Documente Academic
Documente Profesional
Documente Cultură
1 Introduction
1.1 Background
KSB is tendering to deliver the pumps for the Canoas pumping station, a waste water intake.
Next to the delivery of the pumps a physical scale model test is required to assure that the
feeding of the pumps meets all acceptance criteria. KSB has requested Deltares to provide a
proposal for both CFD and physical model testing. The document at hand presents the proposal
for these studies.
1.2 Objectives
The objective of the CFD modelling is to determine whether large scale flow patterns will occur
in the pumping station which can have a negative influence on the feeding of the pumps.
The objective of the physical model study is to optimize the flow patterns towards the pump
compartments and to verify and optimize the pump feeding against the ANSI/HI 9.8-2018
acceptance criteria under all relevant operating conditions from a hydraulic point of view.
Moreover, the behaviour of sediments will be assessed.
Deltares has over fifteen years of experience in performing CFD studies for various hydraulic
applications. The presence of experimental facilities gives a unique position to verify our CFD
against our own experimental measurements. Thanks to this experience Deltares’ CFD experts
have developed a set of best practices for the simulation of a wide range of hydraulic
applications, including approach flows in pumping stations, navigation lock levelling systems,
weir overflows and other multi-phase flows. These best practices involve mesh grading,
appropriate turbulence treatment and other aspects in order to obtain reliable results within a
practical time frame.
Quotation
Date Our reference Page
May 29, 2019 11203901-001-HYE-0001 3 of 19
2 System Description
The waste water coming from the main tunnel is flowing via three screening channels into two
wet wells. In each well three suction chambers with pumps are located. Moreover, a weir is
located at a level of about EL. 2517 m to discharge an excess flow into the spillway. A top view
and a side view of the pumping station are given in respectively Figure 2.1 and Figure 2.2.
The discharge per pump depends on the operating condition and varies between 4 m 3/s and
6.4 m3/s per pump. The minimum flow through the pumping station will be 6.2 m 3/s while the
maximum capacity is 38.4 m 3/s.
The exact water levels at which the pumping station will be operated are not yet known. For this
proposal, it is assumed that the minimum water level at which the pumping station will be
continuous operated is about EL. 2514 m. At maximum capacity the water level is assumed to
be about EL. 2518 m.
Figure 2.2 Cross section of the pumping station in the discharge well.
Quotation
Date Our reference Page
May 29, 2019 11203901-001-HYE-0001 4 of 19
A CFD study will be performed for the pumping station, the wet well including a representative
part of the intake tunnels will be modelled.
A range of techniques are available within Star-CCM+, to simultaneously solve the equations for
mass conservation, momentum conservation (Navier-Stokes equations), heat transfer and
turbulence. Several turbulence models and numerical solvers are available. These models and
solvers, as well as the solution strategy, can be specified by the user. In the experience of
Deltares’ CFD experts, this code is well capable of fulfilling the requirements of this assignment.
Deltares uses Star-CCM+ on a regular basis to asses approach flows in pumping stations as
part of optimisation and verification studies of large pumping stations for power and desalination
plants.
The flow patterns in the intake structure will be studied for three scenario’s (operating conditions).
A scenario is defined by a water level in the pumping station, the number of pumps in operation
and their discharge and the position of the stop logs (open or closed). The simulations will
assume steady-state conditions. Both dry and rainy weather conditions will be taken into
account. Two of the scenario’s offered will have a water level below the overflow weir crest level
and one of the scenario’s will have a water level above the overflow weir crest level.
The design as provided by KSB will be used for the simulations. The numerical model will include
a representative part of the intake tunnel, the screening channels, the wet wells, suction
chambers and suction pipes until the pump inlet. The screens will be modelled as a resistance
of which the resistance depends on the clogging percentage of the screen. For high water level
conditions, also the spillway wall and a representative part of the emergency tunnel will be
Quotation
Date Our reference Page
May 29, 2019 11203901-001-HYE-0001 5 of 19
included. As boundary conditions a discharge boundary will be used at the pomps. At the
remaining boundaries a pressure boundary will be used.
3.3 Scenarios
We offer to simulate three different scenario’s (operating conditions). It is our experience that by
performing those simulations a good overview is obtained of the functioning of the structure.
Additional information obtained by simulating a start-up or stop of the system is limited and is not
covered in the scope of the CFD study. The water levels that can occur should be provided by
KSB.
Deltares experts will analyse the results and when required, measures will be proposed to
improve the flow pattern. It is not expected that major measures to the intake structure are
required. Therefore, in view of time, proposed measures will be tested during the physical model
test. Simulations of these measures in CFD is not included in the scope of work, but offered as
an optional activity. When (preliminary) results of the CFD simulations are available, a video
conference will be held with all parties to discuss whether additional CFD simulations has to be
performed. If the proposed measures have to be assessed in CFD, this will impact the time
schedule for the physical model testing with about 3 weeks.
3.6 Deliverable
The findings of the CFD studies will be presented in a comprehensive report.
– Description of objectives
– Description of the structure subject to CFD modelling, initial model geometry
(including 3D rendering) and mesh
– Overview of initial geometry, scenarios, boundary conditions and simulations
– Overview of the CFD settings used (among others mesh size and turbulence model
used)
– Performance criteria
– Model results
– Expert analysis, evaluations and recommendations
The results of the CFD simulations will be exported to a format which can be imported in
Paraview and delivered to KSB. However, before the simulations start, the Client should inform
Deltares which results should be exported. Deltares will not be responsible for any post-
processing performed in Paraview.
Quotation
Date Our reference Page
May 29, 2019 11203901-001-HYE-0001 6 of 19
A physical model test will be performed in which the approach flow towards the pumps will be
optimised such that proper pump feeding according to the ANSI/HI 9.8-2018 standard will be
obtained. The following work will be performed:
• Construction of the model,
• Submittals of the test procedure (including model drawings),
• Testing of the model and necessary modifications,
• Final testing of the model,
• Witness testing,
• Submittal of the physical model report,
• Video presenting of the physical model test.
A detailed description of these activities is given in the remaining of this Chapter.
A desk assessment is not included. That means that the water levels at the pumps for the
different operating conditions should be provided by KSB.
4.1 Introduction
The objective of this study is to optimize the pump sump design and the feeding of the pumps in
a physical model. The pumping station is reproduced to scale and will be tested in order to:
• Check pump working under the given operating conditions (combination of water level and
pumps in operation),
• Design and develop small modifications to achieve acceptable feeding of the pumps.
A scale model will be constructed in Deltares IOS-1 or IOS-2 basin. The designs as provided by
KSB will be tested in order to check proper pump feeding under the different operating conditions.
If the criteria for proper pump feeding are not fulfilled for example due to vortex shedding around
the pump entrance, at most three different (small) modifications at the pump suction chamber to
improve pump working are included in the current scope. Small modifications are limited to
splitters, corner fillings (horizontal or vertical), baffles and surface beams. Modifications and
provisions will be applied after consultation with KSB. The final design will be tested for the
relevant operating conditions. A one day witness test will be held with KSB (and the end-Client)
at Deltares’ office in Delft after completion of the tests.
For the model a scale of about 1:10 is proposed, using Froude scaling. This means that the
Froude number in the model is the same as the Froude number in reality. The scale will be such
that the Reynolds and Weber numbers based on the bellmouth are appropriate in order to
represent sufficiently high turbulence intensity and to avoid scale effects.
Quotation
Date Our reference Page
May 29, 2019 11203901-001-HYE-0001 7 of 19
Figure 4.1 Top view of the pumping station. The part within the blue box will be modelled.
In the physical model, the suction piping will be reproduced to scale with the pump entrance. The
part until the impeller will be modelled (see Figure 4.2). From the impeller onwards, the pump
will be modelled as a straight pipe (according to the ANSI/HI 9.8-2018 standard). The suction
pipe will be equipped with a roto-meter, while an additional suction line will be constructed and
be equipped with a pitot velocity meter to assess the velocity profile. Pump action will be obtained
by a downstream pump. The flow rate in the suction line is accurately measured with an
electromagnetic flow meter (accuracy about 2 % of measured flow).
Figure 4.2 Drawing provided by KSB of the pumps. The suction piping will be modelled in detail up to the red line.
The physical model tests will be performed for three water levels: minimum and maximum water
level and a third water level to be determined later. Various combinations of pump and screen
operation are tested.
Quotation
Date Our reference Page
May 29, 2019 11203901-001-HYE-0001 8 of 19
The screens are reproduced by a perforated plate with the correct flow guiding effects. The model
will be accurately constructed and will be made of plywood and Perspex. It will be assured that
there will be sufficient viewing properties to observe the flow patterns near the suction piping of
the pumps. The model will be located in Deltares’ IOS-1 or IOS-2 basin.
Testing will be performed by using clean water as a medium. This is common practice as the
properties of waste water are often unknown and differ from system to system. Therefore, clean
water will be used to reach proper pump feeding according to the ANSI/HI 9.8-2018 standard.
Thereafter, some tests will be performed to determine the behaviour of solids in the pumping
station. These tests will be performed with particles representing the floating solids and particles
representing the settling solids. The tests with solids will be performed during the final testing.
Note that these tests can only be performed when the characteristics of the waste water (particle
size, particle density, amount of solids) are provided by KSB.
4.3 Testing
In order to maintain the quality of the test, the measurements will not start until a constant flow
rate and a stable water level in the model has been established.
The flow conditions in the pumping station are judged by the following measurements:
· Determination of the flow pattern in the sump by means of dye injection,
· Vortex building and air entrainment into suction pipes of the pumps by means of dye
injection and visual observations,
· Tornado building (bottom and wall) by means of dye injection,
· Swirl in the suction pipe at the impeller inlet with a roto-meter,
· Velocity profile and velocity fluctuations in the suction pipe at the impeller inlet by means
of pitot tubes.
Moreover, some additional tests will be performed for a limit number of test conditions. These
tests are further discussed in Section 4.5. These additional tests are:
• Calibration of the flow over the spillway crest.
• Velocity measurements at certain cross-sections in the intake structure, including
pressure difference measurements to be able to determine the head loss between
different parts of the system.
• Behaviour of solids.
Table 4.1: Number of tests to be performed for the physical model test.
Final test Supplementary tests
Initial Optimization test
tests Ex. Velocity
(per modification) Velocity profiles Clogging Air Entrainment
150%
20 5 2 2 2 1
Testing of the design (provided by KSB) without any flow guiding structures like splitters and
fillings in the pump compartments. Assessment of the hydraulic behaviour of the pumping station
is based on criteria for proper pump operation regarding vortex building, air entrainment, pre-
rotation, and flow patterns (flow separation, instabilities, dead zone building).
For each of these tests, the screen will be assumed cleaned at 100%. A dedicated clogging test
will be performed during Phase III (final testing).
The test results will be compared with the acceptance criteria given in the ANSI/HI 9.8-2018
standard. If they do not fulfil the requirements, optimization tests will be performed (Phase II). If
the test results of Phase I are acceptable (which is not in line with the expectations), Deltares
will skip Phase II and proceed with Phase III.
Assessment of the hydraulic behaviour of the pumping station (including the screening channels)
is based on criteria for proper pump operation: vortex building, air entrainment, pre-rotation and
flow patterns (flow separation, instabilities, dead zone building.
Quotation
Date Our reference Page
May 29, 2019 11203901-001-HYE-0001 10 of 19
1. Velocity profiles of the pumps: This test is performed in order to determine whether these
pumps are functioning within the acceptance criteria related to the velocity profile.
2. Exaggerated velocity tests: The exaggerated velocity test (Fr ex = 1.5 x Frprototype) is
performed in order to check on any significant scale effects for free surface vortices (not
expected with the proposed scale). The occurrence of free-surface vortices will be checked.
5 Deliverables
5.2.1 Drawings
Prototype drawings will be submitted for review. After approval of the prototype drawings, model
drawings will be submitted in the Test procedure report.
5.2.4 Video
A movie will be made, in the English language, showing all stages of each physical model
investigation from testing of the original design up to the final design.
Quotation
Date Our reference Page
May 29, 2019 11203901-001-HYE-0001 12 of 19
6 Required data
· Concept drawings with foreseen dimensions and levels of the intake structure in AutoCAD
format,
· Detailed drawings with dimensions of the pumps in AutoCAD format,
· Screen drawings including the details such as mesh size,
· Operational water levels at the pumps for all operational conditions to be tested in the
physical scale model tests (on request Deltares can perform a head loss calculation to
determine the operational water levels at the pumps),
· Possible operating conditions,
· Relevant discharges of all pumps,
· Dimensions that cannot be changed.
· Characteristics of the solids in the waste water (particle size, particle density, amount of
solids).
Quotation
Date Our reference Page
May 29, 2019 11203901-001-HYE-0001 13 of 19
The start of the work depends on available capacity of manpower and facilities at the time of
settlement of all contractual issues, but will normally be within two weeks after the order of
commence. Commencement of the work can start after receipt of all input data. A definite
reservation of the facilities will be made based upon settlement of all contractual issues.
The tentative time schedule is valid provided that the Client reacts within:
• one week for reports
• one day for drawings
• one day for proposed modifications during the optimisation phase (discussion will be
performed via video conference)
1
If an additional CFD simulation has to be performed for a proposed measure, three additional
weeks are required for the CFD modelling and thus the physical model testing will be delayed by
three weeks.