Sunteți pe pagina 1din 54

SingleSite Solution

V100R003C00

SingleSite9202 DPS Solution


Introduction and Installation Guide

Issue 01
Date 2015-11-20

HUAWEI TECHNOLOGIES CO., LTD.


Copyright © Huawei Technologies Co., Ltd. 2015. All rights reserved.
No part of this document may be reproduced or transmitted in any form or by any means without prior written
consent of Huawei Technologies Co., Ltd.

Trademarks and Permissions

and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective
holders.

Notice
The purchased products, services and features are stipulated by the contract made between Huawei and the
customer. All or part of the products, services and features described in this document may not be within the
purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information,
and recommendations in this document are provided "AS IS" without warranties, guarantees or
representations of any kind, either express or implied.

The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.

Huawei Technologies Co., Ltd.


Address: Huawei Industrial Base
Bantian, Longgang
Shenzhen 518129
People's Republic of China

Website: http://www.huawei.com
Email: support@huawei.com

Issue 01 (2015-11-20) Huawei Proprietary and Confidential i


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide Contents

Contents

1 About This Document.................................................................................................................. 1


2 Solution Introduction................................................................................................................... 2
2.1 Application Scenarios.....................................................................................................................................................3
2.2 Hardware Models........................................................................................................................................................... 4
2.3 Device Layout.................................................................................................................................................................4
2.4 Power Distribution Solution........................................................................................................................................... 4
2.5 Monitoring Principles..................................................................................................................................................... 5
2.6 Transmission Cables....................................................................................................................................................... 6
2.7 Technical Specifications................................................................................................................................................. 6

3 Installation Preparations.............................................................................................................. 8
3.1 Engineering Preparations................................................................................................................................................9
3.1.1 Reference Documents..................................................................................................................................................9
3.1.2 Tools and Instruments..................................................................................................................................................9
3.1.3 Skills and Requirements for Installation Personnel...................................................................................................10
3.2 Before the Installation...................................................................................................................................................11

4 SingleSite DPS Solution Installation Guideline.................................................................. 13


4.1 Installation Process....................................................................................................................................................... 14
4.2 Installation of the Main Device and the DPS............................................................................................................... 14
4.2.1 Installation Space Requirements............................................................................................................................... 15
4.2.2 Installing Power Modules/Blade RRUs/Battery Modules.........................................................................................21
4.2.3 Installing the Main Device and the DPS on the Wall................................................................................................ 23
4.2.4 Installing the Main Device and the DPS on the Pole................................................................................................ 25
4.2.5 Installing the Main Device and the DPS on U-steels................................................................................................ 36
4.2.6 Installing the Main Device and the DPS on Angle Steels......................................................................................... 38
4.2.7 Installing the Main Device and the DPS on the Indoor Rack....................................................................................40
4.2.8 Installing the Main Device and the DPS on the OPS-06........................................................................................... 42
4.3 Cable Installation of the Main Device and the DPS..................................................................................................... 44
4.3.1 Cabling Requirements............................................................................................................................................... 44
4.3.2 Cable Connections..................................................................................................................................................... 45
4.3.3 Cable Installation Process..........................................................................................................................................46
4.4 Checking the Installation.............................................................................................................................................. 47
4.5 Powering on and Commissioning the Main Device and the DPS................................................................................ 48

Issue 01 (2015-11-20) Huawei Proprietary and Confidential ii


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide Contents

5 Acronyms and Abbreviations................................................................................................... 49

Issue 01 (2015-11-20) Huawei Proprietary and Confidential iii


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 1 About This Document

1 About This Document

Scope
This document describes the distributed power system (DPS) solution, including the hardware
models, device layout, power supply methods, monitoring principles, application scenarios,
technical specifications, and installation guidelines.

Intended Audience
This document is intended for:
l Installation and commissioning engineers
l Technical support engineers

Issue
l 01(2015-11-20)
Compared with Draft A (2015-09-20), this issue incorporates the following changes:
– No contents are added or deleted
– Modified the following information:
Section Description

4.2.3 Installing the Equip the PWR with the RRU or the BAT, then install
Main Device and the them on the wall or on the pole in normal mode.
DPS on the Wall

4.2.4 Installing the Change Figure 4-32 and Figure 4-34


Main Device and the
DPS on the Pole Add Figure 4-27

l Draft A(2015-09-20)

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 1


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 2 Solution Introduction

2 Solution Introduction

This chapter describes the main device configuration and the DPS solution. The main device
refers to main devices of NEs and the DPS is composed of the power supply unit (PSU),
transforming module and battery module. DPU30D, DPU30A and DBU20B function as the
PSU, transforming module and battery module, respectively.

2.1 Application Scenarios


The DPS solution is used to provide power supply and power backup for main devices in the
sites with RRU remotely deployed, EasyMacro sites, small cell sites, and LampSite sites.
2.2 Hardware Models
This section describes the hardware models of the main device and the DPS.
2.3 Device Layout
For details about the device layout, see relevant solution documentations and installation
guides of the main device and the DPS.
2.4 Power Distribution Solution
This section describes the power distribution solution for NEs.
2.5 Monitoring Principles
This section describes the monitoring principles used between the main device and DPS,
including ways of connecting to the element management system (EMS), monitoring
parameters, and hardware monitoring ports.
2.6 Transmission Cables
This section describes the types and specifications of transmission cables.
2.7 Technical Specifications
For details about technical specifications of the main device, see technical specifications of
the main devices.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 2


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 2 Solution Introduction

2.1 Application Scenarios


The DPS solution is used to provide power supply and power backup for main devices in the
sites with RRU remotely deployed, EasyMacro sites, small cell sites, and LampSite sites.

Table 2-1 Application scenarios


Scenarios and Configuration Load Load Typical Max Maximum
Type Quantity Power imu Load Power
Consum m Consumption
ption Pow
er
Con
sum
ptio
n

Site with LTE FDD/ LTE AC 1 to 3 300 450 1350


RRU TDD RRU with DC
remotely lower power
deployed AC
and
DC

Indoor RRUs, AC 1 to 3 250 320 960


including GSM DC
and LTE TDD
RRUs AC
and
DC

EasyMacr LTE FDD AC 1 to 3 250 330 990


o
LTE TDD AC 1 to 3 300 375 1125
DC

LampSite One RHUB, AC 1 500 800 800


which supplies
power for up to
eight pRRUs in
PoE mode

Small cell One to three AC 1 to 3 190 205 615


small cells

One to three AC 2 to 4 190 205 248


small cells and AC 42.5
one transmission and 2
device (PTN910) DC

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 3


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 2 Solution Introduction

2.2 Hardware Models


This section describes the hardware models of the main device and the DPS.
The following table lists the hardware models of the DPS.

Table 2-2 Hardware models


Part Name Model Version

PSU DPU30D TP4860H V500R001C00

Transforming Module DPU30A TP4860H V500R001C10

Battery Module DBU20B TP4860H V500R001C00

For details about hardware models of the main device, see documentations about the models
of main devices.

Table 2-3 Main device documentation


Main Device Document Name Title

3900 series base stations, 3900 Series Base Station Product Description >
including macro base Documentation Hardware
stations, EasyMacro base Description
stations, and LampSite base
stations.

Small cell site Product documentation under: Description >


Wireless Network > Small Cell at Hardware
http://support.huawei.com Description
For example, BTS3205E product
documentation

2.3 Device Layout


For details about the device layout, see relevant solution documentations and installation
guides of the main device and the DPS.
l Obtain solution documentations of the main device from relevant product
documentations or the knowledge base.
l Install the DPS by following instructions provided in DPU30D-N06A1 & DBU20B-
N12A1 Distributed Power System Quick Guide.

2.4 Power Distribution Solution


This section describes the power distribution solution for NEs.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 4


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 2 Solution Introduction

Table 2-4 Power distribution solution


Part Name Power Supply Position Connector Type

DPU30D Four-output connector: Quick connector


Three paths are for DC
loads and the current of each
path is 30 A. One path is for
batteries and the current of
this path is 40 A.

DPU30A Four-output connector: Quick connector


Three paths are for AC
loads and the current of each
path is 10 A. One path is for
batteries and the current of
this path is 40 A.

DBU20B Two-path power connector Quick connector

2.5 Monitoring Principles


This section describes the monitoring principles used between the main device and DPS,
including ways of connecting to the element management system (EMS), monitoring
parameters, and hardware monitoring ports.

Ways of connecting to the EMS


 The site power manager (SPM) is supported. The following figure shows the access
solution.

Figure 2-1 EMS in which the SPM is available in SRAN11.0 or later versions.

In the indoor scenario, the DPS connects to the RRU through the RS485 port and is
managed by SPM.
 Power management bus protocol is supported. The following figure shows the solution.

Figure 2-2 Dynamic environment system based on the power management bus protocol

 Dry-contact based monitoring is supported. The following figure shows the solution.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 5


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 2 Solution Introduction

Figure 2-3 EMS in which dry-contact-based monitoring is available in SRAN9.0 or


earlier versions

Monitoring Parameters
Monitoring parameters include:

l PSU: eID reading, input and output voltages and currents, temperature, AC power-off
alarm, battery status, and alarm status
l Battery module: battery equalizing and floating charging status, charging and
discharging voltages and currents, temperature and alarm status
l Transforming module: eID reading, input and output voltages and currents, temperature
and alarm status.

Hardware monitoring port


The hardware monitoring port is shown as follows:

l The indoor distributed power backup devices connect to the RRU through an RRU
monitoring port.
l Other indoor distributed power backup devices connect to CAN ports and the Bluetooth
port is reserved.

2.6 Transmission Cables


This section describes the types and specifications of transmission cables.

l Signal cable connection:


– PSUs should be interconnected using DB9–DB15 cables.
– PSUs should be connected to lithium batteries using DB9–DB9 cables.
– Lithium batteries should be interconnected using DB9–DB9 cables.
l Connecting remote monitoring cables (two optional methods):
– PSUs should be connected to RRUs using DB15–DB15 cables. In this situation,
cable labels must be considered.
– PSUs should be connected to a monitoring device using DB15–dry contact cables.

For details about port pins, see DPU30D-N06A1 & DBU20B-N12A1 Distributed Power
System Quick Guide

2.7 Technical Specifications


For details about technical specifications of the main device, see technical specifications of
the main devices.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 6


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 2 Solution Introduction

Table 2-5 PSU technical specifications


Item Technical Specifications

Dimensions (H x W x D) 400 mm x 300 mm x 50 mm (15.75 in. x 11.81 in. x 1.97


in.)

Weight 7 kg

Input operating voltage 110 V AC/220 V AC/HVDC 85 V to 400 V

Output voltage –48 V DC

Maximum output power 1500 W

Operating temperature –40°C to +55°C (41°F to 131°F)

Table 2-6 Technical specifications of the transforming module


Item Technical Specifications

Dimensions (H x W x D) 400 mm x 300 mm x 50 mm (15.75 in. x 11.81 in. x 1.97


in.)

Weight 7 kg

Input operating voltage 110 V AC/220 V AC/–48 V DC

Output voltage 220 V AC

Maximum output power 1500 W

Operating temperature –40°C to +55°C

Table 2-7 Technical specifications of the battery module


Item Technical Specifications

Dimensions (H x W x D) 400 mm x 300 mm x 120 mm (15.75 in. x 11.81 in. x 4.72)

Weight 18 kg

Input operating voltage –48 V DC

Output voltage –48 V DC

Capacity 20 Ah

Operating temperature –40°C to +55°C (41°F to 131°F)

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 7


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 3 Installation Preparations

3 Installation Preparations

This chapter describes the engineering preparations and information to be known before the
installation.

3.1 Engineering Preparations


This section describes the reference documents, tools, and instruments that must be ready
before the installation. In addition, it provides the skills and prerequisites that installation
engineers must have.
3.2 Before the Installation
This section describes the necessary information to be known before installation, including
the dimensions and size, ports, installation scenarios and installation space requirements for
the main device and the DPS as well as user equipment requirements and cabling
requirements.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 8


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 3 Installation Preparations

3.1 Engineering Preparations


This section describes the reference documents, tools, and instruments that must be ready
before the installation. In addition, it provides the skills and prerequisites that installation
engineers must have.

3.1.1 Reference Documents


Ensure that you have obtained all the related documents before the installation.
Ensure that you have been familiar with the following documents before installation.
l For details about installing a main device by following instructions provided in 3900
Series Base Station Product Documentation.
Product documentation under: Wireless Network > Small Cell at http://
support.huawei.com
l For details about installing a DPS by following instructions provided in DPU30D-N06A1
& DBU20B-N12A1 Distributed Power System Quick Guide

3.1.2 Tools and Instruments


This section lists the tools and instruments that must be obtained before installation.

NOTE

Take proper electrostatic discharge (ESD) protection measures, for example, wear ESD gloves, to
prevent electrostatic damage to the boards or electronic components when installing components or
cables.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 9


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 3 Installation Preparations

3.1.3 Skills and Requirements for Installation Personnel


Installation personnel must be qualified, trained, and familiar with operation methods and
safety precautions before performing any operations.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 10


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 3 Installation Preparations

Before the installation, pay attention to the following items:


l The customer's technical engineers must be trained by Huawei and be familiar with
installation and operation methods.
l The number of the onsite personnel depends on the engineering schedule and installation
environment. In most cases, three to five onsite personnel are recommended.
l During cable installation, pay attention to the following requirements:
– Before installing power cables, cut off the external power supply and switch off all
the circuit breakers on power supply and base station devices.
– The colors and appearances of the power cables in this document are for reference
only, which may differ from those of the cables used onsite. If cables are purchased
locally, the colors and appearances of the cables may be different from those shown
in this document.
– Contact Huawei technical support to ensure whether customer-provided cables and
connectors can be used or whether fixed-length cables can be shortened.
– The following two figures show the correct installation methods of cord end
terminals and OT terminals.

Figure 3-1 Installation of core end terminals

Figure 3-2 Installation of OT terminals

3.2 Before the Installation


This section describes the necessary information to be known before installation, including
the dimensions and size, ports, installation scenarios and installation space requirements for
the main device and the DPS as well as user equipment requirements and cabling
requirements.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 11


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 3 Installation Preparations

l Dimensions of the main device and the DPS


For details about dimensions of the main device and the DPS, see documentations about
the dimensions and size requirements for the main device and power supply system.
l Ports on the main device and the DPS
For details about ports on the main device and the DPS, see documentations about ports
on the panels of the main device and power supply system, including ports at the bottom,
in the cable cavity and indicators.
l Installation scenarios of the main device and the DPS
For details about the installation scenarios of the main device and the DPS, see
documentations about the installation scenarios of the main device and power supply
system.
l Installation space requirements for the main device and the DPS
For details about the installation requirements for the main device and the DPS, see
documentations about the requirements on space and spacing for installing the main
device and power system.
l Cabling requirements
For details about the cabling requirement, see documentations about the main device and
power system.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 12


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

4 SingleSite DPS Solution Installation


Guideline

This chapter describes the installation guideline for installing the DPS and main devices.

4.1 Installation Process


This section describes how to install the DPS site, including the installation of main device,
power module, battery module, and cables as well as hardware installation and check and
power-on check.
4.2 Installation of the Main Device and the DPS
This section describes the space requirements for installing the main device and the DPS,
installation scenarios, and the installation of power modules, blade RRUs or battery modules.
For details about how to install the main device and the DPS, see related documentations
about the main device and power supply system.
4.3 Cable Installation of the Main Device and the DPS
This section describes how to install cables for the main device and the DPS.
4.4 Checking the Installation
This section describes items to be checked after the main device and the DPS hardware are
installed.
4.5 Powering on and Commissioning the Main Device and the DPS
This section introduces how to power on and commission the main device and the DPS.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 13


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

4.1 Installation Process


This section describes how to install the DPS site, including the installation of main device,
power module, battery module, and cables as well as hardware installation and check and
power-on check.
The following figure shows the installation process.

Figure 4-1 Installation process

4.2 Installation of the Main Device and the DPS


This section describes the space requirements for installing the main device and the DPS,
installation scenarios, and the installation of power modules, blade RRUs or battery modules.
For details about how to install the main device and the DPS, see related documentations
about the main device and power supply system.
The main device and the DPS can be installed on the wall, pole, u-steel, angle steel, indoor
rack, or OPS06, depending on installation environments.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 14


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

4.2.1 Installation Space Requirements


This section describes the installation space requirements for the main device and the DPS.

NOTE

Blade RRU cannot be equipped with the blade battery directly.

The following figures show the installation space requirements.

l It is recommended that the mounting bracket be installed 1200 mm (47.24 in.) to 1600
mm (62.99 in.) above the ground, as shown in the following figures.

Figure 4-2 Height requirement for installing the mounting kits (1)

Figure 4-3 Height requirement for installing the mounting kits (2)

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 15


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

l The following figure shows the minimum space requirement for installing a single
device in normal mode on the wall.

Figure 4-4 Space requirements for installing a single device in normal mode on the wall

l The following figure shows the space requirements for installing a single device in side-
mounted mode on the wall.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 16


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-5 Space requirements for installing a single device in side-mounted mode

l The following figures show space requirements for installing multiple devices in
centralized mode.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 17


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-6 Space requirements for installing multiple devices in centralized mode

Figure 4-7 Minimum space requirements for installing multiple devices in centralized
mode

l Install the second set of RRU mounting kits at least 80 mm (3.15 in.) above or below the
first set of RRU mounting kits, as shown in the following figures.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 18


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-8 Installing the second set of RRU mounting kits

l The following figures show the space requirement for installing multiple devices on the
wall in normal mode.

Figure 4-9 Space requirements for installing multiple devices on the wall in normal
mode

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 19


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-10 Minimum space requirement for installing multiple devices on the wall in
normal mode

l The following figure shows the minimum horizontal spacing between RRUs.

Figure 4-11 Requirements for minimum horizontal spacing

l The following figure shows the minimum vertical spacing between RRUs.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 20


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-12 Requirements for minimum vertical spacing

4.2.2 Installing Power Modules/Blade RRUs/Battery Modules


This section describes the procedure for installing DPU30D or DPU30A power modules,
blade RRUs, and battery modules.

Background Information
The following figure shows the connection kit and hanging kit used in combinations.

Figure 4-13 Connection kit and hanging kit

Procedure
Step 1 Install the DPU30D or DPU30A connection kit onto the rear of the RRU or the battery
module, and use an M6 inner hexagon torque screwdriver to tighten the captive screw into the
hole of the connection kit with a torque of 5 N·m (44.25 lbf·in.) so that the connection kit and
main bracket are firmly secured, as shown in the following figure.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 21


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-14 Installing the connection kits of DPU30D/DPU30A

Step 2 Install the DPU30D or DPU30A connection kit onto the DPU30D/DPU30A power module,
and use an M6 inner hexagon torque screwdriver to tighten the captive screw into the hole of
the DPU30D/DPU30A with a torque of 5 N·m (44.25 lbf·in.) so that the connection kit and
PSU are firmly secured, as shown in the following figure.

Figure 4-15 Installing DPU30D/DPU30A

Step 3 Install the hanging kits onto the front or side panel of the RRU and battery module, and use an
M6 inner hexagon torque screwdriver to tighten the captive screw into the hole of the RRU or
the battery module with a torque of 5 N m (44.25 lbf·in.), as shown in the following figure.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 22


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-16 Installing the mounting kits of the RRU or the battery module

----End

4.2.3 Installing the Main Device and the DPS on the Wall
This section describes the procedure and precautions for installing a main device and a DPS
on the wall.

Installation Requirements
The main device and the DPS are installed on the wall in normal mode. The main device or
the DPS can use the same mounting kits. Requirements for the wall are as follows:
l The main device and the DPS are installed separately on the reinforced concrete bearing
wall with the concrete strength class C25 or higher.
l For each device, the wall must be capable of bearing the weight four times the weight of
the device and a force of 1.25 kN (281.25 lbf) pulled by a bolt outwards.
l Expansion anchor bolts must be tightened using the torque of 30 N·m (265.52 lbf·in.) so
that the bolts stay secured without damaging the wall.
l In any scenario, to ensure the heat dissipation of devices and waterproof performance of
ports at the bottom, devices must be equipped with bottoms downward and the angle
between devices and the vertical line must be less than 10 degrees.

Installation Scenarios
The DPS can be installed in remote RRU deployment, EasyMacro, small cell, and LampSite
scenarios.
In the following figures, RRU, Micro, or AAU indicates the main device, PWR indicates the
power module, and BAT indicates the battery module.
l Centralized installation on the wall

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 23


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

– Three RRUs and one PWR are installed on the wall, as shown in the following
figure.

Figure 4-17 Application scenario of three RRUs and one PWR

It is recommended that RRUs and PWR be installed in sequence. The PWR is


installed at the right side of RRUs. The PWR is close to the user AC power system
with its heat dissipation system facing outwards.
– Three RRUs, one PWR, and one BAT are installed on the wall, as shown in the
following figure.

Figure 4-18 Application scenario of three RRUs, one PWR and one BAT

It is recommended that the RRUs, PWR and BAT be installed in sequence. PWR is
close to the user AC power system. RRUs are installed at the left side of the PWR
and the BAT is at its right side. The BAT must be away from strong heat sources.
NOTE

Equip the PWR with the RRU or BAT, then install them on the wall or on pole in normal
mode, as shown in the following figure.

Figure 4-19 Installing the combined PWR and RRU on pole

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 24


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

l Non-centralized installation
Due to the aesthetic factor and other limitations, it is recommended that the PWR and the
main device be installed separately while the BAT is installed close to the PWR on the
wall, as shown in the following figures.

Figure 4-20 Application scenario of one micro, one PWR, and one BAT

Figure 4-21 Application scenario of one AAU, one PWR, and one BAT

4.2.4 Installing the Main Device and the DPS on the Pole
This section describes the procedure and precautions for installing a main device and a DPS
on the pole.

Installation Requirements
Space for installing one RRU allows two PWRs to be installed side by side and requirements
for installing the main device and the DPS on the pole are as follows:

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 25


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

l Poles whose diameter is less than 60 mm must be reconstructed.


l Up to two RRUs can be installed on a pole whose diameter ranges from 60 mm to 76
mm (2.36 in. to 2.99 in.).
l Three or more RRUs can be installed on a pole whose diameter is greater than 76 mm
(2.99 in.).
– Up to six RRUs can be installed on a pole whose diameter ranges from 76 mm to
114 mm (2.99 in. to 4.48 in.).
– If more than three RRUs are installed on a pole, they must be installed in different
layers. Before installation, the bearing capacity of the pole must be confirmed with
the customer.
l The diameter of the big poles ranges from 114 mm to 400 mm (4.48 in. to 15.75 in.),
such as monitoring poles, cable poles, and concrete poles. The RRU with a standard
mounting kit cannot be installed on the big pole. Before such an RRU is installed on a
big pole, the appropriate mounting kit must be obtained. Installation requirements are
shown as follows:
– Only one RRU can be installed on each mounting kit.
– The device can only be installed in normal mode instead of side-mounted mode.

Figure 4-22 Installing the RRU on the big pole

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 26


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-23 Mounting kits for installing the RRU on a big pole

Installation Scenarios
In the following figures, RRU or AAU indicates the main device, PWR indicates the power
module, and BAT indicates the battery module.
l Installation scenarios of the RRU and the small cell:
– Three RRUs/BATs and one PWR are installed in side-mounted mode on a pole
whose diameter is greater than 76 mm (2.99 in.).
It is recommended that RRUs be installed side by side and the PWR be installed at
the right side of the RRUs, as shown in the following figure.

Figure 4-24 Application scenario of three RRUs and one PWR

– Three RRUs and two PWRs are installed in side-mounted mode on a pole whose
diameter is greater than 76 mm (2.99 in.).
It is recommended that two PWRs and three RRUs be installed on the pole, as
shown in the following figure.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 27


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-25 Application scenario of three RRUs and two PWRs

– One RRU, one PWR, and one BAT are installed in side-mounted mode.
It is recommended that RRU be installed at the upper side while the BAT and PWR
are installed side by side at the lower side, with the BAT attaching to the main pole
and the heat sink fins of the PWR pointing outward, as shown in the following
figure.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 28


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-26 Application scenario of one RRU, one PWR, and one BAT (1)

The RRU is installed on the pole while the PWR and the BAT are installed side by
side. A sheet metal box is installed between the PWR and the RRU, or a spacing is
reserved between them, as shown in the following figure.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 29


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-27 Application scenario of one RRU, one PWR, and one BAT (2)

– One RRU, one PWR, and two BATs are installed in side-mounted mode.
It is recommended that the RRU be installed on the pole while the PWR and the
BATs are installed on the pole in side-mounted mode, with the heat sink fins of the
PWR pointing outward.

Figure 4-28 Application scenario of one RRU, one PWR, and two BATs

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 30


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

– Three RRUs, one PWR, and three BATs are installed in side-mounted mode.
It is recommended that the three RRUs be installed side by side at the upper side of
the pole while the BAT and PWR are installed side by side at the lower side, with
the heat sink fins of the PWR pointing outward, as shown in the following figure.

Figure 4-29 Application scenario of three RRUs, one PWR, and three BATs

– Six RRUs, two PWRs, and two BATs are installed in the side-mounted mode.
It is recommended that six RRUs be installed on three poles with two RRUs
installed on each pole. BATs and PWRs are installed on two of the three poles with

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 31


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

one BAT and one PWR on each pole and the heat sink fins of PWRs pointing
outward, as shown in the following figure.

Figure 4-30 Application scenario of six RRUs, two PWRs, and two BATs

– Six RRUs, two PWRs, and four BATs are installed in side-mounted mode.
It is recommended that six RRUs be installed at the upper side of the pole in two
layers while BATs and PWRs are installed at the lower side in two layers with two
BATs and one PWR in each layer, as shown in the following figure.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 32


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-31 Application scenario of six RRUs, two PWRs, and four BATs

l Installation scenario of EasyMacro:

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 33


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

– One AAU and one PWR are installed in normal mode.


It is recommended that the AAU be installed at the upper side on the pole while the
PWR is installed at the lower side with its heat sink fins pointing outwards, as
shown in the following figure.

Figure 4-32 Application scenario of one AAU and one PWR

– One AAU, one PWR, and two BATs are installed in side-mounted mode.
It is recommended that the AAU be installed at the upper side of the pole while the
PWR and BATs are installed at the lower side, with the heat sink fins of the PWR
pointing outward, as shown in the following figure.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 34


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-33 Application scenario of one AAU, one PWR, and two BATs

l Installation scenario of a big pole with a diameter of 114 mm to 400 mm (4.49 in. to
15.75 in.)
One RRU, one PWR, and one BAT are installed in normal mode, as shown in the
following figure.
It is recommended that RRU be installed at the upper side while PWR and BAT are
installed at the lower side in normal mode. In addition, these devices are tied with the big
pole by steel tapes and a set of mounting kits can install only one BAT or PWR.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 35


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-34 Application scenario of one RRU, one PWR, and one BAT

4.2.5 Installing the Main Device and the DPS on U-steels


This section describes the procedure and precautions for installing the main device and the
DPS on U-steels.
The following figure shows U-steel specifications.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 36


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-35 U-steel specifications

Installation Requirements
For details about U-steel installation requirements, see Installation Requirements.
U-steel can be installed on the ground or the tower and each piece of U-steel allows only one
main device or one DPS to be installed in normal mode, as shown in the following figure. If
the width of the narrower edges of the U-steel is less than 40 mm (1.57 in.), only the a and b
modes are supported.

Figure 4-36 Top views of four installation modes

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 37


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Installation Scenario

Figure 4-37 Application scenario of one RRU, one PWR, and one BAT

4.2.6 Installing the Main Device and the DPS on Angle Steels
This section describes the procedure and precautions for installing a main device and a DPS
on angle steels.
The following figure shows the angle steel specifications.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 38


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-38 Angle steel specifications

Installation Requirements
Angle steel can be installed on the ground or a tower and a piece of angle steel allows only
one main device or one DPS to be installed in normal mode.
For details about angle steel installation requirements, see Installation Requirements.
The following figure shows the top view of the device installed on angle steel.

Figure 4-39 Installation method

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 39


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Installation Scenario

Figure 4-40 Application scenario of one RRU, one PWR, and one BAT

4.2.7 Installing the Main Device and the DPS on the Indoor Rack
This section describes the procedure and precautions for installing a main device and a DPS
on the indoor rack.
Indoor racks are applicable for installing the RRU and the blade DPS on the indoor ground, as
shown in the following figure.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 40


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Table 4-1 Indoor centralized rack


Item Specification

Function Install the distributed base station (DBS), indoor mini box (IMB), RRU
or DPS.

Weight The weight of the empty rack is less than or equal to 45 kilograms.

Dimensions (H Cabinet: 1730 mm x 600 mm x 600 mm (68.11 in. x 23.62 in. x 23.62
x W x D) in.)

Free space When the height of the equipment room is two meters, 3 U and 3 U
space is available for installing two modules at the bottom of the rack.
Up to six devices can be installed in side-mounted mode, with three
installed at the upper layer and three installed at the lower layer. Up to
two devices can be installed in normal mode, with one installed at the
upper layer and the other installed at the lower layer.

Installation Ground installation (except wood floor)


Method

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 41


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-41 Schematic diagram of installing the indoor rack

Installation Requirements
l The dimensions of modules cannot exceed 490 mm x 380 mm x 170 mm (19.29 in. x
14.96 in. x 6.69 in.) and these modules can be installed in side-mounted mode.
l The total heat consumption of devices installed on the rack cannot exceed 650 W. When
RRUs or PWRs are installed in two layers, the temperature is required to decrease by ten
degrees. When they are installed in one layer, the temperature is required to decrease by
5 degrees.
l RRUs and PWRs are installed in layers. RRUs are installed on the upper layer while
PWRs and lithium battery are installed on the lower layer.
l Lithium battery which must be kept away from heat sources cannot be installed between
two RRUs.

4.2.8 Installing the Main Device and the DPS on the OPS-06
This section describes the procedure and precautions for installing the main device and the
DPS on the OPS-06.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 42


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

OPS-06 provides an auxiliary solution for installing RRUs centralizedly on a pole or on the
bottom of a pole outdoors. An OPS-06 consists of an OPS-06P pole and an OPS-06T
attachment plate, as shown in the following figure.

Figure 4-42 Exterior of the OPS-06

Table 4-2 OPS06 specifications

Item Specifications

Dimensions (D x H) of OPS-06P 240 mm x 1020 mm (9.45 in. x 40.16 in.). The


diameters of the fixed disk and the pole are 240 mm
(9.45 in.) and 89 mm (3.50 in.), respectively.

Dimensions (W x D x H) 594 mm x 396 mm x 60 mm (23.39 in. x 15.59 in. x


2.35 in.)

Installation requirements The OPS-06 must be fixed on the concrete floor or


U-steel using bolts. In scenarios where U-steel is
used, an OAP600 base can be configured to install
the poles.

Mounting method Tighten the bolts

Installation Capability A single OPS-06P supports up to six RRUs or


PWRs.

Capacity expansion method Two OPS-06Ps can be stacked to support a


maximum of 12 RRUs. The operating temperature of
RRUs needs to be decreased by 5 degrees.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 43


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-43 Exterior of the OPS-06

Installation Requirements
Requirements for installing the main device and the DPS on the OPS06 are as follows:
l RRUs are installed at the upper side while the DPS is installed at the lower side.
l RRUs are installed together. In addition, battery modules which must be away from the
heat source are equipped with the PWRs.
l Attention must be paid on stress balance of the pole and the heat dissipation of battery
modules.

4.3 Cable Installation of the Main Device and the DPS


This section describes how to install cables for the main device and the DPS.

4.3.1 Cabling Requirements


Cables must be routed according to the specified cabling requirements to prevent interference
between signals.
General Cabling Requirements
The bending radius of the cables must meet the following requirements:

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 44


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

l The bending radius of a power cable or a protection ground (PGND) cable must be at
least three times the diameter of the cable.
l The bending radius of a signal cable must be at least five times the diameter of the cable.

The cables must be bound as follows:

l Cables of the same type are bound together.


l Different types of cables are separately routed with a minimum spacing of 30 mm (1.18
in.) and cannot be entangled.
l The cables must be bound tightly and neatly. The sheaths of the cables must not be
damaged.
l Cable ties are installed in the same direction, and those at the same horizontal line must
be at the same level.
l The excess of indoor cable ties is trimmed off and a slack of 5 mm (0.2 in.) is reserved
for outdoor cable ties, without remaining rough edges.
l Labels or nameplates are attached to both ends, joints, or turns of cables after they are
installed.

Security Requirements

l Cables are routed away from sharp objects or wall burrs. If these positions are inevitable,
cables are protected with protection pipes.
l Cables are routed away from heat sources, or heat-insulation materials are added
between cables and heat sources.
l Sufficient slack is provided in cables at turns or the position close to a device, facilitating
cable and device maintenance. The recommended slack is 0.1 m (0.33 in.).

Indoor Cabling Requirements

l Each cable is routed indoors through the feeder window.


l Drip loops are reserved for all cables outside the feeder window and meet the
requirements for the minimum bending radius.
l When cables are routed indoors, engineers are required indoors for cooperation.
l The feeder window must be waterproofed.

4.3.2 Cable Connections


This section describes the cable connection between the main device and the DPS in typical
scenarios.

NOTE

Cables of the main device and the DPS cannot be cascaded.


Up to five DBU20Bs can be connected in parallel.
Up to four DPU30Ds or DPU30As can be connected in parallel.

The following figure shows the connection between the main device and DPS over the load
ports when a DBU20B and a DPU30D or a DPU30A provide power supply or power backup
for the main device.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 45


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-44 Cable Connections

The following figure shows the connection between the main device and DPS over the load
ports when five DBU20Bs and four DPU30Ds or four DPU30As provide power supply or
power backup for the main device.

Figure 4-45 Cable Connections

The following figure shows the connection between the main device and DPS over the load
ports when one DBU20B and two DPU30Ds or two DPU30As provide power supply or
power backup for the main device.

Figure 4-46 PGND cable connection

4.3.3 Cable Installation Process


This section describes how to install cables for the main device and the DPS.
The following figure shows how to install cables for the main device and the DPS.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 46


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

Figure 4-47 Cable installation process

4.4 Checking the Installation


This section describes items to be checked after the main device and the DPS hardware are
installed.

The table provides the checklist for the hardware installation.

Table 4-3 Checklist for the hardware installation

No. Item

1 The installation positions of the main device and the DPS strictly comply with
the engineering design and meets space requirements. Sufficient space is
reserved for equipment maintenance.

2 The main device and the DPS are firmly installed.

3 The cover plate is securely installed on the device cabling cavity.

4 Waterproof measures have been taken for the main device and the DPS.

5 Power cables and PGND cables must be complete without connectors or


joints. Cables are firmly soldered.

6 All signal cables, monitoring cables, power cables and PGND cables are not
short-circuited or reversely connected and are not damaged or broken.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 47


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 4 SingleSite DPS Solution Installation Guideline

No. Item

7 Cables meet requirements on the bending radius, bundling and security.

8 PGND cables and lightening protection cables of the main device and the DPS
meet the requirements.

9 The signal cables are not damaged or broken, and the connectors are intact.

10 Labels are correct, legible, and complete at both ends of each cable, feeder,
and jumper.

4.5 Powering on and Commissioning the Main Device and


the DPS
This section introduces how to power on and commission the main device and the DPS.
For details about powering on and commissioning the main device, see sections about
powering on and commissioning the main device in relevant installation guides.
For details about powering on and commissioning the DPS, see sections about powering on
and commissioning the DPS in relevant installation guides.

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 48


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 5 Acronyms and Abbreviations

5 Acronyms and Abbreviations

AC alternating current

BBU baseband unit

BLVD battery low voltage disconnection

BTS base transceiver station

DC direct current

DCB deep cycle battery

DCDU direction current distribution unit

DDF digital distribution frame

DG diesel generator

DRFU double radio frequency unit

EMUA environment monitoring unit type A

EMUB environment monitoring unit type B

ESU energy storage unit

FCB fast charge battery

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 49


Copyright © Huawei Technologies Co., Ltd.
SingleSite Solution
SingleSite9202 DPS Solution Introduction and Installation
Guide 5 Acronyms and Abbreviations

GATM GSM antenna and TMA control module

LLVD load low voltage disconnection

PSU power supply unit

RFC radio frequency cabinet

RFU radio frequency unit

RRU radio remote unit

SCB solar cycle battery

SLPU signal lightning protection unit

Issue 01 (2015-11-20) Huawei Proprietary and Confidential 50


Copyright © Huawei Technologies Co., Ltd.

S-ar putea să vă placă și