CRONOGRAMA VALORIZADO DE EJECUCION DE OB

OBRA :
MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA I.E. Nº 1637 JESUS YIREH, NIVEL INICIAL DISTRITO DE TRUJILLO - PROVINCIA DE TRUJILLO - RE

CLIENTE : ALUMNO: DENIS DAVID BARRETO VASQUEZ


LUGAR : DISTRITO DE TRUJILLO - PROVINCIA DE TRUJILLO- REGION LA LIBERTAD

SETIEMBRE SETIEMBRE OCTUBRE OCTUBRE


PARTIDA 1era QUINCENA 2da QUINCENA 3era QUINCENA 4ta QUINCENA
01 15 16 30 01 15 16 31

I.E. Nº 1637 JESUS YIREH

1.00 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD, SEGURIDAD Y SALUD


1.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES 18,247.88 18,247.88
1.02 SEGURIDAD Y SALUD 1,150.00 1,150.00 1,150.00 1,150.00
2.00 ESTRUCTURAS
2.01 MOVIMIENTO DE TIERRAS 15,202.85 10,266.07
2.02 OBRAS DE CONCRETO SIMPLE 7,385.89 7,385.89 9,534.52
2.03 OBRAS DE CONCRETO ARMADO 34,481.85 34,481.85 121,628.74 121,628.74
2.04 ESTRUCTURA METALICA

3.00 ARQUITECTURA
3.01 MUROS Y TABIQUES DE ALBAÑILERIA 17,145.74 17,145.74
3.02 REVOQUES Y REVESTIMIENTOS 15,214.78
3.03 CIELORRASOS 6,245.13
3.04 PISOS Y PAVIMENTOS
3.05 ZOCALOS Y CONTRAZOCALOS
3.06 COBERTURAS
3.07 CARPINTERIA DE MADERA
3.08 CARPINTERIA METALICA
3.09 CERRAJERIA
3.10 VIDRIOS, CRISTALES Y SIMILARES
3.11 PINTURAS
3.12 VARIOS, LIMPIEZA Y JARDINERIA
3.13 MOBILIARIO

4.00 INSTALACIONES SANITARIAS


4.01 APARATOS SANITARIOS Y ACCESORIOS
4.02 SISTEMA DE AGUA FRIA 1,332.78 1,332.78
4.03 DESAGUE Y VENTILACION 884.38 884.38

5.00 INSTALACIONES ELECTRICAS Y MECANICAS


5.01 SALIDAS PARA ALUMBRADO, TOMACORRIENTES, FUERZA Y SEÑALES DEBILES
5.02 CANALIZACION, CONDUCTOS O TUBERIAS
5.03 ARTEFACTOS
5.04 CAJAS
5.05 TABLERO GENERAL Y DISTRIBUCION
5.06 CONEXIÓN A LA RED EXTERNA DE MEDIDORES
5.07 INSTALACION DEL SISTEMA PUESTA A TIERRA
5.08 VARIOS

COSTO DIRECTO 76,468.47 71,531.69 151,676.16 163,601.55

GASTOS GENERALES (10.00%) 7,646.85 7,153.17 15,167.62 16,360.16

UTILIDAD (5.00%) 3,823.42 3,576.58 7,583.81 8,180.08

SUB TOTAL 87,938.74 82,261.44 174,427.58 188,141.78

I.G.V. 18.00 % 15,828.97 14,807.06 31,396.97 33,865.52

PRESUPUESTO DE LA OBRA 103,767.71 97,068.50 205,824.55 222,007.30

AVANCE PARCIAL ( % ) 10.60 9.92 21.03 22.68


AVANCE ACUMULADO ( % ) 10.60 20.52 41.55 64.24

20.52 43.71
ON DE OBRA

TRUJILLO - REGION LA LIBERTAD

NOVIEMBRE NOVIEMBRE DICIEMBRE DICIEMBRE TOTAL


5ta QUINCENA 6ta QUINCENA 7ma QUINCENA 8va QUINCENA ( S/. )
01 15 16 30 01 15 15 31

36,495.76
1,150.00 1,150.00 1,150.00 1,150.00 9,200.00

25,468.92
24,306.30
312,221.18
24,865.56 24,865.56 49,731.12

25,457.45 59,748.93
15,214.78 15,214.78 45,644.34
6,245.13 8,572.17 8,572.17 29,634.60
14,574.87 4,752.17 19,327.04
2,739.45 2,739.45
3,478.31 3,478.31
4,873.56 4,873.56
3,880.75 3,880.75
1,876.40 1,876.40
2,154.27 2,154.27 4,308.54
4,711.41 4,711.41 9,422.82
2,478.64 2,478.64
18,437.54 4,323.22 4,323.22 4,323.22 31,407.20

4,837.21 4,837.21
1,332.78 3,998.34
884.38 2,653.14

4,459.42 4,459.42 6,976.17 15,895.01


4,830.84 4,830.84
6,976.17 6,976.17
639.74 639.74
1,278.36 1,278.36
746.70 746.70
1,243.67 1,243.67
1,874.97 1,874.97

98,047.04 75,314.29 46,009.57 38,569.24 721,218.01

9,804.70 7,531.43 4,600.96 3,856.92 72,121.80

4,902.35 3,765.71 2,300.48 1,928.46 36,060.90

112,754.10 86,611.43 52,911.01 44,354.63 829,400.72

20,295.74 15,590.06 9,523.98 7,983.83 149,292.13

133,049.83 102,201.49 62,434.99 52,338.46 978,692.85

13.59 10.44 6.38 5.35


77.83 88.27 94.65 100.00

24.04 11.73 100.00