Discharge
When submitting the Final Statement, the Contractor shall submit a written discharge which confirms that the
total of the Final Statement represents full and final settlement of all moneys due to the Contractor under or
in connection with the Contract.
Within 28 days after receiving the Final Statement and written discharge, the Engineer will issue to the
Employer the Final Payment Certificate.