Project week Duration

Start Finish 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
no. (Weeks)
Contract / collection of data 24-Jun-19 30-Jun-19 1 x
Task 1 CFD modelling1 1-Jul-19 25-Aug-19 8
Model set-up 1-Jul-19 14-Jul-19 2 x x
Simulations 8-Jul-19 28-Jul-19 3 x x x
Analysis 22-Jul-19 4-Aug-19 2 x x
Reporting 29-Jul-19 25-Aug-19 4 x D R F
Task 2 Physical model testing 22-Jul-19 3-Nov-19 15
Prototype drawings 22-Jul-19 4-Aug-19 2 D F
Model drawings 22-Jul-19 11-Aug-19 3 x D F
Test 5-Aug-19 1-Sep-19 4 x D R F
Model construction 5-Aug-19 8-Sep-19 5 x x x x x
Initial testing 9-Sep-19 22-Sep-19 2 x x
Optimization testing 23-Sep-19 6-Oct-19 2 x x
Final testing (incl. solids) 7-Oct-19 20-Oct-19 2 x x
Witness test 21-Oct-19 27-Oct-19 1 x
Reporting 14-Oct-19 3-Nov-19 3 x x D

D= submission of draft report;


R= Review by the Client;
F= Submission of final report