(WATER COOLED )
No RECEIVING YES NO
01. Unit and components are inspected for shipping damage
02. Unit is checked for missing material
03. Check nameplate unit data so that it matches the sales order
requirement
WATER PIPING
01. Water circuit connection are connected (return/supply chilled
water)
02. Strainer installed ahead of condenser (Water in )
03. Pressure Gauge installed (water in and water out)
04 Pressure in ………..psi (kg/cm2)
Pressure out ………psi (kg/cm2)
05. Gate Valve installed (water in and water out)
06. Balancing Valve (Globe) installed (water out)
07. Thermometer installed (water in and water out)
08. Vibration Eleminator / Flexible connection installed
09. Flow switch or differential pressure switch installed (water out)
10. Air Vent installed (Water out )
12. Cooling tower, pump and standby pump is installed
ELECTRICAL
01. Main power supply available
02. Main power connected to the unit
03. All system control connected to control panel (refer to wiring)
04. Check phase of rotation with phase meter
1
2
8
7
4
5
R
TE T
WA TLE
OU 10
R
TE
WA LET 9
IN