Sunteți pe pagina 1din 139

BASIC RATES Labour

Code Description Unit


00100 Bandhani per Day
00101 Bhisti per Day
00102 Blacksmith 1 st class per Day
00103 Blacksmith 2nd class per Day
00111 Carpenter 1st class per Day
00112 Carpenter 2nd class per Day
00113 Chowkidar per Day
00114 Beldar per Day
00115 Coolie per Day
00116 Fitter (grade 1) per Day
00117 Assistant Fitter or 2nd class Fitter per Day
00119 Glazier per Day
00122 Mason (for plaster of paris work) 1st class per Day
00123 Mason (brick layer) 1st class per Day
00124 Mason (brick layer) 2nd class per Day
00125 Mason (for plain stone work) 2nd class per Day
00126 Mason (for ornamental stone work) 1st class per Day
00127 Driver for (Road roller, concrete mixer, Trucks etc.) per Day
00128 Mate per Day
00129 Sewer man per Day
00130 Mistry per Day
00131 Painter per Day
00132 Rock Excavator per Day
00133 Rock Breaker per Day
00134 Rock Hole Driller per Day
00135 Stone Chiseller per Day
00138 Sprayer (for bitumen, tar etc.) per Day
00139 Skilled Beldar (for floor rubbing etc.) per Day
00141 White Washer per Day
00154 Nozzel man/ gun man per Day
00155 Mason (average) per Day
00156 Carpenter (average) pee Day
00157 Operator (Pile/ Special machine) per Day
00159 Skilled torch operator for laying tack per Day
00160 Technician per Day
00161 Helper (Technician) per Day
00162 Labour for fabrication of uPVC extruded casement/ sliding windows
and doors including drilling holes, fixing of fittings & hardwares, hire
charges of drill machine and electricity charges etc. per Day
00163 Labour for installation of uPVC extruded casement/ sliding windows
and doors including scaffolding per Day
00164 Security guard without gun (8 hours shift duty per day) per Day
00165 Security guard with gun (8 hours shift duty per day) per Day
Rate
617
617
738
679
738
679
558
558
558
738
679
679
738
738
679
679
738
738
617
558
738
679
558
558
558
617
617
617
617
738
709
709
738
738
775
558

485

430
617
679
Item No:-1
Dismantlling the existing stone masonry including sorting out and satacking the useful materials and
removing the debries and making good the damage etc. complete as directed.
Rate Ananlysis for 1 CM work.
1(a) In lime mortar.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 1.10 Each. 350.00 385.00
Total cost for 1.0 m3 Rs. :- 385.00
Add 2% for Sundries & T & P 7.70
Add 8% C.P & O.H. charges 30.80
Total cost for 1.0 m3 Rs. :- 423.50
Add. 1% for Labour cess 4.24
Total cost for 1.0 m3 Rs. :- 427.70
Say Rs. 428.00
1(b) In cement mortar
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 1.30 Each. 350.00 455.00
3
Total cost for 1.0 m Rs. :- 455.00
Add 2% for Sundries & T & P 9.10
Add 8% C.P & O.H. charges 36.40
Total cost for 1.0 m3 Rs. :- 500.50
Add. 1% for Labour cess 5.01
Total cost for 1.0 m3 Rs. :- 505.50
Say Rs. 506.00
Item No:-2
Dismentalling the existing brick masonry including sorting out and satacking the useful materials and
removing the debries and making good the damage etc. complete as directed.
Rate Ananlysis for 1 CM work.
2(a) Inlime mortar.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 1.10 Each. 350.00 385.00
Total cost for 1.0 m3 Rs. :- 385.00
Add 2% for Sundries & T & P 7.70
Add 8% C.P & O.H. charges 30.80
Total cost for 1.0 m3 Rs. :- 423.50
Add. 1% for Labour cess 4.24
Total cost for 1.0 m3 Rs. :- 427.70
Say Rs. 428.00
2(b) In cement mortar
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 1.30 Each. 350.00 455.00

31 file:///conversion/tmp/scratch/446077116.xls Dismantling
Total cost for 1.0 m3 Rs. :- 455.00
Add 2% for Sundries & T & P 9.10
Add 8% C.P & O.H. charges 36.40
Total cost for 1.0 m3 Rs. :- 500.50
Add. 1% for Labour cess 5.01
Total cost for 1.0 m3 Rs. :- 505.50
Say Rs. 506.00
2(c) In mud mortar
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.80 Each. 350.00 280.00
Total cost for 1.0 m3 Rs. :- 280.00
Add 2% for Sundries & T & P 5.60
Add 15% C.P & O.H. charges 42.00
Total cost for 1.0 m3 Rs. :- 327.60
Add. 1% for Labour cess 3.28
Total cost for 1.0 m3 Rs. :- 330.90
Say Rs. 331.00
Item No:A-3
Dismentalling the existing foundation concrete including the dismentalled stuff including sorting out
and satacking the useful materials andrenoving the debries and making good the damage etc.
complete as directed.
Rate Ananlysis for 1 CM work.
3(a) In lime concrete.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 1.50 Each. 350.00 525.00
3
Total cost for 1.0 m Rs. :- 525.00
Add 2% for Sundries & T & P 10.50
Add 8% C.P & O.H. charges 42.00
Total cost for 1.0 m3 Rs. :- 577.50
Add. 1% for Labour cess 5.78
Total cost for 1.0 m3 Rs. :- 583.30
Say Rs. 583.00
3(b) In cement concrete.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 2.00 Each. 350.00 700.00
3
Total cost for 1.0 m Rs. :- 700.00
Add 2% for Sundries & T & P 14.00
Add 8% C.P & O.H. charges 56.00
Total cost for 1.0 m3 Rs. :- 770.00
Add. 1% for Labour cess 7.70
Total cost for 1.0 m3 Rs. :- 777.70
Say Rs. 778.00
3(c) R.C.C for super structure.
Sr. Rate Amount
Description Qty Unit

31 file:///conversion/tmp/scratch/446077116.xls Dismantling
Sr.
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 2.25 Each. 350.00 787.50
3
Total cost for 1.0 m Rs. :- 787.50
Add 2% for Sundries & T & P 15.75
Add 8% C.P & O.H. charges 63.00
Total cost for 1.0 m3 Rs. :- 866.25
Add. 1% for Labour cess 8.66
Total cost for 1.0 m3 Rs. :- 874.90
Say Rs. 875.00
Item No.:-4
Dismentalling the R.C.C. work & disposing off the stuff including stacking of the useful
materials etc.complete as directed.
Rate Ananlysis for 1 CM work.
4(a) Light reinforcement. (Main bar up to 16 mm dia.)
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 3.00 Each. 350.00 1050.00
Total cost for 1.0 m3 Rs. :- 1050.00
Add 2% for Sundries & T & P 21.00
Add 8% C.P & O.H. charges 84.00
Total cost for 1.0 m3 Rs. :- 1155.00
Add. 1% for Labour cess 11.55
Total cost for 1.0 m3 Rs. :- 1166.60
Say Rs. 1167.00
4(b) Heavy reinforcement. (Main bar above 16 mm dia.)
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 3.50 Each. 350.00 1225.00
Total cost for 1.0 m3 Rs. :- 1225.00
Add 2% for Sundries & T & P 24.50
Add 8% C.P & O.H. charges 98.00
Total cost for 1.0 m3 Rs. :- 1347.50
Add. 1% for Labour cess 13.48
Total cost for 1.0 m3 Rs. :- 1361.00
Say Rs. 1361.00
Item No.:-5(A)
Dismentalling the existing R.C.C.pipes including sorting out and stacking of the useful materials of the
following diameter including refilling the tranches etc. complete as directed. (NP-2 pipes)
Rate Ananlysis for 1 M work.
5(A)(a):- 225 mm to 400 mm dia.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.60 Each. 350.00 210.00
Total cost for 1.0 m Rs. :- 210.00
Add 2% for Sundries & T & P 4.20
Add 15% C.P & O.H. charges 31.50

31 file:///conversion/tmp/scratch/446077116.xls Dismantling
Total cost for 1.0 m Rs. :- 245.70
Add. 1% for Labour cess 2.46
Total cost for 1.0 m3 Rs. :- 248.20
Say Rs. 248.00
5(A)(b):- 450 mm to 600 mm dia.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 1.00 Each. 350.00 350.00
Total cost for 1.0 m Rs. :- 350.00
Add 2% for Sundries & T & P 7.00
Add 15% C.P & O.H. charges 52.50
Total cost for 1.0 m Rs. :- 409.50
Add. 1% for Labour cess 4.10
Total cost for 1.0 m3 Rs. :- 413.60

5(A)(c):- 650 mm to 900 mm dia.


Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 1.50 Each. 350.00 525.00
Total cost for 1.0 m Rs. :- 525.00
Add 2% for Sundries & T & P 10.50
Add 15% C.P & O.H. charges 78.75
Total cost for 1.0 m Rs. :- 614.25
Add. 1% for Labour cess 6.14
Total cost for 1.0 m3 Rs. :- 620.40
5(A)(d):- 1000 mm to 1200 mm dia.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 2.20 Each. 350.00 770.00
Total cost for 1.0 m Rs. :- 770.00
Add 2% for Sundries & T & P 15.40
Add 15% C.P & O.H. charges 115.50
Total cost for 1.0 m Rs. :- 900.90
Add. 1% for Labour cess 9.01
Total cost for 1.0 m3 Rs. :- 909.90
5(A)(e):- Above 1200 mm dia.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 2.50 Each. 350.00 875.00
Total cost for 1.0 m Rs. :- 875.00
Add 2% for Sundries & T & P 17.50
Add 15% C.P & O.H. charges 131.25
Total cost for 1.0 m Rs. :- 1023.75
Add. 1% for Labour cess 10.24
Total cost for 1.0 m3 Rs. :- 1034.00
Item No.:- 5(B)
Dismentalling the existing I.R.S.pipes including sorting out and stacking of the useful materials of the

31 file:///conversion/tmp/scratch/446077116.xls Dismantling
following diameter including refilling the tranches etc. complete as directed. (NP-2 pipes)
Rate Ananlysis for 1 M work.
5(B)(a):- 450 mm to 600 mm dia.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 1.50 Each. 350.00 525.00
Total cost for 1.0 m Rs. :- 525.00
Add 2% for Sundries & T & P 10.50
Add 15% C.P & O.H. charges 78.75
Total cost for 1.0 m Rs. :- 614.25
Add. 1% for Labour cess 6.14
Total cost for 1.0 m3 Rs. :- 620.40

5(B)(b):- 650 mm to 900 mm dia.


Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 2.50 Each. 350.00 875.00
Total cost for 1.0 m Rs. :- 875.00
Add 2% for Sundries & T & P 17.50
Add 15% C.P & O.H. charges 131.25
Total cost for 1.0 m Rs. :- 1023.75
Add. 1% for Labour cess 10.24
Total cost for 1.0 m3 Rs. :- 1034.00
5(B)(c):- 1000 mm to 1600 mm dia.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 3.50 Each. 350.00 1225.00
Total cost for 1.0 m Rs. :- 1225.00
Add 2% for Sundries & T & P 24.50
Add 15% C.P & O.H. charges 183.75
Total cost for 1.0 m Rs. :- 1433.25
Add. 1% for Labour cess 14.33
Total cost for 1.0 m Rs. :- 1447.60
Item No. :- 6
Dismentalling the existing road surface including disposing off the dismentalled materials and stacking the
useful materials as directed.
Rate Ananlysis for 1 M2 work.
6(a) Cement concrete road.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.35 Each. 350.00 122.50
Total cost for 1.0 m2 Rs. :- 122.50
Add 2% for Sundries & T & P 2.45

31 file:///conversion/tmp/scratch/446077116.xls Dismantling
Add 15% C.P & O.H. charges 18.38
Total cost for 1.0 m Rs. :-
2
143.33
Add. 1% for Labour cess 1.43
Total cost for 1.0 m2 Rs. :- 144.80
6(b) Asphalt road.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.15 Each. 350.00 52.50
Total cost for 1.0 m Rs. :-
2
52.50
Add 2% for Sundries & T & P 1.05
Add 15% C.P & O.H. charges 7.88
Total cost for 1.0 m2 Rs. :- 61.43
Add. 1% for Labour cess 0.61
Total cost for 1.0 m2 Rs. :- 62.00

6(c) W.B.M Road.


Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.10 Each. 350.00 35.00
Total cost for 1.0 m Rs. :-
2
35.00
Add 2% for Sundries & T & P 0.70
Add 15% C.P & O.H. charges 5.25
Total cost for 1.0 m2 Rs. :- 40.95
Add. 1% for Labour cess 0.41
Total cost for 1.0 m2 Rs. :- 41.40
Item No. :- 7
Dismentalling the brick pitching including sorting out and stacking of the useful material on site including
removing the rabbish etc. complete as directed.
Rate Analysis for 1M2
7(a) 8 cm thick.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.10 Each. 350.00 35.00
Total cost for 1.0 m2 Rs. :- 35.00
Add 2% for Sundries & T & P 0.70
Add 15% C.P & O.H. charges 5.25
Total cost for 1.0 m2 Rs. :- 40.95
Add. 1% for Labour cess 0.41
Total cost for 1.0 m2 Rs. :- 41.40
7(b) 12 cm thick.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.12 Each. 350.00 42.00

31 file:///conversion/tmp/scratch/446077116.xls Dismantling
Total cost for 1.0 m2 Rs. :- 42.00
Add 2% for Sundries & T & P 0.84
Add 15% C.P & O.H. charges 6.30
Total cost for 1.0 m2 Rs. :- 49.14
Add. 1% for Labour cess 0.49
Total cost for 1.0 m2 Rs. :- 49.60
7(c) 23 cm thick.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.20 Each. 350.00 70.00
Total cost for 1.0 m2 Rs. :- 70.00
Add 2% for Sundries & T & P 1.40
Add 15% C.P & O.H. charges 10.50
Total cost for 1.0 m2 Rs. :- 81.90
Add. 1% for Labour cess 0.82
Total cost for 1.0 m2 Rs. :- 82.70

Item No. :- 8
Demolishing roofing including demolishing battens etc. including sorting out the useful materials and stacking
the different compnents seperately as and where directed.
Rate Analysis for 1M2
8(a) Manglore tiles roofing.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.20 Each. 350.00 70.00
Total cost for 1.0 m2 Rs. :- 70.00
Add 2% for Sundries & T & P 1.40
Add 15% C.P & O.H. charges 10.50
Total cost for 1.0 m2 Rs. :- 81.90
Add. 1% for Labour cess 0.82
Total cost for 1.0 m2 Rs. :- 82.70
8(b) Corrugated Iron Sheet.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.20 Each. 350.00 70.00
Total cost for 1.0 m2 Rs. :- 70.00
Add 2% for Sundries & T & P 1.40
Add 15% C.P & O.H. charges 10.50
Total cost for 1.0 m2 Rs. :- 81.90
Add. 1% for Labour cess 0.82
Total cost for 1.0 m2 Rs. :- 82.70
8(c) A. C. Sheet.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00

31 file:///conversion/tmp/scratch/446077116.xls Dismantling
(B) LABOUR:-
1 Labour 0.20 Each. 350.00 70.00
Total cost for 1.0 m Rs. :-
2
70.00
Add 2% for Sundries & T & P 1.40
Add 15% C.P & O.H. charges 10.50
Total cost for 1.0 m2 Rs. :- 81.90
Add. 1% for Labour cess 0.82
Total cost for 1.0 m2 Rs. :- 82.70
Item No. :- 9
Removing doors and windows including frame work from stone or brick masonry including carting them &
stacking as and wghere directed and making good the damages of the walls etc.
Rate Analysis for 1 No.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour. 0.25 Each. 350.00 87.50
2 Carpenter.(II-Class) 0.25 Each. 130.00 32.50
Total cost for 1.0 m2 Rs. :- 120.00
Add 2% for Sundries & T & P 2.40
Add 15% C.P & O.H. charges 18.00
Total cost for 1.0 m2 Rs. :- 140.40
Add. 1% for Labour cess 1.40
Total cost for 1.0 m2 Rs. :- 141.80

Item No. :- 10
Demolishing flooring including bedding removing the debries including sorting out materials seperately as and
where directed removing the rubbish etc. complete and making good the damages as directed.
Rate Analysis for 1 M2
10(a) Indian Patent stone.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.15 Each. 350.00 52.50
Total cost for 1.0 m2 Rs. :- 52.50
Add 2% for Sundries & T & P 1.05
Add 15% C.P & O.H. charges 7.88
Total cost for 1.0 m2 Rs. :- 61.43
Add. 1% for Labour cess 0.61
Total cost for 1.0 m2 Rs. :- 62.00
10(b) Brick paving.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.10 Each. 350.00 35.00
Total cost for 1.0 m Rs. :-
2
35.00
Add 2% for Sundries & T & P 0.70
Add 15% C.P & O.H. charges 5.25
Total cost for 1.0 m2 Rs. :- 40.95
Add. 1% for Labour cess 0.41
Total cost for 1.0 m2 Rs. :- 41.40
10(c) Stone paving.
Sr. Rate Amount
Description Qty Unit

31 file:///conversion/tmp/scratch/446077116.xls Dismantling
Sr.
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.15 Each. 350.00 52.50
Total cost for 1.0 m Rs. :-
2
52.50
Add 2% for Sundries & T & P 1.05
Add 15% C.P & O.H. charges 7.88
Total cost for 1.0 m2 Rs. :- 61.43
Add. 1% for Labour cess 0.61
Total cost for 1.0 m2 Rs. :- 62.00
10(d) Cement Tiles.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.10 Each. 350.00 35.00
Total cost for 1.0 m Rs. :-
2
35.00
Add 2% for Sundries & T & P 0.70
Add 15% C.P & O.H. charges 5.25
Total cost for 1.0 m2 Rs. :- 40.95
Add. 1% for Labour cess 0.41
Total cost for 1.0 m2 Rs. :- 41.40

Item No. :- 11(A)


Dismentalling the rubble pitching including sorting out and stacking of the useful materials on site including
removing the rubbish etc. complete as directed.
Rate Analysis for 1 M2
1 Pucca rubble pitching in cement or lime mortar.
11(A)(a):- 23 cm thick.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.30 Each. 350.00 105.00
Total cost for 1.0 m2 Rs. :- 105.00
Add 2% for Sundries & T & P 2.10
Add 15% C.P & O.H. charges 15.75
Total cost for 1.0 m2 Rs. :- 122.85
Add. 1% for Labour cess 1.23
Total cost for 1.0 m2 Rs. :- 124.10
11(A)(b):- 30 cm thick.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.40 Each. 350.00 140.00
Total cost for 1.0 m2 Rs. :- 140.00
Add 2% for Sundries & T & P 2.80
Add 15% C.P & O.H. charges 21.00
Total cost for 1.0 m2 Rs. :- 163.80
Add. 1% for Labour cess 1.64

31 file:///conversion/tmp/scratch/446077116.xls Dismantling
Total cost for 1.0 m2 Rs. :- 165.40
11(A)(c):- 45 cm thick.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.60 Each. 350.00 210.00
Total cost for 1.0 m Rs. :-
2
210.00
Add 2% for Sundries & T & P 4.20
Add 15% C.P & O.H. charges 31.50
Total cost for 1.0 m2 Rs. :- 245.70
Add. 1% for Labour cess 2.46
Total cost for 1.0 m2 Rs. :- 248.20
11(A)(d):- 60 cm thick.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.80 Each. 350.00 280.00
Total cost for 1.0 m2 Rs. :- 280.00
Add 2% for Sundries & T & P 5.60
Add 15% C.P & O.H. charges 42.00
Total cost for 1.0 m2 Rs. :- 327.60
Add. 1% for Labour cess 3.28
Total cost for 1.0 m2 Rs. :- 330.90
2 Dry Rubble pitching.

11(B)(a):- 23 cm thick.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.10 Each. 350.00 35.00
Total cost for 1.0 m Rs. :-
2
35.00
Add 2% for Sundries & T & P 0.70
Add 15% C.P & O.H. charges 5.25
Total cost for 1.0 m2 Rs. :- 40.95
Add. 1% for Labour cess 0.41
Total cost for 1.0 m2 Rs. :- 41.40
11(B)(b):- 30 cm thick.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.15 Each. 350.00 52.50
Total cost for 1.0 m Rs. :-
2
52.50
Add 2% for Sundries & T & P 1.05
Add 15% C.P & O.H. charges 7.88
Total cost for 1.0 m2 Rs. :- 61.43
Add. 1% for Labour cess 0.61
Total cost for 1.0 m2 Rs. :- 62.00
11(B)(c):- 45 cm thick.
Sr. Rate Amount
Description Qty Unit

31 file:///conversion/tmp/scratch/446077116.xls Dismantling
Sr.
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.20 Each. 350.00 70.00
Total cost for 1.0 m Rs. :-
2
70.00
Add 2% for Sundries & T & P 1.40
Add 15% C.P & O.H. charges 10.50
Total cost for 1.0 m2 Rs. :- 81.90
Add. 1% for Labour cess 0.82
Total cost for 1.0 m2 Rs. :- 82.70
11(B)(d):- 60 cm thick.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.30 Each. 350.00 105.00
Total cost for 1.0 m Rs. :-
2
105.00
Add 2% for Sundries & T & P 2.10
Add 15% C.P & O.H. charges 15.75
Total cost for 1.0 m2 Rs. :- 122.85
Add. 1% for Labour cess 1.23
Total cost for 1.0 m2 Rs. :- 124.10

Item No.:- 12
Scrapping out the old plaster & cleaning the surface including racking out the joints 20 mm deep etc. complete.
Rate Analysis for 1M2
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.10 Each. 350.00 35.00
Total cost for 1.0 m2 Rs. :- 35.00
Add 2% for Sundries & T & P 0.70
Add 15% C.P & O.H. charges 5.25
Total cost for 1.0 m2 Rs. :- 40.95
Add. 1% for Labour cess 0.41
Total cost for 1.0 m2 Rs. :- 41.40
Item No.:- 13
Scrapping the old white or colour wash including scaffolding etc. complete.
Rate Analysis for 1M2
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.04 Each. 350.00 14.00
Total cost for 1.0 m2 Rs. :- 14.00
Add 2% for Sundries & T & P 0.28

31 file:///conversion/tmp/scratch/446077116.xls Dismantling
Add 15% C.P & O.H. charges 2.10
Total cost for 1.0 m Rs. :-
2
16.38
Add. 1% for Labour cess 0.16
Total cost for 1.0 m2 Rs. :- 16.50
Item No.:- 14
Scrapping the old oil paint and preparing the surface etc. complete.
(a) Iron Work
Rate Analysis for 1M2
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.10 Each. 350.00 35.00
Total cost for 1.0 m Rs. :-
2
35.00
Add 2% for Sundries & T & P 0.70
Add 15% C.P & O.H. charges 5.25
Total cost for 1.0 m2 Rs. :- 40.95
Add. 1% for Labour cess 0.41
Total cost for 1.0 m2 Rs. :- 41.40
(b) Wood work.
Rate Analysis for 1M2
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.05 Each. 350.00 17.50
Total cost for 1.0 m Rs. :-
2
17.50
Add 2% for Sundries & T & P 0.35
Add 15% C.P & O.H. charges 2.63
Total cost for 1.0 m2 Rs. :- 20.48
Add. 1% for Labour cess 0.20
Total cost for 1.0 m2 Rs. :- 20.70

Item No.:- 15
Removing of exiting disturbed C.C.Block lining including opening of joints, stacking the same and
disposing of stuff as directed etc. complete with all leads and lifts.
Rate Analysis for 1M2
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.05 Each. 350.00 17.50
Total cost for 1.0 m Rs. :-
2
17.50
Add 2% for Sundries & T & P 0.35
Add 15% C.P & O.H. charges 2.63
Total cost for 1.0 m2 Rs. :- 20.48
Add. 1% for Labour cess 0.20
Total cost for 1.0 m2 Rs. :- 20.70
Item No.:- 16
Removing of exiting disturbed R.C.C.trough lining including opening of joints, stacking the same and
disposing of stuff as directed etc. complete with all leads and lifts.
Rate Analysis for 1M2
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
(A) MATERIALS:- 0.00 - 0.00 0.00

31 file:///conversion/tmp/scratch/446077116.xls Dismantling
(B) LABOUR:-
1 Labour 0.05 Each. 350.00 17.50
Total cost for 1.0 m Rs. :-
2
17.50
Add 2% for Sundries & T & P 0.35
Add 15% C.P & O.H. charges 2.63
Total cost for 1.0 m2 Rs. :- 20.48
Add. 1% for Labour cess 0.20
Total cost for 1.0 m2 Rs. :- 20.70
Item No.:- 17
Dismantiling / Removing old damaged structural steel including cutting, seperating and stacking or
depositing as directed etc. complete.
Rate Analysis for 1.0 kg.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1 Dismantiling / Removing old damaged structural steel 1.00 kg. 4.00 4.00
including cutting, seperating and stacking ordepositing as
directed etc. complete.
Add. 1% for Labour cess 0.04
Total cost for 1.0 Kg. Rs. :- Total:- 4.00

31 file:///conversion/tmp/scratch/446077116.xls Dismantling
31 file:///conversion/tmp/scratch/446077116.xls Dismantling
31 file:///conversion/tmp/scratch/446077116.xls Dismantling
31 file:///conversion/tmp/scratch/446077116.xls Dismantling
31 file:///conversion/tmp/scratch/446077116.xls Dismantling
31 file:///conversion/tmp/scratch/446077116.xls Dismantling
31 file:///conversion/tmp/scratch/446077116.xls Dismantling
31 file:///conversion/tmp/scratch/446077116.xls Dismantling
31 file:///conversion/tmp/scratch/446077116.xls Dismantling
31 file:///conversion/tmp/scratch/446077116.xls Dismantling
31 file:///conversion/tmp/scratch/446077116.xls Dismantling
31 file:///conversion/tmp/scratch/446077116.xls Dismantling
31 file:///conversion/tmp/scratch/446077116.xls Dismantling
31 file:///conversion/tmp/scratch/446077116.xls Dismantling
Item No:-1
Excavation for foundation in all sorts of soil including yellow, sandy, gravelly, soft and hard
murrum etc. in dry condition including depositing the excavated stuff in uniform layers in banks
or as and where directed etc. complete for lead upto 1 km and

(a) Above water table


I. Excavation and loading.
Excavation with poclane Ex. 280 model.
Bucket Capacity = 0.90 Cum.
OUTPUT OF BUCKET CAPACITY 0.96 CUM IS AVAILABLE IN CWC WORKING
GROUP REPORT TABLE(F) FOR OUTPUT OF 0.90CUM BUCKET CAPACITY
MULTIPLIED BY 0.94
Ideal production for 0.96 M B.C
3
= 161 Soil + 176 Sand
Ideal production for 0.90 M3 B.C = 151.34 Soil + 165 Sand
Average = 158.39 Cum.
Factors affecting the out put
1.Factor for depth of cut and and angle
of swing. = 0.98 (% of optimum depth= 80

Angle of swing.=90
2. Operating factor
(Excellent)(table C) = 0.92
3. Job management factor
(Excellent management
condition and good job
condition) (tableD) = 0.78
4. Bucket fill factor (table E) = 1.00
Out put per hour = 158.39 0.98 0.92 0.78 1.00
= 111.39 Cum/hours
Cost of excavation 2500.00 = 2500.00 / 111.39
(Annexure-1) = 22.44 Rs./Cum…….(A)
II. Transportation
Cost of transportion.
1. Dumper/Truck carriage capacity. = 10.00 M.Ton.
2. Density. 1.60 M.Ton./Cum.
3. Body capacity = 10/1.60 = 6.25 Cum.
CYCLE TIME
LOADING TIME = BODY CAPACITY/EXCAVATOR OUTPUT
= (6.25x60.00)/111.40 = 3.37 Min.
LOADED HAUL TIME
(Speed =45 KMPH) = (100x60)/45 = 1.33 Min.
UNLOADING, TURNING, DUMPING, & SPOTTING TIME = 3.30 Min.
(AS PER CWC W.G.R. P. NO.93)
EMPTY HAUL TIME = (1.00x60.00)/50 = 1.20 Min.
TOTAL CYCLE TIME = 9.20 Min.
TOTAL NO OF TRIPS PER WORKING HOUR OF 50 MIN.
= (50.00/9.20) = 5.43 TRIPS
OUTPUT OF TIPPER = 6.25 5.43 0.8
(with 80% effeciency) = 27.15 M3/HOUR
Hourly use rate of Dumper = (Hourly use rate/Output)
(As per Annex ) 750.00 = 750/27.15 = 27.62 Rs.(B)
Total cost of excavation
Loading, Unloading and
transportation=(A)+(B) = 22.44 27.62 = Rs. 50.07 (C)
Cost of breaking clods & spreading in uniform layars @ 20% = Rs. 4.49

72-A file:///conversion/tmp/scratch/446077116.xls Earth work Machine


of excavation cost.
Total = Rs. 54.56
Add for
Tools & Plant 1% = Rs. 0.55
Contractor profit & Over heads 10% = Rs. 8.18
Grand Total = Rs. 63.29
add 1% labour Cess = Rs. 0.63
Rate per Cum = Rs. 64.00
(a) Below water table
I. Excavation and loading.
Excavation with poclane Ex. 280 model.
Bucket Capacity = 0.90 Cum.
OUTPUT OF BUCKET CAPACITY 0.96 CUM IS AVAILABLE IN CWC WORKING
GROUP REPORT TABLE(F) FOR OUTPUT OF 0.90CUM BUCKET CAPACITY
MULTIPLIED BY 0.94
Ideal production for 0.96 M3 B.C = 161 Soil + 176 Sand
Ideal production for 0.90 M B.C
3
= 151.34 Soil + 165 Sand
Average = 158.39 Cum.
Factors affecting the out put
1.Factor for depth of cut and and
angle of swing. = 0.98 (% of optimum dept 80
Angle of swing.=90
2. Operating factor
(Excellent)(table C) = 0.92
3. Job management factor
(Excellent management
condition and good job
condition) (tableD) = 0.78
4. Bucket fill factor (table E) = 1.00
Out put per hour = 158.39 0.98 0.92 0.78 1.00
= 111.39 Cum/hours (Annexure-1)
Cost of excavation = 1508/111.39
1508.00 = 12.45 Rs./Cum…….(A)
II. Transportation
Cost of transportion.
1. Dumper carriage capacity. = 10.00 M.Ton.
2. Density. 1.7 M.Ton./Cum.
3. Body capacity = 10/1.7 = 5.88235 Cum.
CYCLE TIME
LOADING TIME = BODY CAPACITY/EXCAVATOR OUTPUT
= (5.88x60.00)/111.40 = 3.17 Min.
LOADED HAUL TIME
(Speed =45 KMPH) = (100x60)/45 = 1.33 Min.
UNLOADING, TURNING, DUMPING, & SPOTTING TIME = 3.30 Min.
(AS PER CWC W.G.R. P. NO.93)
EMPTY HAUL TIME = (1.00x60.00)/50 = 1.20 Min.
TOTAL CYCLE TIME = 9.00 Min.
TOTAL NO OF TRIPS PER WORKING HOUR OF 50 MIN.
= (50.00/9.00) = 5.55 TRIPS
OUTPUT OF TIPPER = 5.88 5.55 0.8
(with 80% effeciency) = 26.12 M3/HOUR
Hourly use rate of Dumper = (Hourly use rate/Output)
(As per Annex-2) 678.00 = 678.00/26.12 = 25.9595 Rs.(B)
Total cost of excavation

72-A file:///conversion/tmp/scratch/446077116.xls Earth work Machine


Loading, Unloading and
transportation=(A)+(B) = 12.45 + 25.96 = Rs. 38.41 (C)
Cost of breaking clods & spreading in uniform layars @ 20% = Rs. 2.49
of excavation cost.
Add cost of dewatering @ 10% of cost of excavation. = Rs. 1.25
Total = Rs. 42.15
Add for
Tools & Plant 1% = Rs. 0.42
Contractor profit & Over heads 15% = Rs. 6.32
Grand Total = Rs. 48.89
Add. 1% labour Cess = Rs. 0.49
Rate per Cum say = Rs. 49.40
Item No.:-2
Excavation for foundation in SOFT ROCK including depositing the excavated
stuff as and where directed etc. complete for lead upto 1 km and all lift.
(a) Above water table
I. Excavation and loading.
Excavation with poclane Ex. 280 model.
Bucket Capacity = 0.90 Cum.
OUTPUT OF BUCKET CAPACITY 0.96 CUM IS AVAILABLE IN CWC WORKING
GROUP REPORT TABLE(F) FOR OUTPUT OF 0.90CUM BUCKET CAPACITY
MULTIPLIED BY 0.94
Ideal production for 0.96 M3 B.C = 99 (common excavation in rock & roots)
Ideal production for 0.90 M3 B.C = 93.06 Soil
Average = 93.06 Cum.
Factors affecting the out put
1.Factor for depth of cut and and
angle of swing. = 0.98 (% of optimum dept 80
Angle of swing.=90
2. Operating factor
(Excellent)(table C) = 0.92
3. Job management factor
(Excellent management
condition and good job
condition) (tableD) = 0.78
4. Bucket fill factor (table E) = 0.75
Out put per hour = 93.06 0.98 0.92 0.78 0.75
= 49.08 Cum/hours (Annexure-1)
Cost of excavation = 1508/111.39
(As per Annex-1) 1508.00 = 30.72 Rs./Cum…….(A)
II. Transportation
Cost of transportion.
1. Dumper carriage capacity. = 10.00 M.Ton.
2. Density. 2.1 M.Ton./Cum.
3. Body capacity = 10/2.1 = 4.76 Cum.
CYCLE TIME
LOADING TIME = BODY CAPACITY/EXCAVATOR OUTPUT
= (4.76x60.00)/49.08 = 5.82 Min.
LOADED HAUL TIME
(Speed =45 KMPH) = (100x60)/45 = 1.33 Min.
UNLOADING, TURNING, DUMPING, & SPOTTING TIME = 3.30 Min.
(AS PER CWC W.G.R. P. NO.93)
EMPTY HAUL TIME = (1.00x60.00)/50 = 1.20 Min.
TOTAL CYCLE TIME = 11.65 Min.

72-A file:///conversion/tmp/scratch/446077116.xls Earth work Machine


TOTAL NO OF TRIPS PER WORKING HOUR OF 50 MIN.
= (50.00/11.65) = 4.29 TRIPS
OUTPUT OF TIPPER = 4.76 4.29 0.8
(with 80% effeciency) = 16.35 M3/HOUR
Hourly use rate of Dumper = (Hourly use rate/Output)
(As per Annex-2) 678.00 = 678/16.35 = 41.4718 Rs.(B)
Total cost of excavation
Loading, Unloading and
transportation=(A)+(B)= 30.72 + 41.47 = Rs. 72.20 (C)
Cost of breaking clods & spreading in uniform layars @ 20% = Rs. 6.14
of excavation cost.
Total = Rs. 78.34
Add for
Tools & Plant 1% = Rs. 0.78
Contractor profit & Over heads 15% = Rs. 11.75
Grand Total = Rs. 90.87
Add 1% labour cess = Rs. 0.91
Rate per Cum = Rs. 91.80
(a) Below water table
I. Excavation and loading.
Excavation with poclane Ex. 280 model.
Bucket Capacity = 0.90 Cum.
OUTPUT OF BUCKET CAPACITY 0.96 CUM IS AVAILABLE IN CWC WORKING
GROUP REPORT TABLE(F) FOR OUTPUT OF 0.90CUM BUCKET CAPACITY
MULTIPLIED BY 0.94
Ideal production for 0.96 M3 B.C = 99 (common excavation in rock & roots)
Ideal production for 0.90 M3 B.C = 93.06
Average = 93.06 Cum.
Factors affecting the out put
1.Factor for depth of cut and and
angle of swing. = 0.98 (% of optimum dept 80
Angle of swing.=90
2. Operating factor
(Excellent)(table C) = 0.92
3. Job management factor
(Excellent management
condition and good job
condition) (tableD) = 0.78
4. Bucket fill factor (table E) = 0.75
Out put per hour = 93.06 0.98 0.92 0.78 0.75
= 49.08 Cum/hours (Annexure-1)
Cost of excavation = 1508/49.08
(As per Annex-1) 1508.00 = 30.72 Rs./Cum…….(A)
II. Transportation
Cost of transportion.
1. Dumper carriage capacity. = 10.00 M.Ton.
2. Density. 2.2 M.Ton./Cum.
3. Body capacity = 10 = 4.55 Cum.
CYCLE TIME
LOADING TIME = BODY CAPACITY/EXCAVATOR OUTPUT
= (4.55x60.00)/49.08 = 5.56 Min.
LOADED HAUL TIME
(Speed =45 KMPH) = (100x60)/45 = 1.33 Min.
UNLOADING, TURNING, DUMPING, & SPOTTING TIME = 3.30 Min.

72-A file:///conversion/tmp/scratch/446077116.xls Earth work Machine


(AS PER CWC W.G.R. P. NO.93)
EMPTY HAUL TIME = (1.00x60.00)/50 = 1.20 Min.
TOTAL CYCLE TIME = 11.39 Min.
TOTAL NO OF TRIPS PER WORKING HOUR OF 50 MIN.
= (50.00/11.39) = 4.39 TRIPS
OUTPUT OF TIPPER = 4.55 4.39 0.8
(with 80% effeciency) = 15.98 M3/HOUR
Hourly use rate of Dumper = (Hourly use rate/Output)
(As per Annex-2) 678.00 = 678/15.98 = 42.44 Rs.(B)
Total cost of excavation
Loading, Unloading and
transportation=(A)+(B)= 30.72 + 42.44 = Rs. 73.16 (C)
Cost of breaking clods & spreading in uniform layars @ 20% = Rs. 6.14
of excavation cost.
Add cost of dewatering @ 10% of cost of excavation. = Rs. 3.07
Total = Rs. 82.38
Add for
Tools & Plant 1% = Rs. 0.82
Contractor profit & Over heads 15% = Rs. 12.36
Grand Total = Rs. 95.56
Add 1% labour cess = Rs. 0.96
Rate per Cum say = Rs. 96.50
Item No.:- 3
Excavation for foundation in HARD ROCK including blasting and chiseling if necessary
sorting out and stacking seperately the usable rubble, depositing the excavated stuff
as directed including back filling trenches with suitable excavated stuff etc. complete for
lead upto 1 km. and all lifts.
(a) Above wate table
I. COST OF ROCK EXCAVATION BY DRILLING & BLASTING.
A. Cost of drilling hole and blasting material
Hourly use rate of jack hammer = 658.00 Rs./hr. (Annexure-5)
Size of drilling hole 38mm dia.
Hole pattern/m=1.52x1.5 = 2.31
Depth of drilling/100Cum of rock = 100/2.31 = 43.29
Hori. Drilling and pump efficiency
@5% = 2.16
Total = 45.45 m
Rate of drilling/hr. = 6.00 m
Rate of drilling by jack hammer = Hourly use rate if jack hammerx45.45/6
= (658x45.45)/6 4984.35
Cost of drilling rods including bit and miscellaneous supplies & 10%
= 498.435
Cost of drilling/100Cum = 5482.79
Cost of drilling/Cum = 54.83 Rs./Cum.
B. Cost of blasting.
Explosive / m. of hole = 1.34 kg.
Explosive / Cum. = 1.34/2.31 = 0.58 kg.
Assuming that the drilling hole can be filled with dynamite upto 75% capacity.
Hence quantity of explosive/100 = 0.75 0.58 100
Cum of rock = 43.51 kg.
Cost of gelatin/Kg. = 44.00
Total cost of gelatin = 1914.29 Per 100 Cum.
C. Cost of electric detonator.
Quantity of rock/1.0m. Depth

72-A file:///conversion/tmp/scratch/446077116.xls Earth work Machine


No. of hole/100Cum. = 100/2.31 = 43.29
Cost of electric detonator(elect) = 8.00
Total cost of detonator = 346.32 per 100 Cum.
D. Blasting batteries, primer and
loading wire etc.
For 100 Cum = 50% cost of electric detonator
= 173.16 per 100 Cum.
E. Stemming @ 40% of cost of
electric detonator = 138.53 per 100 Cum.
Total charges of drilling and
basting = 8055.08 per 100 Cum.
Cost of drilling and blasting/Cum = 80.55 per Cum.
(a) Above water table
I. Excavation and loading.
Excavation with poclane Ex. 280 model.
Bucket Capacity = 0.90 Cum.
OUTPUT OF BUCKET CAPACITY 0.96 CUM IS AVAILABLE IN CWC WORKING
GROUP REPORT TABLE(F) FOR OUTPUT OF 0.90CUM BUCKET CAPACITY
MULTIPLIED BY 0.94
Ideal production for 0.96 M3 B.C = 119 (rock well blasted)
Ideal production for 0.90 M B.C
3
= 111.86
Average = 111.86 Cum.
Factors affecting the out put
1.Factor for depth of cut and and
angle of swing. = 0.98 (% of optimum dept 80
Angle of swing.=90
2. Operating factor
(Excellent)(table C) = 0.92
3. Job management factor
(Excellent management
condition and good job
condition) (tableD) = 0.78
4. Bucket fill factor (table E) = 0.75
Out put per hour = 111.86 0.98 0.92 0.78 0.75
= 59.00 Cum/hours (Annexure-1)
Cost of excavation = 1508/59.00
(As per Annex-1) 1508.00 = 25.56 Rs./Cum…….(A)
II. Transportation
Cost of transportion.
1. Dumper carriage capacity. = 10.00 M.Ton.
2. Density. 2.4 M.Ton./Cum.
3. Body capacity = 10/2.1 = 4.17 Cum.
CYCLE TIME
LOADING TIME = BODY CAPACITY/EXCAVATOR OUTPUT
= (4.17x60.00)/59.00 = 4.24 Min.
LOADED HAUL TIME
(Speed =45 KMPH) = (100x60)/45 = 1.33 Min.
UNLOADING, TURNING, DUMPING, & SPOTTING TIME = 3.30 Min.
(AS PER CWC W.G.R. P. NO.93)
EMPTY HAUL TIME = (1.00x60.00)/50 = 1.20 Min.
TOTAL CYCLE TIME = 10.07 Min.
TOTAL NO OF TRIPS PER WORKING HOUR OF 50 MIN.
= (50.00/10.07) = 4.97 TRIPS
OUTPUT OF TIPPER = 4.17 4.97 0.8

72-A file:///conversion/tmp/scratch/446077116.xls Earth work Machine


(with 80% effeciency) = 16.56 M3/HOUR
Hourly use rate of Dumper = (Hourly use rate/Output)
(As per Annex-2) 678.00 = 678/16.56 = 40.95 Rs.(B)
Total cost of excavation
Loading, Unloading and
transportation=(A)+(B)= 25.56 + 40.95 = Rs. 66.51 (C)
Cost of breaking clods & spreading in uniform layars @ 20% = Rs. 5.11
of excavation cost.
Total = Rs. 71.63
ADD COST FOR DRILLING & BLASTING = Rs. 80.55
Total = Rs. 152.18
Add for
Tools & Plant 1% = Rs. 1.52
Contractor profit & Over heads 15% = Rs. 22.83
Grand Total = Rs. 176.52
Add 1% labour cess = Rs. 1.77
Rate per Cum = Rs. 178.30
(b) Below wate table
I. COST OF ROCK EXCAVATION BY DRILLING & BLASTING.
A. Cost of drilling hole and blasting material
Hourly use rate of jack hammer = 658.00 Rs./hour (Annexure-5)
Size of drilling hole 38mm dia.
Hole pattern/m=1.52x1.5 = 2.31
Depth of drilling/100Cum of rock = 100/2.31 = 43.29
Hori. Drilling and pump efficiency
@5% = 2.16
Total = 45.45 m
Rate of drilling/hr. = 6.00 m
Rate of drilling by jack hammer = Hourly use rate if jack hammerx45.45/6
= (658x45.45)/6 4984.35
Cost of drilling rods including bit and miscellaneous supplies & 10%
= 498.435
Cost of drilling/100Cum = 5482.79
Cost of drilling/Cum = 54.83 Rs./Cum.
B. Cost of blasting.
Explosive / m. of hole = 1.34 kg.
Explosive / Cum. = 1.34/2.31 = 0.58 kg.
Assuming that the drilling hole can be filled with dynamite upto 75% capacity.
Hence quantity of explosive/100 = 0.75 0.58 100
Cum of rock = 43.51 kg.
Cost of gelatin/Kg. = 44.00
Total cost of gelatin = 1914.29 Per 100 Cum.
C. Cost of electric detonator.
Quantity of rock/1.0m. Depth
No. of hole/100Cum. = 100/2.31 = 43.29
Cost of electric detonator = 8.00
Total cost of detonator = 346.32 per 100 Cum.
D. Blasting batteries, primer and
loading wire etc.
For 100 Cum = 50% cost of electric detonator
= 173.16 per 100 Cum.
E. Stemming @ 40% of cost of
electric detonator = 138.53 per 100 Cum.
Total charges of drilling and

72-A file:///conversion/tmp/scratch/446077116.xls Earth work Machine


basting = 8055.08 per 100 Cum.
Cost of drilling and blasting/Cum = 80.55 per Cum.
(a) Above water table
I. Excavation and loading.
Excavation with poclane Ex. 280 model.
Bucket Capacity = 0.90 Cum.
OUTPUT OF BUCKET CAPACITY 0.96 CUM IS AVAILABLE IN CWC WORKING
GROUP REPORT TABLE(F) FOR OUTPUT OF 0.90CUM BUCKET CAPACITY
MULTIPLIED BY 0.94
Ideal production for 0.96 M3 B.C = 119 (rock well blasted)
Ideal production for 0.90 M B.C
3
= 111.86
Average = 111.86 Cum.
Factors affecting the out put
1.Factor for depth of cut and and
angle of swing. = 0.98 (% of optimum dept 80
Angle of swing.=90
2. Operating factor
(Excellent)(table C) = 0.92
3. Job management factor
(Excellent management
condition and good job
condition) (tableD) = 0.78
4. Bucket fill factor (table E) = 0.75
Out put per hour = 111.86 0.98 0.92 0.78 0.75
= 59.00 Cum/hours (Annexure-1)
Cost of excavation = 1508/59.00
(As per Annex-1) 1508.00 = 25.56 Rs./Cum…….(A)
II. Transportation
Cost of transportion.
1. Dumper carriage capacity. = 10.00 M.Ton.
2. Density. 2.5 M.Ton./Cum.
3. Body capacity = 10/2.1 = 4.00 Cum.
CYCLE TIME
LOADING TIME = BODY CAPACITY/EXCAVATOR OUTPUT
= (4.00x60.00)/59.00 = 4.07 Min.
LOADED HAUL TIME
(Speed =45 KMPH) = (100x60)/45 = 1.33 Min.
UNLOADING, TURNING, DUMPING, & SPOTTING TIME = 3.30 Min.
(AS PER CWC W.G.R. P. NO.93)
EMPTY HAUL TIME = (1.00x60.00)/50 = 1.20 Min.
TOTAL CYCLE TIME = 9.90 Min.
TOTAL NO OF TRIPS PER WORKING HOUR OF 50 MIN.
= (50.00/10.07) = 5.05 TRIPS
OUTPUT OF TIPPER = 4.00 5.05 0.8
(with 80% effeciency) = 16.17 M3/HOUR
Hourly use rate of Dumper = (Hourly use rate/Output)
(As per Annex-2) 678.00 = 678/16.17 = 41.94 Rs.(B)
Total cost of excavation
Loading, Unloading and
transportation=(A)+(B)= 25.56 + 41.94 = Rs. 67.50 (C)
Cost of breaking clods & spreading in uniform layars @ 20% = Rs. 5.11
of excavation cost.
Add cost of dewatering @ 10% of cost of excavation and
loading (i.e 20.34+61.49) = Rs. 10.61

72-A file:///conversion/tmp/scratch/446077116.xls Earth work Machine


Total = Rs. 83.22
ADD COST FOR DRILLING & BLASTING = Rs. 80.55
Total = Rs. 163.78
Add for
Tools & Plant 1% = Rs. 1.64
Contractor profit & Over heads 15% = Rs. 24.57
Grand Total = Rs. 189.98
Add 1% labour cess = Rs. 1.90
Rate per Cum = Rs. 191.90
Item No.:-4
Back filling the foundation trenches around the structures etc. with selected stuff including
watering, ramming, compacting etc. complete.
Rate for 1 Cum.
Capacity of water tanker. = 10000.00 Liter.
Cost of water including filing the = 100.00 Rs./No.
tanker
Average lead. = 3.00 Km.
CYCLE TIME.
LOADING TIME = 10.00 Min.
LOADED HAUL TIME = (3.0x60)/30
= 6.00 Min.
UNLOADING, TURNING,DUMPING & SPOTTING TIME = 15.00 Min.
(AS PER CWC W.G.R. P.NO.93)
EMPTY HAUL TIME = (3.0x60)/40
= 4.5 Min.
TOTAL CYCLE TIME = 35.50 Min.
TOTAL NO. OF TRIPS PER WORKING HOUR OF 50 MIN.
= 50/35.50
= 1.41 TRIPS
WATER CARRIED PER HOUR = 14100 LITERS
HOURLY USE RATE OF TANKER= 678.00 Rs./hour. (Annexure-2)
Transportation Cost = (Hourly use rate/output)= 678/14100
= 0.05 Rs./ltr.
Considering 80 ltr. water required for 1 Cum of soil.
Cost of wate/Cum = (100x80)/10000+80x.04
= 4.00 Rs./Cum.
Cost of vibratory roller = 1715.00 Rs./hr. As per Annex-6)
Out put of roller. = 200 Cum/hour
Cost of rolling = 1715 / 200
= 8.575 Rs./Cum.
Total Cost = 12.58 Rs./Cum.
Add for T & P 1% = 0.13
Add C.P & O.H Charges. 15% = 1.89
Total Charges per Cum. = 14.59 Rs./Cum.
Add 1% labour cess = 0.15
Say = 14.70 Rs./Cum.

72-A file:///conversion/tmp/scratch/446077116.xls Earth work Machine


Item No:5

Excavation for foundation in all sorts of soil including sandy and gravelly soil, soft murrum
including depositing the excavated stuff as and where directed including back filling the
tranches with suitable excavated stuff etc. complete for lead up to 50 meter and lift as under.

Rate Ananlysis for 1 CM work.


Sr. Rate Amount
Description Qty Unit
No Rs. Ps. Rs. Ps.
(a) Lift up to 1.5 meter
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.30 Each. 300.00 90.00
3
Total cost for 1.0 m Rs. :- 90.00
Add 1.0% for Sundries & T & P 0.90
Add 5% C.P & O.H. charges 4.50
Total cost for 1.0 m3 Rs. :- 95.40
Add 1% labour cess 0.95
Total cost for 1.0 m3 Rs. :- 96.40
(b) Lift up to 1.5 to 3.0 meter
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.56 Each. 300.00 168.00
3
Total cost for 1.0 m Rs. :- 168.00
Add 1.5% for Sundries & T & P 2.52
Add 7% C.P & O.H. charges 11.76
Total cost for 1.0 m3 Rs. :- 182.28
Add 1% labour cess 1.82
Total cost for 1.0 m3 Rs. :- 184.10
(c) Lift up to 3.0 to 4.5 meter
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.59 Each. 300.00 177.00
3
Total cost for 1.0 m Rs. :- 177.00
Add 1.5% for Sundries & T & P 2.66
Add 7% C.P & O.H. charges 12.39
Total cost for 1.0 m3 Rs. :- 192.05
Add 1% labour cess 1.92
Total cost for 1.0 m3 Rs. :- 194.00
(d) Lift up to 4.5 to 6.0 meter
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.63 Each. 300.00 189.00
3
Total cost for 1.0 m Rs. :- 189.00
Add 1.5% for Sundries & T & P 2.84
Add 7% C.P & O.H. charges 13.23
Total cost for 1.0 m3 Rs. :- 205.07
Add 1% labour cess 2.05
Total cost for 1.0 m3 Rs. :- 207.10
(e.) For each additional 1.50 lift up to 12.0meter.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Labour 0.065 Each. 300.00 19.50
3
Total cost for 1.0 m Rs. :- 19.50
Add 1.5% for Sundries & T & P 0.29
Add 7% C.P & O.H. charges 1.37
Total cost for 1.0 m3 Rs. :- 21.16
Add 1% labour cess 0.21
Total cost for 1.0 m3 Rs. :- 21.40
Item No:6

100
file:///conversion/tmp/scratch/446077116.xls Earth work Manual
Excavation for foundation in hard murrum including depositing the excavated stuff as and
where directed including back filling the excavated trenches with suitable excavated stuff
etc. complete for lead up to 50 meter and lift as under.
Rate Ananlysis for 1 CM work.
Sr. Rate Amount
Description Qty Unit
No Rs. Ps. Rs. Ps.
(a) Lift up to 1.5 meter
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Mazdoor 0.78 Each. 300.00 234.00
3
Total cost for 1.0 m Rs. :- 234.00
Add 1.5% for Sundries & T & P 3.51
Add 7% C.P & O.H. charges 16.38
Total cost for 1.0 m3 Rs. :- 253.89
Add 1% labour cess 2.54
Total cost for 1.0 m3 Rs. :- 253.90
(b) Lift up to 1.5 to 3.0 meter
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Mazdoor 0.81 Each. 300.00 243.00
Total cost for 1.0 m3 Rs. :- 243.00
Add 1.5% for Sundries & T & P 3.65
Add 7% C.P & O.H. charges 17.01
Total cost for 1.0 m3 Rs. :- 263.66
Add 1% labour cess 2.64
Total cost for 1.0 m3 Rs. :- 263.70
(c) Lift up to 3.0 to 4.5 meter
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Mazdoor 0.86 Each. 300.00 258.00
3
Total cost for 1.0 m Rs. :- 258.00
Add 1.5% for Sundries & T & P 3.87
Add 7% C.P & O.H. charges 18.06
Total cost for 1.0 m3 Rs. :- 279.93
Add 1% labour cess 2.80
Total cost for 1.0 m3 Rs. :- 282.70
(d) Lift up to 4.5 to 6.0 meter
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Mazdoor 0.90 Each. 300.00 270.00
3
Total cost for 1.0 m Rs. :- 270.00
Add 1.5% for Sundries & T & P 4.05
Add 7% C.P & O.H. charges 18.90
Total cost for 1.0 m3 Rs. :- 292.95
Add 1% labour cess 2.93
Total cost for 1.0 m3 Rs. :- 295.90
(e) For each additional 1.50 lift up to 12.0meter.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Mazdoor 0.070 Each. 300.00 21.00
3
Total cost for 1.0 m Rs. :- 21.00
Add 1.5% for Sundries & T & P 0.32
Add 7% C.P & O.H. charges 1.47
Total cost for 1.0 m3 Rs. :- 22.79
Add 1% labour cess 0.23
Total cost for 1.0 m3 Rs. :- 23.00
Item No:7
Excavation for foundation in soft rock including depositing the excavated stuff as and where
directed including back filling the trenches with suitable excavated stuff etc. completefor
lead up to 50 meter and lift as under

100
file:///conversion/tmp/scratch/446077116.xls Earth work Manual
Rate Ananlysis for 1 CM work.
Sr. Rate Amount
Description Qty Unit
No Rs. Ps. Rs. Ps.
(a) Lift up to 1.5 meter
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Mazdoor 1.40 Each. 300.00 420.00
3
Total cost for 1.0 m Rs. :- 420.00
Add 2% for Sundries & T & P 8.40
Add 15% C.P & O.H. charges 63.00
Total cost for 1.0 m3 Rs. :- 491.40
Add 1% labour cess 4.91
Total cost for 1.0 m3 Rs. :- 496.30
(b) Lift up to 1.5 to 3.0 meter
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Mazdoor 1.42 Each. 300.00 426.00
3
Total cost for 1.0 m Rs. :- 426.00
Add 2% for Sundries & T & P 8.52
Add 15% C.P & O.H. charges 63.90
Total cost for 1.0 m3 Rs. :- 498.42
Add 1% labour cess 4.98
Total cost for 1.0 m3 Rs. :- 503.40
(c) Lift up to 3.0 to 4.5 meter
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Mazdoor 1.48 Each. 300.00 444.00
3
Total cost for 1.0 m Rs. :- 444.00
Add 2% for Sundries & T & P 8.88
Add 15% C.P & O.H. charges 66.60
Total cost for 1.0 m3 Rs. :- 519.48
Add 1% labour cess 5.19
Total cost for 1.0 m3 Rs. :- 524.70
(d) Lift up to 4.5 to 6.0 meter
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Mazdoor 1.56 Each. 300.00 468.00
3
Total cost for 1.0 m Rs. :- 468.00
Add 2% for Sundries & T & P 9.36
Add 15% C.P & O.H. charges 70.20
Total cost for 1.0 m3 Rs. :- 547.56
Add 1% labour cess 5.48
Total cost for 1.0 m3 Rs. :- 553.00
(e) For each additional 1.50 lift up to 12.0meter.
(A) MATERIALS:- 0.00 - 0.00 0.00
(B) LABOUR:-
1 Mazdoor 0.073 Each. 300.00 21.90
3
Total cost for 1.0 m Rs. :- 21.90
Add 2% for Sundries & T & P 0.44
Add 15% C.P & O.H. charges 3.29
Total cost for 1.0 m3 Rs. :- 25.62
Add 1% labour cess 0.26
Total cost for 1.0 m3 Rs. :- 25.90

100
file:///conversion/tmp/scratch/446077116.xls Earth work Manual
Item No.:8

Providing and laying plain/ reinforced ordinery portland cement concrete of various grade
with cement, sand and coarse aggregates including centering, shuttering, batching,
mixing,transporting, placing, vibrating, smooth finishing, curing etc. complete for all lead
and lifts(BATCHING PLANT BASED)(INCLUDING DEWATERING)
Rate Ananlysis for 1 Cum. work. (A) Placement site : Foundation.
(i) M 7.50 grade.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.47 Cum. 1500.00 705.00
(c) Cement 3.4 Bag 340.00 1156.00
Total :- 3730.00
2.0 LABOURS
(a) Unskilled Majdoor 0.90 Each. 300.00 270.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
Total :- 340.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 314.54 279.94
(b) Carriage of sand 0.47 Cum. 262.22 123.24
(c) Carriage of cement 0.17 MT. 210.27 35.75
Total :- 438.93
4.0 HIRING AND RUNNING CHARGES.
(a) Weight batching & mixing plant, transit
80.00 80.00
mixer vibrator (Annexure-10)
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. 50.00 50.00
3
Total cost for 1.0 m Rs. :- 4638.93
6.0 DEWATERING CHARGES Add 2% of concrete cost. 92.78
Add 1.5% for Sundries & T & P 63.00
Add 7% C.P & O.H. charges 294.00
Total cost for 1.0 m3 Rs. :- 5088.71
Add 1% labour cess 50.89
Total cost for 1.0 m3 Rs. :- 5140.00
Item No.:9
Rate Ananlysis for 1 Cum. work. (A) Placement site : Foundation.
(ii) M 10 grade.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.47 Cum. 1500.00 705.00
(c) Cement 4.2 Bag 340.00 1428.00
Total :- 4002.00
2.0 LABOURS
(a) Unskilled Majdoor 0.90 Each. 300.00 270.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
Total :- 340.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 314.54 279.94
(b) Carriage of sand 0.47 Cum. 262.22 123.24
(c) Carriage of cement 0.21 MT. 210.27 44.16
Total :- 447.34
4.0 HIRING AND RUNNING CHARGES.
(a) Weight batching & mixing plant, transit 80.00 80.00
mixer vibrator (Annexure-10)

140 file:///conversion/tmp/scratch/446077116.xls Concrete


5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. 50.00 50.00
3
Total cost for 1.0 m Rs. :- 4919.34
Add 1.5% for Sundries & T & P 67.08
Add 7% C.P & O.H. charges 313.04
Total cost for 1.0 m3 Rs. :- 5299.46
Add 1% labour cess 52.99
Total cost for 1.0 m3 Rs. :- 5352.50
Item No.:10
Rate Ananlysis for 1 Cum. work.
(B) Placement site :Raft, Bottom slab of barrel, footing of columns, abutment and bottom
slab of sump etc.
(i) M 15 grade.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.445 Cum. 1500.00 667.50
(c) Cement 5.4 Bag 340.00 1836.00
Total :- 4372.50
2.0 LABOURS
(a) Unskilled Majdoor 0.90 Each. 300.00 270.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
Total :- 340.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 314.54 279.94
(b) Carriage of sand 0.445 Cum. 262.22 116.69
(c) Carriage of cement 0.27 MT. 210.27 56.77
Total :- 453.40
4.0 HIRING AND RUNNING CHARGES.
(a) Weight batching & mixing plant, transit 80.00 80.00
mixer vibrator (Annexure-10)
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. 70.00 70.00
Total cost for 1.0 m3 Rs. :- 5315.90
6.0 DEWATERING CHARGES
Add 2% of concrete cost. 106.32
Add 1.5% for Sundries & T & P 72.94
Add 7% C.P & O.H. charges 340.38
Total cost for 1.0 m3 Rs. :- 5835.53
Add 1% labour cess 58.36
Total cost for 1.0 m3 Rs. :- 5893.90
Item No.:11
Rate Ananlysis for 1 Cum. work.
(B) Placement site :Raft, Bottom slab of barrel, footing of columns, abutment and bottom
slab of sump etc.
(ii) M 20 grade.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.85 Cum. 2100.00 1785.00
(b) Sand 0.425 Cum. 1500.00 637.50
(c) Cement 7 Bag 340.00 2380.00
Total :- 4802.50
2.0 LABOURS
(a) Unskilled Majdoor 0.90 Each. 300.00 270.00

140 file:///conversion/tmp/scratch/446077116.xls Concrete


(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
Total :- 340.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.85 Cum. 314.54 267.36
(b) Carriage of sand 0.425 Cum. 262.22 111.44
(c) Carriage of cement 0.35 MT. 210.27 73.59
Total :- 452.40
4.0 HIRING AND RUNNING CHARGES.
(a) Weight batching & mixing plant, transit 80.00 80.00
mixer vibrator (Annexure-10)
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. 70.00 70.00
3
Total cost for 1.0 m Rs. :- 5744.90
6.0 DEWATERING CHARGES
Add 2% of concrete cost. 114.90
Add 1.5% for Sundries & T & P 79.39
Add 7% C.P & O.H. charges 370.48
Total cost for 1.0 m3 Rs. :- 6309.66
Add 1% labour cess 63.10
Total cost for 1.0 m3 Rs. :- 6372.80
Item No.:11
Rate Ananlysis for 1 Cum. work.
(B) Placement site :Raft, Bottom slab of barrel, footing of columns, abutment and bottom
slab of sump etc.
(iii) M 25 grade.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.78 Cum. 2100.00 1638.00
(b) Sand 0.39 Cum. 1500.00 585.00
(c) Cement 7.4 Bag 340.00 2516.00
Total :- 4739.00
2.0 LABOURS
(a) Unskilled Majdoor 0.90 Each. 300.00 270.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
Total :- 340.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.78 Cum. 314.54 245.34
(b) Carriage of sand 0.39 Cum. 262.22 102.27
(c) Carriage of cement 0.37 MT. 210.27 77.80
Total :- 425.41
4.0 HIRING AND RUNNING CHARGES.
(a) Weight batching & mixing plant, transit 80.00 80.00
mixer vibrator (Annexure-10)
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. 70.00 70.00
Total cost for 1.0 m3 Rs. :- 5654.41
6.0 DEWATERING CHARGES
Add 2% of concrete cost. 169.63
Add 1.5% for Sundries & T & P 104.58
Add 7% C.P & O.H. charges 784.35
Total cost for 1.0 m3 Rs. :- 6712.97
Add 1% labour cess 67.13
Total cost for 1.0 m3 Rs. :- 6780.00
Item No.:12
Rate Ananlysis for 1 Cum. work.

140 file:///conversion/tmp/scratch/446077116.xls Concrete


(B) Placement site :Raft, Bottom slab of barrel, footing of columns, abutment and bottom
slab of sump etc.
(iv) M 30 grade.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.78 Cum. 2100.00 1638.00
(b) Sand 0.39 Cum. 1500.00 585.00
(c) Cement 7.8 MT. 340.00 2652.00
Total :- 4875.00
2.0 LABOURS
(a) Unskilled Majdoor 0.90 Each. 300.00 270.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
Total :- 340.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.78 Cum. 314.54 245.34
(b) Carriage of sand 0.39 Cum. 262.22 102.27
(c) Carriage of cement 0.39 MT. 210.27 82.01
Total :- 429.61
4.0 HIRING AND RUNNING CHARGES.
(a) Weight batching & mixing plant, transit 80.00 80.00
mixer vibrator (Annexure-10)
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. 70.00 70.00
Total cost for 1.0 m3 Rs. :- 5794.61
6.0 DEWATERING CHARGES
Add 3% of concrete cost. 173.84
Add 2% for Sundries & T & P 107.30
Add 15% C.P & O.H. charges 804.75
Total cost for 1.0 m3 Rs. :- 6880.50
Add 1% labour cess 68.81
Total cost for 1.0 m3 Rs. :- 6949.30
Item No.:-15
Brick Ballast in foundation with concrete of cement, sand and gravel in following
proportionincluding centering shuttering, temping, smooth finishing, curing etc. complete as
directed for all lead and lift (i) Prop : 1:5:10
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate.(Gravel) 0.89 Cum. 1600.00 1424.00
(b) Sand 0.445 Cum. 2100.00 934.50
(c) Cement 2.6 Bag 340.00 884.00
Total :- 3242.50
2.0 LABOURS 0.09187
(a) Unskilled Majdoor 1.90 Each. 300.00 570.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 730.00
3.0 CARRIAGE OF MATERIAL
(a) Coarse aggregate.(Gravel) 0.89 Cum. 262.22 233.38
(b) Carriage of sand. 0.445 Cum. 262.22 116.69
(c) Carriage of cement. 0.16 MT. 210.27 33.64
Total :- 383.71
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 450.00 450.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00

140 file:///conversion/tmp/scratch/446077116.xls Concrete


Total cost for 1.0 m3 Rs. :- 4856.21
Add 2% for Sundries & T & P 10.95
Add 7% C.P & O.H. charges 313.08
Total cost for 1.0 m3 Rs. :- 5180.23
Add 1% labour cess 51.80
Total cost for 1.0 m3 Rs. :- 5232.00
(ii) Prop : 1:4:8
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 1600.00 1424.00
(b) Sand 0.445 Cum. 2100.00 934.50
(c) Cement 3.4 Bag 340.00 1156.00
Total :- 3514.50
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 262.22 233.38
(b) Carriage of sand. 0.445 Cum. 262.22 116.69
(c) Carriage of cement. 3.4 MT. 210.27 714.92
Total :- 1064.98
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 150.00 150.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
Total cost for 1.0 m3 Rs. :- 5479.48
Add 2% for Sundries and T & P 14.00
Add 7% C.P & O.H. charges 309.02
Total cost for 1.0 m3 Rs. :- 5802.50
Add 1% labour cess 58.02
Total cost for 1.0 m3 Rs. :- 5861.00
(iii) Prop : 1:3:6
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. (Gravel) 0.89 Cum. 1600.00 1424.00
(b) Sand 0.47 Cum. 1500.00 705.00
(c) Cement 0.22 MT. 340.00 74.80
Total :- 2203.80
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Coarse aggregate. (Gravel) 0.89 Cum. 262.22 233.38
(b) Carriage of sand. 0.47 Cum. 262.22 123.24
(c) Carriage of cement. 0.22 MT. 210.27 46.26
Total :- 402.88
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00

140 file:///conversion/tmp/scratch/446077116.xls Concrete


Total cost for 1.0 m3 Rs. :- 3436.68
Add 2% for Sundries & T & P 60.68
Add 15% C.P & O.H. charges 455.07
Total cost for 1.0 m3 Rs. :- 3952.42
Add 1% labour cess 39.52
Total cost for 1.0 m3 Rs. :- 3991.90
(iv) Prop : 1:2:4
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate.(Gravel) 0.89 Cum. 1600.00 1424.00
(b) Sand 0.47 Cum. 1500.00 705.00
(c) Cement 0.32 MT. 340.00 108.80
Total :- 2237.80 0.306
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate.(grvel) 0.89 Cum. 262.22 233.38
(b) Carriage of sand. 0.47 Cum. 262.22 123.24
(c) Carriage of cement. 0.32 MT. 210.27 67.29
Total :- 423.91
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
Total cost for 1.0 m3 Rs. :- 3491.71
Add 2% for Sundries & T & P 61.36
Add 15% C.P & O.H. charges 460.17
Total cost for 1.0 m3 Rs. :- 4013.23
Add 1% labour cess 40.13
Total cost for 1.0 m3 Rs. :- 4053.40
(v) Prop : 1:1.5:3
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate.(Gravel) 0.85 Cum. 1600.00 1360.00
(b) Sand 0.425 Cum. 1500.00 637.50
(c) Cement 0.40 MT. 340.00 135.15
Total :- 2132.65
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate.(grvel) 0.85 Cum. 262.22 222.89
(b) Carriage of sand. 0.425 Cum. 262.22 111.44
(c) Carriage of cement. 0.3975 MT. 210.27 83.58
Total :- 417.91
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00

140 file:///conversion/tmp/scratch/446077116.xls Concrete


Total cost for 1.0 m3 Rs. :- 3380.56
Add 2% for Sundries & T & P 59.25
Add 15% C.P & O.H. charges 444.40
Total cost for 1.0 m3 Rs. :- 3884.21
Add 1% labour cess 38.84
Total cost for 1.0 m3 Rs. :- 3923.10
Item No.:-16
Filling in foundation with concrete of cement, sand and burnt brick balast in following
proportion including centering, shuttering, temping, smooth finishing, curing etc. complete as
as directed for all lead and lifts.
(i) Prop : 1:5:10
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate.(brick balast) 0.89 Cum. 130.00 115.70
(b) Sand 0.445 Cum. 1500.00 667.50
(c) Cement 0.13 MT. 340.00 44.20
Total :- 827.40
2.0 LABOURS
(a) Unskilled Majdoor 1.90 Each. 300.00 570.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 730.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 189.42 168.58
(b) Carriage of sand. 0.445 Cum. 262.22 116.69
(c) Carriage of cement. 0.16 MT. 210.27 33.64
Total :- 318.91
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
Total cost for 1.0 m3 Rs. :- 2006.31
Add 2% for Sundries & T & P 33.75
Add 15% C.P & O.H. charges 253.11
Total cost for 1.0 m3 Rs. :- 2293.17
Add 1% labour cess 22.93
Total cost for 1.0 m3 Rs. :- 2316.10
(ii) Prop : 1:4:8
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate.(brick balast) 0.89 Cum. 130.00 115.70
(b) Sand 0.445 Cum. 1500.00 667.50
(c) Cement 0.17 MT. 340.00 57.80
Total :- 841.00
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 189.42 168.58
(b) Carriage of sand. 0.445 Cum. 262.22 116.69
(c) Carriage of cement. 0.17 MT. 210.27 35.75
Total :- 321.02

140 file:///conversion/tmp/scratch/446077116.xls Concrete


4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
3
Total cost for 1.0 m Rs. :- 1992.02
Add 2% for Sundries & T & P 33.42
Add 15% C.P & O.H. charges 250.65
Total cost for 1.0 m3 Rs. :- 2276.09
Add 1% labour cess 22.76
Total cost for 1.0 m3 Rs. :- 2298.80
(iii) Prop : 1:3:6
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate.(brick balast) 0.89 Cum. 130.00 115.70
(b) Sand 0.47 Cum. 1500.00 705.00
(c) Cement 0.22 MT. 340.00 74.80
Total :- 895.50
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 189.42 168.58
(b) Carriage of sand. 0.47 Cum. 262.22 123.24
(c) Carriage of cement. 0.22 MT. 210.27 46.26
Total :- 338.09
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
3
Total cost for 1.0 m Rs. :- 2063.59
Add 2% for Sundries & T & P 34.51
Add 15% C.P & O.H. charges 258.83
Total cost for 1.0 m3 Rs. :- 2356.92
Add 1% labour cess 23.57
Total cost for 1.0 m3 Rs. :- 2380.50
(iv) Prop : 1:2:4
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate.(brick balast) 0.89 Cum. 130.00 115.70
(b) Sand 0.47 Cum. 1500.00 705.00
(c) Cement 0.32 MT. 340.00 108.80
Total :- 929.50
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 189.42 168.58
(b) Carriage of sand. 0.47 Cum. 262.22 123.24
(c) Carriage of cement. 0.32 MT. 210.27 67.29
Total :- 359.11

140 file:///conversion/tmp/scratch/446077116.xls Concrete


4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
3
Total cost for 1.0 m Rs. :- 2118.61
Add 2% for Sundries & T & P 35.19
Add 15% C.P & O.H. charges 263.93
Total cost for 1.0 m3 Rs. :- 2417.73
Add 1% labour cess 24.18
Total cost for 1.0 m3 Rs. :- 2441.90
(v) Prop : 1:1.5:3
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate.(brick balast) 0.85 Cum. 130.00 110.50
(b) Sand 0.425 Cum. 1500.00 637.50
(c) Cement 0.40 MT. 340.00 135.15
Total :- 883.15
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.85 Cum. 189.42 161.01
(b) Carriage of sand. 0.425 Cum. 262.22 111.44
(c) Carriage of cement. 0.3975 MT. 210.27 83.58
Total :- 356.03
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
3
Total cost for 1.0 m Rs. :- 2069.18
Add 2% for Sundries & T & P 34.26
Add 15% C.P & O.H. charges 256.97
Total cost for 1.0 m3 Rs. :- 2360.42
Add 1% labour cess 23.60
Total cost for 1.0 m3 Rs. :- 2384.00
Item No.:-17
Filling in foundation with concrete of cement, sand and metal (up to 5cm size) in following
proportion including centering, shuttering, temping, smooth finishing, curing etc. complete as
directed for all lead and lifts.
(i) Prop : 1:5:10
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.445 Cum. 1500.00 667.50
(c) Cement 0.13 MT. 340.00 44.20
Total :- 2580.70
2.0 LABOURS
(a) Unskilled Majdoor 1.90 Each. 300.00 570.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 730.00
3.0 CARRIAGE OF MATERIAL

140 file:///conversion/tmp/scratch/446077116.xls Concrete


(a) Carriage of coarse aggregate. 0.89 Cum. 314.54 279.94
(b) Carriage of sand. 0.445 Cum. 262.22 116.69
(c) Carriage of cement. 0.16 MT. 210.27 33.64
Total :- 430.27
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
Total cost for 1.0 m3 Rs. :- 3870.97
Add 2% for Sundries & T & P 68.81
Add 15% C.P & O.H. charges 516.11
Total cost for 1.0 m3 Rs. :- 4455.89
Add 1% labour cess 44.56
Total cost for 1.0 m3 Rs. :- 4500.40
(ii) Prop : 1:4:8
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.445 Cum. 1500.00 667.50
(c) Cement 0.17 MT. 340.00 57.80
Total :- 2594.30
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 314.54 279.94
(b) Carriage of sand. 0.445 Cum. 262.22 116.69
(c) Carriage of cement. 0.17 MT. 210.27 35.75
Total :- 432.37
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
Total cost for 1.0 m3 Rs. :- 3856.67
Add 2% for Sundries & T & P 68.49
Add 15% C.P & O.H. charges 513.65
Total cost for 1.0 m3 Rs. :- 4438.81
Add 1% labour cess 44.39
Total cost for 1.0 m3 Rs. :- 4483.20
(iii) Prop : 1:3:6
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.47 Cum. 1500.00 705.00
(c) Cement 0.22 MT. 340.00 74.80
Total :- 2648.80
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL

140 file:///conversion/tmp/scratch/446077116.xls Concrete


(a) Carriage of coarse aggregate. 0.89 Cum. 314.54 279.94
(b) Carriage of sand. 0.47 Cum. 262.22 123.24
(c) Carriage of cement. 0.22 MT. 210.27 46.26
Total :- 449.44
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 70.00 70.00
Total cost for 1.0 m3 Rs. :- 3948.24
Add 2% for Sundries & T & P 69.98
Add 15% C.P & O.H. charges 524.82
Total cost for 1.0 m3 Rs. :- 4543.04
Add 1% labour cess 45.43
Total cost for 1.0 m3 Rs. :- 4588.50
(iv) Prop : 1:2:4
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.47 Cum. 1500.00 705.00
(c) Cement 0.32 MT. 340.00 108.80
Total :- 2682.80
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 314.54 279.94
(b) Carriage of sand. 0.47 Cum. 262.22 123.24
(c) Carriage of cement. 0.32 MT. 210.27 67.29
Total :- 470.47
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
Total cost for 1.0 m3 Rs. :- 3983.27
Add 2% for Sundries & T & P 70.26
Add 15% C.P & O.H. charges 526.92
Total cost for 1.0 m3 Rs. :- 4580.45
Add 1% labour cess 45.80
Total cost for 1.0 m3 Rs. :- 4626.30
(v) Prop : 1:1.5:3
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.85 Cum. 2100.00 1785.00
(b) Sand 0.425 Cum. 1500.00 637.50
(c) Cement 0.40 MT. 340.00 135.15
Total :- 2557.65
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL

140 file:///conversion/tmp/scratch/446077116.xls Concrete


(a) Carriage of coarse aggregate. 0.85 Cum. 314.54 267.36
(b) Carriage of sand. 0.425 Cum. 262.22 111.44
(c) Carriage of cement. 0.3975 MT. 210.27 83.58
Total :- 462.38
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
Total cost for 1.0 m3 Rs. :- 3850.03
Add 2% for Sundries & T & P 67.75
Add 15% C.P & O.H. charges 508.15
Total cost for 1.0 m3 Rs. :- 4425.94
Add 1% labour cess 44.26
Total cost for 1.0 m3 Rs. :- 4470.20
Item No.:-18
Providing and laying plain/reinforced cement concrete of cement, sand and metal (20 to
25mm size) in following proportion including centering, shuttering, temping, smooth finishing,
curing etc. complete as directed for all leads and lifts.
(i) Prop : 1:5:10
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.445 Cum. 1500.00 667.50
(c) Cement 0.13 MT. 340.00 44.20
Total :- 2580.70
2.0 LABOURS
(a) Unskilled Majdoor 1.90 Each. 300.00 570.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 730.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 314.54 279.94
(b) Carriage of sand. 0.445 Cum. 262.22 116.69
(c) Carriage of cement. 0.16 MT. 210.27 33.64
Total :- 430.27
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 50.00 50.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
Total cost for 1.0 m3 Rs. :- 3840.97
Add 2% for Sundries & T & P 68.21
Add 15% C.P & O.H. charges 511.61
Total cost for 1.0 m3 Rs. :- 4420.79
Add 1% labour cess 44.21
Total cost for 1.0 m3 Rs. :- 4465.00
(ii) Prop : 1:4:8
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.445 Cum. 1500.00 667.50
(c) Cement 0.17 MT. 340.00 57.80
Total :- 2594.30
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00

140 file:///conversion/tmp/scratch/446077116.xls Concrete


(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 314.54 279.94
(b) Carriage of sand. 0.445 Cum. 262.22 116.69
(c) Carriage of cement. 0.17 MT. 210.27 35.75
Total :- 432.37
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
3
Total cost for 1.0 m Rs. :- 3856.67
Add 2% for Sundries & T & P 68.49
Add 15% C.P & O.H. charges 513.65
Total cost for 1.0 m3 Rs. :- 4438.81
Add 1% labour cess 44.39
Total cost for 1.0 m3 Rs. :- 4483.20
(iii) Prop : 1:3:6
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.47 Cum. 1500.00 705.00
(c) Cement 0.22 MT. 340.00 74.80
Total :- 2648.80
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 314.54 279.94
(b) Carriage of sand. 0.47 Cum. 262.22 123.24
(c) Carriage of cement. 0.22 MT. 210.27 46.26
Total :- 449.44
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 70.00 70.00
3
Total cost for 1.0 m Rs. :- 3948.24
Add 2% for Sundries & T & P 69.98
Add 15% C.P & O.H. charges 524.82
Total cost for 1.0 m3 Rs. :- 4543.04
Add 1% labour cess 45.43
Total cost for 1.0 m3 Rs. :- 4588.50
(iv) Prop : 1:2:4
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.47 Cum. 1500.00 705.00
(c) Cement 0.32 MT. 340.00 108.80
Total :- 2682.80
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00

140 file:///conversion/tmp/scratch/446077116.xls Concrete


(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 314.54 279.94
(b) Carriage of sand. 0.47 Cum. 262.22 123.24
(c) Carriage of cement. 0.32 MT. 210.27 67.29
Total :- 470.47
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
3
Total cost for 1.0 m Rs. :- 3983.27
Add 2% for Sundries & T & P 70.26
Add 15% C.P & O.H. charges 526.92
Total cost for 1.0 m3 Rs. :- 4580.45
Add 1% labour cess 45.80
Total cost for 1.0 m3 Rs. :- 4626.30
(v) Prop : 1:1.5:3
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.85 Cum. 2100.00 1785.00
(b) Sand 0.425 Cum. 1500.00 637.50
(c) Cement 0.40 MT. 340.00 135.15
Total :- 2557.65
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.85 Cum. 314.54 267.36
(b) Carriage of sand. 0.425 Cum. 262.22 111.44
(c) Carriage of cement. 0.3975 MT. 210.27 83.58
Total :- 462.38
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
3
Total cost for 1.0 m Rs. :- 3850.03
Add 2% for Sundries & T & P 67.75
Add 15% C.P & O.H. charges 508.15
Total cost for 1.0 m3 Rs. :- 4425.94
Add 1% labour cess 44.26
Total cost for 1.0 m3 Rs. :- 4470.20
Item No.:-19
Providing and laying plain/reinforced cement concrete of cement, sand and metal (above
12mm & upto 20mm size) in following proportion including centering, shuttering, temping, smooth
finishing, curing etc. complete as directed for all leads and lifts.
(i) Prop : 1:5:10
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.445 Cum. 1500.00 667.50
(c) Cement 0.13 MT. 340.00 44.20

140 file:///conversion/tmp/scratch/446077116.xls Concrete


Total :- 2580.70
2.0 LABOURS
(a) Unskilled Majdoor 1.90 Each. 300.00 570.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 730.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 314.54 279.94
(b) Carriage of sand. 0.445 Cum. 262.22 116.69
(c) Carriage of cement. 0.16 MT. 210.27 33.64
Total :- 430.27
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
Total cost for 1.0 m3 Rs. :- 3870.97
Add 2% for Sundries & T & P 68.81
Add 15% C.P & O.H. charges 516.11
Total cost for 1.0 m3 Rs. :- 4455.89
Add 1% labour cess 44.56
Total cost for 1.0 m3 Rs. :- 4500.40
(ii) Prop : 1:4:8
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.445 Cum. 1500.00 667.50
(c) Cement 0.17 MT. 340.00 57.80
Total :- 2594.30
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 314.54 279.94
(b) Carriage of sand. 0.445 Cum. 262.22 116.69
(c) Carriage of cement. 0.17 MT. 210.27 35.75
Total :- 432.37
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
Total cost for 1.0 m3 Rs. :- 3856.67
Add 2% for Sundries & T & P 68.49
Add 15% C.P & O.H. charges 513.65
Total cost for 1.0 m3 Rs. :- 4438.81
Add 1% labour cess 44.39
Total cost for 1.0 m3 Rs. :- 4483.20
(iii) Prop : 1:3:6
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.47 Cum. 1500.00 705.00
(c) Cement 0.22 MT. 340.00 74.80

140 file:///conversion/tmp/scratch/446077116.xls Concrete


Total :- 2648.80
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 314.54 279.94
(b) Carriage of sand. 0.47 Cum. 262.22 123.24
(c) Carriage of cement. 0.22 MT. 210.27 46.26
Total :- 449.44
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 70.00 70.00
Total cost for 1.0 m3 Rs. :- 3948.24
Add 2% for Sundries & T & P 69.98
Add 15% C.P & O.H. charges 524.82
Total cost for 1.0 m3 Rs. :- 4543.04
Add 1% labour cess 45.43
Total cost for 1.0 m3 Rs. :- 4588.50
(iv) Prop : 1:2:4
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.47 Cum. 1500.00 705.00
(c) Cement 0.32 MT. 340.00 108.80
Total :- 2682.80
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 314.54 279.94
(b) Carriage of sand. 0.47 Cum. 262.22 123.24
(c) Carriage of cement. 0.32 MT. 210.27 67.29
Total :- 470.47
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
Total cost for 1.0 m3 Rs. :- 3983.27
Add 2% for Sundries & T & P 70.26
Add 15% C.P & O.H. charges 526.92
Total cost for 1.0 m3 Rs. :- 4580.45
Add 1% labour cess 45.80
Total cost for 1.0 m3 Rs. :- 4626.30
(v) Prop : 1:1.5:3
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.85 Cum. 1800.00 1530.00
(b) Sand 0.425 Cum. 2100.00 892.50
(c) Cement 7.95 bag 340.00 2703.00

140 file:///conversion/tmp/scratch/446077116.xls Concrete


Total :- 5125.50
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 300.00 540.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 450.00 45.00
(d) Bhisti. 0.30 Each. 300.00 90.00
Total :- 700.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.85 Cum. 314.54 267.36
(b) Carriage of sand. 0.425 Cum. 262.22 111.44
(c) Carriage of cement. 0.40 MT. 210.27 84.11
Total :- 462.91
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 80.00 80.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 50.00 50.00
Total cost for 1.0 m3 Rs. :- 6418.41
Add 2% for Sundries & T & P 119.11
Add 15% C.P & O.H. charges 893.33
Total cost for 1.0 m3 Rs. :- 7430.85
Add 1% labour cess 74.31
Total cost for 1.0 m3 Rs. :- 7505.20

140 file:///conversion/tmp/scratch/446077116.xls Concrete


Item No.:8

Providing and laying plain/ reinforced ordinery portland cement concrete of various grade
with cement, sand and coarse aggregates including centering, shuttering, batching,
mixing,transporting, placing, vibrating, smooth finishing, curing etc. complete for all lead and
lifts(BATCHING PLANT BASED)(INCLUDING DEWATERING)
Rate Ananlysis for 1 Cum. work. (A) Placement site : Foundation.
(i) Proportion 1:4:8.
Sr. No. Rate Amount
Description Qty Unit
Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 425.00 378.25
(b) Sand 0.47 Cum. 135.00 63.45
(c) Cement 3.4 Bag 320.00 1088.00
Total :- 1529.70
2.0 LABOURS
(a) Unskilled Majdoor 0.90 Each. 350.00 315.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 400.00 40.00
Total :- 380.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 314.54 279.94
(b) Carriage of sand 0.47 Cum. 262.22 123.24
(c) Carriage of cement 0.17 MT. 210.27 35.75
Total :- 438.93
4.0 HIRING AND RUNNING CHARGES.
(a) Weight batching & mixing plant, transit
0.00 0.00
mixer vibrator (Annexure-10)
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. 48.00 48.00
3
Total cost for 1.0 m Rs. :- 2396.63
6.0 DEWATERING CHARGES Add 2% of concrete cost. 47.93
Add 1.5% for Sundries & T & P 29.37
Add 7% C.P & O.H. charges 137.04
Total cost for 1.0 m3 Rs. :- 2610.97
Add 1% labour cess 26.11
Total cost for 1.0 m3 Rs. :- 2637.00
Item No.:9
Rate Ananlysis for 1 Cum. work. (A) Placement site : Foundation.
(ii) Prop 1:3:6
Sr. No. Rate Amount
Description Qty Unit
Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.47 Cum. 2400.00 1128.00
(c) Cement 4.2 Bag 380.00 1596.00
Total :- 4593.00
2.0 LABOURS
(a) Unskilled Majdoor 0.90 Each. 350.00 315.00
(b) Mason 1st. class. 0.05 Each. 600.00 30.00
(c) Mason II nd. class. 0.10 Each. 500.00 50.00
Total :- 395.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 90.00 80.10
(b) Carriage of sand 0.47 Cum. 90.00 42.30
(c) Carriage of cement 0.21 MT. 100.00 21.00
Total :- 143.40
4.0 HIRING AND RUNNING CHARGES.
(a) Weight batching & mixing plant, transit 0.00 0.00
mixer vibrator (Annexure-10)

140 file:///conversion/tmp/scratch/446077116.xls Concrete


5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. 50.00 50.00
3
Total cost for 1.0 m Rs. :- 5181.40
Add 1.5% for Sundries & T & P 75.57
Add 7% C.P & O.H. charges 352.66
Total cost for 1.0 m3 Rs. :- 5609.63
Add 1% labour cess 56.10
Total cost for 1.0 m3 Rs. :- 5665.70
Item No.:10
Rate Ananlysis for 1 Cum. work.
(B) Placement site :Raft, Bottom slab of barrel, footing of columns, abutment and bottom slab
of sump etc.
(i) Proportions 1:2:4.
Sr. No. Rate Amount
Description Qty Unit
Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 2100.00 1869.00
(b) Sand 0.445 Cum. 2400.00 1068.00
(c) Cement 5.4 Bag 380.00 2052.00
Total :- 4989.00
2.0 LABOURS
(a) Unskilled Majdoor 0.90 Each. 350.00 315.00
(b) Mason 1st. class. 0.05 Each. 600.00 30.00
(c) Mason II nd. class. 0.10 Each. 500.00 50.00
Total :- 395.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 200.00 178.00
(b) Carriage of sand 0.445 Cum. 190.00 84.55
(c) Carriage of cement 0.27 MT. 120.00 32.40
Total :- 294.95
4.0 HIRING AND RUNNING CHARGES.
(a) Weight batching & mixing plant, transit 0.00 0.00
mixer vibrator (Annexure-10)
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. 70.00 70.00
Total cost for 1.0 m3 Rs. :- 5748.95
6.0 DEWATERING CHARGES
Add 2% of concrete cost. 114.98
Add 1.5% for Sundries & T & P 81.81
Add 7% C.P & O.H. charges 381.78
Total cost for 1.0 m3 Rs. :- 6327.52
Add 1% labour cess 63.28
Total cost for 1.0 m3 Rs. :- 6390.80
Item No.:11
Rate Ananlysis for 1 Cum. work.
(B) Placement site :Raft, Bottom slab of barrel, footing of columns, abutment and bottom slab
of sump etc.
(ii) Proportion 1:1.5:3
Sr. No. Rate Amount
Description Qty Unit
Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.85 Cum. 2100.00 1785.00
(b) Sand 0.425 Cum. 2600.00 1105.00
(c) Cement 7 Bag 380.00 2660.00
Total :- 5550.00
2.0 LABOURS
(a) Unskilled Majdoor 0.90 Each. 350.00 315.00

140 file:///conversion/tmp/scratch/446077116.xls Concrete


(b) Mason 1st. class. 0.05 Each. 600.00 30.00
(c) Mason II nd. class. 0.10 Each. 500.00 50.00
Total :- 395.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.85 Cum. 320.00 272.00
(b) Carriage of sand 0.425 Cum. 280.00 119.00
(c) Carriage of cement 0.35 MT. 250.00 87.50
Total :- 478.50
4.0 HIRING AND RUNNING CHARGES.
(a) Weight batching & mixing plant, transit 250.00 250.00
mixer vibrator (Annexure-10)
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. 70.00 70.00
3
Total cost for 1.0 m Rs. :- 6743.50
6.0 DEWATERING CHARGES
Add 2% of concrete cost. 134.87
Add 1.5% for Sundries & T & P 93.98
Add 7% C.P & O.H. charges 438.55
Total cost for 1.0 m3 Rs. :- 7410.90
Add 1% labour cess 74.11
Total cost for 1.0 m3 Rs. :- 7485.00
Item No.:11
Rate Ananlysis for 1 Cum. work.
(B) Placement site :Raft, Bottom slab of barrel, footing of columns, abutment and bottom slab
of sump etc.
(iii) Prop 1:1:2 .
Sr. No. Rate Amount
Description Qty Unit
Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.78 Cum. 425.00 331.50
(b) Sand 0.39 Cum. 135.00 52.65
(c) Cement 7.4 Bag 320.00 2368.00
Total :- 2752.15
2.0 LABOURS
(a) Unskilled Majdoor 0.90 Each. 350.00 315.00
(b) Mason 1st. class. 0.05 Each. 500.00 25.00
(c) Mason II nd. class. 0.10 Each. 400.00 40.00
Total :- 380.00
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.78 Cum. 314.54 245.34
(b) Carriage of sand 0.39 Cum. 262.22 102.27
(c) Carriage of cement 0.37 MT. 210.27 77.80
Total :- 425.41
4.0 HIRING AND RUNNING CHARGES.
(a) Weight batching & mixing plant, transit 0.00 0.00
mixer vibrator (Annexure-10)
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. 70.00 70.00
Total cost for 1.0 m3 Rs. :- 3627.56
6.0 DEWATERING CHARGES
Add 2% of concrete cost. 108.83
Add 1.5% for Sundries & T & P 64.04
Add 7% C.P & O.H. charges 480.32
Total cost for 1.0 m3 Rs. :- 4280.75
Add 1% labour cess 42.81
Total cost for 1.0 m3 Rs. :- 4324.00

140 file:///conversion/tmp/scratch/446077116.xls Concrete


1590.1060070671

35.28755
0.035401
35.31 1.7655
91.806 1.428572
0.147267

140 file:///conversion/tmp/scratch/446077116.xls Concrete


0.290182

8.290909

140 file:///conversion/tmp/scratch/446077116.xls Concrete


2833.333 2857.143

140 file:///conversion/tmp/scratch/446077116.xls Concrete


Item No.:-21
Providing and placing in position reinforcement bars including cutting, bending
welding,joints where necessary, hooking etc. complete as per drawing for all lead
and lifts.
(A) High yeild strength deformed (HYSD tor steel)
Rate Analysis for 1.0 M.T
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Steel 1.05 MT. 34000.00 35700.00
(b) Binding wire. 7.50 Kg. 45.00 337.50
Total:- 36037.50
2.0 LABOURS.
(a) Unskilled Mazdoor. 6.00 Each. 350.00 2100.00
(b) Blacksmith I st. class. 6.00 Each. 450.00 2700.00
Total:- 4800.00
3.0 CARRIAGE OF MATERIALS.
(a) Carriage steel 1.05 MT. 300.00 315.00
Add 2% for Sundries & T & P 816.75
Add 8% C.P & O.H. charges 3267.00
Total cost for 1.0 MT Rs. :- 45236.25
Add 1% labour cess 452.36
Total cost for 1.0 MT Rs. :- Say Rs 4569.00 45689.00
Item No.:-21
(B) TMT steel
Rate Analysis for 1.0 M.T
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Steel 1.05 MT. 36000.00 37800.00
(b) Binding wire. 7.50 Kg. 50.00 375.00
Total:- 38175.00
2.0 LABOURS.
(a) Unskilled Mazdoor. 6.00 Each. 350.00 2100.00
(b) Blacksmith I st. class. 6.00 Each. 450.00 2700.00
Total:- 4800.00
3.0 CARRIAGE OF MATERIALS.
(a) Carriage steel 1.05 MT. 300.00 315.00
Add 2% for Sundries & T & P 859.50
Add 15% C.P & O.H. charges 6446.25
Total cost for 1.0 MT Rs. :- 50595.75
Add 1% labour cess 505.96
Total cost for 1.0 MT Rs. :- Say Rs 5110.00 51102.00
Item No.:-21
(C) TMT-CRS steel
Rate Analysis for 1.0 M.T
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Steel 1.05 MT. 35000.00 36750.00
(b) Binding wire. 7.50 Kg. 50.00 375.00
Total:- 37125.00
2.0 LABOURS.
(a) Unskilled Mazdoor. 6.00 Each. 350.00 2100.00
(b) Blacksmith I st. class. 6.00 Each. 450.00 2700.00
Total:- 4800.00
3.0 CARRIAGE OF MATERIALS.
(a) Carriage steel 1.05 MT. 300.00 315.00
Add 2% for Sundries & T & P 838.50
Add 15% C.P & O.H. charges 6288.75
Total cost for 1.0 MT Rs. :- 49367.25
Add 1% labour cess 493.67
Total cost for 1.0 MT Rs. :- Say Rs 4986.10 49860.90
Item No.:-22
Providing and fixing in position (different diameter) NP-2 R.C.C pipe with collar including
filling and caulking the joints with cement mortar 1:1 proportion, finishing, curing etc.
complete for all lead and lifts.
(a) NP-2 class 225 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP2 class 225mm dia. 10.00 M. 330.00 3300.00
(b) Sand. 0.02 Kg. 135.00 2.03
(c) Cement.(OPC) 0.02 MT. 6400.00 128.00
Total:- 3430.03
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.26 Each. 350.00 441.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.64 Each. 500.00 320.00
(d) Bhisti. 0.20 Each. 350.00 70.00
Total:- 831.00
3.0 CARRIAGE OF MATERIALS.
(a) NP2 class 225mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.02 Kg. 262.22 3.93
(c) Cement.(OPC) 0.02 MT. 210.27 4.21
Total:- 8.14
Add 2% for Sundries & T & P 85.22
Add 8% C.P & O.H. charges 340.88
Total cost for 10.0 RM. Rs. :- 4695.27
Add 1% labour cess 46.95
Total cost for 1.0 RM. Rs. :- Total:- 474.22
Say Rs. :- 474.00
Item No.: 22
(b) NP-2 class 300 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP2 class 300 mm dia. 10.00 M. 330.00 3300.00
(b) Sand. 0.018 Kg. 135.00 2.43
(c) Cement.(OPC) 0.0255 MT. 6400.00 163.20
Total:- 3465.63
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.26 Each. 350.00 441.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.64 Each. 500.00 320.00
(d) Bhisti. 0.20 Each. 350.00 70.00
Total:- 831.00
3.0 CARRIAGE OF MATERIALS.
(a) NP2 class 300 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.018 Kg. 262.22 4.72
(c) Cement.(OPC) 0.0255 MT. 210.27 5.36
Total:- 10.08
Add 2% for Sundries & T & P 85.93
Add 15% C.P & O.H. charges 644.49
Total cost for 10.0 RM. Rs. :- 5037.14
Add 1% labour cess 50.37
Total cost for 1.0 RM. Rs. :- Total:- 508.80
Say Rs. :- 509.00
Item No.: 22
(c) NP-2 class 450 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP2 class 450 mm dia. 10.00 M. 600.00 6000.00
(b) Sand. 0.029 Kg. 135.00 3.92
(c) Cement.(OPC) 0.0410 MT. 6400.00 262.40
Total:- 6266.32
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.50 Each. 350.00 525.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.75 Each. 500.00 375.00
(d) Bhisti. 0.33 Each. 350.00 115.50
Total:- 1015.50
3.0 CARRIAGE OF MATERIALS.
(a) NP2 class 450 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.029 Kg. 262.22 7.60
(c) Cement.(OPC) 0.0410 MT. 210.27 8.62
Total:- 16.23
Add 2% for Sundries & T & P 145.64
Add 8% C.P & O.H. charges 582.55
Total cost for 10.0 RM. Rs. :- 8026.22
Add 1% labour cess 80.26
Total cost for 1.0 RM. Rs. :- Total:- 810.60
Say Rs. :- 811.00
Item No.: 22
(d) NP-2 class 600 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP2 class 600 mm dia. 10.00 M. 800.00 8000.00
(b) Sand. 0.032 Kg. 135.00 4.32
(c) Cement.(OPC) 0.0460 MT. 6400.00 294.40
Total:- 8298.72
2.0 LABOURS.
(a) Unskilled Mazdoor. 2.00 Each. 350.00 700.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.00 Each. 500.00 500.00
(d) Bhisti. 0.37 Each. 350.00 129.50
Total:- 1329.50
3.0 CARRIAGE OF MATERIALS.
(a) NP2 class 600 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.032 Kg. 262.22 8.39
(c) Cement.(OPC) 0.0460 MT. 210.27 9.67
Total:- 18.06
Add 2% for Sundries & T & P 192.56
Add 8% C.P & O.H. charges 770.26
Total cost for 10.0 RM. Rs. :- 10609.11
Add 1% labour cess 106.09
Total cost for 1.0 RM. Rs. :- 1071.50
Say Rs. :- 1072.00
Item No.: 22
(e) NP-2 class 750 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP2 class 750 mm dia. 10.00 M. 1200.00 12000.00
(b) Sand. 0.032 Kg. 135.00 4.32
(c) Cement.(OPC) 0.0560 MT. 6400.00 358.40
Total:- 12362.72
2.0 LABOURS.
(a) Unskilled Mazdoor. 3.00 Each. 350.00 1050.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.08 Each. 500.00 540.00
(d) Bhisti. 0.42 Each. 350.00 147.00
Total:- 1737.00
3.0 CARRIAGE OF MATERIALS.
(a) NP2 class 750 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.032 Kg. 262.22 8.39
(c) Cement.(OPC) 0.0560 MT. 210.27 11.78
Total:- 20.17
Add 2% for Sundries & T & P 281.99
Add 8% C.P & O.H. charges 1127.98
Total cost for 10.0 RM. Rs. :- 15529.86
Add 1% labour cess 155.30
Total cost for 1.0 RM. Rs. :- 1568.50
Say Rs. :- 1569.00
Item No.: 22
(f) NP-2 class 800 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP2 class 800 mm dia. 10.00 M. 1350.00 13500.00
(b) Sand. 0.032 Kg. 135.00 4.32
(c) Cement.(OPC) 0.0560 MT. 6400.00 358.40
Total:- 13862.72
2.0 LABOURS.
(a) Unskilled Mazdoor. 3.00 Each. 350.00 1050.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.08 Each. 500.00 540.00
(d) Bhisti. 0.42 Each. 350.00 147.00
Total:- 1737.00
3.0 CARRIAGE OF MATERIALS.
(a) NP2 class 800 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.032 Kg. 262.22 8.39
(c) Cement.(OPC) 0.0560 MT. 210.27 11.78
Total:- 20.17
Add 2% for Sundries & T & P 311.99
Add 8% C.P & O.H. charges 1247.98
Total cost for 10.0 RM. Rs. :- 17179.86
Add 1% labour cess 171.80
Total cost for 1.0 RM. Rs. :- 1735.20
Say Rs. :- 1735.00
Item No.: 22
(g) NP-2 class 900 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP2 class 900 mm dia. 10.00 M. 1500.00 15000.00
(b) Sand. 0.050 Kg. 135.00 6.75
(c) Cement.(OPC) 0.0710 MT. 6400.00 454.40
Total:- 15461.15
2.0 LABOURS.
(a) Unskilled Mazdoor. 4.00 Each. 350.00 1400.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.25 Each. 500.00 625.00
(d) Bhisti. 0.50 Each. 350.00 175.00
Total:- 2200.00
3.0 CARRIAGE OF MATERIALS.
(a) NP2 class 900 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.050 Kg. 262.22 13.11
(c) Cement.(OPC) 0.0710 MT. 210.27 14.93
Total:- 28.04
Add 2% for Sundries & T & P 353.22
Add 8% C.P & O.H. charges 1412.89
Total cost for 10.0 RM. Rs. :- 19455.31
Add 1% labour cess 194.55
Total cost for 1.0 RM. Rs. :- 1965.00
Say Rs. :- 1965.00
Item No.: 22
(h) NP-2 class 1050 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP2 class 1050 mm dia. 10.00 M. 1700.00 17000.00
(b) Sand. 0.057 Kg. 135.00 7.70
(c) Cement.(OPC) 0.0810 MT. 6400.00 518.40
Total:- 17526.10
2.0 LABOURS.
(a) Unskilled Mazdoor. 5.00 Each. 350.00 1750.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.70 Each. 500.00 850.00
(d) Bhisti. 0.55 Each. 350.00 192.50
Total:- 2792.50
3.0 CARRIAGE OF MATERIALS.
(a) NP2 class 1050 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.057 Kg. 262.22 14.95
(c) Cement.(OPC) 0.0810 MT. 210.27 17.03
Total:- 31.98
Add 2% for Sundries & T & P 406.37
Add 8% C.P & O.H. charges 1625.49
Total cost for 10.0 RM. Rs. :- 22382.43
Add 1% labour cess 223.82
Total cost for 1.0 RM. Rs. :- 2260.60
Say Rs. :- 2261.00
Item No.: 22
(i) NP-2 class 1100 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP2 class 1100 mm dia. 10.00 M. 1750.00 17500.00
(b) Sand. 0.064 Kg. 135.00 8.64
(c) Cement.(OPC) 0.0920 MT. 6400.00 588.80
Total:- 18097.44
2.0 LABOURS.
(a) Unskilled Mazdoor. 6.00 Each. 350.00 2100.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 2.00 Each. 500.00 1000.00
(d) Bhisti. 0.55 Each. 350.00 192.50
Total:- 3292.50
3.0 CARRIAGE OF MATERIALS.
(a) NP2 class 1100 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.064 Kg. 262.22 16.78
(c) Cement.(OPC) 0.0920 MT. 210.27 19.34
Total:- 36.13
Add 2% for Sundries & T & P 427.80
Add 8% C.P & O.H. charges 1711.20
Total cost for 10.0 RM. Rs. :- 23565.06
Add 1% labour cess 235.65
Total cost for 1.0 RM. Rs. :- 2380.10
Say Rs. :- 2380.00
Item No.: 22
(j) NP-2 class 1200 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP2 class 1200 mm dia. 10.00 M. 1900.00 19000.00
(b) Sand. 0.071 Kg. 135.00 9.59
(c) Cement.(OPC) 0.1000 MT. 6400.00 640.00
Total:- 19649.59
2.0 LABOURS.
(a) Unskilled Mazdoor. 8.00 Each. 350.00 2800.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 2.00 Each. 500.00 1000.00
(d) Bhisti. 0.67 Each. 350.00 234.50
Total:- 4034.50
3.0 CARRIAGE OF MATERIALS.
(a) NP2 class 1200 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.071 Kg. 262.22 18.62
(c) Cement.(OPC) 0.1000 MT. 210.27 21.03
Total:- 39.64
Add 2% for Sundries & T & P 473.68
Add 8% C.P & O.H. charges 1894.73
Total cost for 10.0 RM. Rs. :- 26092.14
Add 1% labour cess 260.92
Total cost for 1.0 RM. Rs. :- 2635.30
Say Rs. :- 2635.00
Item No.:23
Providing and fixing in position (different diameter) I.S NP-3 class reinforced
pipe with caulking the joints with cement mortar 1:1 proportion using jute string
soaked in cementslurry, finishing, joints and laying pipes to the designed grade
and levels, curing etc.complete for all leads and lift.
(a) NP-3 class 300 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP-3 class 300 mm dia. 10.00 M. 750.00 7500.00
(b) Sand. 0.018 Kg. 135.00 2.43
(c) Cement.(OPC) 0.0255 MT. 6400.00 163.20
Total:- 7665.63
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.26 Each. 350.00 441.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.64 Each. 500.00 320.00
(d) Bhisti. 0.20 Each. 350.00 70.00
Total:- 831.00
3.0 CARRIAGE OF MATERIALS.
(a) NP-3 class 300 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.018 Kg. 262.22 4.72
(c) Cement.(OPC) 0.0255 MT. 210.27 5.36
Total:- 10.08
Add 2% for Sundries & T & P 169.93
Add 8% C.P & O.H. charges 679.73
Total cost for 10.0 RM. Rs. :- 9356.37
Add 1% labour cess 93.56
Total cost for 1.0 RM. Rs. :- 945.00
Say Rs. :- 945.00
Item No.: 23
(b) NP-3 class 450 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP-3 class 450 mm dia. 10.00 M. 850.00 8500.00
(b) Sand. 0.029 Kg. 135.00 3.92
(c) Cement.(OPC) 0.0410 MT. 6400.00 262.40
Total:- 8766.32
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.50 Each. 350.00 525.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.75 Each. 500.00 375.00
(d) Bhisti. 0.33 Each. 350.00 115.50
Total:- 1015.50
3.0 CARRIAGE OF MATERIALS.
(a) NP-3 class 450 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.029 Kg. 262.22 7.60
(c) Cement.(OPC) 0.0410 MT. 210.27 8.62
Total:- 16.23
Add 2% for Sundries & T & P 195.64
Add 8% C.P & O.H. charges 782.55
Total cost for 10.0 RM. Rs. :- 10776.22
Add 1% labour cess 107.76
Total cost for 1.0 RM. Rs. :- 1088.40
Say Rs. :- 1088.00
Item No.: 23
(c) NP-3 class 600 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP-3 class 600 mm dia. 10.00 M. 1800.00 18000.00
(b) Sand. 0.032 Kg. 135.00 4.32
(c) Cement.(OPC) 0.0460 MT. 6400.00 294.40
Total:- 18298.72
2.0 LABOURS.
(a) Unskilled Mazdoor. 2.00 Each. 350.00 700.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.00 Each. 500.00 500.00
(d) Bhisti. 0.37 Each. 350.00 129.50
Total:- 1329.50
3.0 CARRIAGE OF MATERIALS.
(a) NP-3 class 600 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.032 Kg. 262.22 8.39
(c) Cement.(OPC) 0.0460 MT. 210.27 9.67
Total:- 18.06
Add 2% for Sundries & T & P 392.56
Add 8% C.P & O.H. charges 1570.26
Total cost for 10.0 RM. Rs. :- 21609.11
Add 1% labour cess 216.09
Total cost for 1.0 RM. Rs. :- 2182.50
Say Rs. :- 2183.00
Item No.: 23
(d) NP-3 class 750 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP2 class 750 mm dia. 10.00 M. 1900.00 19000.00
(b) Sand. 0.032 Kg. 135.00 4.32
(c) Cement.(OPC) 0.0560 MT. 6400.00 358.40
Total:- 19362.72
2.0 LABOURS.
(a) Unskilled Mazdoor. 3.00 Each. 350.00 1050.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.08 Each. 500.00 540.00
(d) Bhisti. 0.42 Each. 350.00 147.00
Total:- 1737.00
3.0 CARRIAGE OF MATERIALS.
(a) NP-3 class 750 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.032 Kg. 262.22 8.39
(c) Cement.(OPC) 0.0560 MT. 210.27 11.78
Total:- 20.17
Add 2% for Sundries & T & P 421.99
Add 8% C.P & O.H. charges 1687.98
Total cost for 10.0 RM. Rs. :- 23229.86
Add 1% labour cess 232.30
Total cost for 1.0 RM. Rs. :- 2346.20
Say Rs. :- 2346.00
Item No.: 23
(e) NP-3 class 900 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP-3 class 900 mm dia. 10.00 M. 2200.00 22000.00
(b) Sand. 0.050 Kg. 135.00 6.75
(c) Cement.(OPC) 0.0710 MT. 6400.00 454.40
Total:- 22461.15
2.0 LABOURS.
(a) Unskilled Mazdoor. 4.00 Each. 350.00 1400.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.25 Each. 500.00 625.00
(d) Bhisti. 0.50 Each. 350.00 175.00
Total:- 2200.00
3.0 CARRIAGE OF MATERIALS.
(a) NP-3 class 900 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.050 Kg. 262.22 13.11
(c) Cement.(OPC) 0.0710 MT. 210.27 14.93
Total:- 28.04
Add 2% for Sundries & T & P 493.22
Add 15% C.P & O.H. charges 3699.17
Total cost for 10.0 RM. Rs. :- 28881.59
Add 1% labour cess 288.82
Total cost for 1.0 RM. Rs. :- 2917.00
Say Rs. :-
Item No.: 23
(f) NP-3 class 1100 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP-3 class 1100 mm dia. 10.00 M. 3300.00 33000.00
(b) Sand. 0.064 Kg. 135.00 8.64
(c) Cement.(OPC) 0.0920 MT. 6400.00 588.80
Total:- 33597.44
2.0 LABOURS.
(a) Unskilled Mazdoor. 6.00 Each. 350.00 2100.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 2.00 Each. 500.00 1000.00
(d) Bhisti. 0.55 Each. 350.00 192.50
Total:- 3292.50
3.0 CARRIAGE OF MATERIALS.
(a) NP-3 class 1100 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.064 Kg. 262.22 16.78
(c) Cement.(OPC) 0.0920 MT. 210.27 19.34
Total:- 36.13
Add 2% for Sundries & T & P 737.80
Add 15% C.P & O.H. charges 5533.49
Total cost for 10.0 RM. Rs. :- 43197.36
Add 1% labour cess 431.97
Total cost for 1.0 RM. Rs. :- 4362.90
Say Rs. :- 4049.30
Item No.: 23
(g) NP-3 class 1200 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) NP-3 class 1200 mm dia. 10.00 M. 3800.00 38000.00
(b) Sand. 0.071 Kg. 135.00 9.59
(c) Cement.(OPC) 0.1000 MT. 6400.00 640.00
Total:- 38649.59
2.0 LABOURS.
(a) Unskilled Mazdoor. 8.00 Each. 350.00 2800.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 2.00 Each. 500.00 1000.00
(d) Bhisti. 0.67 Each. 350.00 234.50
Total:- 4034.50
3.0 CARRIAGE OF MATERIALS.
(a) NP-3 class 1200 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.071 Kg. 262.22 18.62
(c) Cement.(OPC) 0.1000 MT. 210.27 21.03
Total:- 39.64
Add 2% for Sundries & T & P 853.68
Add 15% C.P & O.H. charges 6402.61
Total cost for 10.0 RM. Rs. :- 49980.02
Add 1% labour cess 499.80
Total cost for 1.0 RM. Rs. :- 5048.00
Say Rs. :-
Item No.: 24
Providing and fixing in position (different diameter) I.R.S, NP-4 R.C.C pipe with caulking
the joints with cement mortar 1:1 proportion using jute string soaked in cement slurry,
finishing joints, and laying pipes to the designed grade and levels, curing et
(a) I.R.S/NP-4 class 300 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) I.R.S/NP-4 class 300 mm dia. 10.00 M. 520.00 5200.00
(b) Sand. 0.011 Kg. 135.00 1.49
(c) Cement.(OPC) 0.0150 MT. 6400.00 96.00
Total:- 5297.49
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.26 Each. 350.00 441.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.64 Each. 500.00 320.00
(d) Bhisti. 0.20 Each. 350.00 70.00
Total:- 831.00
3.0 CARRIAGE OF MATERIALS.
(a) I.R.S/NP-4 class 300 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.011 Kg. 262.22 2.88
(c) Cement.(OPC) 0.0150 MT. 210.27 3.15
Total:- 6.04
Add 2% for Sundries & T & P 122.57
Add 15% C.P & O.H. charges 919.27
Total cost for 10.0 RM. Rs. :- 7176.37
Add 1% labour cess 71.76
Total cost for 1.0 RM. Rs. :- 724.80
Say Rs. :-
Item No.: 24
(b) I.R.S/NP-4 class 450 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) I.R.S/NP-4 class 450 mm dia. 10.00 M. 805.00 8050.00
(b) Sand. 0.021 Kg. 135.00 2.84
(c) Cement.(OPC) 0.0310 MT. 6400.00 198.40
Total:- 8251.24
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.50 Each. 350.00 525.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.75 Each. 500.00 375.00
(d) Bhisti. 0.33 Each. 350.00 115.50
Total:- 1015.50
3.0 CARRIAGE OF MATERIALS.
(a) I.R.S/NP-4 class 450 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.021 Kg. 262.22 5.51
(c) Cement.(OPC) 0.0310 MT. 210.27 6.52
Total:- 12.02
Add 2% for Sundries & T & P 185.33
Add 15% C.P & O.H. charges 1390.01
Total cost for 10.0 RM. Rs. :- 10854.10
Add 1% labour cess 108.54
Total cost for 1.0 RM. Rs. :- 1096.30
Say Rs. :-
Item No.: 24
(c) I.R.S/NP-4 class 600 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) I.R.S/NP-4 class 600 mm dia. 10.00 M. 987.00 9870.00
(b) Sand. 0.025 Kg. 135.00 3.38
(c) Cement.(OPC) 0.0360 MT. 6400.00 230.40
Total:- 10103.78
2.0 LABOURS.
(a) Unskilled Mazdoor. 2.00 Each. 350.00 700.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.00 Each. 500.00 500.00
(d) Bhisti. 0.30 Each. 350.00 105.00
Total:- 1305.00
3.0 CARRIAGE OF MATERIALS.
(a) I.R.S/NP-4 class 600 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.025 Kg. 262.22 6.56
(c) Cement.(OPC) 0.0360 MT. 210.27 7.57
Total:- 14.13
Add 2% for Sundries & T & P 228.18
Add 15% C.P & O.H. charges 1711.32
Total cost for 10.0 RM. Rs. :- 13362.39
Add 1% labour cess 133.62
Total cost for 1.0 RM. Rs. :- 1349.60
Say Rs. :-
Item No.: 24
(d) I.R.S/NP-4 class 800 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) I.R.S/NP-4 class 800 mm dia. 10.00 M. 1452.00 14520.00
(b) Sand. 0.032 Kg. 135.00 4.32
(c) Cement.(OPC) 0.0460 MT. 6400.00 294.40
Total:- 14818.72
2.0 LABOURS.
(a) Unskilled Mazdoor. 2.50 Each. 350.00 875.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.90 Each. 500.00 450.00
(d) Bhisti. 0.38 Each. 350.00 133.00
Total:- 1458.00
3.0 CARRIAGE OF MATERIALS.
(a) I.R.S/NP-4 class 800 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.032 Kg. 262.22 8.39
(c) Cement.(OPC) 0.0460 MT. 210.27 9.67
Total:- 18.06
Add 2% for Sundries & T & P 325.53
Add 15% C.P & O.H. charges 2441.51
Total cost for 10.0 RM. Rs. :- 19061.83
Add 1% labour cess 190.62
Total cost for 1.0 RM. Rs. :- 1925.20
Say Rs. :-
Item No.: 24
(e) I.R.S/NP-4 class 900 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) I.R.S/NP-4 class 900 mm dia. 10.00 M. 1730.00 17300.00
(b) Sand. 0.039 Kg. 135.00 5.27
(c) Cement.(OPC) 0.0560 MT. 6400.00 358.40
Total:- 17663.67
2.0 LABOURS.
(a) Unskilled Mazdoor. 3.00 Each. 350.00 1050.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.25 Each. 500.00 625.00
(d) Bhisti. 0.40 Each. 350.00 140.00
Total:- 1815.00
3.0 CARRIAGE OF MATERIALS.
(a) I.R.S/NP-4 class 900 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.039 Kg. 262.22 10.23
(c) Cement.(OPC) 0.0560 MT. 210.27 11.78
Total:- 22.00
Add 2% for Sundries & T & P 389.57
Add 15% C.P & O.H. charges 2921.80
Total cost for 10.0 RM. Rs. :- 22812.04
Add 1% labour cess 228.12
Total cost for 1.0 RM. Rs. :- 2304.00
Say Rs. :-
Item No.: 24
(f) I.R.S/NP-4 class 1050 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) I.R.S/NP-4 class 1050 mm dia. 10.00 M. 2299.00 22990.00
(b) Sand. 0.042 Kg. 135.00 5.67
(c) Cement.(OPC) 0.0600 MT. 6400.00 384.00
Total:- 23379.67
2.0 LABOURS.
(a) Unskilled Mazdoor. 4.00 Each. 350.00 1400.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 2.00 Each. 500.00 1000.00
(d) Bhisti. 0.42 Each. 350.00 147.00
Total:- 2547.00
3.0 CARRIAGE OF MATERIALS.
(a) I.R.S/NP-4 class 1100 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.042 Kg. 262.22 11.01
(c) Cement.(OPC) 0.0600 MT. 210.27 12.62
Total:- 23.63
Add 2% for Sundries & T & P 518.53
Add 15% C.P & O.H. charges 3889.00
Total cost for 10.0 RM. Rs. :- 30357.83
Add 1% labour cess 303.58
Total cost for 1.0 RM. Rs. :- 3066.10
Say Rs. :-
Item No.: 24
(g) I.R.S/NP-4 class 1200 mm dia. pipe.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) I.R.S/NP-4 class 1200 mm dia. 10.00 M. 2880.00 28800.00
(b) Sand. 0.053 Kg. 135.00 7.21
(c) Cement.(OPC) 0.0760 MT. 6400.00 486.40
Total:- 29293.61
2.0 LABOURS.
(a) Unskilled Mazdoor. 5.00 Each. 350.00 1750.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 2.00 Each. 500.00 1000.00
(d) Bhisti. 0.60 Each. 350.00 210.00
Total:- 2960.00
3.0 CARRIAGE OF MATERIALS.
(a) NP-3 class 1200 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.053 Kg. 262.22 14.00
(c) Cement.(OPC) 0.0760 MT. 210.27 15.98
Total:- 29.98
Add 2% for Sundries & T & P 645.07
Add 15% C.P & O.H. charges 4838.04
Total cost for 10.0 RM. Rs. :- 37766.71
Add 1% labour cess 377.67
Total cost for 1.0 RM. Rs. :- 3814.40
Say Rs. :-
Item No.:-25
Providing and fixing in position (different diameter) R.C.C, P1 pressure pipe with
collar including filling and caulking the joints with cement mortar 1:1 proportion,
finishing, curing etc. complete for all lead and lifts.
(a) R.C.C., P1 pressure pipe 150 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P1 pressure pipe 150 mm dia. 10.00 M. 300.00 3000.00
(b) Sand. 0.012 Kg. 135.00 1.62
(c) Cement.(OPC) 0.015 MT. 6400.00 96.00
Total:- 3097.62
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.20 Each. 350.00 420.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.60 Each. 500.00 300.00
(d) Bhisti. 0.18 Each. 350.00 63.00
Total:- 783.00
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P1 pressure pipe 150 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.012 Kg. 262.22 3.15
(c) Cement.(OPC) 0.015 MT. 210.27 3.15
Total:- 6.30
Add 2% for Sundries & T & P 77.61
Add 8% C.P & O.H. charges 310.45
Total cost for 10.0 RM. Rs. :- 4274.98
Add 1% labour cess 42.75
Total cost for 1.0 RM. Rs. :- 431.80
Say Rs. :- 432.00
Item No.:-25
(b) R.C.C., P1 pressure pipe 225 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P1 pressure pipe 225 mm dia. 10.00 M. 254.00 2540.00
(b) Sand. 0.02 Kg. 135.00 2.03
(c) Cement.(OPC) 0.02 MT. 6400.00 128.00
Total:- 2670.03
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.26 Each. 350.00 441.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.64 Each. 500.00 320.00
(d) Bhisti. 0.20 Each. 350.00 70.00
Total:- 831.00
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P1 pressure pipe 225 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.02 Kg. 262.22 3.93
(c) Cement.(OPC) 0.02 MT. 210.27 4.21
Total:- 8.14
Add 2% for Sundries & T & P 70.02
Add 15% C.P & O.H. charges 525.15
Total cost for 10.0 RM. Rs. :- 4104.34
Add 1% labour cess 41.04
Total cost for 1.0 RM. Rs. :- 414.50
Say Rs. :-
Item No.: 25
(c) R.C.C., P1 pressure pipe 300 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P1 pressure pipe 300 mm dia. 10.00 M. 347.00 3470.00
(b) Sand. 0.018 Kg. 135.00 2.43
(c) Cement.(OPC) 0.0255 MT. 6400.00 163.20
Total:- 3635.63
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.26 Each. 350.00 441.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.64 Each. 500.00 320.00
(d) Bhisti. 0.20 Each. 350.00 70.00
Total:- 831.00
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P1 pressure pipe 300 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.018 Kg. 262.22 4.72
(c) Cement.(OPC) 0.0255 MT. 210.27 5.36
Total:- 10.08
Add 2% for Sundries & T & P 89.33
Add 15% C.P & O.H. charges 669.99
Total cost for 10.0 RM. Rs. :- 5236.04
Add 1% labour cess 52.36
Total cost for 1.0 RM. Rs. :- 528.80
Say Rs. :-
Item No.: 25
(d) R.C.C., P1 pressure pipe 450 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P1 pressure pipe 450 mm dia. 10.00 M. 615.00 6150.00
(b) Sand. 0.029 Kg. 135.00 3.92
(c) Cement.(OPC) 0.0410 MT. 6400.00 262.40
Total:- 6416.32
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.50 Each. 350.00 525.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.75 Each. 500.00 375.00
(d) Bhisti. 0.33 Each. 350.00 115.50
Total:- 1015.50
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P1 pressure pipe 450 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.029 Kg. 262.22 7.60
(c) Cement.(OPC) 0.0410 MT. 210.27 8.62
Total:- 16.23
Add 2% for Sundries & T & P 148.64
Add 15% C.P & O.H. charges 1114.77
Total cost for 10.0 RM. Rs. :- 8711.45
Add 1% labour cess 87.11
Total cost for 1.0 RM. Rs. :- 879.90
Say Rs. :-
Item No.: 25
(e) R.C.C., P1 pressure pipe 600 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P1 pressure pipe 600 mm dia. 10.00 M. 854.00 8540.00
(b) Sand. 0.032 Kg. 135.00 4.32
(c) Cement.(OPC) 0.0460 MT. 6400.00 294.40
Total:- 8838.72
2.0 LABOURS.
(a) Unskilled Mazdoor. 2.00 Each. 350.00 700.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.00 Each. 500.00 500.00
(d) Bhisti. 0.37 Each. 350.00 129.50
Total:- 1329.50
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P1 pressure pipe 600 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.032 Kg. 262.22 8.39
(c) Cement.(OPC) 0.0460 MT. 210.27 9.67
Total:- 18.06
Add 2% for Sundries & T & P 203.36
Add 15% C.P & O.H. charges 1525.23
Total cost for 10.0 RM. Rs. :- 11914.88
Add 1% labour cess 119.15
Total cost for 1.0 RM. Rs. :- 1203.40
Say Rs. :-
Item No.: 25
(f) R.C.C., P1 pressure pipe 750 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P1 pressure pipe 750 mm dia. 10.00 M. 1108.00 11080.00
(b) Sand. 0.032 Kg. 135.00 4.32
(c) Cement.(OPC) 0.0560 MT. 6400.00 358.40
Total:- 11442.72
2.0 LABOURS.
(a) Unskilled Mazdoor. 3.00 Each. 350.00 1050.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.08 Each. 500.00 540.00
(d) Bhisti. 0.42 Each. 350.00 147.00
Total:- 1737.00
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P1 pressure pipe 750 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.032 Kg. 262.22 8.39
(c) Cement.(OPC) 0.0560 MT. 210.27 11.78
Total:- 20.17
Add 2% for Sundries & T & P 263.59
Add 15% C.P & O.H. charges 1976.96
Total cost for 10.0 RM. Rs. :- 15440.44
Add 1% labour cess 154.40
Total cost for 1.0 RM. Rs. :- 1559.50
Say Rs. :-
Item No.: 25
(g) R.C.C., P1 pressure pipe 900 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P1 pressure pipe 900 mm dia. 10.00 M. 1507.00 15070.00
(b) Sand. 0.032 Kg. 135.00 4.32
(c) Cement.(OPC) 0.0560 MT. 6400.00 358.40
Total:- 15432.72
2.0 LABOURS.
(a) Unskilled Mazdoor. 3.00 Each. 350.00 1050.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.08 Each. 500.00 540.00
(d) Bhisti. 0.42 Each. 350.00 147.00
Total:- 1737.00
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P1 pressure pipe 900 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.032 Kg. 262.22 8.39
(c) Cement.(OPC) 0.0560 MT. 210.27 11.78
Total:- 20.17
Add 2% for Sundries & T & P 343.39
Add 15% C.P & O.H. charges 2575.46
Total cost for 10.0 RM. Rs. :- 20108.74
Add 1% labour cess 201.09
Total cost for 1.0 RM. Rs. :- 2031.00
Say Rs. :-
Item No.: 25
(h) R.C.C., P1 pressure pipe 1050 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P1 pressure pipe 1050 mm dia. 10.00 M. 1641.00 16410.00
(b) Sand. 0.050 Kg. 135.00 6.75
(c) Cement.(OPC) 0.0710 MT. 6400.00 454.40
Total:- 16871.15
2.0 LABOURS.
(a) Unskilled Mazdoor. 4.00 Each. 350.00 1400.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.25 Each. 500.00 625.00
(d) Bhisti. 0.50 Each. 350.00 175.00
Total:- 2200.00
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P1 pressure pipe 1050 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.050 Kg. 262.22 13.11
(c) Cement.(OPC) 0.0710 MT. 210.27 14.93
Total:- 28.04
Add 2% for Sundries & T & P 381.42
Add 15% C.P & O.H. charges 2860.67
Total cost for 10.0 RM. Rs. :- 22341.29
Add 1% labour cess 223.41
Total cost for 1.0 RM. Rs. :- 2256.50
Say Rs. :-
Item No.: 25
(i) R.C.C., P1 pressure pipe 1200 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P1 pressure pipe 1200 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.057 Kg. 0.00 0.00
(c) Cement.(OPC) 0.0810 MT. 0.00 0.00
Total:- 0.00
2.0 LABOURS.
(a) Unskilled Mazdoor. 5.00 Each. 0.00 0.00
(b) Mason I st. class. 0.00 Each. 0.00 0.00
(c) Mason II nd. class. 1.70 Each. 0.00 0.00
(d) Bhisti. 0.55 Each. 0.00 0.00
Total:- 0.00
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P1 pressure pipe 1200 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.057 Kg. 0.00 0.00
(c) Cement.(OPC) 0.0810 MT. 0.00 0.00
Total:- 0.00
Add 2% for Sundries & T & P 0.00
Add 15% C.P & O.H. charges 0.00
Total cost for 10.0 RM. Rs. :- 0.00
Add 1% labour cess 0.00
Total cost for 1.0 RM. Rs. :- 0.00
Say Rs. :-
Item No.: 25
(j) R.C.C., P1 pressure pipe 1500 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P1 pressure pipe 1500 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.071 Kg. 0.00 0.00
(c) Cement.(OPC) 0.1000 MT. 0.00 0.00
Total:- 0.00
2.0 LABOURS.
(a) Unskilled Mazdoor. 8.00 Each. 0.00 0.00
(b) Mason I st. class. 0.00 Each. 0.00 0.00
(c) Mason II nd. class. 2.00 Each. 0.00 0.00
(d) Bhisti. 0.67 Each. 0.00 0.00
Total:- 0.00
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P1 pressure pipe 1500 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.071 Kg. 0.00 0.00
(c) Cement.(OPC) 0.1000 MT. 0.00 0.00
Total:- 0.00
Add 2% for Sundries & T & P 0.00
Add 15% C.P & O.H. charges 0.00
Total cost for 10.0 RM. Rs. :- 0.00
Add 1% labour cess 0.00
Total cost for 1.0 RM. Rs. :- 0.00
Say Rs. :-
Item No.:-26
Providing and fixing in position (different diameter) R.C.C, P2 pressure pipe with collar
including filling and caulking the joints with cement mortar 1:1 proportion, finishing, curing
etc. complete for all lead and lifts.
(a) R.C.C., P2 pressure pipe 150 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P2 pressure pipe 150 mm dia. 10.00 M. 182.00 1820.00
(b) Sand. 0.012 Kg. 135.00 1.62
(c) Cement.(OPC) 0.015 MT. 6400.00 96.00
Total:- 1917.62
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.20 Each. 350.00 420.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.60 Each. 500.00 300.00
(d) Bhisti. 0.18 Each. 350.00 63.00
Total:- 783.00
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P2 pressure pipe 150 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.012 Kg. 262.22 3.15
(c) Cement.(OPC) 0.015 MT. 210.27 3.15
Total:- 6.30
Add 2% for Sundries & T & P 54.01
Add 15% C.P & O.H. charges 405.09
Total cost for 10.0 RM. Rs. :- 3166.03
Add 1% labour cess 31.66
Total cost for 1.0 RM. Rs. :- 319.80
Say Rs. :-
Item No.:-26
(b) R.C.C., P2 pressure pipe 225 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P2 pressure pipe 225 mm dia. 10.00 M. 297.00 2970.00
(b) Sand. 0.02 Kg. 135.00 2.03
(c) Cement.(OPC) 0.02 MT. 6400.00 128.00
Total:- 3100.03
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.26 Each. 350.00 441.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.64 Each. 500.00 320.00
(d) Bhisti. 0.20 Each. 350.00 70.00
Total:- 831.00
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P2 pressure pipe 225 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.02 Kg. 262.22 3.93
(c) Cement.(OPC) 0.02 MT. 210.27 4.21
Total:- 8.14
Add 2% for Sundries & T & P 78.62
Add 15% C.P & O.H. charges 589.65
Total cost for 10.0 RM. Rs. :- 4607.44
Add 1% labour cess 46.07
Total cost for 1.0 RM. Rs. :- 465.40
Say Rs. :-
Item No.: 26
(c) R.C.C., P2 pressure pipe 300 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P2 pressure pipe 300 mm dia. 10.00 M. 421.00 4210.00
(b) Sand. 0.018 Kg. 135.00 2.43
(c) Cement.(OPC) 0.0255 MT. 6400.00 163.20
Total:- 4375.63
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.26 Each. 350.00 441.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.64 Each. 500.00 320.00
(d) Bhisti. 0.20 Each. 350.00 70.00
Total:- 831.00
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P2 pressure pipe 300 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.018 Kg. 262.22 4.72
(c) Cement.(OPC) 0.0255 MT. 210.27 5.36
Total:- 10.08
Add 2% for Sundries & T & P 104.13
Add 15% C.P & O.H. charges 780.99
Total cost for 10.0 RM. Rs. :- 6101.84
Add 1% labour cess 61.02
Total cost for 1.0 RM. Rs. :- 616.30
Say Rs. :-
Item No.: 26
(d) R.C.C., P2 pressure pipe 450 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P2 pressure pipe 450 mm dia. 10.00 M. 1157.00 11570.00
(b) Sand. 0.029 Kg. 135.00 3.92
(c) Cement.(OPC) 0.0410 MT. 6400.00 262.40
Total:- 11836.32
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.50 Each. 350.00 525.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.75 Each. 500.00 375.00
(d) Bhisti. 0.33 Each. 350.00 115.50
Total:- 1015.50
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P2 pressure pipe 450 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.029 Kg. 262.22 7.60
(c) Cement.(OPC) 0.0410 MT. 210.27 8.62
Total:- 16.23
Add 2% for Sundries & T & P 257.04
Add 15% C.P & O.H. charges 1927.77
Total cost for 10.0 RM. Rs. :- 15052.85
Add 1% labour cess 150.53
Total cost for 1.0 RM. Rs. :- 1520.30
Say Rs. :-
Item No.: 26
(e) R.C.C., P2 pressure pipe 600 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P2 pressure pipe 600 mm dia. 10.00 M. 1876.00 18760.00
(b) Sand. 0.032 Kg. 135.00 4.32
(c) Cement.(OPC) 0.0460 MT. 6400.00 294.40
Total:- 19058.72
2.0 LABOURS.
(a) Unskilled Mazdoor. 2.00 Each. 350.00 700.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.00 Each. 500.00 500.00
(d) Bhisti. 0.37 Each. 350.00 129.50
Total:- 1329.50
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P2 pressure pipe 600 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.032 Kg. 262.22 8.39
(c) Cement.(OPC) 0.0460 MT. 210.27 9.67
Total:- 18.06
Add 2% for Sundries & T & P 407.76
Add 15% C.P & O.H. charges 3058.23
Total cost for 10.0 RM. Rs. :- 23872.28
Add 1% labour cess 238.72
Total cost for 1.0 RM. Rs. :- 2411.10
Item No.: 26
(f) R.C.C., P2 pressure pipe 750 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P2 pressure pipe 750 mm dia. 10.00 M. 2539.00 25390.00
(b) Sand. 0.032 Kg. 135.00 4.32
(c) Cement.(OPC) 0.0560 MT. 6400.00 358.40
Total:- 25752.72
2.0 LABOURS.
(a) Unskilled Mazdoor. 3.00 Each. 350.00 1050.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.08 Each. 500.00 540.00
(d) Bhisti. 0.42 Each. 350.00 147.00
Total:- 1737.00
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P2 pressure pipe 750 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.032 Kg. 262.22 8.39
(c) Cement.(OPC) 0.0560 MT. 210.27 11.78
Total:- 20.17
Add 2% for Sundries & T & P 549.79
Add 15% C.P & O.H. charges 4123.46
Total cost for 10.0 RM. Rs. :- 32183.14
Add 1% labour cess 321.83
Total cost for 1.0 RM. Rs. :- 3250.50
Say Rs. :-
Item No.: 26
(g) R.C.C., P2 pressure pipe 900 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P2 pressure pipe 900 mm dia. 10.00 M. 4145.00 41450.00
(b) Sand. 0.032 Kg. 135.00 4.32
(c) Cement.(OPC) 0.0560 MT. 6400.00 358.40
Total:- 41812.72
2.0 LABOURS.
(a) Unskilled Mazdoor. 3.00 Each. 350.00 1050.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.08 Each. 500.00 540.00
(d) Bhisti. 0.42 Each. 350.00 147.00
Total:- 1737.00
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P2 pressure pipe 900 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.032 Kg. 262.22 8.39
(c) Cement.(OPC) 0.0560 MT. 210.27 11.78
Total:- 20.17
Add 2% for Sundries & T & P 870.99
Add 15% C.P & O.H. charges 6532.46
Total cost for 10.0 RM. Rs. :- 50973.34
Add 1% labour cess 509.73
Total cost for 1.0 RM. Rs. :- 5148.30
Say Rs. :-
Item No.: 26
(h) R.C.C., P2 pressure pipe 1050 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P2 pressure pipe 1050 mm dia. 10.00 M. 4986.00 49860.00
(b) Sand. 0.050 Kg. 135.00 6.75
(c) Cement.(OPC) 0.0710 MT. 6400.00 454.40
Total:- 50321.15
2.0 LABOURS.
(a) Unskilled Mazdoor. 4.00 Each. 350.00 1400.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.25 Each. 500.00 625.00
(d) Bhisti. 0.50 Each. 350.00 175.00
Total:- 2200.00
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P2 pressure pipe 1050 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.050 Kg. 262.22 13.11
(c) Cement.(OPC) 0.0710 MT. 210.27 14.93
Total:- 28.04
Add 2% for Sundries & T & P 1050.42
Add 15% C.P & O.H. charges 7878.17
Total cost for 10.0 RM. Rs. :- 61477.79
Add 1% labour cess 614.78
Total cost for 1.0 RM. Rs. :- 6209.30
Say Rs. :-
Item No.: 26
(i) R.C.C., P2 pressure pipe 1200 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P2 pressure pipe 1200 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.057 Kg. 0.00 0.00
(c) Cement.(OPC) 0.0810 MT. 0.00 0.00
Total:- 0.00
2.0 LABOURS.
(a) Unskilled Mazdoor. 5.00 Each. 0.00 0.00
(b) Mason I st. class. 0.00 Each. 0.00 0.00
(c) Mason II nd. class. 1.70 Each. 0.00 0.00
(d) Bhisti. 0.55 Each. 0.00 0.00
Total:- 0.00
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P2 pressure pipe 1200 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.057 Kg. 0.00 0.00
(c) Cement.(OPC) 0.0810 MT. 0.00 0.00
Total:- 0.00
Add 2% for Sundries & T & P 0.00
Add 15% C.P & O.H. charges 0.00
Total cost for 10.0 RM. Rs. :- 0.00
Add 1% labour cess 0.00
Total cost for 1.0 RM. Rs. :- 0.00
Say Rs. :-
Item No.: 26
(j) R.C.C., P2 pressure pipe 1500 mm dia.
A RATE ANALYSIS FOR 10.0 RM.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) R.C.C., P2 pressure pipe 1500 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.071 Kg. 0.00 0.00
(c) Cement.(OPC) 0.1000 MT. 0.00 0.00
Total:- 0.00
2.0 LABOURS.
(a) Unskilled Mazdoor. 8.00 Each. 0.00 0.00
(b) Mason I st. class. 0.00 Each. 0.00 0.00
(c) Mason II nd. class. 2.00 Each. 0.00 0.00
(d) Bhisti. 0.67 Each. 0.00 0.00
Total:- 0.00
3.0 CARRIAGE OF MATERIALS.
(a) R.C.C., P2 pressure pipe 1500 mm dia. 10.00 M. 0.00 0.00
(b) Sand. 0.071 Kg. 0.00 0.00
(c) Cement.(OPC) 0.1000 MT. 0.00 0.00
Total:- 0.00
Add 2% for Sundries & T & P 0.00
Add 15% C.P & O.H. charges 0.00
Total cost for 10.0 RM. Rs. :- 0.00
Add 1% labour cess 0.00
Total cost for 1.0 RM. Rs. :- 0.00
Say Rs. :-
Item No.: 27
Providing and laying uncoarsed rubble masonary in ordinary portland cement mortar 1:5
proportion in foundation including curing etc. complete for all lead and lifts.
A RATE ANALYSIS FOR 1.0 Cum.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Rubble 1.00 Cum. 170.00 170.00
(b) Sand. 0.350 Cum. 135.00 47.25
(c) Cement.(OPC) 0.1050 MT. 6400.00 672.00
(d) Through & bond stone. 7.0000 No. 25.00 175.00
Total:- 1064.25
2.0 LABOURS.
(a) Unskilled Mazdoor. 2.00 Each. 350.00 700.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.70 Each. 500.00 350.00
(d) Bhisti. 0.15 Each. 350.00 52.50
Total:- 1102.50
3.0 CARRIAGE OF MATERIALS.
(a) Rubble 1.00 M. 410.44 410.44
(b) Sand. 0.350 Kg. 262.22 91.78
(c) Cement.(OPC) 0.1050 MT. 210.27 22.08
(d) Through & bond stone. 7.0000 No. 0.00 0.00
Total:- 524.30
Add 2% for Sundries & T & P 43.34
Add 15% C.P & O.H. charges 325.01
Total cost for 1.0 M3. Rs. :- 3059.39
Add 1% labour cess 30.59
Total cost for 1.0 M3. Rs. :- 3090.00
Item No.: 28
Providing and laying uncoarsed rubble masonary in ordinary portland cement mortar 1:5
proportion in superstructure including scaffolding, racking out joints, curing etc. complete for
all lead and lifts.
A RATE ANALYSIS FOR 1.0 Cum.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Rubble 1.00 Cum. 170.00 170.00
(b) Sand. 0.350 Cum. 135.00 47.25
(c) Cement.(OPC) 0.1050 MT. 6400.00 672.00
(d) Through & bond stone. 7.0000 No. 25.00 175.00
Total:- 1064.25
2.0 LABOURS.
(a) Unskilled Mazdoor. 2.50 Each. 350.00 875.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.80 Each. 500.00 400.00
(d) Bhisti. 0.20 Each. 350.00 70.00
Total:- 1345.00
3.0 CARRIAGE OF MATERIALS.
(a) Rubble 1.00 CM. 410.44 410.44
(b) Sand. 0.350 Kg. 262.22 91.78
(c) Cement.(OPC) 0.1050 MT. 210.27 22.08
(d) Through & bond stone. 7.0000 No. 0.00 0.00
Total:- 524.30
Add 2% for Sundries & T & P 48.19
Add 15% C.P & O.H. charges 361.39
Total cost for 1.0 M3. Rs. :- 3343.12
Add 1% labour cess 33.43
Total cost for 1.0 M3. Rs. :- 3376.50
Item No.: 29
Providing and laying coarsed rubble masonary in ordinary portland cement mortar 1:5
proportion in superstructure including scaffolding, racking out joints, curing etc. complete for
all lead and lifts.
A RATE ANALYSIS FOR 1.0 Cum.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Rubble 1.10 Cum. 170.00 187.00
(b) Sand. 0.320 Cum. 135.00 43.20
(c) Cement.(OPC) 0.0960 MT. 6400.00 614.40
Total:- 844.60
2.0 LABOURS.
(a) Unskilled Mazdoor. 2.60 Each. 350.00 910.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.00 Each. 500.00 500.00
(d) Bhisti. 0.20 Each. 350.00 70.00
Total:- 1480.00
3.0 CARRIAGE OF MATERIALS.
(a) Rubble 1.10 CM. 410.44 451.48
(b) Sand. 0.320 Kg. 262.22 83.91
(c) Cement.(OPC) 0.0960 MT. 210.27 20.19
Total:- 555.58
Add 2% for Sundries & T & P 46.49
Add 15% C.P & O.H. charges 348.69
Total cost for 1.0 M3. Rs. :- 3275.36
Add 1% labour cess 32.75
Total cost for 1.0 M3. Rs. :- 3308.10
Item No.: 30
Providing and laying burnt brick (conventional size) masonary for foundation in ordinary
portland cement mortar 1:6 proportion including racking out joints upto 15mm. depth curing
etc. complete for all lead and lifts.
A RATE ANALYSIS FOR 1.0 Cum.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Bricks 520.00 No. 2.30 1196.00
(b) Sand. 0.220 Cum. 135.00 29.70
(c) Cement.(OPC) 0.0530 MT. 6400.00 339.20
Total:- 1564.90
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.80 Each. 350.00 630.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.50 Each. 500.00 250.00
(d) Bhisti. 0.20 Each. 350.00 70.00
Total:- 950.00
3.0 CARRIAGE OF MATERIALS.
(a) Bricks 520.00 No. 0.38 197.93
(b) Sand. 0.220 Kg. 262.22 57.69
(c) Cement.(OPC) 0.0530 MT. 210.27 11.14
Total:- 266.77
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 50.60
Add 15% C.P & O.H. charges 379.49
Total cost for 1.0 M3. Rs. :- 3226.75
Add 1% labour cess 32.27
Total cost for 1.0 M3. Rs. :- 3259.00
Item No.: 31 2040.80
Providing and laying burnt brick (conventional size) masonary for foundation in ordinary
portland cement mortar 1:5 proportion including racking out joints upto 15mm. depth curing
etc. complete for all lead and lifts.
A RATE ANALYSIS FOR 1.0 Cum.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Bricks 520.00 No. 2.30 1196.00
(b) Sand. 0.220 Cum. 135.00 29.70
(c) Cement.(OPC) 0.0650 MT. 6400.00 416.00
Total:- 1641.70
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.80 Each. 350.00 630.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.50 Each. 500.00 250.00
(d) Bhisti. 0.20 Each. 350.00 70.00
Total:- 950.00
3.0 CARRIAGE OF MATERIALS.
(a) Bricks 520.00 No. 0.38 197.93
(b) Sand. 0.220 Kg. 262.22 57.69
(c) Cement.(OPC) 0.0650 MT. 210.27 13.67
Total:- 269.29
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 52.13
Add 15% C.P & O.H. charges 391.01
Total cost for 1.0 M3. Rs. :- 3319.13
Add 1% labour cess 33.19
Total cost for 1.0 M3. Rs. :- 3352.30
Item No.: 32 2111.30
Providing and laying burnt brick (conventional size) masonary for superstructure in
ordinary portland cement mortar 1:6 proportion including racking out joints upto 15mm. depth
curing etc. complete for all lead and lifts.
A RATE ANALYSIS FOR 1.0 Cum.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Bricks 520.00 No. 2.30 1196.00
(b) Sand. 0.220 Cum. 135.00 29.70
(c) Cement.(OPC) 0.0530 MT. 6400.00 339.20
Total:- 1564.90
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.80 Each. 350.00 630.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.50 Each. 500.00 250.00
(d) Bhisti. 0.25 Each. 350.00 87.50
Total:- 967.50
3.0 CARRIAGE OF MATERIALS.
(a) Bricks 520.00 No. 0.38 197.93
(b) Sand. 0.220 Kg. 262.22 57.69
(c) Cement.(OPC) 0.0530 MT. 210.27 11.14
Total:- 266.77
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 50.95
Add 15% C.P & O.H. charges 382.11
Total cost for 1.0 M3. Rs. :- 3247.22
Add 1% labour cess 32.47
Total cost for 1.0 M3. Rs. :- 3279.70
Item No.: 33
Providing and laying burnt brick (conventional size) masonary for superstructure in
ordinary portland cement mortar 1:5 proportion including racking out joints upto 15mm. depth
curing etc. complete for all lead and lifts.
A RATE ANALYSIS FOR 1.0 Cum.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Bricks 500.00 No. 2.30 1150.00
(b) Sand. 0.220 Cum. 135.00 29.70
(c) Cement.(OPC) 0.0650 MT. 6400.00 416.00
Total:- 1595.70
2.0 LABOURS.
(a) Unskilled Mazdoor. 2.00 Each. 350.00 700.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.60 Each. 500.00 300.00
(d) Bhisti. 0.25 Each. 350.00 87.50
Total:- 1087.50
3.0 CARRIAGE OF MATERIALS.
(a) Bricks 500.00 No. 0.38 190.32
(b) Sand. 0.220 Kg. 262.22 57.69
(c) Cement.(OPC) 0.0650 MT. 210.27 13.67
Total:- 261.68
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 53.96
Add 15% C.P & O.H. charges 404.73
Total cost for 1.0 M3. Rs. :- 3418.57
Add 1% labour cess 34.19
Total cost for 1.0 M3. Rs. :- 3452.80
Item No.: 34 2125.76
Providing water proof cement plaster 20mm thick in cement mortar 1:3 proportion with
one kilogram of water proofing material per bag (50Kg) of cement including cleaning the
surface, neat finishing, curing scaffoldong etc. complete for all leads and lifts.
A RATE ANALYSIS FOR 100.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Water proofing materials. 22.40 Kg. 40.00 896.00
(b) Sand. 2.350 Cum. 135.00 317.25
(c) Cement.(OPC) 1.1200 MT. 6400.00 7168.00
Total:- 8381.25
2.0 LABOURS.
(a) Unskilled Mazdoor. 15.00 Each. 350.00 5250.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 10.00 Each. 500.00 5000.00
(d) Bhisti. 7.00 Each. 350.00 2450.00
Total:- 12700.00
3.0 CARRIAGE OF MATERIALS.
(a) Water proofing materials. 22.40 M. 0.00 0.00
(b) Sand. 2.350 Kg. 262.22 616.22
(c) Cement.(OPC) 1.1200 MT. 210.27 235.50
Total:- 851.72
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 421.93
Add 15% C.P & O.H. charges 3164.44
Total cost for 100.0 M2. Rs. :- 25534.33
Add 1% labour cess 255.34
Total cost for 1.0 M2. Rs. :- Say:- 257.90 257.90
Item No.: 35
Providing cement plaster in various thickness and proportion including smooth
finishing, curing, scaffolding etc. complete for all leads and lifts as under.
(a) Cement mortar 1:3 proportion.
(i) 20.00mm thickness.
A RATE ANALYSIS FOR 100.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Water proofing materials. 0.00 Kg. 40.00 0.00
(b) Sand. 2.350 Cum. 135.00 317.25
(c) Cement.(OPC) 1.1200 MT. 6400.00 7168.00
Total:- 7485.25
2.0 LABOURS.
(a) Unskilled Mazdoor. 15.00 Each. 350.00 5250.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 10.00 Each. 500.00 5000.00
(d) Bhisti. 7.00 Each. 350.00 2450.00
Total:- 12700.00
3.0 CARRIAGE OF MATERIALS.
(a) Water proofing materials. 0.00 M. 0.00 0.00
(b) Sand. 2.350 Kg. 262.22 616.22
(c) Cement.(OPC) 1.1200 MT. 210.27 235.50
Total:- 851.72
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 404.01
Add 15% C.P & O.H. charges 3030.04
Total cost for 100.0 M2. Rs. :- 24486.01
Add 1% labour cess 244.86
Total cost for 1.0 M2. Rs. :- Say:- 247.30 247.30
Item No.: 35
(a) Cement mortar 1:3 proportion.
(ii) 12.00mm thickness.
A RATE ANALYSIS FOR 100.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Water proofing materials. 0.00 Kg. 40.00 0.00
(b) Sand. 1.420 Cum. 135.00 191.70
(c) Cement.(OPC) 0.6700 MT. 6400.00 4288.00
Total:- 4479.70
2.0 LABOURS.
(a) Unskilled Mazdoor. 10.00 Each. 350.00 3500.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 7.00 Each. 500.00 3500.00
(d) Bhisti. 5.00 Each. 350.00 1750.00
Total:- 8750.00
3.0 CARRIAGE OF MATERIALS.
(a) Water proofing materials. 0.00 Kg. 0.00 0.00
(b) Sand. 1.420 Kg. 262.22 372.35
(c) Cement.(OPC) 0.6700 MT. 210.27 140.88
Total:- 513.23
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 264.89
Add 15% C.P & O.H. charges 1986.71
Total cost for 100.0 M2. Rs. :- 16009.53
Add 1% labour cess 160.10
Total cost for 1.0 M2. Rs. :- Say:- 161.70 161.70
Item No.: 35
(a) Cement mortar 1:2 proportion.
(i) 20.00mm thickness.
A RATE ANALYSIS FOR 100.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Water proofing materials. 0.00 Kg. 40.00 0.00
(b) Sand. 2.100 Cum. 135.00 283.50
(c) Cement.(OPC) 1.5000 MT. 6400.00 9600.00
Total:- 9883.50
2.0 LABOURS.
(a) Unskilled Mazdoor. 15.00 Each. 350.00 5250.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 10.00 Each. 500.00 5000.00
(d) Bhisti. 7.00 Each. 350.00 2450.00
Total:- 12700.00
3.0 CARRIAGE OF MATERIALS.
(a) Water proofing materials. 0.00 Kg. 0.00 0.00
(b) Sand. 2.100 Kg. 262.22 550.66
(c) Cement.(OPC) 1.5000 MT. 210.27 315.41
Total:- 866.07
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 451.97
Add 15% C.P & O.H. charges 3389.78
Total cost for 100.0 M2. Rs. :- 27306.31
Add 1% labour cess 273.06
Total cost for 1.0 M2. Rs. :- Say:- 275.80 275.80
Item No.: 35
(a) Cement mortar 1:2 proportion.
(ii) 12.00mm thickness.
A RATE ANALYSIS FOR 100.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Water proofing materials. 0.00 Kg. 40.00 0.00
(b) Sand. 1.200 Cum. 135.00 162.00
(c) Cement.(OPC) 0.9000 MT. 6400.00 5760.00
Total:- 5922.00
2.0 LABOURS.
(a) Unskilled Mazdoor. 10.00 Each. 350.00 3500.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 7.00 Each. 500.00 3500.00
(d) Bhisti. 5.00 Each. 350.00 1750.00
Total:- 8750.00
3.0 CARRIAGE OF MATERIALS.
(a) Water proofing materials. 0.00 M. 0.00 0.00
(b) Sand. 1.200 Kg. 262.22 314.66
(c) Cement.(OPC) 0.9000 MT. 210.27 189.24
Total:- 503.91
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 293.74
Add 15% C.P & O.H. charges 2203.05
Total cost for 100.0 M2. Rs. :- 17687.70
Add 1% labour cess 176.88
Total cost for 1.0 M2. Rs. :- Say:- 178.60 178.60
Item No.: 36
Providing epoxy plaster 6mm to 8mm average thickness with suitable spcified resin,
hardner and aggregates as per I.S-9162 in proportion 0.7:0.3:6.5 by weight spcified on
exposed damaged, old and rough surface of aqueduct as with prior application of necessary
primer coat of hardner and resin in proportion 2:1 by weight confirming I.S-9197 to give proper
bond between old surface and epoxy plaster including necessary cleaning, scraping of old
surface of existing concrete including scaffolding tool bars for job w
A RATE ANALYSIS FOR 100.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
0.00 0.00
0.00 0.00
0.00 0.00
Total:- 0.00
2.0 LABOURS.
(a) Unskilled Mazdoor. 10.00 Each. 0.00 0.00
(b) Mason I st. class. 0.00 Each. 0.00 0.00
(c) Mason II nd. class. 7.00 Each. 0.00 0.00
(d) Bhisti. 5.00 Each. 0.00 0.00
Total:- 0.00
3.0 CARRIAGE OF MATERIALS.
0.00 0.00
0.00 0.00
0.00 0.00
Total:- 0.00
4.0 SCAFFOLDING LS 0.00 0.00
Add 2% for Sundries & T & P 0.00
Add 15% C.P & O.H. charges 0.00
Total cost for 100.0 M2. Rs. :- 0.00
Add 1% labour cess 0.00
Total cost for 1.0 M2. Rs. :- Say:- 0.00 0.00
Item No.: 37
Providing and laying 300 mm thick pucca rubble pitching in cement mortar 1:5
proportion with the surface pointed with cement mortar of 1:3 proportion including curing etc.
complete for all leads & lifts.
A RATE ANALYSIS FOR 10.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Rubble 3.00 Cum. 170.00 510.00
(b) Sand. 1.100 Cum. 135.00 148.50
(c) Cement.(OPC) 0.4000 MT. 6400.00 2560.00
Total:- 3218.50
2.0 LABOURS.
(a) Unskilled Mazdoor. 5.00 Each. 350.00 1750.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.00 Each. 500.00 500.00
(d) Bhisti. 0.50 Each. 350.00 175.00
Total:- 2425.00
3.0 CARRIAGE OF MATERIALS.
(a) Rubble 3.00 Cum. 410.44 1231.32
(b) Sand. 1.100 Cum. 262.22 288.44
(c) Cement.(OPC) 0.4000 MT. 210.27 84.11
Total:- 1603.87
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 113.17
Add 15% C.P & O.H. charges 848.78
Total cost for 10.0 M2. Rs. :- 8224.32
Add 1% labour cess 82.24
Total cost for 1.0 M2. Rs. :- Say:- 830.70 830.70
Item No.: 38
Providing and laying 230 mm thick pucca rubble pitching in cement mortar 1:5
proportion with the surface pointed with cement mortar of 1:3 proportion including curing etc.
complete for all leads & lifts.
A RATE ANALYSIS FOR 10.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Rubble 2.30 Cum. 170.00 391.00
(b) Sand. 1.000 Cum. 135.00 135.00
(c) Cement.(OPC) 0.3300 MT. 6400.00 2112.00
Total:- 2638.00
2.0 LABOURS.
(a) Unskilled Mazdoor. 4.00 Each. 350.00 1400.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.00 Each. 500.00 500.00
(d) Bhisti. 0.40 Each. 350.00 140.00
Total:- 2040.00
3.0 CARRIAGE OF MATERIALS.
(a) Rubble 2.30 Cum. 410.44 944.01
(b) Sand. 1.000 Cum. 262.22 262.22
(c) Cement.(OPC) 0.3300 MT. 210.27 69.39
Total:- 1275.62
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 93.86
Add 15% C.P & O.H. charges 703.95
Total cost for 10.0 M2. Rs. :- 6766.43
Add 1% labour cess 67.66
Total cost for 1.0 M2. Rs. :- Say:- 683.40 683.40
Item No.: 39
Providing and laying 450 mm thick pucca rubble pitching laid in cement mortar 1:5
proportion with the surface pointed with cement mortar of 1:3 proportion including curing etc.
complete for all leads & lifts.
A RATE ANALYSIS FOR 10.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Rubble 4.72 Cum. 170.00 802.40
(b) Sand. 1.670 Cum. 135.00 225.45
(c) Cement.(OPC) 0.5000 MT. 6400.00 3200.00
Total:- 4227.85
2.0 LABOURS.
(a) Unskilled Mazdoor. 7.00 Each. 350.00 2450.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.00 Each. 500.00 500.00
(d) Bhisti. 0.50 Each. 350.00 175.00
Total:- 3125.00
3.0 CARRIAGE OF MATERIALS.
(a) Rubble 4.72 Cum. 410.44 1937.28
(b) Sand. 1.670 Cum. 262.22 437.91
(c) Cement.(OPC) 0.5000 MT. 210.27 105.14
Total:- 2480.32
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 147.36
Add 15% C.P & O.H. charges 1105.18
Total cost for 10.0 M2. Rs. :- 11100.70
Add 1% labour cess 111.01
Total cost for 1.0 M2. Rs. :- Say:- 1121.20 1121.20
Item No.: 40
Providing and laying pucca rubble pitching laid in cement mortar 1:4 proportion with the
surface pointed with cement mortar of 1:3 proportion for following thickness including curing
etc. complete for all leads & lifts.
(a) For 40cm thickness.
A RATE ANALYSIS FOR 10.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Rubble 5.00 Cum. 170.00 850.00
(b) Sand. 1.500 Cum. 135.00 202.50
(c) Cement.(OPC) 0.5500 MT. 6400.00 3520.00
Total:- 4572.50
2.0 LABOURS.
(a) Unskilled Mazdoor. 8.00 Each. 350.00 2800.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 6.00 Each. 500.00 3000.00
(d) Bhisti. 0.80 Each. 350.00 280.00
Total:- 6080.00
3.0 CARRIAGE OF MATERIALS.
(a) Rubble 5.00 Cum. 410.44 2052.20
(b) Sand. 1.500 Cum. 262.22 393.33
(c) Cement.(OPC) 0.5500 MT. 210.27 115.65
Total:- 2561.18
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 213.35
Add 15% C.P & O.H. charges 1600.13
Total cost for 10.0 M2. Rs. :- 15042.15
Add 1% labour cess 150.42
Total cost for 1.0 M2. Rs. :- Say:- 1519.30 1519.30
Item No.: 40
(b) For 30cm thickness.
A RATE ANALYSIS FOR 10.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Rubble 3.70 Cum. 170.00 629.00
(b) Sand. 1.800 Cum. 135.00 243.00
(c) Cement.(OPC) 0.4500 MT. 6400.00 2880.00
Total:- 3752.00
2.0 LABOURS.
(a) Unskilled Mazdoor. 8.00 Each. 350.00 2800.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 6.00 Each. 500.00 3000.00
(d) Bhisti. 0.80 Each. 350.00 280.00
Total:- 6080.00
3.0 CARRIAGE OF MATERIALS.
(a) Rubble 3.70 Cum. 410.44 1518.63
(b) Sand. 1.800 Cum. 262.22 472.00
(c) Cement.(OPC) 0.4500 MT. 210.27 94.62
Total:- 2085.25
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 196.94
Add 15% C.P & O.H. charges 1477.05
Total cost for 10.0 M2. Rs. :- 13606.24
Add 1% labour cess 136.06
Total cost for 1.0 M2. Rs. :- Say:- 1374.20 1374.20
Item No.: 40
(c) For 23cm thickness.
A RATE ANALYSIS FOR 10.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Rubble 2.80 Cum. 170.00 476.00
(b) Sand. 0.800 Cum. 135.00 108.00
(c) Cement.(OPC) 0.3500 MT. 6400.00 2240.00
Total:- 2824.00
2.0 LABOURS.
(a) Unskilled Mazdoor. 8.00 Each. 350.00 2800.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 6.00 Each. 500.00 3000.00
(d) Bhisti. 0.80 Each. 350.00 280.00
Total:- 6080.00
3.0 CARRIAGE OF MATERIALS.
(a) Rubble 2.80 Cum. 410.44 1149.23
(b) Sand. 0.800 Cum. 262.22 209.78
(c) Cement.(OPC) 0.3500 MT. 210.27 73.59
Total:- 1432.60
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 178.38
Add 15% C.P & O.H. charges 1337.85
Total cost for 10.0 M2. Rs. :- 11867.83
Add 1% labour cess 118.68
Total cost for 1.0 M2. Rs. :- 1198.70
Item No.: 41
Providing panel pitching having panels of 3.0m x 3.0m with U.C.R masonary in cement
mortar 1:5, 0.45m wide and 0.60m deep around panels including filling the panels with dry
rubble 0.45m thick and filling the voids with earth as directed.
A RATE ANALYSIS FOR 1.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) U.C.R Masonary in C.M 1:5. 1.74 Cum. 3376.50 5880.17
(b) Dry rubble pitching. 4.050 Cum. 522.20 2114.91
Rate per Cum of pitching (for dry pitching) 4699.80
Total cost for 15.21 M2. Rs. :- 4699.80
Add 1% labour cess 47.00
Total cost for 1.0 M2. Rs. :- Say:- 312.10 312.10
Item No.: 42
Providing panel pitching having panels of 3.0m x 3.0m in cement concrete 1:3:6, 0.30
wide and 0.60m deep around panels including filling the panels with dry rubble 0.45m thick
and filling the voids with earth as directed.
A RATE ANALYSIS FOR 1.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Cost of cement concrete. 1.13 Cum. 4588.50 5203.36
(b) Dry rubble pitching. 4.050 Cum. 522.20 2114.91
Cost of dry rubble pitching 7318.27
Total cost for 15.21 M2. Rs. :- 7318.27
Add 1% labour cess 73.18
Total cost for 1.0 M2. Rs. :- Say:- 486.00 486.00
Item No.: 43
Providing and laying dry rubble pitching of various thickness to required grade
including trimming of earth work , hand packing the interstices with spauls, filling earth in
interstices panneling complete for all leads and lifts.
(a) For 300mm thickness.
A RATE ANALYSIS FOR 1.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Rubble 0.375 Cum. 170.00 63.75
(b) Sand. 0.000 Cum. 135.00 0.00
(c) Cement.(OPC) 0.0000 MT. 6400.00 0.00
Total:- 63.75
2.0 LABOURS.
(a) Unskilled Mazdoor. 0.20 Each. 350.00 70.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.10 Each. 500.00 50.00
(d) Bhisti. 0.00 Each. 350.00 0.00
Total:- 120.00
3.0 CARRIAGE OF MATERIALS.
(a) Rubble 0.38 Cum. 410.44 153.92
(b) Sand. 0.000 Cum. 262.22 0.00
(c) Cement.(OPC) 0.0000 MT. 210.27 0.00
Total:- 153.92
4.0 SCAFFOLDING LS 0.00 0.00
Add 2% for Sundries & T & P 3.68
Add 15% C.P & O.H. charges 27.56
Total cost for 1.0 M2. Rs. :- 368.90
Total cost for 1.0 M2. Rs. :- 369.00
Add 1% labour cess 3.69
Total cost for 1.0 M2. Rs. :- Say:- 372.70 372.70
Item No.: 43
(b) For 450mm thickness.
A RATE ANALYSIS FOR 1.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Rubble 0.560 Cum. 170.00 95.20
(b) Sand. 0.000 Cum. 135.00 0.00
(c) Cement.(OPC) 0.0000 MT. 6400.00 0.00
Total:- 95.20
2.0 LABOURS.
(a) Unskilled Mazdoor. 0.25 Each. 350.00 87.50
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.13 Each. 500.00 62.50
(d) Bhisti. 0.00 Each. 350.00 0.00
Total:- 150.00
3.0 CARRIAGE OF MATERIALS.
(a) Rubble 0.56 Cum. 410.44 229.85
(b) Sand. 0.000 Cum. 262.22 0.00
(c) Cement.(OPC) 0.0000 MT. 210.27 0.00
Total:- 229.85
4.0 SCAFFOLDING LS 0.00 0.00
Add 2% for Sundries & T & P 4.90
Add 15% C.P & O.H. charges 36.78
Total cost for 1.0 M2. Rs. :- 516.73
Total cost for 1.0 M2. Rs. :- 517.00
Add 1% labour cess 5.17
Total cost for 1.0 M2. Rs. :- Say:- 522.20 522.20
Item No.: 43
(c) For 600mm thickness.
A RATE ANALYSIS FOR 1.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Rubble 0.750 Cum. 170.00 127.50
(b) Sand. 0.000 Cum. 135.00 0.00
(c) Cement.(OPC) 0.0000 MT. 6400.00 0.00
Total:- 127.50
2.0 LABOURS.
(a) Unskilled Mazdoor. 0.30 Each. 350.00 105.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 0.15 Each. 500.00 75.00
(d) Bhisti. 0.00 Each. 350.00 0.00
Total:- 180.00
3.0 CARRIAGE OF MATERIALS.
(a) Rubble 0.75 Cum. 410.44 307.83
(b) Sand. 0.000 Cum. 262.22 0.00
(c) Cement.(OPC) 0.0000 MT. 210.27 0.00
Total:- 307.83
4.0 SCAFFOLDING LS 0.00 0.00
Add 2% for Sundries & T & P 6.15
Add 15% C.P & O.H. charges 46.13
Total cost for 1.0 M2. Rs. :- 667.61
Add 1% labour cess 6.68
Total cost for 1.0 M2. Rs. :- Say:- 674.30 674.30
Item No.: 44
Providing cement mortar pointing to the brick masonary in proportion as under after
racking out joints 20mm deep including smooth finishing, curing scaffolding etc. complete for
all leads and lifts.
(a) Cement mortar 1:2 proportion.
A RATE ANALYSIS FOR 100.0 Sqm.
Sr. Rate Amount
Description Qty Unit
Sr. Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Sand. 0.350 Cum. 135.00 47.25
(b) Cement.(OPC) 0.2500 MT. 6400.00 1600.00
Total:- 1647.25
2.0 LABOURS.
(a) Unskilled Mazdoor. 9.00 Each. 350.00 3150.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 6.00 Each. 500.00 3000.00
(d) Bhisti. 5.00 Each. 350.00 1750.00
Total:- 7900.00
3.0 CARRIAGE OF MATERIALS.
(a) Sand. 0.350 Cum. 262.22 91.78
(b) Cement.(OPC) 0.2500 MT. 210.27 52.57
Total:- 144.34
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 191.25
Add 15% C.P & O.H. charges 1434.34
Total cost for 100.0 M2. Rs. :- 11332.18
Add 1% labour cess 113.32
Total cost for 1.0 M2. Rs. :- Say :- 114.50 114.50
Item No.: 44
(b) Cement mortar 1:1 proportion.
A RATE ANALYSIS FOR 100.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Sand. 0.210 Cum. 135.00 28.35
(b) Cement.(OPC) 0.3100 MT. 6400.00 1984.00
Total:- 2012.35
2.0 LABOURS.
(a) Unskilled Mazdoor. 9.00 Each. 350.00 3150.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 6.00 Each. 500.00 3000.00
(d) Bhisti. 5.00 Each. 350.00 1750.00
Total:- 7900.00
3.0 CARRIAGE OF MATERIALS.
(a) Sand. 0.210 Cum. 262.22 55.07
(b) Cement.(OPC) 0.3100 MT. 210.27 65.18
Total:- 120.25
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 198.55
Add 15% C.P & O.H. charges 1489.10
Total cost for 100.0 M2. Rs. :- 11735.25
Add 1% labour cess 117.35
Total cost for 1.0 M2. Rs. :- Say:- 118.50 118.50
Item No.: 45
Providing cement mortar pointing to the Stone masonary in proportion as under after
racking out joints 20mm deep including smooth finishing, curing scaffolding etc. complete for
all leads and lifts.
(a) Cement mortar 1:2 proportion.
A RATE ANALYSIS FOR 100.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Sand. 0.350 Cum. 135.00 47.25
(b) Cement.(OPC) 0.2500 MT. 6400.00 1600.00
Total:- 1647.25
2.0 LABOURS.
(a) Unskilled Mazdoor. 9.00 Each. 350.00 3150.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 6.00 Each. 500.00 3000.00
(d) Bhisti. 5.00 Each. 350.00 1750.00
Total:- 7900.00
3.0 CARRIAGE OF MATERIALS.
(a) Sand. 0.350 Cum. 262.22 91.78
(b) Cement.(OPC) 0.2500 MT. 210.27 52.57
Total:- 144.34
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 191.25
Add 15% C.P & O.H. charges 1434.34
Total cost for 100.0 M2. Rs. :- 11332.18
Add 1% labour cess 113.32
Total cost for 1.0 M2. Rs. :- 114.50
Item No.: 45
(b) Cement mortar 1:1 proportion.
A RATE ANALYSIS FOR 100.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Sand. 0.210 Cum. 135.00 28.35
(b) Cement.(OPC) 0.3100 MT. 6400.00 1984.00
Total:- 2012.35
2.0 LABOURS.
(a) Unskilled Mazdoor. 9.00 Each. 350.00 3150.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 6.00 Each. 500.00 3000.00
(d) Bhisti. 5.00 Each. 350.00 1750.00
Total:- 7900.00
3.0 CARRIAGE OF MATERIALS.
(a) Sand. 0.210 Cum. 262.22 55.07
(b) Cement.(OPC) 0.3100 MT. 210.27 65.18
Total:- 120.25
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 198.55
Add 15% C.P & O.H. charges 1489.10
Total cost for 100.0 M2. Rs. :- 11735.25
Add 1% labour cess 117.35
Total cost for 1.0 M2. Rs. :- Say:- 118.50 118.50

Item No.: 46
Providing cement mortar pointing to the brick masonary in proportion as under after
racking out joints 20mm deep including smooth finishing, curing scaffolding etc. complete
with sulphet resistence cement for all leads and lifts.
(a) Cement mortar 1:2 proportion.
A RATE ANALYSIS FOR 100.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Sand. 0.350 Cum. 2400.00 840.00 3035.71429
(b) Cement.(Su;phat Resistant) 0.2500 MT. 7600.00 1900.00
Total:- 2740.00 7600
2.0 LABOURS.
(a) Unskilled Mazdoor. 9.00 Each. 350.00 3150.00
(b) Mason I st. class. 0.00 Each. 600.00 0.00
(c) Mason II nd. class. 6.00 Each. 0.00 0.00
(d) Bhisti. 5.00 Each. 300.00 1500.00
Total:- 4650.00
3.0 CARRIAGE OF MATERIALS.
(a) Sand. 0.350 Cum. 250.00 87.50
(b) Cement.(OPC) 0.2500 MT. 220.00 55.00
Total:- 142.50
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 148.10
Add 15% C.P & O.H. charges 1110.75
Total cost for 100.0 M2. Rs. :- 8806.35
Add 1% labour cess 88.06
Total cost for 1.0 M2. Rs. :- Say:- 88.90 88.90
Item No.: 46
(b) Cement mortar 1:1 proportion.
A RATE ANALYSIS FOR 100.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Sand. 0.210 Cum. 135.00 28.35
(b) Cement.(Sulphat Resistant) 0.3100 MT. 6400.00 1984.00
Total:- 2012.35
2.0 LABOURS.
(a) Unskilled Mazdoor. 9.00 Each. 350.00 3150.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 6.00 Each. 500.00 3000.00
(d) Bhisti. 5.00 Each. 350.00 1750.00
Total:- 7900.00
3.0 CARRIAGE OF MATERIALS.
(a) Sand. 0.210 Cum. 262.22 55.07
(b) Cement.(OPC) 0.3100 MT. 210.27 65.18
Total:- 120.25
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 198.55
Add 15% C.P & O.H. charges 1489.10
Total cost for 100.0 M2. Rs. :- 11735.25
Add 1% labour cess 117.35
Total cost for 1.0 M2. Rs. :- Say:- 118.50 118.50
Item No.: 47
Providing cement mortar pointing to the Stone masonary in proportion as under after
racking out joints 20mm deep including smooth finishing, curing scaffolding etc. complete
with sulphet resisrence for all leads and lifts.
(a) Cement mortar 1:2 proportion.
A RATE ANALYSIS FOR 100.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Sand. 0.350 Cum. 135.00 47.25
(b) Cement.(Sulphat Resistant) 0.2500 MT. 6400.00 1600.00
Total:- 1647.25
2.0 LABOURS.
(a) Unskilled Mazdoor. 9.00 Each. 350.00 3150.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 6.00 Each. 500.00 3000.00
(d) Bhisti. 5.00 Each. 350.00 1750.00
Total:- 7900.00
3.0 CARRIAGE OF MATERIALS.
(a) Sand. 0.350 Cum. 262.22 91.78
(b) Cement.(OPC) 0.2500 MT. 210.27 52.57
Total:- 144.34
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 191.25
Add 15% C.P & O.H. charges 1434.34
Total cost for 100.0 M2. Rs. :- 11332.18
Add 1% labour cess 113.32
Total cost for 1.0 M2. Rs. :- Say:- 114.50 114.50
Item No.: 47
(b) Cement mortar 1:1 proportion.
A RATE ANALYSIS FOR 100.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Sand. 0.210 Cum. 135.00 28.35
(b) Cement.(OPC) 0.3100 MT. 6400.00 1984.00
Total:- 2012.35
2.0 LABOURS.
(a) Unskilled Mazdoor. 9.00 Each. 350.00 3150.00
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 6.00 Each. 500.00 3000.00
(d) Bhisti. 5.00 Each. 350.00 1750.00
Total:- 7900.00
3.0 CARRIAGE OF MATERIALS.
(a) Sand. 0.210 Cum. 262.22 55.07
(b) Cement.(OPC) 0.3100 MT. 210.27 65.18
Total:- 120.25
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 198.55
Add 15% C.P & O.H. charges 1489.10
Total cost for 100.0 M2. Rs. :- 11735.25
Add 1% labour cess 117.35
Total cost for 1.0 M2. Rs. :- Say:- 118.50 118.50
Item No.: 48
Providing 20mm thick sand faced cement plaster with consisting of 13mm thick backing
coat in cement mortar 1:3 proportion 8mm thick finishing coat of cement mortar 1:1 including
scaffoldong, watering and curing etc. complete for all lead and lifts.
A RATE ANALYSIS FOR 10.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Sand. 0.200 Cum. 135.00 27.00
(b) Cement.(OPC) 0.170 MT. 6400.00 1088.00
Total:- 1115.00
2.0 LABOURS.
(a) Unskilled Mazdoor. 1.93 Each. 350.00 675.50
(b) Mason I st. class. 0.00 Each. 550.00 0.00
(c) Mason II nd. class. 1.96 Each. 500.00 980.00
(d) Bhisti. 1.69 Each. 350.00 591.50
Total:- 2247.00
3.0 CARRIAGE OF MATERIALS.
(a) Sand. 0.200 Cum. 262.22 52.44
(b) Cement.(OPC) 0.170 MT. 210.27 35.75
Total:- 88.19
4.0 SCAFFOLDING LS 15.00 15.00
Add 2% for Sundries & T & P 67.54
Add 15% C.P & O.H. charges 506.55
Total cost for 10.0 M2. Rs. :- 4039.28
Add 1% labour cess 40.39
Total cost for 1.0 M2. Rs. :- Say:- 408.00 408.00
Item No.: 49
Providing and laying 75mm wearing coat of ordinery portland cement concrete M-15
grade including laying on proper camber, tamping, screening, finishing, broomung or grooving
etc. complete for all leds and lifts.(MANULLY WITH CONVENTIONAL MIXER)
A RATE ANALYSIS FOR 100.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 6.675 Cum. 303.00 2022.53
(b) Sand. 3.337 Cum. 135.00 450.50
(c) Cement.(OPC) 2.400 MT. 6400.00 15360.00
Total:- 17833.02
2.0 LABOURS.
(a) Unskilled Mazdoor. 10.00 Each. 350.00 3500.00
(b) Mason I st. class. 0.25 Each. 550.00 137.50
(c) Mason II nd. class. 0.90 Each. 500.00 450.00
(d) Bhisti. 3.00 Each. 350.00 1050.00
Total:- 5137.50
3.0 CARRIAGE OF MATERIALS.
(a) Coarse aggregate. 6.675 Cum. 314.54 2099.55
(b) Sand. 3.337 Cum. 262.22 875.03
(c) Cement.(OPC) 2.400 MT. 210.27 504.65
Total:- 3479.23
4.0 HIRE AND RUNNING CHARGES.
Hire and running charges of mixer. 7.50 Hr. 50.00 375.00
Add 2% for Sundries & T & P 466.91
Add 15% C.P & O.H. charges 3501.83
Total cost for 100.0 M2. Rs. :- 30793.49
Add 1% labour cess 307.93
Total cost for 1.0 M2. Rs. :- Say:- 311.00 311.00
Item No.: 50
providing and laying plain cement concrete in M-15 grade using ordinery
portland cement (OPC) sand and coarse aggregate for R.C.C parapet of 15cm
thickness as per detailed drawing with necessary reinforcement including form
work, batching, mixing, placing,rodding, vibrating, curing, smooth finishing etc.
complete for all leads and lifts.(Including cost of reinforcement)

Considering thickness of parapet = 0.15m & height 1.0m.


Considering steel content@1.45%
Qty of concrete for 10 meter length =0.15x1.0x10=1.5 Cum.
A RATE ANALYSIS FOR 10.0 Sqm.
Sr. Rate Amount
Description Qty Unit
No. Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 1.33 Cum. 2100.00 2793.00
(b) Sand. 0.667 Cum. 1600.00 1067.20
(c) Cement.(OPC) 0.480 MT. 6400.00 3072.00
(d) binding wire. 0.500 Kg. 60.00 30.00
(e) steel. 0.170 MT. 58000.00 9860.00
Total:- 16822.20
2.0 LABOURS.
(a) Unskilled Mazdoor. 2.65 Each. 350.00 927.50
(b) Mason I st. class. 0.08 Each. 550.00 41.25
(c) Mason II nd. class. 0.15 Each. 500.00 75.00
(d) Bhisti. 0.00 Each. 350.00 0.00
Total:- 1043.75
3.0 CARRIAGE OF MATERIALS.
(a) Coarse aggregate. 1.330 Cum. 314.54 418.34
(b) Sand. 0.667 Cum. 262.22 174.90
(c) Cement.(OPC) 0.480 MT. 210.27 100.93
(d) binding wire. 0.000 Kg. 45.00 0.00
(e) steel. 0.170 MT. 300.00 51.00
Total:- 694.17
4.0 HIRE AND RUNNING CHARGES.
Hire and running charges of mixer & Vibr. 1.50 Cum. 90.00 135.00
5.0 CENTERING & SHUTTERING
Cost of centering & shuttering. 1.50 Cum. 70.00 105.00
Add 2% for Sundries & T & P 362.12
Add 8% C.P & O.H. charges 1448.48
Total cost for 10.0 Meter length Rs. :- 20610.71
Add 1% labour cess 206.11
Total cost for 1.0 Meter length Rs. :- Say:- 2082.00 2082.00
50.94 80 1.570475
0.05 320
6400
2120.141
ITEM Providing C.I.Outlet 225 mm. Dia including locking arrangement and neccesary fitting.
:-68.

Unit : RMT 100 S.O.R. Page No Item No: -.


Sr. No. Particulars Quantity Unit Rate Per unit Amount
( A ) MATERIALS

1 Consider length of pipe of 10 gauge 7.10 Kg 43 Kg 305.30


weight of pipe
II/4x(20.63^2-20^2)x45x(7.35/7) 7.1

2 Flangs cover (weight of 6mm) 3.33 Kg 43 Kg 143.22


II/4x(30^2*.60*7.85)/1000 3.3306

3 II/4x(30^2*-20.63^2)*.60*7.85/1000 1.7556 1.76 Kg 43 Kg 75.49

4 II/4x(30^2*-20.63^2)*.60*7.85/1000 1.7556 1.76 Kg 43.00 Kg 75.49

5 Add 10% westage 13.942 1.39 Kg 43.00 Kg 59.95

6 Cost of nut bolt 6.00 No. 8.00 No. 48.00

7 Cost of welding charges 16.28 Kg. 23.00 Kg. 374.44


8 Cost of red oxide 1.00 L.S 50.00 L.S 50.00
Total = 1131.89
Sub-total ( A ) = 1131.89
Water Charges at 1 % of A+B+C. ( If necessary ) 0.00 = 0.00
Tools and Plants at 2 %.of A+B+C. 0.02 = 22.64
Contractor's Profit & O/H charges at 15 %.of A+B+C. 0.15 = 169.78
Grand Total : ( A ) = 1324.31
9 Add 1% for labour cess 13.24
'.' Rate for One No. 1337.56
1314.70 Say 1337.60
Item No.:-74
Filling in foundation with plumb concrete of cement sand and metal (up to 5 cm size) in
proportion 1:3:6 including centering, shuttering, temping, smooth finishing curing for all leads
and lift.
Sr. No. Description Qty Unit Rate Amount
Rs. Ps. Rs. Ps.
1.0 MATERIALS
(a) Coarse aggregate. 0.89 Cum. 425.00 378.25
(b) Sand 0.47 Cum. 135.00 63.45
(c) Cement 0.32 MT. 4300.00 1376.00
Total :- 1817.70
2.0 LABOURS
(a) Unskilled Majdoor 1.80 Each. 109.10 196.38
(b) Mason 1st. class. 0.05 Each. 140.00 7.00
(c) Mason II nd. class. 0.10 Each. 130.00 13.00
(d) Bhisti. 0.30 Each. 110.40 33.12
Total :- 249.50
3.0 CARRIAGE OF MATERIAL
(a) Carriage of coarse aggregate. 0.89 Cum. 290.22 258.30
(b) Carriage of sand. 0.47 Cum. 262.22 123.24
(c) Carriage of cement. 0.32 MT. 210.27 67.29
Total :- 448.83
4.0 HIRING AND RUNNING CHARGES.
(a) Conventional mixer. LS 40.00 40.00
5.0 CENTERING & SHUTTERING
(a) Cost of Centering & Shuttering. LS 61.60 61.60
Total cost for 1.0 m3 Rs. :- 2617.63
Add 2% for Sundries & T & P 43.38
Add 15% C.P & O.H. charges 325.32
Total cost for 1.0 m3 Rs. :- 2986.32
Add 1% labour cess 29.86
Total cost for 1.0 m3 Rs. :- 3016.20
3000.40

Executive Engineer Superintending Enginerr


Surat Canal Division, Surat. Surat Irrigation Circle, Surat.

179 file:///conversion/tmp/scratch/446077116.xls Misce


CHAPTER-1
EARTH WORK
S.No. Description of Items Unit Rate
Excavation for foundation in all sorts of soil including sandy and gravelly soil,
soft murrum including depositing the excavated stuff as and where directed
1 including back filling the tranches with suitable excavated stuff etc. complete
for lead up to 50 meter and lift as under.

a Lift up to 1.5 meter cum 96.40


b Lift up to 1.5 to 3.0 meter cum 184.1
c Lift up to 3.0 to 4.5 meter cum 194.00
d Lift up to 4.5 to 6.0 meter cum 207.10
e For each additional 1.50 lift up to 12.0meter. cum 21.40
Excavation for foundation in hard murrum including depositing the excavated
stuff as and where directed including back filling the excavated trenches with
2 suitable excavated stuff etc. complete for lead up to 50 meter and lift as under.

a Add 5% C.P & O.H. charges cum 2.52


b Add 7% C.P & O.H. charges cum 2.655
c Add 7% C.P & O.H. charges cum 2.84
d Add 7% C.P & O.H. charges cum 0.29
e Add 7% C.P & O.H. charges cum Amount
DESIGN OF CORNER COOLUMN
Pu 250 KN
fck 20 KN/m2
S.B.C 120 KN/m2
Mux 60 KN-m
Muy 50 KN-m
Area req. 1.10P/S.B.C sqm
LXB 2.29 sqm
ex Pu/Muy 5.00
ey Pu/Mux 4.17

For positive stress


6ex/L+6ey/B <=1

qmax < SBC


qmax
< 4
qmin
1+6e/A
< 4
1-6e/A
A = 10e

A/2= c+a/2+e
1.15Pu
AxB=
SBC

DESIGN OF CORNER COLUMN FOOTING


Given P
Mx
My
q (SBC) L
x
MxTy = Mx+Pey
MyTx = My+Pex

Ixx = L4/12
Iyy = L4/12

P MxTy MyTx
σ= ± ±
A Ixx Iyy
smax <_ q (SBC)
y

ex a

ey
x

y
Tender Analysis
S.No. Description of item Unit Qty Rate Amount
Earth work in all kinds of soil cum 63.6 64 4070.4
Extra for excavation for building to
cover dresing. cum 63.6 8
Providing and laying C.C. in position
1:4:8 cum 8.8

S-ar putea să vă placă și