By the end of October, the first shipment of transition pieces (TP) for the MERKUR offshore
wind project had been completed. The brief was to take full responsibility for organising the
transportation and associated engineering, to ship these components from the
manufacturer’s premises to the hub port for the transfer of TPs to the installation vessel.
COORDINADORA, in charge of the engineered transportation, is thrilled to share this
stunning case study exclusively with PES.
22 PES Wind
CORPORATE FOCUS
especially with regards to the lifting transmitting the whole load. That is the
capacity of ship’s cranes. reason why it is necessary to employ load
spreaders on the vessel deck to distribute
Thus, COORDINADORA, an expert in the
the weight and inertia forces efficiently
shipping sector for over 35 years, prepared
along the ship’s own structure, within
a particular RFQ for the ship owners to bid
allowable threshold values.
for the necessary consecutive shipments
along the same route. The only permissible area where it is
possible to connect any securing element
Time has demonstrated the importance of
on this cargo is at the bottom flange in
experience in handling such a complicated
contact with the load spreaders.
negotiation, resulting in full-warranty vessel
Therefore, the mechanical seafastening
features, for several consecutive shipments.
solution has to be applied to the same
It was done by matching the client needs,
load-spreading structures.
not only in terms of technical solvency, but
also the flexibility to integrate into the These were the clear and well-defined
manufacturing schedule. design constraints, together with
minimising the amount of steel weight and
Once the vessel selection process was
welding requirements for economic and
completed in favour of the top category
environmental reasons.
company Rolldock Shipping, a joint team
headed by COORDINADORA’s in-house The solution developed by
engineers started the to design the grillage COORDINADORA consisted of a beams
and sea fastening solution, which is the key grid of 30 mt weight, mostly made with
factor in the transportation of these commercial HEB profiles in 900 mm height
particular type of cargo. reinforced with plates directly welded to
ship hold frames.
Transition pieces are in concept vertical
cylinders, almost 30m high and about 6.5m A securing system was installed on top of the
diameter weighing 330mt. The cargo grillage grid, consisting of 16 mobile clamps,
footprint is only a narrow ring for which were mechanically activated to slip
www.peswind.com 23
CORPORATE FOCUS
24 PES Wind
CORPORATE FOCUS
Operations were closely watched by thresholds were fixed after a detailed advance and the cargo was completely
nominated MWS who finally stamped his engineering study, linking the sea state with unsecured once connected to the ship
signature on the CoA (certificate of the resulting accelerations suffered by crane and a certain minor percentage of the
approval) supporting the resulting jobs cargoes in transit, which had to be kept load on the hook. TP’s were unloaded onto
carried out under their warranty. under maximum values defined by the steel beam grillage previously prepared on
manufacturer to assure cargo integrity. the quay.
The transportation was during the autumn /
winter season, when the sea voyage needs Due to the effect of hurricane Ophelia Once they were discharged and unhooked,
a favourable weather window. This meant battering the English Channel and the Bay a joint survey was carried out inside each
monitoring the weather forecasts to ensure of Biscay on certain dates, the sail away had TP to detect any eventual damage suffered
certain parameters, such as wave to be postponed for two days. The during transportation. The result of all
significant height or wind speed did not expectable sea condition was not deemed inspections was no damage at all to the
exceed the defined thresholds. These safe for sailing within the maximum allowable main body or secondary elements.
motion response and thus the vessel was
TP’s were shifted to a temporary storage
kept at anchor, whilst the weather was
area by crawler crane, where they now
monitored to find a suitable window.
stand waiting for the installation vessel, MV
The COORDINADORA project team, again Sea Challenger, to pick them.
lead by Mr. Serrada travelled to PoD (port
The operation was a new and total success
of discharging), one day in ahead of the
of COORDINADORA’s ETM policy
vessel arrival to check all the preparations.
(Engineered Transport Management) which
Once in Eemshaven, the base port chosen consists of the detailed, comprehensive
by the main contractor, coordination and exhaustive study of all the involved
meetings were held with all parties to ensure transport parameters before it takes place,
the smooth discharge of these first six TPs. and leadership attendance at operations.
Global coordination is the only way to
After a short trip, lasting three days sailing,
ensure a safe job.
the ship arrived at the port with all cargo
safely stowed on board. During the voyage, Now, all efforts focussed on the upcoming
visual seafastening check-ups and random shipments, concluding the transportation of
hydraulic testing were carried out according the 66 TPs, expected to be done in a total
to implemented protocols and good of nine shipments, which we in
practice routines. COORDINADORA are proud to manage as
part of the whole value chain in the offshore
The unloading operation itself took two
wind industry.
days. According to the procedure, 50% of
the seafastening elements were released in www.coordinadoraetm.com
www.peswind.com 25