CARPENTER LABOUR
1 Teak Wood Main Door per sft 350.00
2 Carving Work per sft 100.00
3 Flush Door per sft 210.00
4 Polishing Work per sft 120.00
1 Earthwork Excavation-1Cft
Excavation upto 6 ft Cft 1 10 10.00
Total amount 10.00
OHC 15% 1.50
Rate For 1 cft 11.50
Rate For 100 cft 1,150.00
Rate For 1 Cum 406.36
2 Plain Cement Concrete - 1:5:10 - 100 cft -
cement bags 7.34 390.00 2,862.60
40mm metal cft 93 27.00 2,511.00
River sand cft 60 30.00 1,800.00
Labour charges for concrete incl. ramming cft 100 27.90 2,790.00
Total amount 9,963.60
OHC 15% 1,494.54
For 100 cft 11,458.14
Rate For 1 cft 114.58
Rate For 1 Cum 4,048.81
7 Roof beam & slab concrete - 100 cft - M20 Grade (stilt roof) -
cement bags 19.3 390.00 7,527.00
20mm metal cft 93 27.00 2,511.00
River sand cft 60 30.00 1,800.00
Labour charges For concrete incl. ramming cft 100 172.00 17,200.00
Total amount 29,038.00
OHC 15% 4,355.70
For 100 cft 33,393.70
Rate For 1 cft 333.94
Rate For 1 Cum 11,799.89
13 Ceramic Floor (Wall & Floor tiles) c.m 1:5 100 Sft -
Cement bags 3 390.00 1,170.00
River Sand cft 15 30.00 450.00
Tiles sft 110 35.00 3,850.00
Serafill kg 2.25 60.00 135.00
Labour Charges sft 100 20.00 2,000.00
Total amount 7,605.00
OHC 15% 1,140.75
For 100 Sft 8,745.75
Rate For 1 sft 87.46