Documente Academic
Documente Profesional
Documente Cultură
It is a budget that deals with Capital Expenditure, for example the purchase
of plant and equipment, construction of a building .It is expenditure that is
not easily reversible due to the values committed. There are different types
of capital budgeting expenditures,e.g. Replacement projects and Expansion
projects.
You recall that the goal of financial management is to maximize the wealth
of shareholders by acquiring funds at the least possible cost and utilizing
them to obtain the highest possible return for the shareholders.
In capital budgeting we should be careful not to include cash flows that are
not relevant to the decision under consideration. The relevant cash flows for
capital budgeting purposes are incremental cash flows. Cash flows for a
project are defined as the difference between the cash flows of the firm
without the project and the cash flows with the project :
Project CFt = CFt for the firm - CFt for the firm
with project without project
Accounting income may differ from the cash flows that we consider under
financial management. Income statements mix apples and oranges. For
example, accountants deduct costs, which are cash outflows, from revenues,
which may or may not be entirely cash inflows (some sales may be on
credit). At the same time, they do not deduct capital outlays, which are cash
outflows, but they also deduct depreciation, which is not a cash outflow. In
capital budgeting, it is critical that we base our decisions strictly on cash
flows, the actual dollars that flow into and out of the company during each
time period.
Example
A company is considering investing in a project for which the following
information has been generated:
$
Initial capital outlay (600 000 )
Profit/loss for the year: Year 1 100 000
Year 2 150 000
Year 3 250 000
Year 4 300 000
The capital outlay was on plant and machinery which is expected to have an
economic life of four years with no scarp value.
In capital budgeting, we are concerned with "cash flows", not "profits or
losses". To turn these into cash flows, we add back the depreciation, which
is not a cash outlay. The profits are therefore adjusted as follows :
Sunk Costs
Sunk costs are not incremental costs, so they should not be included in
capital budgeting. A sunk cost is an outlay that has already occurred (or
been committed). Since the outlay has already occurred, it is not affected by
the decision to accept or reject a project.
Opportunity Costs
Externalities
Project cash flows are dividedinto three categories : the initial investment;
the annual cash flows; and the terminal cashflow.
The Initial investment [I0]
The initial investment is the net cash outlay on buying the capital, that is
the plant andequipment, buildings, and other infrastructure for the project.
The amount of the initialpayment and the way it is calculated is determined
by whether the project is a newinvestment project or a replacement project.
In a replacement project, some assets are replaced, and this may result in
the firm nolonger deriving any cash flows from the replaced assets but from
the new assets. Thefollowing factors make up the initial investment in a
replacement project:
The cost of the new project + installation costs + changes in net
working capital. This isa cash outflow (-).
The disposal value of the old assets. The implementation of the new
project results inthe old assets being disposed of. The funds that are
received at the disposal of the oldassets are an inflow (+).
Tax effects. Selling a fixed asset can result in tax effects. The tax savings or
taxpayable as a result of the disposal of the old assets must be incorporated
in the initialinvestment calculation.
In Zimbabwe, tax allowances e.g W&T and SIA are claimed in place of
depreciation charges, which are notrecognized for tax purposes.
The terminal cash flow is the net after tax amount received by the firm when
a project is terminated. For a new investment the estimated terminal cash
flow might include the following : the estimated salvage value of the new
assets, the tax effects due to the disposal of the assets and the recovery of
the net working capital.
The estimated salvage value of the new assets is the amount that is
expected to be received when the assets are sold at the termination of
the project. This is a cash inflow (+).
The tax effects due to the disposal of the assets. This depends on
whether there is a net taxable recoupment (-) or scraping allowance
(+)
Recovery of the net working capital. If there is a change in net working
capital when the project is implemented, we expect an opposite
change to occur at termination of the project. The change is usually
an inflow (+).
Practice Question
The old bus was bought four years ago and now has a market value of $300
000 and a zero book value.
The company elects to claim SIA on the bus using the current rates and has
a tax rate of 30% per year.
Calculate:
1. The initial investment.
2. The annual cash flows.
3. The terminal cash flow of the project.
The effects of a capital budgeting decision continue over many years and
therefore, such a decision may not be easy to reverse. Capital budgeting
decisions also define the strategic direction of the firm because a decision to
move into new products, services or markets, for example, must be preceded
by a capital budgeting expenditure.
A company usually considers more than one project at a time. Based on this
notion, there
are basically two types of the projects: mutually exclusive or independent.
We have seen that the first step in the appraisal of a capital expenditure
project is the determination of the project's net, after-tax cash flows. The
next step after this, is to determine the cost of the funds used in the project.
This is especially important if we are to use discounted cash flow techniques
in our appraisal.
Example
A firm requires $400m to finance its capital project. $300 of this will come
from the issue of new shares on which the investors require a return of 20%.
The balance will be borrowed at an interest rate of 18%.
Ignoring taxation, the weighted average cost of capital for this project would
be:
[(300 / 400) x 0.20] + [(100 /400) x 0.18] = 0.195 = 19.5%.
After we have got our cash flows as well as the cost of the funds used in the
project, we are now in a position to make an appraisal of the project. There
are various elements of the accounting system that are used including;
Payback period.
Discounted payback period.
Net Present Value [NPV] method
Internal Rate of Return [IRR] method.
Modified Internal Rate of Return [MIRR] method.
Profitability Index [PI].
We discuss each of these, including the problems associated with them, and
their merits and demerits in the following subsections.
The Payback method
The payback period tells us the number of years required to recover the
initial cash outlay from the project’s expected net cash flows (The payback
period, defined as the expected number of years required to recover the
original investment). It is the ratio of the initial cash outlay to the annual
net cash flows.
Solution
The payback period = 18 000 / 5 600 = 3.2 years.
In this example, you can see that the payback period falls between 3 years
and 4 years. Toget the actual payback period, we use the following formula:
Payback = Year before full recovery + [unrecovered cost at start of year / cash
flowduring year]
If, for example, the company policy payback was 3 years, then the project
would be accepted. In this sense therefore, the payback period may be said
to be a rough measure of the risk associated with the project. The longer the
payback, the greater the risk, therefore the less acceptable a project is.
In the case of mutually exclusive projects, those with longer paybacks are
eliminated in favour of those with shorter paybacks. As for independent
projects, those with shorter paybacks would be ranked higher than those
with longer paybacks.
The regular payback does not take into account the time value of
money, assuming that cash flows received in the future are just as
good as cash flows received today. In this sense it does not take into
account the cost of capital. A project may be financed by both debt
and equity and we need to factor in the cost of obtaining these funds,
using an appropriate discount rate.
It suffers from “Fish-bait criteria” i.e. (the size of the fish matters, not
just catching something). It focuses only on the covering the initial
investment than profitability.
it ignores cash flows beyond the payback period, as is evident from
the above examples.
To overcome the problems of the regular payback, the expected cash flows
are discounted at the project’s cost of capital. The discounted payback
period is therefore the number of years required to recover the investment
from discounted cash flows .
Example
Solution
Year 0 1 2 3 4
Cash flows -1000 500 400 300 100
Discounted -1000 500
=454.55
400
=330.5
300
=225.39
100
=68.30
1.1 (1.1)^2 (1.1)^3 (1.1)^4
Cash flows
Cumulative -1000 -545.45 -214.89 10.5 78.8
cash flow
= 2.95 years
The discounted payback shows the break-even year after covering the cost of
debt and equity.
The payback discriminates against longer term projects, which may turn out
to be more profitable for the shareholders, by ignoring the cash flows after
the payback period. This is demonstrated for you in the following example.
Example
The cash flows for projects X and Y are as follows :
Project X Project Y
Year 0 (10 000) (10 000)
Year 1 1 000 5 000
Year 2 2 000 3 000
Year 3 3 000 2 000
Year 4 4 000 1 000
Year 5 8 000 500
The payback period for project X is 4 years whereas that for Y is 3 years. If
these projects were mutually exclusive, Y would be accepted and X rejected.
Project Y is, however, a shorter-term project than X in that the cash flows of
X show a rising trend and those for Y are decline drastically after the
payback period.
It is the difference between the present value of the initial cash outlay and
the present value of the cash inflows of project discounted at the cost of the
capital.
The steps to be followed in evaluating a project using the NPV method are as
follows :
Find the present value [PV] of each period’s cash flow, including both
inflows and outflows, discounted at the project’s cost of capital,
Sum the PVs to find the NPV.
If the NPV is positive, accept the project and if the NPV is negative,
reject the project.
For two or more projects, accept the project with the highest NPV, if
the projects are mutually exclusive. If the projects are independent,
accept the project with the highest NPV first and rank them
accordingly.
Example
Solution
𝐶𝐹
Given that ; NPV=∑𝑛𝑡=1 ((1+𝑡)𝑡) – I0
=$1078.82-$1000
=$78.82
This investment has a total value or present value of future cash flows of
$1078.82. Since the investment is acquired at a cost of $1000(the initial
outlay). The investment company is giving up $1000 of its wealth in
exchange of an investment worth $1078.82. This means the investors wealth
has increased by a margin of $78.82.
It can be safely said that: the NPV is the amount by which the investors
wealth increases or decreases as a result of an investment. The decision rule
is:
Solution
If the NPV is positive, the project’s cash flows are generating more than the
required rate of return [RRR]. Since the return to bond holders [the
providers of debt capital] is fixed [ the interest on debt], the extra return
accrues solely to the firm’s stock holders [the providers of equity capital,]
who receive their return [dividend] only after the bond holder have been
paid their fixed amount. It therefore follows that if a firm takes on a zero-
NPV project, the position of the shareholders remains unchanged. The firm
only becomes larger to the extent of the size of the project, but the wealth of
the shareholders, that is the price of the company’s shares, remains
constant.
Practice Question
A project has an initial cash outlay of $800000. The life of the project is 4
years; residual value of the asset in 4 years is $90000. Expected revenue per
year is $650000. $450000 of the capital required is borrowed at 15% after
tax amount. The balance is raised through the issue of new shares at a
required rate 18%. Evaluate if the project is worth investing in or not.
(-$55622.09) NPV=Reject the project
The IRR is the yield or rate of return generated by the project’s internal
cash flows. It is an internally generated rate of return. It can also be defined
as a discount rate that makes the present value of the future after tax cash
flows of a project equal to the initial outlay. It yields an NPV of zero (NPV=0).
𝑪𝑭𝒕
NPV=∑𝒏𝒕=𝟏 (𝟏+𝑰𝑹𝑹)𝒕 − 𝑰𝟎 = 𝟎
𝑛
𝐶𝐹𝑡
∑ =𝐼
(1 + 𝐼𝑅𝑅)𝑡
𝑡=1
At the IRR,NPV=0
Example
Solution
𝐶𝐹𝑡
Given that ; ∑𝑛𝑡=1 (1+𝐼𝑅𝑅)𝑡 = 𝐼
Let’s try to make IRR the subject of the formulae and see if we can win.[we
can’t ]….lol
Also notice that the pattern of the payments is in the form of an annuity.
120000= R×PVIFAn,%
(1+𝐼𝑅𝑅)10 −1
=24000×𝐼𝑅𝑅(1+𝐼𝑅𝑅)^10
x=is the Present Value associated with the lower discount rate
To reduce the Present Value you increase the discount rate (an inverse
relationship) and vice versa.
You can just try any percentage and calculate the PVs so that you compare
with the I0.
=147469.61
This is not the same with Z of $120 000 ,it is greater than Z so let’s
increase the discount rate to get a r PV that is slightly lower or the same as
Z
=107858.07
This is also not equal to Z of $120000. We have to look for another discount
rate which will equalize the PV to Z,but this may take us forever so we resort
to interpolation to find an estimate of this IRR.
The next step is to compare the relationship of X, Y and Z ,so that we knw
which formula to use for our interpolation.
a% IRR b%
X Z Y
10% IRR 18%
147469.61 120000 107858.07
Y Z X
𝑥−𝑧
So IRR =a+ (𝑥−𝑦)(b-a)
147469.61−120000
= 0.1+ (147469.61−107858.07)(0.18-0.10)
27469.61
= 0.1+ (39611.54)(0.08)
=0.1+0.693474931*0.08
=15.5%
Example
Solution
Example
Solution
The IRR is found by trial and error [interpolation] if one is not using a
financial calculator.We apply different discount rates to the cash flows until
we get one which produces an NPV of zero.
Try 9%:
Since this is a positive NPV, we try a higher discount rate, say 12% , to get a
negative NPV:
NPV = [20 000 (3605) + 10 000 (0.567) ] - 80 000
= - 2 230.
Since the NPV is negative, the required discount rate lies somewhere
between 12 % and 9%, as shown in the following diagram, known as the
NPV profile of the project :
NPV ($)
IRR = 10.98%
$ 4 300
-$ 2 230
The IRR is the discount rate that will result in a zero NPV, therefore lies
somewherebetween 9% and 12%. It is found by the following formula :
The decision rule for the IRR is that we should accept the project if the IRR
is greater thanthe RRR, that is the cost of capital. If the IRR is less than the
RRR, then the project shouldbe rejected. If we are comparing two mutually
exclusive projects, we would take the onewith the higher IRR.
Rationale for the IRR
The IRR is the return that is expected to be generated by the project's net
cash flows, assuming that all the cash flows are reinvested into the project.
If the IRR exceeds the cost of the funds used to finance the project [the
RRR], a surplus remains after paying for the funds, and this surplus belongs
to the firm’s shareholders. Therefore, taking on a project whose RRR exceeds
the cost of capital increases the shareholders’ wealth.
The decision criterion is therefore that if the project's internal rate of return
exceeds the required rate of return, the project should be accepted.
The decision criteria for independent projects is to take those projects with a
higher IRR first. If the projects are mutually exclusive, we take on those
projects with a higher IRR and reject those with a lower IRR.
There may be a conflict between the decision resulting from an NPV analysis
and that resulting from an IRR analysis. This conflict arises when the
projects are mutuallyexclusive rather than independent.
For independent projects, the NPV and the IRR always lead to the same
accept / rejectdecision, that is if NPV says accept, IRR also says accept. The
criterion for acceptance isthat the project’s cost of capital [RRR] is less than
[to the left of] the IRR. Whenever theproject’s cost of capital is less than the
IRR, its NPV is positive, therefore the project isacceptable using both
methods. Both methods reject the project if the cost of capital isgreater than
the IRR.
PROJECT A PROJECT B
NPV $100 000 $150 000
IRR 20% 18%
You can see that project A has a lower NPV than project B, but it has a
higher IRR. Thisconflict between A and B is illustrated as below :
Conflict between projects
NPV($)
Cross-over rate
IRRb
IRRa
NPVb
NPVa
Therefore for IRR greater than the cross-over rate, the two methods lead
tothe selection of the same project. However, if the cost of capital [RRR] is
less than thecross-over rate, a conflict arises. The NPV ranks project B
higher but the IRR ranks Ahigher.
You may be wondering ‘How can I deal with such a conflict ?” Let us study
the next example for the answer.
Example :Resolving conflict between NPV and IRR
At this rate of discount the NPV for A is $610.00and the NPV for B is $ 1
026. The IRR for A is 20% and the IRR for B is 18%. Therefore,using the
NPV method, B is preferred to A but using the IRR, A is preferred to B.
We have seen that the cost of capital is the weighted average between the
cost of debt andthe cost of equity. When a project generates cash flows, they
must be paid out to the debtholders and equity holders, who on average
require a return which is equal to the cost ofcapital [the discount rate, or the
RRR].
We have also seen that there are two sources of funds for the firm, debt and
equity.However, in the case of equity, we have internally generated equity,
that is retainedearnings, and new equity. Thus, the cash flows of the project
can be paid out as dividendsafter we have paid interest on debt.
Alternatively, the cash flows can be retained and usedas a substitute for
outside sources of funds, after paying out the interest on debt capital.
Now, suppose that the cost of capital ( RRR, or WACC ) is 18%. This means
that byretaining all the cash flows, we are saving the firm the cost of
obtaining outside sources offunds at a cost of 18%. We can, therefore say
that the value of the cash flows to the firm is18%. As you can see, this value
is an opportunity cost. In other words, it is the requiredrate of return, which
the shareholders would obtain on alternative investments of similarrisk if we
had paid them their dividend instead of retaining the cash flows.
The NPV is regarded as superior to the IRR due to the assumptions they
both make aboutthe treatment of the project’s cash flows. The IRR assumes
that the cash flows arereinvested at the IRR itself. Obviously, the IRR will
vary from project to project,depending on the cash flows of each particular
project. As we have seen, a project is onlyacceptable if the IRR is greater
than the RRR.
Now, if a firm can get funds from outside at the same cost as the RRR,
which is also thediscount rate that is applied to projects, the appropriate
reinvestment rate would be theopportunity cost of capital, that is the RRR.
The NPV assumes that the cash flows from theproject are reinvested at the
RRR, which is built into the NPV method. Thus, whenevaluating mutually
exclusive projects, especially those with timing and scale differences,the NPV
should be used rather than the IRR.
The use of IRR in appraising projects is fraught with problems. Firstly, the
IRR ignores therelative size of the projects, as shown in the following
example:
Project A Project B
Year 0 (350 000) (35 000)
Year 1 – 6 100 000 10 000
Project A is 10 times bigger than project B, therefore more profitable, but
both have thesame IRR of 18%.
PROJECT A PROJECT B
Cash flows ($) Cash flows ($)
YEAR
0 (100 000) (120000)
1 (50000) 50 000
2 60 000 80 000
3 90 000 (50000)
4 80 000 20 000
In spite of the strong academic preference for the NPV over the IRR, surveys
have shown that the IRR is by far the preferred method of investment
appraisal. The IRR is easier to understand as it looks at percentages rather
than absolute figures. In order to take into account the objections regarding
the re-investment assumption, we can modify the IRR by assuming that the
cash flows are re invested at the required rate of return before calculating
the IRR.
The modified internal rate of return (MIRR) is given by the following formula:
Where: TV = the future value of the inflows reinvested at the cost of capital
[known as the terminal value ]
MIRR=the discount rate that forces the present value of the terminal value
to equal the present value of the costs is the.
Suppose we have the following time line for a particular project with a cost
of capital of 10%
0 1 2 3 4
Step 1: Find the terminal value [TV] . This is the total of the future values of
all the cash flows reinvested, that is compounded, at the cost of capital
[RRR], 10%. The TV =$ 1 579.50.
Step 2:Find the discount rate that will give a present value of $1 000 on a
future value of$1 579.50, the IRR. This is found by trial and error in the
normal way. This discount rate is12.1%, which is the MIRR for the project.
Since the MIRR is greater than the cost of capital, 10%, the project is
acceptable. Theconventional IRR for this project would have been 14.5%.
Let us say for example, the required [quoted ] rate of return is 20% under
the current andanticipated conditions and the rate of inflation is currently
running at 10% per year, we cansolve for R [ the real rate ] as follows :
(1 + 0.20 ) = ( 1 + R ) ( 1 + 0.10 )
This means that a return of 20% will protect the shareholders against the
loss of purchasingpower and also provide a real return of 9.1%.
If the information is mixed, that is real cash flows with nominal rates, or
nominal cashflows with real rates, we should :
change nominal cash flows to real cash flows, or
change real cash flows to nominal cash flows,
change nominal rates to real rates, or
change real rates to nominal rates,
,so that nominal cash flows are discounted at nominal rates or real cash
flows are discountedat real rates.
The following nominal cash flows must first be converted to real cash flows
before beingdiscounted at the real rate of 9.1%.
Year Nominal CF Real CF
0 ( 15 000 ) ( 15 000 )
1 9 000 9 000 / ( 1.10 ) = 8 182
2 8 000 8 000 / ( 1.10 )2 = 6 612
3 7 000 7 000 / ( 1.10 )3 = 5 259
Example
A firm is considering a project with an expected economic life of fiveyears.
The following data also relate to the project:
Capital outlay: $ 200 000
Residual value: nil (assuming straight line depreciation)
Expected Annual Net Income :
Year Expected Net Income ($)
1 60 000
2 80 000
3 76 000
4 58 000
Total 274 000
The ARR can alternatively be calculated on the basis of the total investment
rather thanthe average investment as follows:
Capital rationing.
Capital rationing is a situation in which the firm does not have adequate
funds for all itsviable projects.
Single period capital rationing is where capital is limited for the current
period only butwill be freely available in the future.
The profitability index is the ratio between the present value and the cash
outlay on theproject. The PI is a measure of the present value per dollar of
capital invested. A projectshould be accepted if the PI is greater than 1. If we
have capital rationing, projects shouldbe ranked according to their PIs.
Formula:
The next step is to allocate the available funds according to the PI.
The company should take projects 1, 3, and 4. These would require $190
000. The balanceof$60 000 (i.e. $250 000 - $190 000), will then be invested
in a fraction of project 5. Thisfraction will be 67% (i.e. $60 000 / $90 000).
Project 6 cannot be undertaken this year.
If the projects are not divisible, then both 5 and 6 will be shelved for this
year and thefunds left over, $60 000, should be placed in other investments,
such as money marketsecurities.
Practice Questions
1. Discuss the conflict between NPV and IRR.
2. Distinguish between single and multi-period capital rationing.
3. Explain how the profitability index (PI) is used in appraising projects.
Sensitivity analysis
In sensitivity analysis we would want to find out what would happen to the
estimate of the
NPV under different assumptions regarding each input variable. We then
determine theinput variables to which the NPV is most sensitive and put
more resources and effort inestimating those input variables. We then put
more attention to controlling those variablesonce the project has been
implemented.
The following example will show you how the concept of sensitivity analysis
can beapplied:
Example
A project requires an initial investment of $570 000 and provides annual net
cash flows of$220 000 each for a period of 5 years. The cost of capital is
24%.
Solution
NPV = R×PVIFA – I0
NPV = ( 220 000 x 2.7454 ) - 570 000 = $33 988.
2. Suppose the variable cost per unit increases by 10%, resulting in the
decrease of20% in the estimated net annual cash flows. Will the project still
be acceptable?
Solution
New cash flow estimate = 220 000 ( 1 - 0.20 ) = $176 000.
NPV = ( 176 000 x 2.7454 ) - 570 000 = -$86 809.60.
3. By how much should the annual cash flows decline before the NPV falls
to zero?
Solution
This means that annual cash flows should fall to $80 134.04 for the NPV
tofall to zero, that is by 63.58% from the current estimate.