Documente Academic
Documente Profesional
Documente Cultură
Project
Roger A. Farrell, SuperPower, Inc.
Ed Garcia, The BOC Group, Inc.
Albert Keri, American Electric Power
Randy Shaw, Sumitomo Electric U.S.A., Inc.
Fault Current
Limiting No Burden on system during normal operation
Load Impedance
Impedance
ZS
ZL
Normal Operation Environmental benefit and no SF6
ZFCL = 0
Fault Condition
Substation
AC
ZFCL = Z0 A
New
Zline Generator
Substation
MFCL
FCL B
Under fault conditions critical
current is exceeded and the
Addition of one
superconductor transitions to a SC Fault Current Limiter
resistive state, introducing avoids multiple
breaker upgrades when
current limiting impedance into adding new generation
Substation
the grid with a parallel inductor sources
C
R R Rm2
Shunt 22
Matrix Impedance
12
Assembly
L12 L22 Lm2
B C
Elements
R R R
1n 2n mn
L L L
1n 2n mn
Total Voltage = V1 + V2 + V3 +
2G SFCL – Mockup assembly components 1 2 3 4
12 elements, 40 cm long with 4 2G tapes in
parallel per element
8 7 6 5
12 elements connected in series
… + V12
2 sets of 6 shunt coils of 10 mΩ and 5 mΩ
9 10 11 12
Equivalent Circuit
Test Voltage and Current Ranges
Voltage range from 120 Vrms to 1200 Vrms
Fault current ranges from 3 kA peak to 100 kA peak
Device Short Circuit Tests
Start with the lowest fault current setup ( 5kArms at 480 Vrms) and lowest supply voltage
setting, 120 Vrms, and gradually step the voltage up to a maximum of 1200 Vrms
Repeat the above procedure with the 10 kArms and 15 kArms prospective fault currents
Record voltage and current waveforms
1 2 3 4
8 7 6 5
9 10 11 12
V12
Current [kA]
• Producing elements longer than 20 cm is a big challenge 10 400
[V]
0 300
• Using short elements increases number of parts – reduced -10 200
reliability, increased complexity & cost -20 100
• Bulk material with limited cooling surface area -30 0
-40 -100
• BSCCO tubes, length = 20 cm, Cross-sectional area = 5 15 25 35 45 55 65 75 85 95
1.20 cm2, Volume = 24 cm3 Time [ms]
Limited Fault Current Current through HTS Shunt Current Voltage across HTS
Voltage across
HTS elements
Current [kA]
10 3.0
• Overall mass of 2G < BSCCO for same current
[kV]
0 2.0
• Manufacturing longer elements or continuous conductors is -10 1.0
less challenging – significant reduction in connection losses
-20 0.0
• Larger cooling surface area – faster recovery
-30 -1.0
• 2G tape, length = 40 cm, Cross-sectional area ≈ 0.012 cm2, 0 20 40 60 80 100
Volume ≈ 0.48 cm3 Time [ms]
I_total_KEMA I_HTS Ish V_total_KEMA
Stage gate milestone - go/no go decision point 2G Project Schedule - Phase 1 (Alpha) 65 % of 2G dev effort
Operational Extension
* Schedule subject to revision pending further review by SuperPower, SEI, BOC, AEP and DOE
* Schedule subject to revision pending further review by SuperPower, SEI, BOC, AEP and DOE
ORNL • Specialized design and testing support for high voltage matrix components
in a cryogenic environment
• Cryogenic consulting
LANL • Investigate methods to incorporate a heat sink and improve surface area of
2G conductor
• Assist SuperPower by testing 2G elements
• Support matrix testing and conceptual designs