5 R.C.C Work
5.1 P.C.C (1:1.5:3)
5.1.1 Footing 12 5 5 0.67 201.00
5.1.2 Traozoidal Section 12 12.875 1.25 193.13
5.1.3 Column 12 0.75 0.75 4.25 38.25
5.1.4 Tie Beam 1 204.099 0.75 0.75 114.81
6 Formwork
6.1 Footing 12 20 0.67 160.80
6.2 Column 12 3 4.25 153.00
6.3 Tie Beam 1 204.099 1.5 306.15
7 Brickwork
Wall Trench 2 34.08 1.16 2.5 197.66
1.5 27.75 1.16 2.5 120.71
4 24.75 1.16 2.5 287.10
Total Brickwork 605.48 Cft.
B Superstructure
Ground Floor
1 R.C.C Work
1.1 P.C.C (1:1.5:3)
1.1.1 Column 12 0.75 0.75 8.16 55.08
1.1.2 Mono Beam 1 219.599 0.75 0.75 123.52
1.1.3 Slab
Rooms 1 700 1 0.33 231.00
Total P.C.C (1:1.5:3) 409.60 Cft
1.3 Formwork
1.3.1 Column 12 3 8.16 293.76
1.3.2 Mono Beam 1 219.599 1.5 329.40
1.3.3 Slab 1 700 1 700.00
Total Formwork 1323.16 Sq.ft
1150.39
Deduction of D & W
D 1 3.5 0.75 7.5 19.69
D1 5 3 0.75 7 78.75
D2 1 2.5 0.375 7 6.56
954.27 Cft
3 Plaster Work
3.1 Internal & External Plaster
3.1.1 Walls
4 34.08 8.16 1112.37
3 27.75 8.16 679.32
8 24.75 8.16 1615.68
Salab 7 floor 2 700 1 1400.00
4807.37
Deduction of D & W
D 1 3.5 7.5 26.25
D1 5 3 7 105.00
D2 1 2.5 7 17.50
W 3 6 4.5 81.00
W1 3 3 4.5 40.50
Paint 5321.40
5 Flooring
5.1 Screed and Punning
W 3 6 4.5 81.00
W1 3 3 4.5 40.50
Door
D 1 3.5 7.5 26.25
D1 5 3 7 105.00
D2 1 2.5 7 17.50
First Floor
1 R.C.C Work
1.1 P.C.C (1:1.5:3)
1.1.1 Column 12 0.75 0.75 8.16 55.08
1.1.2 Mono Beam 1 15.5 0.75 0.75 8.72
1.1.3 Slab
Rooms 1 700 1 0.33 231.00
Total P.C.C (1:1.5:3) 294.80 Cft
1.3 Formwork
1.3.1 Column 12 3 8.16 293.76
1.3.2 Mono Beam 1 15.5 1.5 23.25
1.3.3 Slab 1 700 1 700.00
Total Formwork 1017.01 Sq.ft
954.27 Cft
3 Plaster Work
3.1 Internal & External Plaster
3.1.1 Walls
4 34.08 8.16 1112.37
3 27.75 8.16 679.32
8 24.75 8.16 1615.68
Salab 7 floor 2 700 1 1400.00
4807.37
Deduction of D & W
D 1 3.5 7.5 26.25
D1 5 3 7 105.00
D2 1 2.5 7 17.50
W 3 6 4.5 81.00
W1 3 3 4.5 40.50
Paint 5321.40
5 Flooring
5.1 Screed and Punning
W 3 6 4.5 81.00
W1 3 3 4.5 40.50
Door
D 1 3.5 7.5 26.25
D1 5 3 7 105.00
D2 1 2.5 7 17.50
1.3 Formwork
1.3.1 Column 12 3 8.16 293.76
1.3.2 Mono Beam 1 15.5 1.5 23.25
1.3.3 Slab 1 700 1 700.00
Total Formwork 1017.01 Sq.ft
1150.39
Deduction of D & W
D 1 3.5 0.75 7.5 19.69
D1 5 3 0.75 7 78.75
D2 1 2.5 0.375 7 6.56
954.27 Cft
3 Plaster Work
3.1 Internal & External Plaster
3.1.1 Walls
4 34.08 8.16 1112.37
3 27.75 8.16 679.32
8 24.75 8.16 1615.68
Salab 7 floor 2 700 1 1400.00
4807.37
Deduction of D & W
D 1 3.5 7.5 26.25
D1 5 3 7 105.00
D2 1 2.5 7 17.50
W 3 6 4.5 81.00
W1 3 3 4.5 40.50
Paint 5321.40
5 Flooring
5.1 Screed and Punning
W 3 6 4.5 81.00
W1 3 3 4.5 40.50
Total Window Fitting 121.50 Sq.ft
Door
D 1 3.5 7.5 26.25
D1 5 3 7 105.00
D2 1 2.5 7 17.50
Third Floor
1 R.C.C Work
1.1 P.C.C (1:1.5:3)
1.1.1 Column 12 0.75 0.75 8.16 55.08
1.1.2 Mono Beam 1 15.5 0.75 0.75 8.72
1.1.3 Slab
Rooms 1 700 1 0.33 231.00
Total P.C.C (1:1.5:3) 294.80 Cft
1.3 Formwork
1.3.1 Column 12 3 8.16 293.76
1.3.2 Mono Beam 1 15.5 1.5 23.25
1.3.3 Slab 1 700 1 700.00
Total Formwork 1017.01 Sq.ft
1150.39
Deduction of D & W
D 1 3.5 0.75 7.5 19.69
D1 5 3 0.75 7 78.75
D2 1 2.5 0.375 7 6.56
954.27 Cft
3 Plaster Work
3.1 Internal & External Plaster
3.1.1 Walls
4 34.08 8.16 1112.37
3 27.75 8.16 679.32
8 24.75 8.16 1615.68
Salab 7 floor 2 700 1 1400.00
4807.37
Deduction of D & W
D 1 3.5 7.5 26.25
D1 5 3 7 105.00
D2 1 2.5 7 17.50
W 3 6 4.5 81.00
W1 3 3 4.5 40.50
Paint 5321.40
5 Flooring
5.1 Screed and Punning
W 3 6 4.5 81.00
W1 3 3 4.5 40.50
Door
D 1 3.5 7.5 26.25
D1 5 3 7 105.00
D2 1 2.5 7 17.50
Top Floor
1 R.C.C Work
1.1 P.C.C (1:1.5:3)
1.1.1 Column 8 0.75 0.75 8.16 36.72
1.1.2 Mono Beam 1 109.66 0.75 0.75 61.68
1.1.3 Slab
Rooms 1 304 1 0.33 100.32
Total P.C.C (1:1.5:3) 198.72 Cft
1.2 Reinforcement (@1.8%) 795.91 Kg
1.3 Formwork
1.3.1 Column 8 3 8.16 195.84
1.3.2 Mono Beam 1 109.66 1.5 164.49
1.3.3 Slab 1 304 1 304.00
Total Formwork 664.33 Sq.ft
Deduction of D & W
D1 5 3 0.375 7 105.00
175.88
3 Plaster Work
3.1 Internal & External Plaster
3.1.1 Walls
3 77.5 8.16 1897.20
Deduction of D & W
D1 2 3 7 42.00
W 3 6 4.5 81.00
W1 1 3 4.5 13.50
136.50
Paint 2311.67
5 Flooring
5.1 Screed and Punning
W 3 6 4.5 81.00
W1 1 3 4.5 13.50
94.50 Sq.ft
Door
D1 2 3 7.5 45.00
1 4.66 4.5
1 3.5 4.5
3 2 4
TABLE NO : 01
Abstract Cost for the Proposed New Building
c. Top Floor
1 R.C.C. Work
1.1 P.C.C for R.C.C Cft 198.72 252.47 50171.79
1.2 Reinforcement Kg 795.91 85.00 67652.26
1.3 Formwork Sq.ft 664.33 60.06 39899.66
2 Brick Work (Local) C.ft 1397.75 242.41 338829.18
3 Door Chaukhat C.ft. 11.32 2806.20 31771.80
Sub Total 528324.68
Sub Total of B 1787512.24
C. Finishing Works
S.No Descriptions Units Quantity Rate (NRs.) Amount (NRs.) Remarks
a. Ground Floor
1 Plaster work Sq.ft 5671.40 20.48 116150.30
2 Painting work Sq.ft 5321.40 6.02 32034.84
3 Flooring
3.1 Screeding and Punning Sq.ft 700.00 35.50 24850.00
3.2 Glazed Tile Sq.ft 278.13 149.25 41510.90
3.3 Marble Work Sq.ft 108.71 243.26 26444.79
4 Door Window fitting work
4.1 Door fitting work Sq.ft 148.75 518.52 77129.85
4.2 Window fitting work Sq.ft 121.50 400.00 48600.00
5 Enamel Painting work Sq.ft 456.19 14.47 6601.03
6 Grill work Sq.ft 121.50 214.04 26005.86
Sub Total 399327.58
b. First Floor
1 Plaster work Sq.ft 5671.40 20.48 116150.30
2 Painting work Sq.ft 5321.40 6.02 32034.84
3 Flooring
3.1 Screeding and Punning Sq.ft 700.00 35.50 24850.00
3.2 Glazed Tile Sq.ft 278.13 149.25 41510.90
3.3 Marble Work Sq.ft 108.71 243.26 26444.79
4 Door Window fitting work
4.1 Door fitting work Sq.ft 148.75 518.52 77129.85
4.2 Window fitting work Sq.ft 121.50 400.00 48600.00
5 Enamel Painting work Sq.ft 456.19 14.47 6601.03
6 Grill work Sq.ft 121.50 214.04 26005.86
Sub Total 373321.72
c. Top Floor
1 Plaster work Sq.ft 198.72 20.48 4069.86
2 Painting work Sq.ft 795.91 6.02 4791.37
3 Flooring
3.1 Screeding and Punning Sq.ft 350.00 35.50 12425.00
3.2 Glazed Tile Sq.ft 1.00 149.25 149.25
4 Door Window fitting work
4.1 Door fitting work Sq.ft 45.00 518.52 23333.40
4.2 Window fitting work Sq.ft 94.50 400.00 37800.00
5 Enamel Painting work Sq.ft 195.75 14.47 2832.50
Sub Total 85401.39
Sub Total of C 858050.69
In Words : Three Million Six Hundred Ninety Thousands Five Hundred Six and Paisa Sixty Eight Only.