Sunteți pe pagina 1din 7

CONSTRUCTION OF BUILDING TO PROVIDE ACCOMMODATION FACILITIES FOR PUBLIC OFFICERS Classic Schedule Layout 24-Apr-19 15:56

Activity Name Original Duration Start Finish Qtr 2, 2019 Qtr 3, 2019
Mar Apr May Jun Jul Aug
Balance work moniter-2 CONSTRUCTION OF BUILDING TO PROVIDE
109.00 01-Apr-19 ACCOMMODATION
31-Jul-19 FACILITIES FOR PUBLIC OFFICERS (Phase I) 31-Jul-19, Balance work moniter-2 CONST

Balance work moniter-2.10 WING 1 82.00 01-Apr-19 04-Jul-19 04-Jul-19, Balance work moniter-2.10 WING 1

Balance work moniter-2.10.4 GROUND FLOOR 5.00 01-Apr-19 05-Apr-19 05-Apr-19, Balance work moniter-2.10.4 GROUND FLOOR
Balance work moniter-2.10.4.5 ELECTRICAL WORKS 5.00 01-Apr-19 05-Apr-19 05-Apr-19, Balance work moniter-2.10.4.5 ELECTRICAL W ORKS
Electrical fittings 3.00 03-Apr-19* 05-Apr-19 Electrical fittings
Electrical wiring 2.00 01-Apr-19* 02-Apr-19 Electrical wiring
Balance work moniter-2.10.3 FIRST FLOOR 70.00 01-Apr-19 22-Jun-19 22-Jun-19, Balance work moniter-2.10.3 FIRST FLOOR
ALUMINUM WORKER 12.00 01-Apr-19* 25-Apr-19 ALUMINUM WORKER
DRAIN LAYER 1.00 05-Apr-19* 05-Apr-19 DRAIN LAYER
MISCELLANEOUS WORK 10.00 01-Apr-19* 23-Apr-19 MISCELLANEOUS WORK
PAVER 7.00 01-Apr-19* 07-Apr-19 PAVER
PLUMBER 4.00 01-Apr-19* 04-Apr-19 PLUMBER
SANITARY FITTINGS 4.00 05-Apr-19* 08-Apr-19 SANITARY FITTINGS
Balance work moniter-2.10.3.5 ELECTRICAL WORKS 30.00 01-Apr-19 13-May-19 13-May-19, Balance work moniter-2.10.3.5 ELECTRICAL WORKS
Electrical fittings 4.00 10-May-19* 13-May-19 Electrical fittings
Electrical wiring 3.00 01-Apr-19* 03-Apr-19 Electrical wiring
Balance work moniter-2.10.3.4 PLASTERER 33.00 26-Apr-19 28-May-19 28-May-19, Balance work moniter-2.10.3.4 PLASTERER
External 3.00 26-May-19* 28-May-19 External
Internal 5.00 26-Apr-19* 30-Apr-19 Internal
Balance work moniter-2.10.3.6 TILER 5.00 08-Apr-19 25-Apr-19 25-Apr-19, Balance work moniter-2.10.3.6 TILER
Floor tiles 2.00 24-Apr-19* 25-Apr-19 Floor tiles
Wall tile s 5.00 08-Apr-19 25-Apr-19 Wall tile s
Balance work moniter-2.10.3.3 PAINTER AND DECORATOR 51.00 03-May-19 22-Jun-19 22-Jun-19, Balance work moniter-2.10.3.3 PAINTER AND DECORATOR
External 7.00 16-Jun-19 22-Jun-19 External
Internal 7.00 03-May-19* 09-May-19 Internal
Balance work moniter-2.10.1 SECOND FLOOR 63.00 01-Apr-19 15-Jun-19 15-Jun-19, Balance work moniter-2.10.1 SECOND FLOOR
ALUMINUM WORKER 15.00 28-Apr-19* 12-May-19 ALUMINUM WORKER
BLOCK LAYER 2.00 01-Apr-19* 02-Apr-19 BLOCK LAYER
DRAIN LAYER 3.00 05-May-19* 07-May-19 DRAIN LAYER
MISCELLANEOUS WORK 10.00 24-Apr-19* 03-May-19 MISCELLANEOUS WORK
PAVER 7.00 28-Apr-19 04-May-19 PAVER
PLUMBER 7.00 28-Apr-19* 04-May-19 PLUMBER
SANITARY FITTINGS 4.00 13-May-19 16-May-19 SANITARY FITTINGS
Balance work moniter-2.10.1.5 ELECTRICAL WORKS 23.00 28-Apr-19 20-May-19 20-May-19, Balance work moniter-2.10.1.5 ELECTRICAL WORKS
Electrical fittings 7.00 14-May-19* 20-May-19 Electrical fittings
Electrical wiring 7.00 28-Apr-19* 04-May-19 Electrical wiring
Balance work moniter-2.10.1.4 PLASTERER 13.00 13-May-19 25-May-19 25-May-19, Balance work moniter-2.10.1.4 PLASTERER
External 7.00 19-May-19* 25-May-19 External
Internal 10.00 13-May-19* 22-May-19 Internal
Balance work moniter-2.10.1.1 PAINTER AND DECORATOR 24.00 23-May-19 15-Jun-19 15-Jun-19, Balance work moniter-2.10.1.1 PAINTER AND DECORATOR
External 14.00 02-Jun-19 15-Jun-19 External
Internal 14.00 23-May-19 05-Jun-19 Internal
Balance work moniter-2.10.1.6 TILER 10.00 02-May-19 11-May-19 11-May-19, Balance work moniter-2.10.1.6 TILER
Floor tiles 10.00 02-May-19* 11-May-19 Floor tiles
Wall tile s 7.00 05-May-19 11-May-19 Wall tile s
Balance work moniter-2.10.5 THIRD FLOOR 65.00 03-Apr-19 19-Jun-19 19-Jun-19, Balance work moniter-2.10.5 THIRD FLOOR
ALUMINUM WORKER 15.00 13-May-19 27-May-19 ALUMINUM WORKER
BLOCK LAYER 2.00 03-Apr-19* 04-Apr-19 BLOCK LAYER
DRAIN LAYER 3.00 12-May-19 14-May-19 DRAIN LAYER
MISCELLANEOUS WORK 10.00 04-May-19* 13-May-19 MISCELLANEOUS WORK
PAVER 7.00 05-May-19* 11-May-19 PAVER
PLUMBER 7.00 05-May-19 11-May-19 PLUMBER
SANITARY FITTINGS 4.00 28-May-19 31-May-19 SANITARY FITTINGS
Balance work moniter-2.10.5.5 ELECTRICAL WORKS 23.00 05-May-19 27-May-19 27-May-19, Balance work moniter-2.10.5.5 ELECTRICAL WORKS
Electrical fittings 7.00 21-May-19* 27-May-19 Electrical fittings
Electrical wiring 7.00 05-May-19* 11-May-19 Electrical wiring
Balance work moniter-2.10.5.4 PLASTERER 20.00 12-May-19 31-May-19 31-May-19, Balance work moniter-2.10.5.4 PLASTERER
External 7.00 12-May-19* 18-May-19 External
Internal 10.00 22-May-19* 31-May-19 Internal
Balance work moniter-2.10.5.3 PAINTER AND DECORATOR 32.00 19-May-19 19-Jun-19 19-Jun-19, Balance work moniter-2.10.5.3 PAINTER AND DECORATOR
External 14.00 19-May-19 01-Jun-19 External
Internal 14.00 06-Jun-19 19-Jun-19 Internal
Balance work moniter-2.10.5.6 TILER 10.00 12-May-19 21-May-19 21-May-19, Balance work moniter-2.10.5.6 TILER
Floor tiles 10.00 12-May-19* 21-May-19 Floor tiles
Wall tile s 7.00 12-May-19 18-May-19 Wall tile s
Balance work moniter-2.10.6 FORTH FLOOR 78.00 05-Apr-19 04-Jul-19 04-Jul-19, Balance work moniter-2.10.6 FORTH FLOOR
ALUMINUM WORKER 15.00 28-May-19 11-Jun-19 ALUMINUM WORKER
BLOCK LAYER 5.00 05-Apr-19* 09-Apr-19 BLOCK LAYER

Actual Work Critical Remaining Work Summary Page 1 of 7 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
CONSTRUCTION OF BUILDING TO PROVIDE ACCOMMODATION FACILITIES FOR PUBLIC OFFICERS Classic Schedule Layout 24-Apr-19 15:56
Activity Name Original Duration Start Finish Qtr 2, 2019 Qtr 3, 2019
Mar Apr May Jun Jul Aug
DRAIN LAYER 3.00 15-May-19 17-May-19 DRAIN LAYER
MISCELLANEOUS WORK 10.00 14-May-19* 23-May-19 MISCELLANEOUS WORK
PAVER 4.00 12-May-19* 15-May-19 PAVER
PLUMBER 14.00 12-May-19 25-May-19 PLUMBER
SANITARY FITTINGS 4.00 04-Jun-19 07-Jun-19 SANITARY FITTINGS
Balance work moniter-2.10.6.5 ELECTRICAL WORKS 33.00 02-May-19 03-Jun-19 03-Jun-19, Balance work moniter-2.10.6.5 ELECTRICAL W ORKS
Electrical fittings 7.00 28-May-19* 03-Jun-19 Electrical fittings
Electrical wiring 7.00 02-May-19* 08-May-19 Electrical wiring
Balance work moniter-2.10.6.4 PLASTERER 40.00 07-May-19 15-Jun-19 15-Jun-19, Balance work moniter-2.10.6.4 PLASTERER
External 5.00 07-May-19* 11-May-19 External
Internal 7.00 09-Jun-19 15-Jun-19 Internal
Balance work moniter-2.10.6.3 PAINTER AND DECORATOR 52.00 14-May-19 04-Jul-19 04-Jul-19, Balance work moniter-2.10.6.3 PAINTER AND DECORATOR
External 5.00 14-May-19 18-May-19 External
Internal 15.00 20-Jun-19 04-Jul-19 Internal
Balance work moniter-2.10.6.6 TILER 10.00 19-May-19 28-May-19 28-May-19, Balance work moniter-2.10.6.6 TILER
Floor tiles 7.00 22-May-19 28-May-19 Floor tiles
Wall tile s 7.00 19-May-19 25-May-19 Wall tiles
Balance work moniter-2.10.7 FIFTH FLOOR 53.00 01-Apr-19 05-Jun-19 05-Jun-19, Balance work moniter-2.10.7 FIFTH FLOOR
BLOCK LAYER 5.00 23-Apr-19* 27-Apr-19 BLOCK LAYER
CONCRETE 3.00 03-Apr-19* 05-Apr-19 CONCRETE
FORM WORK 1.00 02-Apr-19* 02-Apr-19 FORM WORK
MISCELLANEOUS WORK 3.00 24-May-19* 26-May-19 MISCELLANEOUS WORK
PAVER 5.00 16-May-19 20-May-19 PAVER
REINFORCEMENT 1.00 01-Apr-19* 01-Apr-19 REINFORCEMENT
Balance work moniter-2.10.7.5 ELECTRICAL WORKS 28.00 09-May-19 05-Jun-19 05-Jun-19, Balance work moniter-2.10.7.5 ELECTRICAL W ORKS
Electrical fittings 2.00 04-Jun-19 05-Jun-19 Electrical fittings
Electrical wiring 2.00 09-May-19* 10-May-19 Electrical wiring
Balance work moniter-2.10.7.4 PLASTERER 7.00 30-Apr-19 06-May-19 06-May-19, Balance work moniter-2.10.7.4 PLASTERER
External 7.00 30-Apr-19* 06-May-19 External
Balance work moniter-2.10.7.3 PAINTER AND DECORATOR 3.00 08-May-19 10-May-19 10-May-19, Balance work moniter-2.10.7.3 PAINTER AND DECORATOR
External 3.00 08-May-19* 10-May-19 External
Balance work moniter-2.10.8 ROOF 23.00 01-Apr-19 06-May-19 06-May-19, Balance work moniter-2.10.8 ROOF
CEILING WORKS 10.00 08-Apr-19* 30-Apr-19 CEILING WORKS
ROOF PLUMBER FIRST FLOOR 3.00 04-May-19 06-May-19 ROOF PLUMBER FIRST FLOOR
ROOF PLUMBER FORTH FLOOR 7.00 08-Apr-19 27-Apr-19 ROOF PLUMBER FORTH FLOOR
ROOF PLUMBER SECOND FLOOR 3.00 01-May-19 03-May-19 ROOF PLUMBER SECOND FLOOR
ROOF PLUMBER THIRD FLOOR 3.00 28-Apr-19 30-Apr-19 ROOF PLUMBER THIRD FLOOR
ROOF WORK 7.00 01-Apr-19* 07-Apr-19 ROOF WORK

Balance work moniter-2.2 WING 2 109.00 01-Apr-19 31-Jul-19 31-Jul-19, Balance work moniter-2.2 WING

Balance work moniter-2.2.4 GROUND FLOOR 9.00 01-Apr-19 09-Apr-19 09-Apr-19, Balance work moniter-2.2.4 GROUND FLOOR
Balance work moniter-2.2.4.5 ELECTRICAL WORKS 9.00 01-Apr-19 09-Apr-19 09-Apr-19, Balance work moniter-2.2.4.5 ELECTRICAL WORKS
Electrical fittings 7.00 03-Apr-19* 09-Apr-19 Electrical fittings
Electrical wiring 7.00 01-Apr-19 07-Apr-19 Electrical wiring
Balance work moniter-2.2.3 FIRST FLOOR 109.00 01-Apr-19 31-Jul-19 31-Jul-19, Balance work moniter-2.2.3 FIR
ALUMINUM WORKER 12.00 03-Apr-19 27-Apr-19 ALUMINUM WORKER
DRAIN LAYER 8.00 08-Apr-19 28-Apr-19 DRAIN LAYER
MISCELLANEOUS WORK 4.00 01-Apr-19 04-Apr-19 MISCELLANEOUS WORK
PAVER 14.00 01-Apr-19* 27-Apr-19 PAVER
PLUMBER 7.00 01-Apr-19* 07-Apr-19 PLUMBER
SANITARY FITTINGS 4.00 08-Apr-19 24-Apr-19 SANITARY FITTINGS
Balance work moniter-2.2.3.5 ELECTRICAL WORKS 19.00 08-Apr-19 09-May-19 09-May-19, Balance work moniter-2.2.3.5 ELECTRICAL W ORKS
Electrical fittings 5.00 05-May-19* 09-May-19 Electrical fittings
Electrical wiring 5.00 08-Apr-19 25-Apr-19 Electrical wiring
Balance work moniter-2.2.3.4 PLASTERER 90.00 23-Apr-19 21-Jul-19 21-Jul-19, Balance work moniter-2.2.3.4 PLASTERER
External 10.00 12-Jul-19 21-Jul-19 External
Internal 7.00 23-Apr-19* 29-Apr-19 Internal
Balance work moniter-2.2.3.6 TILER 7.00 26-Apr-19 02-May-19 02-May-19, Balance work moniter-2.2.3.6 TILER
Floor tiles 5.00 28-Apr-19* 02-May-19 Floor tiles
Wall tile s 7.00 26-Apr-19* 02-May-19 Wall tiles
Balance work moniter-2.2.3.3 PAINTER AND DECORATOR 97.00 26-Apr-19 31-Jul-19 31-Jul-19, Balance work moniter-2.2.3.3 PA
External 11.00 21-Jul-19 31-Jul-19 External
Internal 12.00 26-Apr-19* 07-May-19 Internal
Balance work moniter-2.2.1 SECOND FLOOR 98.00 01-Apr-19 20-Jul-19 20-Jul-19, Balance work moniter-2.2.1 SECOND FLOOR
ALUMINUM WORKER 12.00 28-Apr-19 09-May-19 ALUMINUM WORKER
BLOCK LAYER 5.00 01-Apr-19 05-Apr-19 BLOCK LAYER
DRAIN LAYER 7.00 05-May-19 11-May-19 DRAIN LAYER
MISCELLANEOUS WORK 4.00 03-May-19 06-May-19 MISCELLANEOUS WORK
PAVER 14.00 28-Apr-19* 11-May-19 PAVER

Actual Work Critical Remaining Work Summary Page 2 of 7 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
CONSTRUCTION OF BUILDING TO PROVIDE ACCOMMODATION FACILITIES FOR PUBLIC OFFICERS Classic Schedule Layout 24-Apr-19 15:56
Activity Name Original Duration Start Finish Qtr 2, 2019 Qtr 3, 2019
Mar Apr May Jun Jul Aug
PLUMBER 7.00 28-Apr-19 04-May-19 PLUMBER
SANITARY FITTINGS 4.00 10-May-19 13-May-19 SANITARY FITTINGS
Balance work moniter-2.2.1.5 ELECTRICAL WORKS 19.00 28-Apr-19 16-May-19 16-May-19, Balance work moniter-2.2.1.5 ELECTRICAL W ORKS
Electrical fittings 7.00 10-May-19* 16-May-19 Electrical fittings
Electrical wiring 7.00 28-Apr-19 04-May-19 Electrical wiring
Balance work moniter-2.2.1.4 PLASTERER 63.00 10-May-19 11-Jul-19 11-Jul-19, Balance work moniter-2.2.1.4 PLASTERER
External 8.00 04-Jul-19 11-Jul-19 External
Internal 7.00 10-May-19 16-May-19 Internal
Balance work moniter-2.2.1.1 PAINTER AND DECORATOR 65.00 17-May-19 20-Jul-19 20-Jul-19, Balance work moniter-2.2.1.1 PAINTER AND D
External 10.00 11-Jul-19* 20-Jul-19 External
Internal 14.00 17-May-19 30-May-19 Internal
Balance work moniter-2.2.1.6 TILER 7.00 12-May-19 18-May-19 18-May-19, Balance work moniter-2.2.1.6 TILER
Floor tiles 7.00 12-May-19* 18-May-19 Floor tiles
Wall tile s 5.00 14-May-19 18-May-19 Wall tile s
Balance work moniter-2.2.5 THIRD FLOOR 83.00 06-Apr-19 10-Jul-19 10-Jul-19, Balance work moniter-2.2.5 THIRD FLOOR
ALUMINUM WORKER 12.00 10-May-19 21-May-19 ALUMINUM WORKER
BLOCK LAYER 7.00 06-Apr-19 25-Apr-19 BLOCK LAYER
DRAIN LAYER 7.00 19-May-19 25-May-19 DRAIN LAYER
MISCELLANEOUS WORK 4.00 07-May-19 10-May-19 MISCELLANEOUS WORK
PAVER 7.00 12-May-19* 18-May-19 PAVER
PLUMBER 14.00 05-May-19 18-May-19 PLUMBER
SANITARY FITTINGS 4.00 22-May-19 25-May-19 SANITARY FITTINGS
Balance work moniter-2.2.5.5 ELECTRICAL WORKS 19.00 05-May-19 23-May-19 23-May-19, Balance work moniter-2.2.5.5 ELECTRICAL W ORKS
Electrical fittings 7.00 17-May-19 23-May-19 Electrical fittings
Electrical wiring 7.00 05-May-19 11-May-19 Electrical wiring
Balance work moniter-2.2.5.4 PLASTERER 51.00 14-May-19 03-Jul-19 03-Jul-19, Balance work moniter-2.2.5.4 PLASTERER
External 7.00 27-Jun-19 03-Jul-19 External
Internal 10.00 14-May-19* 23-May-19 Internal
Balance work moniter-2.2.5.3 PAINTER AND DECORATOR 41.00 31-May-19 10-Jul-19 10-Jul-19, Balance work moniter-2.2.5.3 PAINTER AND DECORATOR
External 7.00 04-Jul-19 10-Jul-19 External
Internal 10.00 31-May-19 09-Jun-19 Internal
Balance work moniter-2.2.5.6 TILER 10.00 19-May-19 28-May-19 28-May-19, Balance work moniter-2.2.5.6 TILER
Floor tiles 7.00 22-May-19 28-May-19 Floor tiles
Wall tile s 5.00 19-May-19* 23-May-19 Wall tile s
Balance work moniter-2.2.6 FORTH FLOOR 81.00 01-Apr-19 03-Jul-19 03-Jul-19, Balance work moniter-2.2.6 FORTH FLOOR
ALUMINUM WORKER 15.00 22-May-19 05-Jun-19 ALUMINUM WORKER
BLOCK LAYER 7.00 14-May-19 20-May-19 BLOCK LAYER
DRAIN LAYER 7.00 26-May-19 01-Jun-19 DRAIN LAYER
MISCELLANEOUS WORK 35.00 19-May-19 22-Jun-19 MISCELLANEOUS WORK
PAVER 14.00 19-May-19 01-Jun-19 PAVER
PLUMBER 14.00 19-May-19* 01-Jun-19 PLUMBER
SANITARY FITTINGS 4.00 02-Jun-19 05-Jun-19 SANITARY FITTINGS
Balance work moniter-2.2.6.2 REINFORCEMENT 37.00 01-Apr-19 20-May-19 20-May-19, Balance work moniter-2.2.6.2 REINFORCEMENT
For Beams & Slabs 12.00 01-May-19 12-May-19 For Beams & Slabs
For Column Shafts 10.00 01-Apr-19 23-Apr-19 For Column Shafts
For other works 7.00 14-May-19 20-May-19 For other works
For roof beams 8.00 09-May-19 16-May-19 For roof beams
Balance work moniter-2.2.6.10 FORMWORK 39.00 04-Apr-19 25-May-19 25-May-19, Balance work moniter-2.2.6.10 FORMWORK
For Beams & Slabs 12.00 29-Apr-19 10-May-19 For Beams & Slabs
For Column Shafts 8.00 04-Apr-19 24-Apr-19 For Column Shafts
For other works 5.00 21-May-19 25-May-19 For other works
For roof beams 7.00 30-Apr-19 06-May-19 For roof beams
Balance work moniter-2.2.6.1 CONCRETER 39.00 27-Apr-19 04-Jun-19 04-Jun-19, Balance work moniter-2.2.6.1 CONCRETER
For Beams & Slabs 1.00 13-May-19 13-May-19 For Beams & Slabs
For Column Shafts 8.00 27-Apr-19 04-May-19 For Column Shafts
For other works 10.00 26-May-19* 04-Jun-19 For other works
For roof beams 4.00 15-May-19 18-May-19 For roof beams
Balance work moniter-2.2.6.5 ELECTRICAL WORKS 9.00 28-May-19 05-Jun-19 05-Jun-19, Balance work moniter-2.2.6.5 ELECTRICAL WORKS
Electrical fittings 7.00 30-May-19 05-Jun-19 Electrical fittings
Electrical wiring 7.00 28-May-19 03-Jun-19 Electrical wiring
Balance work moniter-2.2.6.4 PLASTERER 24.00 03-Jun-19 26-Jun-19 26-Jun-19, Balance work moniter-2.2.6.4 PLASTERER
External 14.00 13-Jun-19 26-Jun-19 External
Internal 7.00 03-Jun-19* 09-Jun-19 Internal
Balance work moniter-2.2.6.3 PAINTER AND DECORATOR 24.00 10-Jun-19 03-Jul-19 03-Jul-19, Balance work moniter-2.2.6.3 PAINTER AND DECORATOR
External 7.00 27-Jun-19 03-Jul-19 External
Internal 14.00 10-Jun-19 23-Jun-19 Internal
Balance work moniter-2.2.6.6 TILER 14.00 29-May-19 11-Jun-19 11-Jun-19, Balance work moniter-2.2.6.6 TILER
Floor tiles 14.00 29-May-19 11-Jun-19 Floor tiles
Wall tile s 7.00 30-May-19 05-Jun-19 Wall tile s

Actual Work Critical Remaining Work Summary Page 3 of 7 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
CONSTRUCTION OF BUILDING TO PROVIDE ACCOMMODATION FACILITIES FOR PUBLIC OFFICERS Classic Schedule Layout 24-Apr-19 15:56
Activity Name Original Duration Start Finish Qtr 2, 2019 Qtr 3, 2019
Mar Apr May Jun Jul Aug
Balance work moniter-2.2.7 FIFTH FLOOR 43.00 14-May-19 25-Jun-19 25-Jun-19, Balance work moniter-2.2.7 FIFTH FLOOR
BLOCK LAYER 14.00 24-May-19 06-Jun-19 BLOCK LAYER
CONCRETE 2.00 17-May-19 18-May-19 CONCRETE
FORM WORK 2.00 15-May-19 16-May-19 FORM WORK
MISCELLANEOUS WORK 3.00 23-Jun-19 25-Jun-19 MISCELLANEOUS WORK
PAVER 7.00 07-Jun-19 13-Jun-19 PAVER
REINFORCEMENT 1.00 14-May-19 14-May-19 REINFORCEMENT
Balance work moniter-2.2.7.5 ELECTRICAL WORKS 5.00 11-Jun-19 15-Jun-19 15-Jun-19, Balance work moniter-2.2.7.5 ELECTRICAL WORKS
Electrical fittings 3.00 13-Jun-19 15-Jun-19 Electrical fittings
Electrical wiring 3.00 11-Jun-19 13-Jun-19 Electrical wiring
Balance work moniter-2.2.7.4 PLASTERER 10.00 03-Jun-19 12-Jun-19 12-Jun-19, Balance work moniter-2.2.7.4 PLASTERER
External 10.00 03-Jun-19 12-Jun-19 External
Balance work moniter-2.2.7.3 PAINTER AND DECORATOR 14.00 10-Jun-19 23-Jun-19 23-Jun-19, Balance work moniter-2.2.7.3 PAINTER AND DECORATOR
7 14.00 10-Jun-19 23-Jun-19 7
Balance work moniter-2.2.7.6 TILER 0.00
Balance work moniter-2.2.8 ROOF 26.00 09-Jun-19 04-Jul-19 04-Jul-19, Balance work moniter-2.2.8 ROOF
CEILING WORKS 10.00 23-Jun-19 02-Jul-19 CEILING WORKS
ROOF PLUMBER FIRST FLOOR 3.00 02-Jul-19 04-Jul-19 ROOF PLUMBER FIRST FLOOR
ROOF PLUMBER FORTH FLOOR 3.00 23-Jun-19 25-Jun-19 ROOF PLUMBER FORTH FLOOR
ROOF PLUMBER SECOND FLOOR 3.00 29-Jun-19 01-Jul-19 ROOF PLUMBER SECOND FLOOR
ROOF PLUMBER THIRD FLOOR 3.00 26-Jun-19 28-Jun-19 ROOF PLUMBER THIRD FLOOR
ROOF WORK 14.00 09-Jun-19* 22-Jun-19 ROOF WORK
TINKER 2.00 23-Jun-19* 24-Jun-19 TINKER
Balance work moniter-2.3 WING 3 96.00 01-Apr-19 18-Jul-19 18-Jul-19, Balance work moniter-2.3 WING 3

Balance work moniter-2.3.4 GROUND FLOOR 9.00 01-Apr-19 09-Apr-19 09-Apr-19, Balance work moniter-2.3.4 GROUND FLOOR
Balance work moniter-2.3.4.5 ELECTRICAL WORKS 9.00 01-Apr-19 09-Apr-19 09-Apr-19, Balance work moniter-2.3.4.5 ELECTRICAL WORKS
Electrical fittings 7.00 03-Apr-19* 09-Apr-19 Electrical fittings
Electrical wiring 7.00 01-Apr-19 07-Apr-19 Electrical wiring
Balance work moniter-2.3.3 FIRST FLOOR 72.00 01-Apr-19 24-Jun-19 24-Jun-19, Balance work moniter-2.3.3 FIRST FLOOR
ALUMINUM WORKER 15.00 28-Apr-19* 12-May-19 ALUMINUM WORKER
BLOCK LAYER 7.00 01-Apr-19 07-Apr-19 BLOCK LAYER
DRAIN LAYER 5.00 05-May-19 09-May-19 DRAIN LAYER
MISCELLANEOUS WORK 7.00 28-Apr-19* 04-May-19 MISCELLANEOUS WORK
PAVER 7.00 28-Apr-19* 04-May-19 PAVER
PLUMBER 7.00 28-Apr-19* 04-May-19 PLUMBER
SANITARY FITTINGS 4.00 05-May-19* 08-May-19 SANITARY FITTINGS
Balance work moniter-2.3.3.5 ELECTRICAL WORKS 39.00 28-Apr-19 05-Jun-19 05-Jun-19, Balance work moniter-2.3.3.5 ELECTRICAL WORKS
Electrical fittings 7.00 30-May-19 05-Jun-19 Electrical fittings
Electrical wiring 7.00 28-Apr-19 04-May-19 Electrical wiring
Balance work moniter-2.3.3.4 PLASTERER 38.00 11-May-19 17-Jun-19 17-Jun-19, Balance work moniter-2.3.3.4 PLASTERER
External 10.00 08-Jun-19 17-Jun-19 External
Internal 7.00 11-May-19 17-May-19 Internal
Balance work moniter-2.3.3.6 TILER 9.00 03-May-19 11-May-19 11-May-19, Balance work moniter-2.3.3.6 TILER
Floor tiles 7.00 05-May-19* 11-May-19 Floor tiles
Wall tile s 7.00 03-May-19 09-May-19 Wall tile s
Balance work moniter-2.3.3.3 PAINTER AND DECORATOR 38.00 18-May-19 24-Jun-19 24-Jun-19, Balance work moniter-2.3.3.3 PAINTER AND DECORATOR
External 7.00 18-Jun-19 24-Jun-19 External
Internal 15.00 18-May-19 01-Jun-19 Internal
Balance work moniter-2.3.1 SECOND FLOOR 66.00 01-Apr-19 18-Jun-19 18-Jun-19, Balance work moniter-2.3.1 SECOND FLOOR
ALUMINUM WORKER 15.00 13-May-19 27-May-19 ALUMINUM WORKER
BLOCK LAYER 7.00 01-Apr-19 07-Apr-19 BLOCK LAYER
DRAIN LAYER 5.00 12-May-19 16-May-19 DRAIN LAYER
MISCELLANEOUS WORK 5.00 05-May-19 09-May-19 MISCELLANEOUS WORK
PAVER 7.00 05-May-19* 11-May-19 PAVER
PLUMBER 7.00 05-May-19 11-May-19 PLUMBER
SANITARY FITTINGS 4.00 28-May-19* 31-May-19 SANITARY FITTINGS
Balance work moniter-2.3.1.5 ELECTRICAL WORKS 39.00 05-May-19 12-Jun-19 12-Jun-19, Balance work moniter-2.3.1.5 ELECTRICAL WORKS
Electrical fittings 7.00 06-Jun-19 12-Jun-19 Electrical fittings
Electrical wiring 7.00 05-May-19 11-May-19 Electrical wiring
Balance work moniter-2.3.1.4 PLASTERER 11.00 28-May-19 07-Jun-19 07-Jun-19, Balance work moniter-2.3.1.4 PLASTERER
External 7.00 01-Jun-19 07-Jun-19 External
Internal 7.00 28-May-19 03-Jun-19 Internal
Balance work moniter-2.3.1.1 PAINTER AND DECORATOR 15.00 04-Jun-19 18-Jun-19 18-Jun-19, Balance work moniter-2.3.1.1 PAINTER AND DECORATOR
External 7.00 08-Jun-19 14-Jun-19 External
Internal 15.00 04-Jun-19 18-Jun-19 Internal
Balance work moniter-2.3.1.6 TILER 7.00 12-May-19 18-May-19 18-May-19, Balance work moniter-2.3.1.6 TILER
Floor tiles 7.00 12-May-19 18-May-19 Floor tiles
Wall tile s 7.00 12-May-19* 18-May-19 Wall tile s

Actual Work Critical Remaining Work Summary Page 4 of 7 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
CONSTRUCTION OF BUILDING TO PROVIDE ACCOMMODATION FACILITIES FOR PUBLIC OFFICERS Classic Schedule Layout 24-Apr-19 15:56
Activity Name Original Duration Start Finish Qtr 2, 2019 Qtr 3, 2019
Mar Apr May Jun Jul Aug
Balance work moniter-2.3.5 THIRD FLOOR 81.00 01-Apr-19 03-Jul-19 03-Jul-19, Balance work moniter-2.3.5 THIRD FLOOR
ALUMINUM WORKER 15.00 28-May-19 11-Jun-19 ALUMINUM WORKER
BLOCK LAYER 7.00 01-Apr-19 07-Apr-19 BLOCK LAYER
DRAIN LAYER 5.00 19-May-19 23-May-19 DRAIN LAYER
MISCELLANEOUS WORK 3.00 10-May-19 12-May-19 MISCELLANEOUS WORK
PAVER 7.00 12-May-19* 18-May-19 PAVER
PLUMBER 7.00 12-May-19 18-May-19 PLUMBER
SANITARY FITTINGS 4.00 12-Jun-19 15-Jun-19 SANITARY FITTINGS
Balance work moniter-2.3.5.5 ELECTRICAL WORKS 39.00 12-May-19 19-Jun-19 19-Jun-19, Balance work moniter-2.3.5.5 ELECTRICAL WORKS
Electrical fittings 7.00 13-Jun-19 19-Jun-19 Electrical fittings
Electrical wiring 7.00 12-May-19* 18-May-19 Electrical wiring
Balance work moniter-2.3.5.4 PLASTERER 25.00 22-May-19 15-Jun-19 15-Jun-19, Balance work moniter-2.3.5.4 PLASTERER
External 10.00 22-May-19 31-May-19 External
Internal 7.00 09-Jun-19 15-Jun-19 Internal
Balance work moniter-2.3.5.3 PAINTER AND DECORATOR 33.00 01-Jun-19 03-Jul-19 03-Jul-19, Balance work moniter-2.3.5.3 PAINTER AND DECORATOR
External 7.00 01-Jun-19 07-Jun-19 External
Internal 15.00 19-Jun-19 03-Jul-19 Internal
Balance work moniter-2.3.5.6 TILER 10.00 19-May-19 28-May-19 28-May-19, Balance work moniter-2.3.5.6 TILER
Floor tiles 10.00 19-May-19 28-May-19 Floor tiles
Wall tile s 7.00 19-May-19 25-May-19 Wall tiles
Balance work moniter-2.3.6 FORTH FLOOR 96.00 01-Apr-19 18-Jul-19 18-Jul-19, Balance work moniter-2.3.6 FORTH FLOOR
ALUMINUM WORKER 15.00 12-Jun-19 26-Jun-19 ALUMINUM WORKER
BLOCK LAYER 16.00 01-Apr-19 29-Apr-19 BLOCK LAYER
DRAIN LAYER 5.00 24-May-19 28-May-19 DRAIN LAYER
MISCELLANEOUS WORK 3.00 13-May-19 15-May-19 MISCELLANEOUS WORK
PAVER 7.00 19-May-19 25-May-19 PAVER
PLUMBER 7.00 19-May-19* 25-May-19 PLUMBER
SANITARY FITTINGS 4.00 19-Jun-19 22-Jun-19 SANITARY FITTINGS
Balance work moniter-2.3.6.5 ELECTRICAL WORKS 39.00 19-May-19 26-Jun-19 26-Jun-19, Balance work moniter-2.3.6.5 ELECTRICAL WORKS
Electrical fittings 7.00 20-Jun-19 26-Jun-19 Electrical fittings
Electrical wiring 7.00 19-May-19 25-May-19 Electrical wiring
Balance work moniter-2.3.6.4 PLASTERER 55.00 07-May-19 30-Jun-19 30-Jun-19, Balance work moniter-2.3.6.4 PLASTERER
External 15.00 07-May-19 21-May-19 External
Internal 15.00 16-Jun-19 30-Jun-19 Internal
Balance work moniter-2.3.6.3 PAINTER AND DECORATOR 61.00 19-May-19 18-Jul-19 18-Jul-19, Balance work moniter-2.3.6.3 PAINTER AND DEC
External 10.00 19-May-19 28-May-19 External
Internal 15.00 04-Jul-19 18-Jul-19 Internal
Balance work moniter-2.3.6.6 TILER 18.00 26-May-19 12-Jun-19 12-Jun-19, Balance work moniter-2.3.6.6 TILER
Floor tiles 15.00 29-May-19 12-Jun-19 Floor tiles
Wall tile s 7.00 26-May-19 01-Jun-19 Wall tile s
Balance work moniter-2.3.7 FIFTH FLOOR 77.00 01-Apr-19 29-Jun-19 29-Jun-19, Balance work moniter-2.3.7 FIFTH FLOOR
BLOCK LAYER 7.00 23-Apr-19 29-Apr-19 BLOCK LAYER
CONCRETE 2.00 03-Apr-19 04-Apr-19 CONCRETE
FORM WORK 1.00 02-Apr-19 02-Apr-19 FORM WORK
MISCELLANEOUS WORK 3.00 16-May-19* 18-May-19 MISCELLANEOUS WORK
PAVER 7.00 26-May-19 01-Jun-19 PAVER
REINFORCEMENT 1.00 01-Apr-19 01-Apr-19 REINFORCEMENT
Balance work moniter-2.3.7.5 ELECTRICAL WORKS 35.00 26-May-19 29-Jun-19 29-Jun-19, Balance work moniter-2.3.7.5 ELECTRICAL WORKS
Electrical fittings 3.00 27-Jun-19 29-Jun-19 Electrical fittings
Electrical wiring 3.00 26-May-19 28-May-19 Electrical wiring
Balance work moniter-2.3.7.4 PLASTERER 7.00 30-Apr-19 06-May-19 06-May-19, Balance work moniter-2.3.7.4 PLASTERER
External 7.00 30-Apr-19 06-May-19 External
Balance work moniter-2.3.7.3 PAINTER AND DECORATOR 5.00 07-May-19 11-May-19 11-May-19, Balance work moniter-2.3.7.3 PAINTER AND DECORATOR
External 5.00 07-May-19 11-May-19 External
Balance work moniter-2.3.8 ROOF 33.00 01-Apr-19 16-May-19 16-May-19, Balance work moniter-2.3.8 ROOF
CEILING WORKS 10.00 05-May-19* 14-May-19 CEILING WORKS
ROOF PLUMBER FIRST FLOOR 3.00 14-May-19 16-May-19 ROOF PLUMBER FIRST FLOOR
ROOF PLUMBER FORTH FLOOR 3.00 05-May-19 07-May-19 ROOF PLUMBER FORTH FLOOR
ROOF PLUMBER SECOND FLOOR 3.00 11-May-19 13-May-19 ROOF PLUMBER SECOND FLOOR
ROOF PLUMBER THIRD FLOOR 3.00 08-May-19 10-May-19 ROOF PLUMBER THIRD FLOOR
ROOF WORK 21.00 01-Apr-19 04-May-19 ROOF WORK
TINKER 3.00 05-May-19 07-May-19 TINKER
Balance work moniter-2.4 WING 4 97.00 01-Apr-19 19-Jul-19 19-Jul-19, Balance work moniter-2.4 WING 4

Balance work moniter-2.4.4 GROUND FLOOR 8.00 01-Apr-19 08-Apr-19 08-Apr-19, Balance work moniter-2.4.4 GROUND FLOOR
Balance work moniter-2.4.4.5 ELECTRICAL WORKS 8.00 01-Apr-19 08-Apr-19 08-Apr-19, Balance work moniter-2.4.4.5 ELECTRICAL WORKS
Electrical fittings 7.00 02-Apr-19* 08-Apr-19 Electrical fittings
Electrical wiring 7.00 01-Apr-19 07-Apr-19 Electrical wiring
Balance work moniter-2.4.3 FIRST FLOOR 97.00 01-Apr-19 19-Jul-19 19-Jul-19, Balance work moniter-2.4.3 FIRST FLOOR

Actual Work Critical Remaining Work Summary Page 5 of 7 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
CONSTRUCTION OF BUILDING TO PROVIDE ACCOMMODATION FACILITIES FOR PUBLIC OFFICERS Classic Schedule Layout 24-Apr-19 15:56
Activity Name Original Duration Start Finish Qtr 2, 2019 Qtr 3, 2019
Mar Apr May Jun Jul Aug
BLOCK LAYER 7.00 01-Apr-19 07-Apr-19 BLOCK LAYER
MISCELLANEOUS WORK 3.00 23-Apr-19* 25-Apr-19 MISCELLANEOUS WORK
Balance work moniter-2.4.3.5 ELECTRICAL WORKS 16.00 08-Apr-19 06-May-19 06-May-19, Balance work moniter-2.4.3.5 ELECTRICAL W ORKS
Electrical fittings 7.00 30-Apr-19 06-May-19 Electrical fittings
Electrical wiring 7.00 08-Apr-19 27-Apr-19 Electrical wiring
Balance work moniter-2.4.3.4 PLASTERER 86.00 23-Apr-19 17-Jul-19 17-Jul-19, Balance work moniter-2.4.3.4 PLASTERER
External 7.00 11-Jul-19 17-Jul-19 External
Internal 7.00 23-Apr-19 29-Apr-19 Internal
Balance work moniter-2.4.3.6 TILER 12.00 06-Apr-19 30-Apr-19 30-Apr-19, Balance work moniter-2.4.3.6 TILER
Floor tiles 12.00 06-Apr-19* 30-Apr-19 Floor tiles
Balance work moniter-2.4.3.3 PAINTER AND DECORATOR 86.00 25-Apr-19 19-Jul-19 19-Jul-19, Balance work moniter-2.4.3.3 PAINTER AND DE
External 7.00 13-Jul-19 19-Jul-19 External
Internal 10.00 25-Apr-19 04-May-19 Internal
Balance work moniter-2.4.1 SECOND FLOOR 95.00 01-Apr-19 17-Jul-19 17-Jul-19, Balance work moniter-2.4.1 SECOND FLOOR
BLOCK LAYER 7.00 01-Apr-19 07-Apr-19 BLOCK LAYER
MISCELLANEOUS WORK 3.00 26-Apr-19 28-Apr-19 MISCELLANEOUS WORK
Balance work moniter-2.4.1.5 ELECTRICAL WORKS 16.00 28-Apr-19 13-May-19 13-May-19, Balance work moniter-2.4.1.5 ELECTRICAL W ORKS
Electrical fittings 7.00 07-May-19 13-May-19 Electrical fittings
Electrical wiring 7.00 28-Apr-19 04-May-19 Electrical wiring
Balance work moniter-2.4.1.4 PLASTERER 86.00 03-Apr-19 10-Jul-19 10-Jul-19, Balance work moniter-2.4.1.4 PLASTERER
External 7.00 04-Jul-19 10-Jul-19 External
Internal 7.00 03-Apr-19 09-Apr-19 Internal
Balance work moniter-2.4.1.1 PAINTER AND DECORATOR 74.00 05-May-19 17-Jul-19 17-Jul-19, Balance work moniter-2.4.1.1 PAINTER AND DEC
External 7.00 11-Jul-19 17-Jul-19 External
Internal 10.00 05-May-19 14-May-19 Internal
Balance work moniter-2.4.1.6 TILER 12.00 01-May-19 12-May-19 12-May-19, Balance work moniter-2.4.1.6 TILER
Floor tiles 12.00 01-May-19* 12-May-19 Floor tiles
Balance work moniter-2.4.5 THIRD FLOOR 88.00 01-Apr-19 10-Jul-19 10-Jul-19, Balance work moniter-2.4.5 THIRD FLOOR
BLOCK LAYER 7.00 17-May-19 23-May-19 BLOCK LAYER
MISCELLANEOUS WORK 3.00 26-May-19 28-May-19 MISCELLANEOUS WORK
Balance work moniter-2.4.5.2 REINFORCEMENT 31.00 01-Apr-19 14-May-19 14-May-19, Balance work moniter-2.4.5.2 REINFORCEMENT
For Beams & Slabs 7.00 29-Apr-19 05-May-19 For Beams & Slabs
For Column Shafts 2.00 01-Apr-19 02-Apr-19 For Column Shafts
For Stair Cases 5.00 10-May-19 14-May-19 For Stair Cases
Balance work moniter-2.4.5.10 FORMWORK 23.00 04-Apr-19 09-May-19 09-May-19, Balance work moniter-2.4.5.10 FORMWORK
For Beams & Slabs 7.00 25-Apr-19 01-May-19 For Beams & Slabs
For Column Shafts 2.00 04-Apr-19 05-Apr-19 For Column Shafts
For Stair Cases 3.00 07-May-19 09-May-19 For Stair Cases
Balance work moniter-2.4.5.1 CONCRETER 26.00 08-Apr-19 16-May-19 16-May-19, Balance work moniter-2.4.5.1 CONCRETER
For Beams & Slabs 1.00 06-May-19 06-May-19 For Beams & Slabs
For Column Shafts 1.00 08-Apr-19 08-Apr-19 For Column Shafts
For Stair Cases 2.00 15-May-19 16-May-19 For Stair Cases
Balance work moniter-2.4.5.5 ELECTRICAL WORKS 9.00 22-May-19 30-May-19 30-May-19, Balance work moniter-2.4.5.5 ELECTRICAL W ORKS
Electrical fittings 7.00 24-May-19* 30-May-19 Electrical fittings
Electrical wiring 7.00 22-May-19 28-May-19 Electrical wiring
Balance work moniter-2.4.5.4 PLASTERER 45.00 20-May-19 03-Jul-19 03-Jul-19, Balance work moniter-2.4.5.4 PLASTERER
External 5.00 29-Jun-19 03-Jul-19 External
Internal 7.00 20-May-19 26-May-19 Internal
Balance work moniter-2.4.5.3 PAINTER AND DECORATOR 50.00 22-May-19 10-Jul-19 10-Jul-19, Balance work moniter-2.4.5.3 PAINTER AND DECORATOR
External 7.00 04-Jul-19 10-Jul-19 External
Internal 10.00 22-May-19 31-May-19 Internal
Balance work moniter-2.4.5.6 TILER 12.00 22-May-19 02-Jun-19 02-Jun-19, Balance work moniter-2.4.5.6 TILER
Floor tiles 12.00 22-May-19* 02-Jun-19 Floor tiles
Balance work moniter-2.4.6 FORTH FLOOR 81.00 01-Apr-19 03-Jul-19 03-Jul-19, Balance work moniter-2.4.6 FORTH FLOOR
BLOCK LAYER 7.00 09-Jun-19 15-Jun-19 BLOCK LAYER
MISCELLANEOUS WORK 3.00 18-Jun-19 20-Jun-19 MISCELLANEOUS WORK
Balance work moniter-2.4.6.2 REINFORCEMENT 41.00 09-May-19 18-Jun-19 18-Jun-19, Balance work moniter-2.4.6.2 REINFORCEMENT
For Beams & Slabs 7.00 01-Jun-19 07-Jun-19 For Beams & Slabs
For Column Shafts 5.00 09-May-19 13-May-19 For Column Shafts
For Stair Cases 5.00 14-Jun-19 18-Jun-19 For Stair Cases
Balance work moniter-2.4.6.10 FORMWORK 33.00 12-May-19 13-Jun-19 13-Jun-19, Balance work moniter-2.4.6.10 FORMWORK
For Beams & Slabs 12.00 23-May-19 03-Jun-19 For Beams & Slabs
For Column Shafts 5.00 12-May-19 16-May-19 For Column Shafts
For Stair Cases 5.00 09-Jun-19 13-Jun-19 For Stair Cases
Balance work moniter-2.4.6.1 CONCRETER 33.00 19-May-19 20-Jun-19 20-Jun-19, Balance work moniter-2.4.6.1 CONCRETER
For Beams & Slabs 1.00 08-Jun-19 08-Jun-19 For Beams & Slabs
For Column Shafts 5.00 19-May-19 23-May-19 For Column Shafts
For Stair Cases 2.00 19-Jun-19 20-Jun-19 For Stair Cases
Balance work moniter-2.4.6.5 ELECTRICAL WORKS 9.00 14-Jun-19 22-Jun-19 22-Jun-19, Balance work moniter-2.4.6.5 ELECTRICAL WORKS

Actual Work Critical Remaining Work Summary Page 6 of 7 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
CONSTRUCTION OF BUILDING TO PROVIDE ACCOMMODATION FACILITIES FOR PUBLIC OFFICERS Classic Schedule Layout 24-Apr-19 15:56
Activity Name Original Duration Start Finish Qtr 2, 2019 Qtr 3, 2019
Mar Apr May Jun Jul Aug
Electrical fittings 7.00 16-Jun-19 22-Jun-19 Electrical fittings
Electrical wiring 7.00 14-Jun-19 20-Jun-19 Electrical wiring
Balance work moniter-2.4.6.4 PLASTERER 76.00 01-Apr-19 28-Jun-19 28-Jun-19, Balance work moniter-2.4.6.4 PLASTERER
External 6.00 23-Jun-19 28-Jun-19 External
Internal 7.00 01-Apr-19 07-Apr-19 Internal
Balance work moniter-2.4.6.3 PAINTER AND DECORATOR 33.00 01-Jun-19 03-Jul-19 03-Jul-19, Balance work moniter-2.4.6.3 PAINTER AND DECORATOR
External 7.00 27-Jun-19 03-Jul-19 External
Internal 10.00 01-Jun-19 10-Jun-19 Internal
Balance work moniter-2.4.6.6 TILER 12.00 11-Jun-19 22-Jun-19 22-Jun-19, Balance work moniter-2.4.6.6 TILER
Floor tiles 12.00 11-Jun-19 22-Jun-19 Floor tiles
Balance work moniter-2.4.7 FIFTH FLOOR 22.00 09-Jun-19 30-Jun-19 30-Jun-19, Balance work moniter-2.4.7 FIFTH FLOOR
BLOCK LAYER 5.00 14-Jun-19 18-Jun-19 BLOCK LAYER
CONCRETE 3.00 11-Jun-19 13-Jun-19 CONCRETE
FORM WORK 2.00 09-Jun-19 10-Jun-19 FORM WORK
MISCELLANEOUS WORK 3.00 21-Jun-19 23-Jun-19 MISCELLANEOUS WORK
PAVER 10.00 19-Jun-19 28-Jun-19 PAVER
Balance work moniter-2.4.7.5 ELECTRICAL WORKS 9.00 19-Jun-19 27-Jun-19 27-Jun-19, Balance work moniter-2.4.7.5 ELECTRICAL WORKS
Electrical fittings 7.00 21-Jun-19 27-Jun-19 Electrical fittings
Electrical wiring 7.00 19-Jun-19 25-Jun-19 Electrical wiring
Balance work moniter-2.4.7.4 PLASTERER 6.00 17-Jun-19 22-Jun-19 22-Jun-19, Balance work moniter-2.4.7.4 PLASTERER
External 6.00 17-Jun-19 22-Jun-19 External
Balance work moniter-2.4.7.3 PAINTER AND DECORATOR 5.00 22-Jun-19 26-Jun-19 26-Jun-19, Balance work moniter-2.4.7.3 PAINTER AND DECORATOR
External 5.00 22-Jun-19 26-Jun-19 External
Balance work moniter-2.4.7.6 TILER 7.00 24-Jun-19 30-Jun-19 30-Jun-19, Balance work moniter-2.4.7.6 TILER
Floor tiles 7.00 24-Jun-19 30-Jun-19 Floor tiles
Balance work moniter-2.4.8 ROOF 12.00 14-Jun-19 25-Jun-19 25-Jun-19, Balance work moniter-2.4.8 ROOF
ROOF PLUMBER FIRST FLOOR 3.00 23-Jun-19 25-Jun-19 ROOF PLUMBER FIRST FLOOR
ROOF PLUMBER FORTH FLOOR 3.00 14-Jun-19 16-Jun-19 ROOF PLUMBER FORTH FLOOR
ROOF PLUMBER SECOND FLOOR 3.00 20-Jun-19 22-Jun-19 ROOF PLUMBER SECOND FLOOR
ROOF PLUMBER THIRD FLOOR 3.00 17-Jun-19 19-Jun-19 ROOF PLUMBER THIRD FLOOR
Balance work moniter-2.9 SITE HANDING OVER 0.00 31-Jul-19 31-Jul-19 31-Jul-19, Balance work moniter-2.9 SITE

Handing over the site 0.00 31-Jul-19 Handing over the site

Actual Work Critical Remaining Work Summary Page 7 of 7 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation

S-ar putea să vă placă și