Documente Academic
Documente Profesional
Documente Cultură
DISTRIBUTION PLANNING
MANUAL
Document Control
Department Document Type Document Title
Distribution Planning
EP Manual
Manual
Issue Approval
Issue Record
Issue No. Date Reason for issuing the manual
0.0 29-02-2016 First issue of the manual
1.0
2.0
3.0
4.0
5.0
Table of Contents
Title Page I
1. Introduction 1
9. Amendments 137
QATAR GENERAL
ELECTRICITY & WATER CORPORATION
ELECTRICITY NETWORK AFFAIRS
PART - 1
INTRODUCTION
PART 1
INTRODUCTION
The Distribution Planning Manual is designed as a reference document to give the Planning
Engineers information to effectively plan Electricity Distribution Systems in Qatar.
Its contents cover Distribution System Design with worked examples on 33kV, 11kV and LV
voltage drop calculations.
Distribution substation design includes indoor and outdoors types of substations showing the
size of plot required for these substations. Protection requirements for the underground and
overhead systems are outlined and their operating principles explained.
Two appendices are included; one for tables of Electrical characteristics of cables and OHL
and the other for a copy of Engineering Recommendations P – 28.
QATAR GENERAL
ELECTRICITY & WATER CORPORATION
ELECTRICITY NETWORK AFFAIRS
PART - 2
DISTRIBUTION SYSTEM DESIGN
PART 2
CONTENTS
Page No.
1.0 Introduction
This part of the manual describes the technical aspects involved in the selection of 33kV,
11kV and LV underground cables and overhead line feeders used in Qatar’s Distribution
Network.
However, if the relevant feeder breaker fails to trip for any reason (such as mechanical
problems in the operating mechanism) then the next upstream circuit breaker (either the bus-
section or the main incomer) has to operate to trip and isolate the fault. This, could be
probably more than 0.5 sec even for close-up faults. Hence it is recommended that the cables
used on the 33kV OHL Distribution Network (without fuses) are rated for one (1) second
fault withstand capacity.
Standard Rating of 3 x 1C – 50 sq.mm Cu/XLPE cable laid in trefoil = 245 A per phase
Reference BICC cables hand book Table A14.14
Thus, the site continuous rating of 3 x 1C – 50 sq.mm Cu/XLPE cable is 245 x 0.7 = 172A
per phase
Hence based on thermal rating considerations the minimum size of 50 sq.mm would be
sufficient for all the 33kV cable connections (such as from 132/33kV station to the 33kV
OHL, road – crossings, transformer 33kV connections…etc). Site continuous rating for
minimum sizes of 3 core cables are given below:
3C x 70mm2 180A
3C x 95mm2 209A
b) The 33kV single core cables will be laid in trefoil ‘touching’ configuration.
3.1 Fault level magnitudes at the source and along the 33kV OHL
The following are the 3-phase and 1-phase (earth) fault current values at the source end and
at various locations along the 33kV OHL route (with ACSR 'R' type conductor) from the
source location (for two different source fault level magnitudes).
Scenario: For 1750MVA Source Fault Level For 700MVA Source Fault Level
The 11kV underground system is supplied from a number of 66/11kV primary substations
situated throughout the State of Qatar.
The 11kV circuits are generally connected in open ring configuration such that a faulty
section of cable can be isolated and supply restored via a normal open point on the 11kV
system.
Refer Figure 2.1 Page 12: 11kV Underground Distribution System Schematic
VIP consumers are sometimes connected on closed rings for security of supply with pilot
wire protection.
The 11kV cables are connected to 11000/433 volt distribution substation of the type
described in Section 3
The connection of the 11000/433 volt distribution substations to form a reliable electricity
supply is an important part of the Planning Engineer's work.
The following criteria are given as a guide to the general principals of 11kV network design.
4.1 Cabling
The first cable section out of the primary substation should be 3C x 240mm² XLPE cable.
The number of switching operations required should be as low as possible, consistent with as
high utilisation of cables as possible.
A design loading of 66% of the cable rating with three (3) switching operations to restore
supply is considered desirable.
Number of switching operations to restore supply is defined as the number of operations that
have to be carried out after the fault has been isolated and the tripped feeder is reclosed at the
source substation.
RMU’s can be either SF6 insulated or oil filled and have 2 Nos. feeder switches and one
transformer control switch.
The transformer control switch may be either switch and HRC fuse combination or circuit
breaker (SF6 / vacuum).
Extensible RMU will be RMU extended by feeder switch or transformer control switch. The
feeder switch is either oil filled or SF6 filled. The transformer control switch is a
combination of HRC fuse and switch or circuit breaker with SF6 or vacuum medium.
Package Unit is incorporated with RMU, Transformer & LV Feeder Pillar inside a metallic
enclosure. RMU & LV feeder are bolted with Transformer. Available Package Unit sizes are
500, 1000 & 1600 KVA with 4 & 6 ways Feeder Pillars.
4.7 Operational
An alternative supply can be manually switched with in a reasonable time of generally three
hours by isolating the fault section of network and restoring supplies by NOP.
The initial design of 11kV system must anticipate as far as possible the load requirements for
the next five years at the projected load growth of the area.
Load growth is difficult to anticipate and load readings will be a good guide.
The number of substations on any one radial circuit is to be limited to a maximum of two
substations. This is to limit the number of standby generators required in the event of a cable
fault. If a third substation is required, then every effort should be made to provide an
alternative supply.
The basis of the design is for the three phase conductors in horizontal formation supported on
steel cross arms on tubular steel poles. Below the phase conductors is a continuous earth
conductor, which is grounded at terminations and at intervals of every ten spans along the
route and at each position where 11kV plant is installed on the supports. Cable sections are
inserted along the network for diversions, road crossings and connections to equipment.
The 11kV OHL circuits are generally radial feeders with teed connections as required along
the feeder, although some 11kV feeders are connected to operate in parallel to compensate
for voltage regulation and some 11kV feeders may be configured to operate on the open ring
principle where security of supply is important.
However, certain actions can be taken to improve the security of supply on OHL network as
follows.
The planning engineer when reviewing the design of OHL network should study the OHL
network and install ABS to limit the outage due to faults. Normally ABS should be installed;
1. At the mid point of an overhead line ring system.
2. At the first pole out from a tee off position if the tee is longer than 1 km.
3. At intervals along the main OHL where there are three or more tee off OHL.
i) The teed circuit has an installed pole mounted transformer capacity of more
than 500kVA and at least three pole mounted transformers installed on the
circuit.
ii) Irrespective of the installed capacity on the 11kV teed circuit the overhead
line is more than 3km in length.
iii) The teed circuit has a history of poor operational performance resulting in
considerable loss of consumer hours.
iv) 11kV DOEF with a slow blowing characteristic and a nominal rating of
100/80/65 Amps will be installed on Teed Radial Circuits.
Group fusing is a design principle where a suitable fuse, normally 80A or 65A slow blowing
characteristic is installed on a teed radial circuit and protects a number of other teed circuits.
11kV drop out expulsion fuses SHALL NOT be installed on the following teed circuits:-
i. 11kV radial teed circuits which may be used to form an operational ring with
an adjacent 11kV circuit in such cases an air break disconnector switch shall
be initially installed.
ii. 11kV drop out expulsion fuses shall not be installed on radial teed circuits
which are controlled by auto reclosers which for operational reasons have had
their recloser features rendered inoperative. Such arrangements will not give
satisfactory discrimination.
5.3.4 Location
11kV DOEF shall be installed on the first pole out from the main line teed position which
will normally be a section pole.
Old Pole mounted auto reclosers are operated on a single shot no reclose mode with a
minimum earth fault current trip setting of 20 Amps. New Pole mounted Auto-reclosers are
available with different settings of O/C , E/F & SEF protection.
The old auto recloser is normally situated at positions on long overhead rural feeders
approximately 3 kms distance from the 11kV source at a point where the existing fault level
is below 100MVA. New auto-reclosers can be installed in 11 kV OHL where existing fault
level is less than 12.5kA.
The auto recloser will operate and lock out for faults down stream.
Before considering to use a voltage regulator, the Planning Engineer should investigate
means of permanent reinforcement from adjacent 11kV OHL networks. However as a
temporary means the voltage regulator is a cost efficient method of improving poor voltage
regulation.
The star point is solidly earthed to the combined HV and steelwork earth. Continuity of
earthing between substations is maintained by means of HV cable sheaths and earth
electrodes at each substations or by the under running earth wire on an 11kV overhead line.
The LV system has 5 wires, ie. 3 Phases + Neutral + Earth. Neutral and earth connections are
directly shorted at distribution substation end. A consumer earth terminal is provided.
The system is non Protective Multiple Earthed, that is the neutral conductor is earthed at one
point only. The consumers installation is protected by a MCCB of appropriate rating.
System design must be such as to maintain at the consumers terminal a voltage of 415/240
with a variation not exceeding +6%.
The neutral conductor shall be of the same size as the phase conductors.
PVC oversheath.
Standard cable sizes: 1C x 800mm2 and 1C x 630mm2 . 1Cx300 mm² LV cables will not be
used in future.
Because of the radial nature of LV mains, tapering of feeders should be designed where it
can be economically justified.
The following sets of rules are intended to guide the planning engineer in deciding on the
configuration of the LV feeder:
Practically without exception the mains leaving the feeder pillar should be
4 core 300mm² even if not justified initially by the anticipated load.
Reduction of cable size from 4 core 300mm² to 4 core 185 mm² may take place at
the point at which the load drops to 75% , and the end length of 4 core 185 mm² is
in excess of 60 metres.
In reducing the size of the distribution cable the planning engineer should bear in
mind the possibility of future substations taking up part of the load of the feeder
and thus affecting his decision on whether to reduce cable size. Experience
suggests that unless a feeder passes very close to the locality of a known future
site for a substation then no consideration may be taken of this future event.
The maximum feeder length should be of the order of 250-300m, the maximum
length is in any case usually dictated by the load picked up by the cable, than by
voltage drop considerations.
Typical sizes of MCCB’s used are 35A SPN, 50A SPN and the remainder are 35A, 50A,
75A, 100A, 150A, 200A, 250A, 300A, 350A and 400A TP&N.
LV service cable to the consumer requiring multi meters will be connected directly to the
main switchboard placed in a suitable location in side the premises.
1. Multi story buildings having independent electrical installation provided load is more than
one LV feeder load.
2. Both LV service cables should be originated from the same substation and same feeder
pillar.
3. LV network availability from the load point of view.
4 Proposal of two LV service cables to a consumer premise should be approved by Section
Head or his deputy.
Otherwise, the owner should allocate a substation site in his land and construct a substation at
his own cost.
7.2 LV Supply to multi story buildings and small industrial consumers using more
than one Transformer.
The following procedure will be applicable when planning engineer will study the building
permit application to the above consumers.
1. Planning engineer will allocate the site of the substation as required in the consumer
building or externally to the consumer building.
2. Design of the substation will include numbers of transformers required by the consumer
matching with the load required by consumer, numbers of switchgears and as per substation
specification shown in this manual.
3. Consumer will be responsible to provide all the transformers required to supply the load.
Consumer will provide a letter of guarantee to supply all transformers before building permit
approval.
4. Planning engineer will follow procedures and duties of issuing the building permit
application as cleared in part 3 section 4 of this manual.
5. Oil transformers or cast resin dry type transformers can be used depends on the location of
the transformers. In case of basement below the transformer room, cast resin dry type
transformers can be approved for installation. Customer shall be responsible to replace cast
resin transformers in case it is needed.
1. Client consultant should allocate substations required matching with load required as
per our specification. Planning engineers design approval following building permit
application stage has been mentioned in this manual part 3 section 4.
2. Client consultant will design the LV distribution inside the compound using either
consumer cubical panel system or feeder pillar using mini pillars.
3. Planning engineer will check and approve the LV design in case of using the mini
pillar system. Building permit office in customers services department will check and
approve the design in using the cubical panel system.
4. The transformers required will be provided by the owner with an under taking letter.
5. The owner must appoint an ENA approved contractor to carry out excavation, cable
laying and jointing of HV distribution cables inside the compound. This will also
include the cable loops between HV switchgear and transformer and transformer to
consumers panel.
6. The contractor will be required to prepare SIV`s, collect these materials from ENA
stores and deliver to the site.
8. The contractor will be required to prepare 'as laid' drawings and transfer these to our
main records prior to our cables being 'live'.
9. ENA will be responsible for plant delivery and installation including the earth bore
and substation earthing.
10. The owner will be responsible for substation site allocation and for all substation civil
works including arrangement of local supply to the substation.
11. HV distribution materials including 11 kV cables, joints, high voltage switchgear, but
excluding the transformers, will be issued by Kahramaa.
12. All works should be carried out under the supervision and instructions of ENA.
13. Despite the above requirements the owner still be obliged to pay the connection fees
in accordance with the law.
14. Reinstatement within the compound which may be required after HV cable
maintenance / repair by ENA, will be done by the owner.
8.1 General
The LV overhead network consists of four wire bare aluminium conductors plus earth wire in
vertical formation supported on steel poles. The earth wire is continuous and under-running
and the same size as the conductor.
Reference may be made to the 11kV Overhead Line Code of Practice - Section 5 for specific
detail on design and construction.
The use of LV overhead networks is now largely confined to rural areas and to situations
where an underground cable is not practicable in the short term, i.e. the lack of adequately
defined utility reserves.
The criteria which determine the choice between an overhead line and an underground cable
system may be defined as follows :-
8.4 The Short Term Need To Meet Commitments To Provide Supplies To Consumers.
In some cases where a development requires a supply but the prevailing conditions make an
underground system impractical then the Planning Engineer may give consideration to the
temporary use of an LV overhead line. Since, in the long term the overhead line would most
probably have to be removed this represents an expensive solution to a short term problem
and the engineer must therefore exercise judgement as to whether in any particular case it is a
reasonable solution.
Within the older urban areas, particularly in Doha, there are LV Overhead networks. The
Planning Engineer, when working in such an area should give consideration to replacement
by underground cable where the cost of doing so is reasonable and particularly where
clearances are less than apply to present practice.
In general tapering should not be used on overhead lines because of the practical difficulties
of staying etc. However, where a short radial feeder is teed off the main line this may be of
an appropriate smaller size conductor.
In an extensive LV network a main line may run physically between two substations, being
broken electrically by a section point on a pole. This facility may be of use in some cases for
temporary back-feeding provided that the main is of adequate capacity.
8.6 Services
The standard overhead service is cross-linked polyethylene XLPE insulated and sheathed to
Standard ED-03-048 three phase and single phase sized 16mm² Spans of suspended cable are
supported on pre-formed helical 'dead ends' attached to LV insulators.
8.7 Consents
Low voltage overhead lines are generally installed on municipal land and it is important that
the Planning Engineer initiates/obtains the necessary permission. Note also that this includes
any requirement for stays.
8.8 Design
When planning a new Overhead Line network, the first section of OHL from the PMT would
normally be constructed using 3 200mm AA. Spurs or tees from the
main line would normally be 3100mm AA.
Low voltage networks from adjacent pole mounted stations will not be interconnected or run
in parallel.
When connecting additional load to an overhead line network check the existing loads to
ensure the existing pole mounted transformer will not be overloaded. Load readings are not
available for PMT, however an assessment can be made by estimating the existing consumer
loads connected to the PMT network and allowing a margin for diversity.
QATAR GENERAL
ELECTRICITY & WATER CORPORATION
ELECTRICITY NETWORK AFFAIRS
PART - 3
DISTRIBUTION SUBSTATION DESIGN
PART 3
DISTRIBUTION SUBSTATION DESIGN
CONTENTS
Page No.
1.0 Introduction
The various distribution substations in the Qatar network can be primarily categorised into
33kV and 11kV substations. This can be further divided into indoor and outdoor type
installations.
The 11kV and 33kV switchgear with their control and protection panels will be installed on
separate pre-prepared foundations. The power transformer will be suitably located on its own
foundation for connection to 11kV and 33kV switchgear by external cabling.
The 33/11kV indoor substation should be located as close as possible to the load centre or
area of reinforcement. Refer to Section 14 of the Distribution Construction Manual for more
detailed installation procedures.
They are ground mounted on a prepared concrete pad and are totally enclosed units with
cable box connections for high voltage and low voltage cable connections. The low voltage
connections will be suitable for single core cable connections (2 per phase) for direct
connection to a single consumer or 6 way feeder pillar. Refer to Fig 3.1 page 36.
The substation will be located in a secure area at the load centre for a group of consumers
and also near to the 33kV overhead line.
Also, where possible, the 33kV/LV GMT Substation and the consumers switchroom shall be
located near to the 33kV OHL to avoid installing long lengths of 33kV cables.
The 33kV three core cable connections will be from the 33kV overhead line via 33kV DOEF
and surge diverters. Refer to Section 13 of the Distribution Construction Manual for more
detailed installation procedures.
The specification details of the pole and transformer are provided in Distribution Equipment
Specification .
Refer to Fig 3.2 Fig 3.3 Fig 3.4 . in pages 38. 39, 40 for typical substation design.
3.3.1.1 Ratings
The two sizes that could be considered for the package substation main transformer rating are
i. 2.5 MVA
ii. 5.0 MVA
For an anticipated maximum load of about 2MW, the 2.5MVA rating could be utilised,
where as for an anticipated load growth of about 3 to 4MW, the 5MVA rating could be used.
For major load centres that require higher ratings than the above, it is considered that such
load centres would justify an indoor 33/11kV Substation.
However, for the Qatar OHL distribution network it is anticipated that the ratings of 2.5MVA
and 5.0MVA would be sufficient to meet the loads required of the 33/11kV OHL distribution
network.
Qatar's 33kV system is derived from the main 220kV transmission network with transformer
Vector Groups as below:
Hence, in order to derive the 11kV system from the above 33kV system, the recommended
vector group for the package substation 33/11kV transformer is YN yno (d1).
The above vector group would produce an 11kV voltage vector identical in phase to that
derived from the existing 66/11kV system.
Therefore 11kV supplies from 33/11kV package substations can be connected directly to
existing 11kV network as a means of reinforcement or operated in parallel connection if
required for operational reasons.
3.3.1.5 Neutral Earthing for the 33/11kV Package Substation 11kV System
Considering single unit operation only and in line with the general philosophy of limiting the
11kV system earth - fault current value to a theoretical maximum value of 750A/main
transformer, it could be considered that a 'Neutral Earthing Resister' (metal grid type) is used
with a resistance value of about 8.5 ohms. This will limit the earth - fault current to a value of
about 750A. The resister could be short-time rated for 30 sec.
However, if the 11kV neutral is solidly earthed, even with 5MVA transformer having an
impedance value of 7.15% (and a zero-sequence impedance value of approx. 80% of the
positive sequence impedance value), the maximum earth-fault current value is not expected
to be more than 4kA. With source impedance values considered, however, the earth-fault
current values could be even lower than the above 4kA level. Hence, with the 11kV cable
screens designed for an earth-fault current value of 4.5kA (1 sec.), in line with the KAHRA
MAA standard practice, the use of Resistor for the 11kV neutral earthing of the package
substation transformer could be avoided, thus making the installation simpler and
more economical.
3.3.1.6 Typical Technical Particulars for Neutral Earthing Resistor (if used)
3.3.1.7 Typical Technical Particulars for the 33/11kV Package S/S Main Transformer
These typical parameters are used to develop the general specification for the design of the
33/11kV Power transformer within the overall specification for the 33/11kV Package
Substation.
Insulation Levels
Lightning Impulse / Power Freq. Withstand)
11kV Vacuum Circuit breaker shall be of 3 pole type ambient temperature 50°C and
in compliance to IEC 60056 standard with the following main technical data:
- Potential transformer shall have the following ratings and comply to IEC 60186
Standards.
Vector Group : YY (Primary winding neutral earthed)
Rated voltage Factor : 1.x x Un continuous / 1.9 x Un for 8 hrs.
Primary voltage : 33 kV, 3 Phase, 50 Hz.
Secondary Voltage : 110 V, 3 Phase, 50 Hz.
(Secondary winding neutral earthed)
Burden : 100 VA
Secondary Fuses/MCB : 5A
Each individual supply to a panel shall be sub-fused from the main bus wiring
(2A fuses).
- Current transformers rated primary current shall be adequate for the circuit rating
under the specified conditions. The rated extended primary current shall be 120%.
The rated secondary current shall be 1A or 5A.
Accuracy class for metering CT's shall be 0.5 where as for protection CT's shall be 3P.
Instrument security for metering CT shall not be greater than 5 and accuracy limit factor for
protection CT shall be 20 for Incoming circuits and 10 for outgoing circuits depending upon
the requirement. Current transformers are type tested and shall comply with IEC 60044-1.
The control circuits shall be protected with MCB’s and shall be graded selectively up to the
circuit main protection device.
3.3.5 Wiring
Common control voltage lines to more than one cubicle terminal and current transformer
wiring must have a minimum cross section at least of 2.5mm².
The minimum cross section for the control wiring and voltage circuits within a panel must be
with at least 1.5mm².
PVC Flexible wires for control wiring shall be used.
The Charger/rectifier with the battery shall have the following specifications:
All instruments to be flush mounted and have a front dimensions of 96 x 96 mm, class 1.5.
Minimum angular deflection of the pointer will be 90°.
Centralized on the panel are the pushbuttons for acknowledging the alarm, lamp test, alarm
reset.
Alarm System
The alarm annunciator unit is a self-contained micro-processor-base with 16 binary channels
for operation from making or breaking field contacts. The fault signals shall be displayed by
means of a long-life light-emitting diodes for visual alarm indication.
The alarm is activated at the same time as the annunciator indication. The indication would
continue to indicate the fault until the fault has been cleared and the reset button has been
pressed. A new alarm shall be given if a second fault occurs before the first fault has been
cleared.
A typical layout of the type of indoor substation is shown in Fig. 3.5 page 48.
For detailed design of this type of indoor substation refer to the civil engineer.
The following drawings can be used for reference:
STD/SUB/ID/OD-01, 02 -Civil design.
STD/SUB/ID/OD-03 -Power / Lighting Design.
The building is 10.8m x 6.5m and approximately 3.65m high. Sometimes the indoor
substation starts as a temporary outdoor substation until the Indoor substation is constructed.
Therefore the area of the required substation should be suitable for outdoor substation plus
the area required to construct the permanent indoor substation.
The land required for a substation depends on civil advice.
Transformer Room:
• TX room size depends on number of transformers.
• TX plinth size is (0.8m*2.1m).
• TX plinth top level is (+0.4m) and the bottom level is (-0.9m) from the road level.
• Setback from the both side of the TX plinth to the nearest wall in parallel with the TX
plinth should be not less than (1.5m).
• Setback from the nearest wall (opposite to the TX plinth) should not be less than (0.8m).
• Distance between the two transformer plinths is (1.0m) if they are in one line.
• Distance between the two transformer plinths is (2.6m) if they are in parallel.
• TX room could be open to sky or ceiled in the ceiled case the clear height shall be (3.65m).
• The floor of TX room could be back-filled area, or concrete where a trench must be
provided with size (0.8m width *1.2m depth).
• Two doors must be provided for the TX room. The main door size is (1.0m * 2.2m)
aluminum louver for (open to sky case) or (2.4m * 2.6m high) for ceiled case for each TX.
The 2nd door must open to the MV room; the size is (1.0m * 2.2m) aluminum sandwich
panel door. In case of any additional TX/s, a separate door for each TX should be provided.
General Notes:
• Crane and cable access to be available always.
• No services inside the substation
• HV room floor finish to be epoxy coated.
• Finished floor level to be very smooth and the tolerance not to be more than (±3mm)
maximum.
• Contact Kahramaa’s Civil Unit before starting the construction of substation, work without
stage-wise inspection and approval will be rejected.
• Substation rooms’ height is (3.65m) minimum.
• Under taking of responsibility of the Structural design is to be submitted to KM at building
Permit stage. Please refer to (Appendix 8)
• Elevation drawings to be submitted to KM before starting the construction of the substation
• Substation levels based on the front road level = +/-0.00.
• MV room details to be designed & checked by the consultant.
• TX room details to be designed & checked by the consultant (if the TX is dry type).
• Elevation of the substation must be matching with that of the main building (design, colour,
etc.).
Transformer Room:
• As per Kahramaa rules and regulations, any TX to be installed above the Ground level must
be a Dry Type. It is the responsibility of the consultant to design the TX room while
respecting the following:
- Provide one separate door for each Transformer (2.4m * 2.6m), aluminium
sandwich panel .
- Provide one door from TX Room to MV Room (1.00m *2.2m), aluminium
sandwich panel door.
- TX room floor level to be +(0.20 M) from outside area facing the TX room.
General Notes:
• Crane, equipment and cable access to the substation to be always available.
• No services inside substation.
• HV room floor finish to be epoxy coated.
• Finished floor level to be very smooth and the tolerance not to be more than (±3mm)
maximum.
• Contact Kahramaa’s Civil Unit before starting the construction of substation, work without
stage-wise inspection and approval will be rejected.
• MV room details to be designed & checked by the consultant.
• TX room details to be designed & checked by the consultant.
• Substation rooms’ height is (3.65m) minimum.
• Under taking of responsibility of the Structural design is to be submitted to KM at building
Permit stage. Please refer to (Appendix 8)
• Substation levels based on the level of the area in front of the substation = +/-0.00.
• Substation and transformer rooms must be provided with a cooling system and equipped
with all necessary handling tools (i.e. cranes, forklift, trolleys, etc.).
• A complete fire hazards study shall be done by consultant whereby the consultant shall
propose a suitable fire fighting system for the electrical substation and transformers rooms.
• Consultant shall provide “method statement” with the building permit application with a
clear drawing showing method of delivery and replacement of the electric equipments in the
substation i.e. transformers and HV switch gears.
• All works should be carried out under the supervision and instructions of Kahramaa.
4.3.3 Substation in the Basement Level (only in West Bay Towers Area)(I/D)
• The required S/STN consists of :
6 High Voltage vacuum circuit breakers + 2 TX's
High Voltage Room:
• HV room size is (6.2m long * 5.8m deep), for 6 VCBs and in case of any additional
VCB's add (0.8 M) per VCB to the length.
• HV room height is (3.65m).
• HV room Trench size (0.8m width * 1.5m depth) along the 6m (Length of the H.V.
room).
• Setback of the HV trench is (0.4m to 1.0m), depends on number of VCBs.
• HV room floor level is (+0.2m) from the outside area facing to the HV room.
• Two doors must be provided for the HV room (aluminium sandwich panel doors).
The main door size is (1.4m width * 2.6m high). The 2nd door (escape door) size is
(1.2m width * 2.2m high). Both doors must lead to an open area.
• Natural ventilation opening size is (0.5m * 1.2m), aluminium louver with sand trap at
high level, and it could be provided with cooling system.
Transformer Room:
• As per Kahramaa rules and regulations, any TX to be installed below the Ground
level must be Dry Type. It is the responsibility of the consultant to design the TX
room while respecting the following:
- Provide one separate door for each Transformer (2.4m * 2.6m), aluminium
(sandwich panel /louver) door.
- Provide one door from TX room to MV room (1.00m * 2.2m), aluminium
sandwich panel door.
- TX room floor level to be (+0.20m) from outside area facing the TX room.
- Trench size to be (0.8m * 1.2m) in the TX room.
- Clear height to be (3.65m).
• The design of the Transformer Room shall comply with Kahramaa design rules and
regulations.
General Notes:
• Crane, equipment and cable access to the substation must be available always.
• No services inside substation.
• HV room floor finish to be epoxy coated.
• Finished floor level to be very smooth and the tolerance not to be more than (±3mm)
maximum.
• Contact Kahramaa’s Civil Unit before starting the construction of substation, work
without stage-wise inspection and approval will be rejected.
• MV room details to be designed & checked by the consultant.
• TX room details to be designed & checked by the consultant.
• Substation rooms’ height is (3.65m) minimum.
• Under taking of responsibility of the Structural design is to be submitted to KM at
building Permit stage. Please refer to (Appendix 8)
• Substation levels based on the level of the area in front of the substation = +/- 0.00.
Substation location should not be below basement level 1.
• Consultant shall provide “method statement” with the building permit application with
a clear drawing showing method of delivery and replacement of the electric
equipments in the substation (i.e. transformers and HV switchgear).
• Provide direct access to the HV room from the ground floor through door and
staircase with KM locks.
• If natural ventilation is not available substation must be provided with a cooling
system.
• All S/STN should be equipped with all necessary handling tools (i.e. cranes, forklift,
trolleys, etc.).
• A complete fire hazards study shall be done by consultant whereby the consultant
shall propose a suitable fire fighting system for the electrical substation and
transformers rooms.
• Consultant shall provide design concept and statement along with clear drawings for
the drainage system design showing effective and complete protection for the
substation from water flood.
• All works should be carried out under the supervision and instructions of Kahramaa.
Cable Trays:
• Cable trays shall comply with the following
o Made of galvanized steel.
o Suitable strength and rigidity.
o Side rails or equivalent structural members.
• Cable trays should not have any sharp edges, burrs or projections that could
damage the cables.
• Cable trays shall be corrosion resistance but if not the system should be protected
from corrosion.
• Cable trays shall include fitting for changes in direction and election of runs.
• Cable trays should be protected from any physical damage and additional protection
should be provided wherever required.
Cable trays specifications should be in compliance with QCS.
Detailed design of this type of outdoor substation depends on switch make and transformer
size, refer to the civil engineer for further details.
The RMU could be replaced with Feeder & Transformer switches as shown in STD-
SUBOD- 07.
The RMU could be replaced with Feeder & Transformer switches as shown in STD-
SUBOD-07.
This type of outdoor substation is useful where space is restricted although it may be
installed in other situations.
The civil works for the unit substation are simple and consist mainly of a rectangular plinth
with cut out for cable entry. Each manufacturer has a different design and a civil construction
drawing is supplied with the equipment.
The location of the outdoor unit substation is important and the following notes apply.
Avoid locations where the unit substation may be damaged by vehicular traffic - if the area is
congested protective concrete stanchion may be erected around the unit substation.
Ensure that sufficient space is available to use a crane to install/remove the unit substation.
Generally a corner position near to the building is most suitable with regard to the free
circulation of air around the unit substation in order to provide sufficient ventilation for the
transformer.
• The floor of S/STN room could be back-filled area, or concrete where a trench must be
provided with size (0.8m width *1.5m depth).
• The height should not be less than (3.65 M) from the top of the Plinth.
• A separate door for the RMU beside the designated door for the TX is required.
• The doors dimensions should be :
o RMU door dimensions should be (1.5 M X 2.6 M)
o TX door dimensions should be (2.4 M x 2.6 M)
o All the doors should be facing the main road.
General Notes:
• Crane and cable access to be available always.
• No services inside substation.
• In case of an M.V. room the finished floor level to be very smooth and the tolerance
not to be more than (±3mm) maximum.
• Contact Kahramaa’s Civil Unit before starting the construction of substation, work
without stage-wise inspection and approval will be rejected.
• Under taking of responsibility of the Structural design is to be submitted to KM at
building Permit stage. Please refer to (Appendix 8)
• Elevation drawings to be submitted to KM before starting the construction of the
substation.
• Substation rooms’ height is (3.65m) minimum.
• Substation levels based on the front road level = +/-0.00.
• M.V. room details to be designed & checked by the consultant.
• TX Plinth details to be designed & checked by the consultant (if the TX is dry type).
• Elevation of the substation must be matching with that of the main building (design,
colour, etc.).
General Notes:
• Crane and cable access to be available always.
• No services inside substation.
• In case of an M.V. room the finished floor level to be very smooth and the tolerance
not to be more than (±3mm) maximum.
• Contact Kahramaa’s Civil Unit before starting the construction of substation, work
without stage-wise inspection and approval will be rejected.
• Under taking of responsibility of the Structural design is to be submitted to KM at
building Permit stage. Please refer to (Appendix 8)
• Elevation drawings to be submitted to KM before starting the construction of the
substation.
• Substation rooms’ height is (3.65m) minimum.
• Substation levels based on the front road level = +/-0.00.
• M.V. room details to be designed & checked by the consultant.
• TX Plinth details to be designed & checked by the consultant (if the TX is dry type).
• Elevation of the substation must be matching with that of the main building
(design, colour, etc.).
A remote outdoor Transformer substation site is installed when the site is isolated from the
main general 11kV system, normally about 150 meters. or more and it is judged that the
security of supply requirement is low and does not require an alternative supply.
Note that the 11kV switchgear controlling the remote 11kV/LV transformer is located at a
substation connected to the main 11kV network.
QATAR GENERAL
ELECTRICITY & WATER CORPORATION
ELECTRICITY NETWORK AFFAIRS
PART - 4
VOLTAGE DROP CALCULATIONS
PART 4
CONTENTS
Page No.
1.0 Introduction
This part of the manual outlines the method used to calculate the voltage drop across
the 33kV, 11kV and LV networks using appropriate worked examples.
2 5
33kV A.1.1.33.5 11kV
100 8.75
10k 250A P 2k A
5km B 150A
2km A 6km E
300A m
m P
P 103.25 99.75 P 96.25 87.5
A A.1.1.1A A A.1.1.2
A A.1.1.5
3.5 5MVA
1km
Package
2 A
7% 33/11kV
P Size Conductor (100mm ACSR)A.1.1.4
2
= (I x d) x Rcos + Xsin
190.53
Vdf = Rcos + Xsin
190.53
VoltageDro p
Rcos + Xsin = = 0.5143 (From the table in Appendix 1, Part 10)
A.km
Some voltage drop on the 11kV system is acceptable as the declared low voltage is
415/240 volts and the no load transformer voltage is 11,000/433/250 voltage.
11000
240 x 3 = 10,560 Volts
433
11,000 10,560
% allowable high voltage drop = % = 4%
11,000
Voltage regulation on the 11kV system should normally be maintained within +5% of
the nominal 11kV on load voltage.
However in the case of rural 11kV Electrical Distribution Networks with extended
OHL a voltage drop of up to 7% may be considered.
This is the voltage drop due to the 11000/433 volt transformer regulation and refers to
the change of secondary terminal voltage between no-load and load conditions. It is
usually quoted as a percent or per unit value for full load at a given power factor.
Transformer regulation is also a function of power factor as well as load and can vary
from about 1% at unit PF full load to 4% at 0.5 PF. This range is shown in the figure
4.1 page 74.
In rural areas with extended 11kV overhead line feeders and large point loads of
(1MVA-2MVA) voltage drop calculations must be made before the load is accepted
for connection to the network. Computer programmes are available for such studies.
However, the following simplified approximate manual method of calculation for a
worked example is shown below.
Connection of 2MVA load at Abdul Ghani Farm on the Al Shalah Primary Network
on the Rawdat Rashid, QTEL circuit.
The schematic drawing Fig 4.2 page 77 is attached and the proposed load is to be
connected at the end of the OHL supplying Mubarak S/S (8281) and Yaqoob S/S
(5640).
Assumptions
11000V
Phase to earth voltage = 6351 V
3
Phase to earth voltage
Transformer HV Terminals = 6351 - 943 = 5408V
Equivalent to Phase/Phase
Voltage at Transformer Terminals = 3 x 5408 = 9367V
This is equivalent to
250
LV Transformer Terminal Voltage = 9367 x = 213 volts
11,000
The voltage at the consumer terminals will be this value (213V) minus the
transformer voltage regulation.
To calculate this value, assume that the proposed consumer's load of 2MVA will be
supplied from an outdoor substation with RMU and 2 x 1000kVA Transformers.
Power Factor PF@ .85, it is estimated that the voltage regulation at the 1000kVA
transformer will be of the order of 4% of the nominal voltage 240V.
4
Thus volt drop at consumer terminals = 213 - (240 x )
100
(assumes no voltage drop on = 213 - 9.6
connection from T/F to
consumer terminals short distance) = 203.4 volts
240 203.4
% voltage regulation = 100 = 15.3%
240
This is an excessive voltage drop on the normally accepted minimum voltage level of
226 volts.
The conclusion is that the line should be reinforced or a new line constructed before
the load is accepted on the Electricity Network.
50 50 50
A A A
250 200 150 100 50A
A 250 200 150
300 A A A A100
A A C A A E
B D F PPP
EEE
50m 50 50 50 D 50 50
m m m m m
50 50 50
A A A
X = 0.0758
= (I x d) x Rcos + Xsin
2.50
VoltageDro p
Rcos + Xsin = (This value can be obtained from the table in
A.km
Appendix 1, Part 10)
For load of 300 Amps at the far end and cable length of 300 metre.
QATAR GENERAL
ELECTRICITY & WATER CORPORATION
ELECTRICITY NETWORK AFFAIRS
PART - 5
FAULT LEVEL CALCULATIONS
PART 5
FAULT LEVEL CALCULATIONS
CONTENTS
Page No.
1.0 Introduction
System fault levels are normally calculated by computer programs but where manual
calculations are necessary the following methods can be used.
Using per unit (or percentage) values related to a common base MVA.
For the following calculations the symbols used have the following meaning;
2.0 Symbols
V= phase-phase voltage (kV)
ZB =
kV 2
MVAB
Z
Zpu = ………………..1
ZB
MVAbase 1
Zpu base 1 = Zpu base 2 x ………………..2
MVAbase 2
MVAbase
Zpu = ………………..3
S
(V B ) 2
ZA = ZB ……………….4
(V A ) 2
And
MVAbase
S= ………………...7
Zpu
3 V
Isc = …………………..8
(2Z1 Z 0 3Z e )
3 MVAbase
Isc = …………………..9
V (2Z1 Z 0 Z e ) pu
Second method is to assume that all impedances have the same power factor and can be
added arithmetically. The calculated value will be lower than the true value but is useful for
the appraisal of abnormal loads or in calculating the reach of relays.
Source Impedance
The resistance component of the source impedance is neglected.
100
Xpu = j = j0.143
700
Refer to formulae (3)
= (0.063 + j0.07)pu
0.0715 100
Xpu = = j1.43 Transformer resistance is
5
neglected.
= (0.167+ j0.333)
(0.167 j 0.333) 100
= pu
(11) 2
= (0.138 + j0.275)pu
= (0.1716 + j0.3135)pu
= 1.223pu
MVAbase 100
S (three phase fault) = 81.8 MVA
Zpu 1.223
100
Isc = = 4.29kA
3 11 1.223
100
S= = 82.9MVA
1.2065
100
Three phase fault level at point ‘A’ = 79.2MVA
1.2621
Which is 3.3% lower compared with the previously calculated value of 81.8MVA.
These two methods are a convenient method of calculating short circuit currents and fault
levels.
Z1 Z 2 Z 0
ZLG = = j1.163pu
3
Z1 = Z2 = (0.063 + j0.07)pu
Assume Z0 = 0.9xZ1
Z0 = j1.287
Z1 Z2 Z3
Cable
0.063 j.07 0.063 j.01 0.49 j.0868
Parallel
2 2 2
Transformer
j1.43 j1.43 j1.287
Parallel
2 2 2
Z1 = .894 1.53o
Z2 = .894 1.53o
Z0 = 3.894 1.50o
Z1 Z 2 Z 0
ZLG =
3
0.894 1.53o .8941.53o 3.8941.5o
= = 1.8935 1.5147o
3
MVAbase 100
S (single phase fault) = 52.8 MVA
Z LG 1.8935
100
Isc = = 2.77kA
3 11 1.8953
1
Zs = = 0.0733pu
273
Cable Impedance:
112
For cable lengths of 2.5km, Zc = 0.26375 Zbase = = 6.05
20
0.26375
Thus, Zc = = 0.0436pu
6.05
Given, each Motor is rated at 1640kW with assumed pf = 0.8 and eff = 0.95;
1640 10 3
FLC, In = = 113.3A
3 11000 0.8 0.95
Fault current contribution by motor during a three phase fault is similar to that of the
starting current of the motor, assuming 7 x FLC.
11 10 3 8.01
Thus, Zm = = 8.01, Zm pu = = 1.32pu
3 793 6.05
Point of three phase fault is assumed to be on one of the 11kV outgoer feeders close to the
11kV switchboard.
1.32
All 6 motors in parallel; = 0.22pu
6
0.0436
All 4 cables in parallel = = 0.0109pu
4
The total motor and cable impedance = 0.22 + 0.0109 = 0.2309pu
1
Three Phase Fault MVA, S = 20 = 359.5MVA
0.0556
359.5 10 6
Short Circuit Current, Isc = = 18.87kA
3 11000
273 10 6
Fault Current through each transformer = = 7.16kA
2 3 11000
18.87 2 7.16
Fault Current through each cable feeder = = 1.14kA
4
4 1.14
Fault Current contributed by each motor = = 0.76kA
6
1000kVA
6.45%
Dyn11
433V
1
Source impedance, Zs = = 0.002857pu assuming base MVA = 1
350
Assume Z2 = Z1 = 0.067357pu
1 1
Fault MVA, S = = = 14.846MVA
Z1 0.067357
14.846 10 6
Short Circuit Current, Isc = = 19.8kA
3 433
3 3
Fault MVA, S = = = 12.857MVA
Z1 Z 2 2 0.067357
12.857 10 6
Short Circuit Current, Isc = = 17.1kA
3 433
3 3
Fault MVA, Sf = = = 15.059MVA
Z1 Z 2 Z 0 2 0.067357 0.0645
15.059 10 6
Short Circuit Current, Isc = = 20.1kA
3 433
QATAR GENERAL
ELECTRICITY & WATER CORPORATION
ELECTRICITY NETWORK AFFAIRS
PART - 6
MOTOR LOADS
PART 6
MOTOR LOADS
CONTENTS
Page No.
1.0 Introduction
This section of the Distribution Planning Manual deals with abnormal loads mainly
considering the starting of large electrical motors. Reference is made to Engineering
Recommendation P28 which is included in Part 10 Appendix A-2 of this manual.
Work examples for voltage drop due to the starting of large electrical motors are
given. Also guidance is given by “rule of thumb” methods for connecting motors to
the Distribution Network.
The magnitude of the starting current of low voltage three phase motors can be
reduced by the use of star / delta starters. On starting the motor terminals are
connected in star mode with a reduction in effective starting current of approximately
3 times and then delta mode for normal running.
Large Electrical Motors (3.3kV, 11kV rated) employ several methods of reducing the
magnitude of the initial starting current. Auto transformers are used where the applied
voltage on starting is gradually increased to start the motor. Capacitor motor starting
reduces the reactive power drawn from the Distribution Network whereby reducing
the magnitude of the motor starting current.
In continuous process works it is often not possible to apply such reduced starting
methods and the large electrical motors have to be started “direct on load” which is
the cause of the network disturbances. In such cases the magnitude of the disturbance
must be assessed with it’s frequency of occurrence before the connection is made to
the Distribution Network.
Accept - 3 phase motors with output rating of 45kW provided the GMT is at
least 500kVA.
ii. 3 Phase motors with a point of common coupling at a pole mounted 11kV / LV
substation.
Accept: - 3 phase motors with output rating of 22.5kW provided the PMT is at
least 200kVA.
iii. In both cases as above and by reference to P28, before a particular size of
motor is connected to the Electricity Distribution Network, it may be necessary
to up rate the size of Transformer.
1. Collect all information on the type of motor and starter that is to be connected to the
electricity network. It will include, size of motor (HP, KW) and method of starting
current.
2. Understand the type of work the motor will perform and the times of starting and
stopping and the frequency of starting/stopping.
3. Define the point of common coupling on the electricity network. What other
consumers are connected and establish if they are voltage sensitive.
Clarify - If the means of starting can be varied to reduce the starting current.
Clarify -The frequency of starting and particular hours of start up and close down.
Impose - In writing operating conditions on the operation of the large motor such as
frequency of starting, time of the start, operator must contact system
control engineer before start up or close down.
Base MVA = 20
Base kV = 11
Base Impedance ZB =
Base Voltage 2 =
112
= 6.05
Base MVA 20
R = 0.0812 /Km
X = 0.0932 /Km
= 0.1218 + j0.1398
MVA base 20
ZS pu = 0.07326 pu = 0.0732690o
Fault Level 273
Z C 0.1218 j 0.1398
ZC pu = 0.0201 j 0.0231 pu | = 0.03065 0.8547o
ZB 6.05
Motor is rated 1640kW at 0.8PF, efficiency 95%. Direct on load starting current equals
7 times FL current.
1640 10 3
Motor current =
3 11000 0.95 0.8
= 113A
ZM = 6351 = 8.02
792
Z M 8.02
ZM pu = = 1.32541 pu90o
Z B 6.05
Total Zpu = ZS pu + ZC pu + ZM pu
= 1.40502.01o
=
0.1038 x 1
1.4050 = 0.0739 pu = 7.3%
An alternative method to calculate the voltage drop is;
20 10 6
Base current = = 1050A
3 11000
This percentage voltage drop of approximately 7.3% at the motor terminals is not acceptable
and at the point of common coupling – the 11kV bus bar would cause voltage disturbance to
consumer even on an infrequent starting routine.
The consumer should be advised to install some form of automatic starting which will reduce
the starting current to about three (3) times full load current and give a voltage drop of about
4%.
This would allow consideration to be given to the motor being started infrequently during the
early hours and to contacting the system control engineer before starting.
Types of automatic starters suitable for this type of motor are automatic sequence auto
transformer and capacitor automatic starting systems.
QATAR GENERAL
ELECTRICITY & WATER CORPORATION
ELECTRICITY NETWORK AFFAIRS
PART - 7
PROTECTION OF UNDERGROUND DISTRIBUTION
NETWORKS
PART 7
PROTECTION OF U/G DISTRIBUTION NETWORKS
CONTENTS
Page No.
1.0 Introduction
1. Unit Protection (differential protection with pilot cable) on 11kV feeders from
primary substations to the first indoor substation + backup IDMT Directional
Overcurrent/directional Earth protection. Unit Protection for 11kV feeders
between indoor substations uses Translay or Solkor ‘R’ schemes. Recent
specification includes Pilot wire protection and IDMT Protection.
2. IDMT protection (over current and earth fault protection) on 11kV feeders
towards substations which are connected on interconnected ring system or
radial systems. For fast clearance of faults Pilot wire Protection also deployed
4. Transformer Protection.
11kV HRC oil immersed fuses in Ring Main Units for transformer
protection.
Time Limit Fuse(TLF) Protection in SF6 Ring Main Units for transformer
protection.
Restricted Earth Fault Protection, inter trip between LV ACB and HV CB.
Inter trip cable should be of adequate size considering voltage drop
between LV ACB and HV CB.
Unit protection schemes are based on the principle that with a healthy circuit the
current entering and leaving the circuit are equal. This type of differential protection
scheme is designed to protect one zone of the 11kV circuit or item of plant.
Current transformer and relays are installed at each end of the 11kV feeder which is
to be protected and are interlinked by pilot wires of a pilot cable.
The schematic diagram shown in Figure 7-1a in page 110 depicts a current balance
arrangement employed by the Solkor R relay.
At each end of the feeder, the secondaries of the current transformers are connected to
the primary winding of a summation transformer as shown above. For various types
of current distribution in the three current transformers on the feeder, a single phase
quantity appears in the summation transformer secondary winding and is applied to
the single pair of pilot circuit. The tapping on the summation transformer primary is
selected to give an optimum balance between the demands of fault setting and
stability.
For external fault conditions, an alternating current circulates around the pilot loop.
This will not cause the relay to operate since the secondary currents at both ends are
equal in magnitude and phase. For an internal fault either fed from a single end or
both ends of the protected feeder zone, unequal magnitude of currents from the CTs
or the direction of current flow will trigger the relay and thus tripping the circuit
breaker.
The schematic diagram shown in Figure 7-1b in page 110 below depicts a voltage
balance arrangement employed by the Translay relay for one phase only as shown
below for the condition of a fault outside the zone and a fault within the protected
zone.
The examples cover the voltage balance arrangement where the CT secondaries are
connected in opposition. Current only flows through the pilot wires and therefore
through the relays when there is a difference in the induced voltages V1 and V2.
This will occur when there is a difference in the primary currents at each end of the
feeder. Therefore in the example shown for a fault outside the protected zone, V1 =
V2 and no current flows to operate the relay, thus the circuit breaker at each end of the
feeder does not trip.
For a fault inside the protected zone the primary currents entering and leaving the
protected feeder are no equal and V1 V2 and secondary currents will flow in both
relays causing a trip of the circuit breaker at each end of the protected circuit.
This type of unit protection is used to protect 11kV feeders from primary substations
to the first indoor substation and also indoor substation to indoor substation to give a
satisfactory discrimination under all fault levels than is possible with the simpler
Inverse Definite Minimum Time (IDMT) relay schemes.
IDMT Protection is used on the 33kV and 11kV circuits to protect against over currents and
earth faults occurring on the distribution network.
The basic schematic diagram for this type of protection is shown in Fig 7.2 in page 113.
The basic method of providing over current relay protection on a 33kV or 11kV feeder is to
install current transformers on the circuit which then feed current into the over current relay
proportional to the circuit current.
When the current exceeds a preset value, the relay will operate at a time determined by the
characteristics of the relay to initiate tripping of the associated circuit breaker.
The over current relay can be of electro-mechanical, static or numeric type. When sufficient
current is passed through the coil from the current transformer, the disc will rotate in case of
electromagnetic relay to operate the tripping circuit. Numeric relays shall be used only in air
conditioned indoor substation.
This type of relay has a time/current characteristic designated inverse time-delay since they
operate after a time delay inversely dependent on the value of the over current and also the
time delay approaches a definite minimum value for the high values of current giving the
type, name of Inverse Definite Minimum Time (IDMT). Note that the time delay can be
adjusted, but is independent of the value of the over current required to operate the relay. By
varying the time delay of successive relay in series, discrimination between relay installed on
different sections of the same feeder can be achieved.
The majority of 11kV system faults occur between one phase and earth and the practice to
protect against such fault is to connect the residual of secondary windings of the current
transformer to one earth fault relay as shown in the schematic diagram Fig 7.2 in page 113.
The earth fault relay will operate when the vectorial sum of the phase current is not equal
thus providing a residual current and earth fault relay is connected such that the residual
current flows through it and trips circuit breaker. Where the minimum fault current is more
than four times of load current, 2 phase O/C and E/F can be used.
When fault current can flow in both directions through the relay location, it is necessary to
make the response of the relay directional by the introduction of directional control elements.
These are basically power measuring devices in which the system voltage is used which the
system voltage is used as a reference for establishing the relative direction or phase of the
fault current.
This type of protection is required in closed ring system and parallel circuits in order that
discrimination is obtained in each direction around the closed ring.
A typical example (Fig 7.3 in page 114) is the operation of the 11kV automatic voltage
regulator at Karana S/S where two incoming 11kV OHL feeders are operated in parallel on to
a common 11kV busbar. In order to provide discrimination, the two incoming 11kV circuit
breakers are fitted with Directional Over current (DOC) and Directional Earth Fault (DEF)
Protection.
The directional protection scheme will only operate for a fault on the 11kV feeder on which
it is installed leaving the healthy second 11kV feeder in operation and therefore no loss of
supply will occur.
The Ground Mounted Transformers may be protected by IDMT over current and earth fault
relays. These relays may have the following characteristics – SI, VI or EIDMT+ High set
instantaneous O/C& E/F elements.
The time delay characteristic should be chosen to discriminate with the circuit protection of
HRC fuses on the secondary side of the transformer. As the primary winding of the
transformer is not earthed, reverse flow of earth fault current is not possible; equally no zero-
sequence current can be transmitted to the secondary system. The setting of the earth fault
protection may therefore be low, with respect to both current and time.
In order to maintain good discrimination the earth fault element must remain stable under
phase fault conditions, which is most likely to be achieved with a low relay setting because
of the use of an high impedance relay. Generally a setting 20-30% is a good compromise
between the conflicting requirements of sensitivity and stability. If phase fault stability is
achieved, the time setting can be reduced to the minimum value, since the time grading of the
earth fault elements is not involved. For a 1000kVA transformer, CT ratio will be 80/5, O/C
setting 75% and E/F setting 40%. TMS for O/C is 0.2 while E/F is 0.1. Also 100/5A ratio
CT`s are used with proper settings.
The typical ratings for Ground Mounted Transformers to be protected by fuse links are 315kVA,
500kVA, 800kVA, 1000kVA, 1250kVA and 1600kVA.
These fuse links are installed in 11kV oil filled fuse switches which protect the transformer.
The principle of operation makes use of a striker pin in the fuse link which operates the trip bar
in the fuse switch to disconnect all phases. The fuse switch is non-fault breaking, this duty being
assigned to the fuse link.
The ratings of these oil tight fuse links are;
GMT Transformer Size Fuse Size
(kVA) (Amps)
315 40
500 56
800 63
1000 71
1250 90
1600 90
The rating and time/current characteristics of these fuse links must satisfy certain criteria
such as;
The fuse link must be capable of carrying the rated full load current of the
transformer and sustain an overload rating of up to 115% .
The 11kV fuse links shall be able to withstand transformer magnetising in
rush current which shall be assumed to be a maximum of (ten) 10 times the
fuse rating for a duration of 0.1 second.
The 11kV fuse link must discriminate with LV fuses for low voltage system
faults.
Ground Mounted Transformers which are controlled by SF6 Ring Main Units use time limit
fuses for transformer protection. The time limit fuse is connected in parallel with the
secondary side of the current transformer and the tripping coil.
The time limit fuse has an inverse time/current characteristic and will normally carry the
current transformer secondary current to by-pass the trip coil. As and when sufficient current
occurs to "blow" the time limit fuse, the whole secondary current is then transferred to the
trip coil which operates to trip the circuit breaker.
The rating time limit fuses for sizes of transformer and CT ratios are:-
The above time limit fuses will co-ordinate with a 400A LV fuse.
The Ground Mounted Distribution Transformer also incorporates a number of other devices
for indication and protection:-
5.4.2 Thermometer
A dial type thermometer indicates the temperature of the oil at the top of the tank. It is
graduated in degrees centigrade and covers the range 40°C to 120°C with increment marks at
5°C intervals. The dial is fitted with pointers to indicate the present oil temperature and its
maximum value.
The pressure relief valve is spring loaded and sits on a seal-seat. When the pressure inside the
tank increases above a certain value, the force on the movable sub-assembly exceeds the
spring force and the valve operates and the alarm contacts are closed. The device is also
fitted with a prominent indicator which remains in place after the operation of the device.
Earth faults on secondary side are not reflected on primary side, when the primary winding is
delta connected or has unearthed star point. In such cases, an earth fault relay connected in
residual circuit of 3 CT's on primary side operates on internal earth faults in primary
windings only. Because earth faults on secondary side do not produce zero sequence current
on primary side. Restricted earth fault protection may then be used to high speed tripping for
faults on star connected earthed secondary winding of power transformer.
This type of fuse link is a unit in which the fuse element is enclosed. The fuse link is replaced
when it operates. The outer cover is of a high grade ceramic which will withstand all thermal
and mechanical stresses to which the fuse link may be subject.
The fuse elements are fitted inside the body. The ends of the fuse elements are connected to
the metal end caps by solder and riveting. The body of the fuse is filled with a suitable
insulating medium which shall be free from organic and metallic impurities and also
moisture. The fuse elements are generally whole pure copper with tin in the eutectic zone.
The current passing through the fuse element produces heat which is proportional to I²t
where I = current, t = time. With a certain current, the temperature rises and the tin bridge
melts producing a break in the circuit. Thereby an arc is produced, which immediately
spreads over the neighbouring elements and which also melt. The metal vapour diffuses with
the filler medium and the product of chemical reaction produces a substance of high
resistance which becomes an insulator. Thereby the space between the caps is filled with a
material of high dielectric strength, as the current is interrupted.
The following are important definitions used when describing HRC fuse.
6.1.9 Cut-off
The melting of fuse-element before the current reaches the prospective peak. The value of
current at which the cut-off occurs is cut-off value.
QATAR GENERAL
ELECTRICITY & WATER CORPORATION
ELECTRICITY NETWORK AFFAIRS
PART - 8
PROTECTION OF OVERHEAD LINE DISTRIBUTION
NETWORKS
PART 8
CONTENTS
Page No.
1.0 Introduction
This part of the manual describes the various types of protection employed for both 33kV
and 11kV Overhead Line Distribution Network
The standard design for the 33kV Rural Distribution Network is:-
Aluminium conductor, steel reinforced, shall be used as standard, primarily in the standard
sizes of 100mm² Hyena ACSR and 200mm² Jaguar ACSR.
The basis of the design is for the three phase conductors in horizontal formation supported by
porcelain insulators on steel crossarms on tubular steel poles. Below the phase conductors
will be a continuous earth conductor of 100mm² (Hyena). This earth conductor shall be
grounded at terminations, at intervals along the route and at each position where 33kV plant
is installed on the supports.
Load break pole mounted switches will be installed at strategic positions on the main line and
at tees to provide a means of isolation.
The 33kV system will be designed on the open radial system.
Interconnection may be possible on the 11kV side of the 33/11kV package substation.
This policy also requires that protective equipment installed to protect the 33kV overhead
line network must be designed to discriminate for faults. That is the nearest protective device
to the fault should be the first to operate thus giving the minimum operating time, reducing
any damage and disconnecting the least number of consumers. The design of the protective
system must allow for second stage back up protection in case the normal first stage
protection fails to operate for any reason.
The protection system must be as simple as possible consistent with the requirement of the
system to be protected.
1. Sensitive Earth Fault (SEF), IDMT overcurrent and earth fault which are
normally installed on the circuit breaker at the 33kV primary substation. Also
the first leg from primary should be provided with Pilot wire Protection or
communication aided distance Protection this requirement as per protection
design of down stream substations..
2. Pole mounted auto recloser installed on OHL with protection and remote
operation facility.
3. Drop Out Expulsion Fuses (DOEF).
4. Air Break Switches (ABS). Strictly ABS is not a protective device but is
included in the section as it's use is complementary to any protective system
design.
5. Clip on fault indicators for visual display only.
2. For typical protection design for 33kV OHL network refer to Fig.-8.1 in Page
140.
3. Pole Mounted Auto recluses will be set for one delayed trip followed by an
instantaneous trip and lock out. This will enable transient faults to be cleared
without shutdown and the time for delayed trip will allow the operation of
other protective devices such as DOEF and surge diverters. On extended 33kV
OHL, additional auto-reclosers may be installed, these will be set to
discriminate with the source circuit breakers and any other auto reclosers.
4. Drop Out Expulsion Fuses (DOEF) fast blowing will be installed on the 33kV
Overhead Line Network as follows :-
33kV DOEF slow blowing shall be installed on Radial Teed Circuits where:
1. The Teed circuit has an installed pole mounted transformer capacity of more than
500kVA and at least three pole mounted transformers installed on the circuit.
2. Irrespective of the installed capacity on the 33kV Teed Circuit the overhead line is
more than 3km in length.
3. The Teed circuit has a history of poor operational performance resulting in
considerable loss of consumer hours. The design and development section shall be
consulted for such cases.
4. Size of DOEF slow blowing will be normally 40/65Amps.
1. On the first 33kV OHL pole from the primary substation with the 33kV single
core cable termination.
2. At cabled road crossings one set of surge diverters shall be fitted to each cable
termination.
3. All cable inserts at crossing under 66kV, 132kV and 220kV overhead lines
shall have surge diverters fitted at each end.
4. One set of surge diverters shall be fitted at Pole Mounted Transformer
positions.
5. One set of surge diverters shall be fitted at the terminal pole of an overhead
line supplying a ground mounted transformer.
1. On the second 33kV OHL pole from the primary substation as a means of
isolation of the 33kV OHL without gaining access to the primary substation to
operate the 33kV circuit breaker.
2. At the mid-load point of an extended overhead line radial feeder as a means of
isolation for restoring supplies during fault location.
3. On a OHL tee, at the first pole where the length of OHL exceed 1 km.
4. At intervals along the main line where there are three or more tee-offs.
The fault indicators shall be installed as single phase units and shall be installed in
groups of three units at each location in order to allow for the detection of all possible
faults.
However where arcing horns are fitted to plant, for example, pole mounted
transformers and these are located within two kilometres of a surge diverter, then the
arcing horn gap setting shall be co-ordinated with the surge diverter characteristic.
The actual gap setting depends on the design of the OHL network. Typically there
shall be a duplex gap settings with a combined minimum setting of 300mm.
The transforming ratio errors of the C.T.s separately correctable on the HV and
LV side of the power transformer.
Separate adjustable differential current high-set instantaneous stage.
Stabilized operating principle prevents spurious function on faults occurring
outside area of protection.
Blocking function, for prevention of spurious operations caused by connection
Inrush currents, based on occurrence of the second and fifth harmonics.
Local display of measured and set values on relay front panel.
Continuous supervision of the electronic circuitry and the operation of the
microprocessor.
Restrictive Earth Fault Protection for HV and LV winding.
The earth fault relay is a non-directional earth-fault relay with two operation stages, a high-
set stage with definite time characteristic and a low-set stage with definite time or
inverse/extremely inverse time operation characteristic. The non-directional earth-fault relay
should have the following salient features:
Four freely configurable output relays for circuit breaker control and signaling.
High immunity to electrical and electromagnetic interference.
Direct numerical readout of setting values, measured values, values recorded on
relay operation, indications etc.
Improved system reliability backed up by a built-in sophisticated self-supervision
system.
E/F Relay can be combined in the O/C relay it self.
A Buchholz relay is fitted in the pipework from the conservator to the main tank to provide
protection for the power transformer against incipient faults in the transformer tank below oil
level or arcing within the transformer winding.
Oil and winding temperature indicators are also utilised to initiate an alarm signal or tripping
of the transformer.
The overcurrent /EF relay shall be an integrated three-phase overcurrent/EF relay intended to
be used for the selective short circuit and earth fault protection of radial feeders. The
overcurrent relay should have the following salient features:
If the Sensitive Earth Fault (SEF) protection feature is not included in the overcurrent
numerical relay, an additional SEF relay will be installed.
3.1 General
In assessing the protection requirements of an OHL network it is necessary to define the
construction and basis of the design of the network.
The 11kV Overhead Line Network in Qatar is based on aluminium conductor, steel
reinforced in standard sizes of 100mm² (Hyena)and 200mm² (Jaguar).
The basis of the design is for the three phase conductors in horizontal formation supported on
steel cross arms on tubular steel poles. Below the phase conductors is a continuous earth
conductor, which is grounded at terminations, at intervals of every ten spans along the route
and at each position where 11kV plant is installed on the supports. Cable sections are inserted
along the network for diversions, road crossings and connection to equipment.
The 11kV overhead lines are generally extended in some cases up to 25 kilometres and there
is a multiplicity of teed overhead circuits.
The 11kV overhead line network is supplied from a number of 66/11kV primary substations
situated throughout the State of Qatar.
- 11kV switchgear with bus section and normally 12 outgoing 11kV feeders.
Older primary substations use oil circuit breakers - new primary substations
use vacuum circuit breakers and outgoing feeders up to 20 or more. Each
circuit breaker is equipped with IDMT protection (overcurrent and earth fault
protection) + pilot wire or SEF protection.
Generally the network is designed on the basis of a radial system although as the network is
developed, the system has become interconnected with Air Break Switches (ABS) used as
Normal Open Points (NOP) between adjacent networks. This NOP has the advantage of
providing an alternative supply to consumers when their normal supply is tripped due to a
fault by closing the ABS.
At the 66/11kV Primary Substations, the neutral is earthed on the 11kV side via earthing
transformers with the following parameters.
Alternatively, Neutral Earthing Resistors are installed with a size of 8.46 ohms fully rated for
30 seconds. Earth fault currents are limited to 1500 amps although parts of the 11kV network
can experience earth fault currents of 4,500 amps.
This recognises the duty to operate a safe and efficient network and to minimise the possible
damage or destruction of Kahramaa Plant/Equipment.
This policy also requires that protective equipment installed to protect the 11kV overhead
line network must be designed to discriminate for faults, that is the nearest protective device
to the fault should be the first to operate thus giving the minimum operating time, reducing
any damage and disconnecting the least number of consumers. The design of the protective
system must allow for second stage back up protection in case the normal first stage
protection fails to operate for any reason.
The protection system must be as simple as possible consistent with the requirement of the
system to be protected.
The melting of the fuse causes dropping of the fuse element under gravity about its
lower hinged support.
Fuses are overcurrent devices and must have ratings well above the maximum
transformer load current in order to carry without blowing during any short
duration overloads that may occur, such as motor starting, also the fuses must
withstand the magnetising in rush current when the pole mounted transformers are
energised. The most suitable type of fuse characteristic to protect this type of
transformer is slow blowing type.
The fault indicators shall be installed as single phase units and shall be
installed in groups of three units at each location in order to allow for the
detection of all possible faults.
The procedure for locating a faulty line is that for an earth fault on a spur line,
all fault indicators located between the source of supply and the faulty section
will trip and start flashing, whilst the units located beyond the faulty section
will not be activated and will not give a flashing light.
7. Arcing Horns
Arcing horns are an important means of lightning protection for bushings
particularly on pole mounted transformers. Duplex gaps are used to protection
pole mounted transformers with a gap setting of 2 x 31mm.
However where arcing horns are fitted to plant, for example, pole mounted
transformers and these are located within two kilometres of a surge diverter,
then the arcing horn gap setting shall be co-ordinated with the surge diverter
characteristic. This entails increasing the gap setting or arcing horns to 80mm,
that is 40mm per gap for duplex gaps.
The source circuit breaker with IDMT O/C & E/F protection
connecting the 11kV overhead line network will not have auto
reclosure features because of the difficulty of co-ordination with the
single shot pole mounted auto reclosers. Sensitive Earth fault (SEF)
relay will provide the necessary back up protection for the 11kV
overhead line network.
ii. Sectionaliser systems require the full range of trip and reclosure
feature of the pole mounted auto reclosers as defined in Specification
ED-02-150 in order to provide proper discrimination. Instead of using
sectionalisers a more effective system is the combined use of Air
Break Switch (ABS). Disconnectors and pole mounted drop out
expulsion fuses used individually on spur lines or on a group fusing
arrangement combined with the use of clip on fault indicators. This
system is illustrated in Drawing Fig.2.
iii. Drop Out Expulsion Fuses (DOEF) used to protect a number of 11kV
overhead lines is an effective method of protection. This is known as
group fusing and is particularly effective when used with Clip on Fault
Indicators.
The use of these systems is shown in the following section of "Typical
Protection Design for 11kV Overhead Line Networks Drawing Fig. 2".
3.6 Typical Protection Design for 11kV Overhead Line Networks and
Plant/Equipment
Refer to Drawing Fig. 8.2 in page 141 for protection system for typical overhead line
network. Protection settings are typical and each particular network requires study by the
protection department.
QATAR GENERAL
ELECTRICITY & WATER CORPORATION
ELECTRICITY NETWORK AFFAIRS
PART - 9
AMENDMENTS
QATAR GENERAL
ELECTRICITY & WATER CORPORATION
ELECTRICITY NETWORK AFFAIRS
PART 10
APPENDICES
PART 10
APPENDICES
CONTENTS
Page No.
APPENDIX 1
3C x 240 b 0.0907 0.078 0.64 0.3963 0.3408 0.1176 259 290 285 319
3C x 185 c 0.118 0.086 0.57 0.4366 0.2960 0.1420 224 252 247 277
3C x 95 f 0.228 0.086 0.44 0.5472 0.2064 0.2428 159 176 175 194
g
3C x 70 0.316 0.090 0.39 0.5846 0.1665 0.3273 133 147 146 162
Depth of Cable = 80 cm
Depth of Cable = 70 cm
200 ACSR R 0.1670 0.333 0.0109 3.4226 0.3340 0.6660 302 0.3151
150 ACSR Q 0.223 0.337 0.0108 3.2340 0.4460 0.6740 260 0.3647
100 ACSR P 0.391 0.350 0.0167 5.2438 0.7820 0.7000 194 0.5143
100 4.75% 0.03712 0.08047 0.280 2.000 DYN 11 2.5 Steps, ±5%, Fixed Tap
200 4.75% 0.03122 0.04303 0.480 2.400 DYN 11 2.5 Steps, ±5%, Fixed Tap
500 4.75% 0.00515 0.01706 1.030 6.860 DYN 11 2.5 Steps, ±5%, Fixed Tap
800 5.16% 0.00293 0.01173 1.500 10.000 DYN 11 2.5 Steps, ±5%, Fixed Tap
1000 6.45% 0.00221 0.01189 1.770 11.800 DYN 11 2.5 Steps, ±5%, Fixed Tap
1250 6% 0.00155 0.00886 2.200 13.000 DYN 11 2.5 Steps, ±5%, Fixed Tap
1600 6% 0.00124 0.00691 2.500 17.000 DYN 11 2.5 Steps, ±5%, Fixed Tap
APPENDIX 2
(filed seperately)
APPENDIX 3
(filed seperately)