Documente Academic
Documente Profesional
Documente Cultură
MEMORANDUM
FACTUAL BACKGROUND
The China-funded Kaliwa Dam project, which will be constructed along Rizal
and Quezon provinces is viewed to increase the water furnish from Angat Dam.
The Kaliwa Dam, which has a peak of 60 meters, is anticipated to put an end to
water shortages in Metro Manila considering it will supply extra 600 million liters
of raw water per day. The Department of Environment and Natural Resources
(DENR) already issued the Kaliwa Dam project with an Environmental Compliance
Certificate (ECC).
The ECC is one of the requirements for the Metropolitan Waterworks and
Sewerage System (MWSS) and China Energy Engineering Corp. to proceed with the
12.2 billion peso project, along with a free prior and informed consent from the
indigenous people. According to the DENR, the ECC was once issued by way of the
Environmental Management Bureau to the project after
it satisfied the requirements of the Environmental Impact Statement System.
1
However, the Commission on Human Rights allegedly said that there would
possibly have been a fake consultation and approval from the affected indigenous
communities.
At stake, the project would submerge parts of General Nakar and Infanta in
Quezon Province. It would also have an effect on the Sierra Madre in Tanay, Rizal,
some organizations claim. According to Haribon Foundation , the town of Infanta
which is a delta or a landform created by deposition of sediment, would possibly be
erased from the map if this project pushes through. But the MWSS said they
will provide housing and other resources for the indigenous people who will be
affected.
Environmental groups also said the flooding caused by the project will
displace and kill species that live in the area. But President Rodrigo Duterte said he
is ready to use expropriation or the police power of the state to put an end to water
shortages, even if the environment is at risk.
In 2014, the Kaliwa Dam project was initially rolled out as a PPP project, with
two qualifying bidders — SMC-K Water Consortium (San Miguel Holdings Corp.
and Korea Water Resources Corp.); and the Abeima-Datem Consortium (Albeinsa
Infraestructura Medio Ambiento S.A and Datem Inc.) The project involved the
development of a new water source to meet the increasing water demands by
constructing a redundant dam for Metro Manila's domestic water supply. The
government, however, under the administration of Duterte, in March 2017 chose to
instead push through with the project under an ODA scheme.
2
The Metropolitan Manila Waterworks System (MWSS) is pushing an
important project, the proposed New Centennial Water Source Project (NCWSP). It
will involve the construction of a dam at the Kaliwa River (Laiban Dam), and a smaller
dam (Kaliwa Dam) downstream to maximize the water supply, give additional 600
million liters per day (MLD) to augment the 4,000 MLD from Angat Dam in Bulacan
which provides potable drinking water. This is important not only because of rising
water demand but also for backup, in case the old Angat Dam will be damaged by
a strong earthquake.
1. San Miguel mulls legal steps as Kaliwa dam project to be funded by China ODA
(Oct. 3, 2017).
2. MWSS expects three Chinese firms to buy Kaliwa dam project bid documents
(Feb. 16, 2018).
3. China-funded Kaliwa dam, LGU surveillance projects seen making progress (July
19, 2018).
4. Manila Water flags risk of water shortage between 2021 and 2023 (Aug. 30, 2018).
So the original proponent GUDC, then San Miguel, Datem, other bidders
were somehow lost in the process when the Duterte administration came. Then
GUDC was given consideration because its proposal is about 30% cheaper than the
China-funded one.
3
In support of the above stated facts the Plaintiff presented the gathered
information and summarized them in the exhibit to wit:
Exhibit “A”
It shows that not only that the cost is higher under China contractors
because of its oversized design and other factors, the rest of Philippine taxpayers
will be involved in paying this higher cost. This is anomalous because the users-pay
principle under integrated PPP works just fine.
The MWSS website said that “Project Cost P18.7 Billion, to be funded from
ODA from China. Loan Signing scheduled on the state visit of China President Xi
Jinping on Nov. 19-21, 2018.” Wow, formalizing the anomaly.
4
A. WHETHER OR NOT KALIWA DAM IS IN CONSONANCE WITH THE
PROVISIONS ON WATER CODE OF THE PHILIPPINES.
ARGUMENT:
DISCUSSION:
5
B. Dam reservoirs are a significant source of greenhouse gas emissions, most
notably methane, which is up to 30 times more potent than carbon dioxide in
trapping heat in the atmosphere and causing global warming. Large dams emit
enormous amounts of greenhouse gases during construction.
D. Kaliwa Dam will be constructed within the zone of two active tectonic
plates represented by the Philippine Fault Zone and the Valley Fault System.
Many large-scale earthquakes were recorded in the past in this area, and
the relative movement of 6 centimeters was observed in 1991-1993 along the
Philippine fault line.
The Philippine fault zone has a potential to cause very high seismic
activity, as what was recorded in the earthquake of July 18, 1880, when the old
churches of Infanta, Mauban (both in Quezon province) and Manila Cathedral
were devastated.
PRAYER:
6
WHEREFORE, these aforementioned reasons are more than enough to call
into serious question the wisdom of pushing through with the construction of Kaliwa
Dam. To ensure water security in Metro Manila, a dam cannot deliver this
alone. There is need to explore all viable solutions that will create the
least adverse impact to the environment and our pe ople.Premises
Considered and in the Interest of justice it is most respectfully prayed that the
Petition be GRANTED.
Respectfully submitted,
Greetings:
Kindly submit the foregoing motion to the Honorable Court immediately upon
receipt hereof for its kind consideration and resolution.
EXPLANATION
7
Copies of the foregoing Memorandum was served to the Office of Solicitor General
indicated below via registered mail (with return card), due to lack of messengerial
personnel to effect personal service.
Copy furnished: