B. INVESTIGATION ON LAND
Setting out and excavating pits at each borehole location, of 1M x 1M minimum
size at the bottom, in all types of soil/fill/soft rock/slag upto 2.5 M depth
B-1 below ground level, for locating underground cables, utility lines, etc. including 25 Cum 3,000 18%
dewatering, shoring et., as required, all materials, tools, plants and labour
complete.
Setting up boring rig at each borehole location as decided by Engineer. (Any
B-2 crisscross or back and forth movement of boring rig can take place. No 0 Nos. 1500 18%
additional compensation will be payable by the owner for such movements).
Boring 150 mm dia. Through all kinds of soils, weathered rock, and soft
(disintegrated) rock including chiseling with adequate/ suitable equipment
B-3 including prevention of collapse of bore hole walls wherever necessary for
depths measured below existing ground level:
a) 0 – 10 m 300 Rm 2,000 18%
b) 10m to 20m 300 Rm 2,500 18%
c) 20m to 30m 300 Rm 3,000 18%
Boring through rock using Nx size diamond bit/double tube core barrel
B-6 including collecting and preservation the rock core in wooden boxes in a
proper sequence, recording recovery & RQD, maintaining drilling observations
for the following depths measured below existing GL
a) 0-10 m Rm
b)10 m & above 200 Rm 2,500 18%
Conducting Standard Penetration tests and collecting and transporting the
B-7 60 Nos. 250 18%
samples collected from split spoon sampler as per specification.
B-9 Obtaining undisturbed samples from trial pits and test pits including 10 Nos.
numbering, specifying the depth at which it is collected and sealing the same. 2,000 18%
B-10 Collecting bulk disturbed samples from test pits and trial pits. 10 Nos. 2,000 18%
Collecting ground water samples from drill holes (minimum 2 liters) including
B-11 preservation and transportation to laboratory 30 Nos. 1,000 18%
B-12 Recording of stable ground water table for each bore hole as per specification 30 Nos. 500 18%
B-13 Conducting Electrical Resistivity tests as per IS 3043 5 Nos. 8,000 18%
Conducting Field Permeability test in trail pits at 2.5m and 4m depth by falling
B-14 head or constant head method as per IS:5529. 5 Nos. 10,000 18%
Setting out & Conducting cyclic Plate load test as specified in IS: 5249 at 3M
below ground level as directed including excavation, shoring, dewatering,
B-15 backfilling with compacted earth, placement of kentledge, etc. all materials and 3 Nos. 120,000 18%
labour complete in all respects as per IS:1888 & IS: 5249.
Setting out and conducting routine plate load test as specified in IS:1888 at 3
B-16 M below ground level as directed including excavation, shoring, dewatering, 5 Nos.
backfilling with compacted earth, placement of kentledge, etc. all materials and 80,000 18%
labour complete in all respect.
C-14 Full chemical analysis of ground water including pH value, sulphates, 30 Nos.
chlorides, carbonates, nitrates organic matter, etc. 1500 18%
C-15 Crushing strength of rock on specimens of NX size with co-eff of softening 30 Nos. 1800 18%
C-16 Water absorption & porosity of rock samples 15 Nos. 800 18%
C-17 Bulk density of rock 30 Nos. 350 18%
C-18 Unconfined compressive strength of rock 30 Nos. 1200 18%
C-19 Point load strength index of rock 30 Nos. 1500 18%
C-20 Slake durability index of rock 30 Nos. 2000 18%
C-21 Specific gravity of rock 30 Nos. 300 18%
D. PREPARATION OF REPORT
Preparation and submission of four copies of draft report and ten copies of
final report of geotechnical investigations and foundation recommendations. 80,000 18%
D-1. Lump-sum
(No additional compensation is payable by the owner for any expenses
incurred by the contractor for travel, etc. Or for meetings / discussions with
owner / consultants)
All equipments,rigs, crane of any capacity, scaffolding, manlifter etc required for execution shall be in contractor scope. Equipment used for execution at the time of mo
than 3 year old from manufacturing date.
The Rate quoted by you should ensure complete execution of work/activity mentioned against each line of Rate schedule. The rates quote will deemed to include all ac
mentioned or not, which are required for satisfactory and complete execution of work.
The price quoted shall be fixed and firm till completion of the job.
The price offer shall be valid upto 90 days from date of submission
Note:
1 Necessary Gate pass is in client,s scope.
2 Moblization of men and machineries within 10 days on receiving of work order
3 25% advance on work order amount.
4 Time to time running bill will claimed on copmetion of field work.
5 90 % payment against runing bill.
6 10% on submission of final test report.
7 Client supervision during work is in your scope.
tion for
270
63 52500 61950
54 60000 70800
A TOTAL 2925810.00
45 15000 17700
90 15000 17700
81 4500 5310
81 4500 5310
81 4500 5310
(C ) TOTAL 507990.00
ipment used for execution at the time of mobilisation shall not be more
The rates quote will deemed to include all activities, whether specifically