Sunteți pe pagina 1din 18

S.

No Descriptions Nos L (Ft) B (Ft) H (Ft) Amount Units


A Foundation Work
a. Ground Floor
1 Earth Work in Excavation
1.1 Pillar Foundation 12 5 5 5 1500.00
1.2 Wall Trench 2 21.33 2 2.25 191.97
1.5 15 2 2.25 101.25
4 16.25 2 2.25 292.50

Total Foundation Work 2085.72 Cft

2 Earth Work in Filling


2.1 Back Filling 625.72
2.2 Filling Up to Tie Beam Level 1 625 1 2 1250.00

Total Earth Work in Filling 1875.72 Cft

3 Flat Brick Soiling


1.1 Footing 12 5 5 300.00
1.2 Tie Beam Trench
2 34.08 1.16 79.07
1.5 27.75 1.16 48.29
4 24.75 1.16 114.84
1.3 Rooms 1 625 1 625.00

Total Flat Brick Soiling 1167.19 Sq.ft

4 3" th P.C.C Work(1:3:6) 291.80 Cft

5 R.C.C Work
5.1 P.C.C (1:1.5:3)
5.1.1 Footing 12 5 5 0.67 201.00
5.1.2 Traozoidal Section 12 12.875 1.25 193.13
5.1.3 Column 12 0.75 0.75 4.25 38.25
5.1.4 Tie Beam 1 204.099 0.75 0.75 114.81

Total P.C.C Work (1:1.5:3) 547.18 Cft

5.2 Reinforcement (@1.8) 2191.51 Kg

6 Formwork
6.1 Footing 12 20 0.67 160.80
6.2 Column 12 3 4.25 153.00
6.3 Tie Beam 1 204.099 1.5 306.15

Total Formwork 619.95 Sq.ft.

7 Brickwork
Wall Trench 2 34.08 1.16 2.5 197.66
1.5 27.75 1.16 2.5 120.71
4 24.75 1.16 2.5 287.10
Total Brickwork 605.48 Cft.

B Superstructure
Ground Floor
1 R.C.C Work
1.1 P.C.C (1:1.5:3)
1.1.1 Column 12 0.75 0.75 8.16 55.08
1.1.2 Mono Beam 1 219.599 0.75 0.75 123.52
1.1.3 Slab
Rooms 1 700 1 0.33 231.00
Total P.C.C (1:1.5:3) 409.60 Cft

1.2 Reinforcement (@1.8%) 1640.51 Kg

1.3 Formwork
1.3.1 Column 12 3 8.16 293.76
1.3.2 Mono Beam 1 219.599 1.5 329.40
1.3.3 Slab 1 700 1 700.00
Total Formwork 1323.16 Sq.ft

2 Local Brick Work


2 34.08 0.75 8.16 417.14
1.5 27.75 0.375 8.16 127.37
4 24.75 0.75 8.16 605.88

1150.39
Deduction of D & W
D 1 3.5 0.75 7.5 19.69
D1 5 3 0.75 7 78.75
D2 1 2.5 0.375 7 6.56

W 3 6 0.75 4.5 60.75


W1 3 3 0.75 4.5 30.38

Total Local Brick Work 196.13

954.27 Cft

3 Plaster Work
3.1 Internal & External Plaster
3.1.1 Walls
4 34.08 8.16 1112.37
3 27.75 8.16 679.32
8 24.75 8.16 1615.68
Salab 7 floor 2 700 1 1400.00
4807.37
Deduction of D & W
D 1 3.5 7.5 26.25
D1 5 3 7 105.00
D2 1 2.5 7 17.50

W 3 6 4.5 81.00
W1 3 3 4.5 40.50

Total Local Brick Work 270.25

Total Plaster Work 5671.40

Paint 5321.40

4 Internal & external Paint 5321.40 Sq.ft

5 Flooring
5.1 Screed and Punning

Floor 1 700 1 700.00

Total Screed and Punning Work 700.00 Sq.ft

5.2 Porcelain tile


5.2.1 Toilet Bath 1 18 6 108.00
1 5 5.25 26.25
5.2.2 Kitchen floor 1 13.08 11 143.88
Total Tile Work 278.13 Sq.ft

6 Door and Window Fitting


6.1 Chaukhat Work
D 1 18.5 0.333 0.25 1.54
D1 5 17 0.333 0.25 7.08
D2 1 16.5 0.333 0.25 1.37
0.333 0.25 0.00
W 3 29.6 0.333 0.25 7.39
W1 3 19.5 0.333 0.25 4.87

Total chaukhat work 22.25 Cu.Ft.


6.2 Pannel Work
Window

W 3 6 4.5 81.00
W1 3 3 4.5 40.50

Total Window Fitting 121.50 Sq.ft

Door
D 1 3.5 7.5 26.25
D1 5 3 7 105.00
D2 1 2.5 7 17.50

Total Door Fitting 148.75 Sq.ft

7 Enamel Paint painting work 456.19 Sq.ft

8 Total Grill Work 121.50 Sq.ft

9 Marble work 1 9.5 10.5 99.75


16 3.5 0.16 8.96
108.71 Sq.ft

10 Wooden parquetting work


living room 1 12.5 11.5

First Floor
1 R.C.C Work
1.1 P.C.C (1:1.5:3)
1.1.1 Column 12 0.75 0.75 8.16 55.08
1.1.2 Mono Beam 1 15.5 0.75 0.75 8.72
1.1.3 Slab
Rooms 1 700 1 0.33 231.00
Total P.C.C (1:1.5:3) 294.80 Cft

1.2 Reinforcement (@1.8%) 1180.70 Kg

1.3 Formwork
1.3.1 Column 12 3 8.16 293.76
1.3.2 Mono Beam 1 15.5 1.5 23.25
1.3.3 Slab 1 700 1 700.00
Total Formwork 1017.01 Sq.ft

2 Local Brick Work


2 34.08 0.75 8.16 417.14
1.5 27.75 0.375 8.16 127.37
4 24.75 0.75 8.16 605.88
1150.39
Deduction of D & W
D 1 3.5 0.75 7.5 19.69
D1 5 3 0.75 7 78.75
D2 1 2.5 0.375 7 6.56

W 3 6 0.75 4.5 60.75


W1 3 3 0.75 4.5 30.38

Total Local Brick Work 196.13

954.27 Cft

3 Plaster Work
3.1 Internal & External Plaster
3.1.1 Walls
4 34.08 8.16 1112.37
3 27.75 8.16 679.32
8 24.75 8.16 1615.68
Salab 7 floor 2 700 1 1400.00
4807.37
Deduction of D & W
D 1 3.5 7.5 26.25
D1 5 3 7 105.00
D2 1 2.5 7 17.50

W 3 6 4.5 81.00
W1 3 3 4.5 40.50

Total Local Brick Work 270.25

Total Plaster Work 5671.40

Paint 5321.40

4 Internal & external Paint 5321.40 Sq.ft

5 Flooring
5.1 Screed and Punning

Floor 1 700 1 700.00

Total Screed and Punning Work 700.00 Sq.ft

5.2 Porcelain tile


5.2.1 Toilet Bath 1 18 6 108.00
1 5 5.25 26.25
5.2.2 Kitchen floor 1 13.08 11 143.88
Total Tile Work 278.13 Sq.ft

6 Door and Window Fitting


6.1 Chaukhat Work
D 1 18.5 0.333 0.25 1.54
D1 5 17 0.333 0.25 7.08
D2 1 16.5 0.333 0.25 1.37
0.333 0.25 0.00
W 3 29.6 0.333 0.25 7.39
W1 3 19.5 0.333 0.25 4.87

Total chaukhat work 22.25 Cu.Ft.

6.2 Pannel Work


Window

W 3 6 4.5 81.00
W1 3 3 4.5 40.50

Total Window Fitting 121.50 Sq.ft

Door
D 1 3.5 7.5 26.25
D1 5 3 7 105.00
D2 1 2.5 7 17.50

Total Door Fitting 148.75 Sq.ft

7 Enamel Paint painting work 456.19 Sq.ft

8 Total Grill Work 121.50 Sq.ft

9 Marble work 1 9.5 10.5 99.75


16 3.5 0.16 8.96
108.71 Sq.ft

10 Wooden parquetting work


living room 1 12.5 11.5
Second Floor
1 R.C.C Work
1.1 P.C.C (1:1.5:3)
1.1.1 Column 12 0.75 0.75 8.16 55.08
1.1.2 Mono Beam 1 15.5 0.75 0.75 8.72
1.1.3 Slab
Rooms 1 700 1 0.33 231.00
Total P.C.C (1:1.5:3) 294.80 Cft

1.2 Reinforcement (@1.8%) 1180.70 Kg

1.3 Formwork
1.3.1 Column 12 3 8.16 293.76
1.3.2 Mono Beam 1 15.5 1.5 23.25
1.3.3 Slab 1 700 1 700.00
Total Formwork 1017.01 Sq.ft

2 Local Brick Work


2 34.08 0.75 8.16 417.14
1.5 27.75 0.375 8.16 127.37
4 24.75 0.75 8.16 605.88

1150.39
Deduction of D & W
D 1 3.5 0.75 7.5 19.69
D1 5 3 0.75 7 78.75
D2 1 2.5 0.375 7 6.56

W 3 6 0.75 4.5 60.75


W1 3 3 0.75 4.5 30.38

Total Local Brick Work 196.13

954.27 Cft

3 Plaster Work
3.1 Internal & External Plaster
3.1.1 Walls
4 34.08 8.16 1112.37
3 27.75 8.16 679.32
8 24.75 8.16 1615.68
Salab 7 floor 2 700 1 1400.00
4807.37
Deduction of D & W
D 1 3.5 7.5 26.25
D1 5 3 7 105.00
D2 1 2.5 7 17.50
W 3 6 4.5 81.00
W1 3 3 4.5 40.50

Total Local Brick Work 270.25

Total Plaster Work 5671.40

Paint 5321.40

4 Internal & external Paint 5321.40 Sq.ft

5 Flooring
5.1 Screed and Punning

Floor 1 700 1 700.00

Total Screed and Punning Work 700.00 Sq.ft

5.2 Porcelain tile


5.2.1 Toilet Bath 1 18 6 108.00
1 5 5.25 26.25
5.2.2 Kitchen floor 1 13.08 11 143.88
Total Tile Work 278.13 Sq.ft

6 Door and Window Fitting


6.1 Chaukhat Work
D 1 18.5 0.333 0.25 1.54
D1 5 17 0.333 0.25 7.08
D2 1 16.5 0.333 0.25 1.37
0.333 0.25 0.00
W 3 29.6 0.333 0.25 7.39
W1 3 19.5 0.333 0.25 4.87

Total chaukhat work 22.25 Cu.Ft.

6.2 Pannel Work


Window

W 3 6 4.5 81.00
W1 3 3 4.5 40.50
Total Window Fitting 121.50 Sq.ft

Door
D 1 3.5 7.5 26.25
D1 5 3 7 105.00
D2 1 2.5 7 17.50

Total Door Fitting 148.75 Sq.ft

7 Enamel Paint painting work 456.19 Sq.ft

8 Total Grill Work 121.50 Sq.ft

9 Marble work 1 9.5 10.5 99.75


16 3.5 0.16 8.96
108.71 Sq.ft

10 Wooden parquetting work


living room 1 12.5 11.5

Third Floor
1 R.C.C Work
1.1 P.C.C (1:1.5:3)
1.1.1 Column 12 0.75 0.75 8.16 55.08
1.1.2 Mono Beam 1 15.5 0.75 0.75 8.72
1.1.3 Slab
Rooms 1 700 1 0.33 231.00
Total P.C.C (1:1.5:3) 294.80 Cft

1.2 Reinforcement (@1.8%) 1180.70 Kg

1.3 Formwork
1.3.1 Column 12 3 8.16 293.76
1.3.2 Mono Beam 1 15.5 1.5 23.25
1.3.3 Slab 1 700 1 700.00
Total Formwork 1017.01 Sq.ft

2 Local Brick Work


2 34.08 0.75 8.16 417.14
1.5 27.75 0.375 8.16 127.37
4 24.75 0.75 8.16 605.88

1150.39
Deduction of D & W
D 1 3.5 0.75 7.5 19.69
D1 5 3 0.75 7 78.75
D2 1 2.5 0.375 7 6.56

W 3 6 0.75 4.5 60.75


W1 3 3 0.75 4.5 30.38
Total Local Brick Work 196.13

954.27 Cft

3 Plaster Work
3.1 Internal & External Plaster
3.1.1 Walls
4 34.08 8.16 1112.37
3 27.75 8.16 679.32
8 24.75 8.16 1615.68
Salab 7 floor 2 700 1 1400.00
4807.37
Deduction of D & W
D 1 3.5 7.5 26.25
D1 5 3 7 105.00
D2 1 2.5 7 17.50

W 3 6 4.5 81.00
W1 3 3 4.5 40.50

Total Local Brick Work 270.25

Total Plaster Work 5671.40

Paint 5321.40

4 Internal & external Paint 5321.40 Sq.ft

5 Flooring
5.1 Screed and Punning

Floor 1 700 1 700.00

Total Screed and Punning Work 700.00 Sq.ft

5.2 Porcelain tile


5.2.1 Toilet Bath 1 18 6 108.00
1 5 5.25 26.25
5.2.2 Kitchen floor 1 13.08 11 143.88
Total Tile Work 278.13 Sq.ft

6 Door and Window Fitting


6.1 Chaukhat Work
D 1 18.5 0.333 0.25 1.54
D1 5 17 0.333 0.25 7.08
D2 1 16.5 0.333 0.25 1.37
0.333 0.25 0.00
W 3 29.6 0.333 0.25 7.39
W1 3 19.5 0.333 0.25 4.87

Total chaukhat work 22.25 Cu.Ft.

6.2 Pannel Work


Window

W 3 6 4.5 81.00
W1 3 3 4.5 40.50

Total Window Fitting 121.50 Sq.ft

Door
D 1 3.5 7.5 26.25
D1 5 3 7 105.00
D2 1 2.5 7 17.50

Total Door Fitting 148.75 Sq.ft

7 Enamel Paint painting work 456.19 Sq.ft

8 Total Grill Work 121.50 Sq.ft

9 Marble work 1 9.5 10.5 99.75


16 3.5 0.16 8.96
108.71 Sq.ft

10 Wooden parquetting work


living room 1 12.5 11.5

Top Floor
1 R.C.C Work
1.1 P.C.C (1:1.5:3)
1.1.1 Column 8 0.75 0.75 8.16 36.72
1.1.2 Mono Beam 1 109.66 0.75 0.75 61.68
1.1.3 Slab
Rooms 1 304 1 0.33 100.32
Total P.C.C (1:1.5:3) 198.72 Cft
1.2 Reinforcement (@1.8%) 795.91 Kg

1.3 Formwork
1.3.1 Column 8 3 8.16 195.84
1.3.2 Mono Beam 1 109.66 1.5 164.49
1.3.3 Slab 1 304 1 304.00
Total Formwork 664.33 Sq.ft

2 Local Brick Work


3 77.5 0.75 8.16 1422.90

Parapit 1 66.99 0.75 3 150.73


1573.63

Deduction of D & W
D1 5 3 0.375 7 105.00

W 3 6 0.75 4.5 60.75


W1 1 3 0.75 4.5 10.13

175.88

Total Local Brick Work 1397.75 Cft

3 Plaster Work
3.1 Internal & External Plaster
3.1.1 Walls
3 77.5 8.16 1897.20

Parapit 1 66.99 3 200.97


slab 2 350 1 700.00
2798.17

Deduction of D & W
D1 2 3 7 42.00

W 3 6 4.5 81.00
W1 1 3 4.5 13.50

136.50

Total plaster 2661.67 Cft

Paint 2311.67

Porcelain Glazed tile work


Toilet Tile 1 27.5 6
1 8 7

Toilet Tile 1 23.5 11


1 6 7

5 Flooring
5.1 Screed and Punning

Floor & slab 1 350 1 350.00

Total Screed and Punning Work 350.00 Sq.ft

6 Door and Window Fitting


6.1 Chaukhat Work
D1 2 17 0.333 0.25 2.83

W 3 25.5 0.333 0.25 6.37


W1 1 25.5 0.333 0.25 2.12

Total chaukhat work 11.32 Cu.Ft.

6.2 Pannel Work


Window

W 3 6 4.5 81.00
W1 1 3 4.5 13.50
94.50 Sq.ft

Door
D1 2 3 7.5 45.00

Total Door Fitting 45.00 Sq.ft

7 Enamel Paint painting work 195.75 Sq.ft


Remark
4 3 7.5
2 2.5 7.5
1 3 7.5
4 3 4.5
6 3 7
1 3.5 7
1 3.5 4

1 4.66 4.5
1 3.5 4.5
3 2 4
TABLE NO : 01
Abstract Cost for the Proposed New Building

Owner : Glory Sodemba


Site : Sainbu V.D.C. ward no: 03/ka, Bhaisepati, Lalitpur

A. Foundation Upto Plinth


S.No Descriptions Units Quantity Rate (NRs.) Amount (NRs.) Remarks

1 Earth Work in Excavation Work Cft 2085.72 7.38 15392.61


2 Earth filling Work Cft 1875.72 11.05 20726.66
3 Brick Soling work Sq.ft. 1167.19 92.60 108081.85
4 P.C.C Work Cft. 291.80 194.88 56865.53
5 P.C.C for R.C.C Cft 547.18 252.47 138146.71
6 Reinforcement Kg 2191.51 85.00 186278.73
7 Formwork Sq.ft 619.95 60.06 37234.11
8 Brick Work Cft 605.48 242.41 146773.56
Sub Total (A) 709,499.76

B. Super Structure work


S.No Descriptions Units Quantity Rate (NRs.) Amount (NRs.) Remarks
a. Ground Floor
R.C.C. Work
1.1 P.C.C for R.C.C Cft 409.60 252.47 103412.83
1.2 Reinforcement Kg 1640.51 85.00 139443.14
1.3 Formwork Sq.ft 1323.16 60.06 79468.90
2 Brick Work (Local) C.ft 1150.39 242.41 278866.45
3 Door Chaukhat C.ft. 22.25 2806.20 62445.60
Sub Total 663636.92
b. First Floor
1 R.C.C. Work
1.1 P.C.C for R.C.C Cft 294.80 252.47 74427.84
1.2 Reinforcement Kg 1180.70 85.00 100359.42
1.3 Formwork Sq.ft 1323.00 60.06 79459.38
2 Brick Work (Local) C.ft 1150.39 242.41 278866.04
3 Door Chaukhat C.ft. 22.25 2806.20 62437.95
Sub Total 595550.63

c. Top Floor
1 R.C.C. Work
1.1 P.C.C for R.C.C Cft 198.72 252.47 50171.79
1.2 Reinforcement Kg 795.91 85.00 67652.26
1.3 Formwork Sq.ft 664.33 60.06 39899.66
2 Brick Work (Local) C.ft 1397.75 242.41 338829.18
3 Door Chaukhat C.ft. 11.32 2806.20 31771.80
Sub Total 528324.68
Sub Total of B 1787512.24

C. Finishing Works
S.No Descriptions Units Quantity Rate (NRs.) Amount (NRs.) Remarks
a. Ground Floor
1 Plaster work Sq.ft 5671.40 20.48 116150.30
2 Painting work Sq.ft 5321.40 6.02 32034.84
3 Flooring
3.1 Screeding and Punning Sq.ft 700.00 35.50 24850.00
3.2 Glazed Tile Sq.ft 278.13 149.25 41510.90
3.3 Marble Work Sq.ft 108.71 243.26 26444.79
4 Door Window fitting work
4.1 Door fitting work Sq.ft 148.75 518.52 77129.85
4.2 Window fitting work Sq.ft 121.50 400.00 48600.00
5 Enamel Painting work Sq.ft 456.19 14.47 6601.03
6 Grill work Sq.ft 121.50 214.04 26005.86
Sub Total 399327.58

b. First Floor
1 Plaster work Sq.ft 5671.40 20.48 116150.30
2 Painting work Sq.ft 5321.40 6.02 32034.84
3 Flooring
3.1 Screeding and Punning Sq.ft 700.00 35.50 24850.00
3.2 Glazed Tile Sq.ft 278.13 149.25 41510.90
3.3 Marble Work Sq.ft 108.71 243.26 26444.79
4 Door Window fitting work
4.1 Door fitting work Sq.ft 148.75 518.52 77129.85
4.2 Window fitting work Sq.ft 121.50 400.00 48600.00
5 Enamel Painting work Sq.ft 456.19 14.47 6601.03
6 Grill work Sq.ft 121.50 214.04 26005.86
Sub Total 373321.72

c. Top Floor
1 Plaster work Sq.ft 198.72 20.48 4069.86
2 Painting work Sq.ft 795.91 6.02 4791.37
3 Flooring
3.1 Screeding and Punning Sq.ft 350.00 35.50 12425.00
3.2 Glazed Tile Sq.ft 1.00 149.25 149.25
4 Door Window fitting work
4.1 Door fitting work Sq.ft 45.00 518.52 23333.40
4.2 Window fitting work Sq.ft 94.50 400.00 37800.00
5 Enamel Painting work Sq.ft 195.75 14.47 2832.50
Sub Total 85401.39
Sub Total of C 858050.69

Total cost of the Building 3355062.68


D a. Sanitary and Water supply ( @ 5% of Civil work ) 167753.13
b. Electrification ( @ 5% of Civil work ) 167753.13

Total Cost of the Building & Fixture 3,690,568.95

In Words : Three Million Six Hundred Ninety Thousands Five Hundred Six and Paisa Sixty Eight Only.