Documente Academic
Documente Profesional
Documente Cultură
1. During the execution of a project, procedures for project control and record
keeping become indispensable tools to managers and other participants in the
construction process.
2. These tools serve the dual purpose of recording the financial transactions that
occur as well as giving managers an indication of the progress and problems
associated with a project.
5. The time at which major cost savings can be achieved is during planning and
design for the project. During the actual construction, changes are likely to
delay the project and lead to inordinate cost increases. As a result, the focus of
project control is on fulfilling the original design plans or indicating deviations
from these plans, rather than on searching for significant improvements and
cost savings.
7. For example, schedule information and cost accounts are usually kept
separately. As a result, project managers themselves must synthesize a
comprehensive view from the different reports on the project plus their own
field observations.
UNIT-5
COST CONTROL, MONITORING AND ACCOUNTING
8. In particular, managers are often forced to infer the cost impacts of schedule
changes, rather than being provided with aids for this process. Communication
or integration of various types of information can serve a number of useful
purposes, although it does require special attention in the establishment of
project control procedures.
1. The final or detailed cost estimate provides a baseline for the assessment of
financial performance during the project.
2. To the extent that costs are within the detailed cost estimate, then the project is
thought to be under financial control.
4. For control and monitoring purposes, the original detailed cost estimate is
typically converted to a project budget, and the project budget is used
subsequently as a guide for management.
5. Specific items in the detailed cost estimate become job cost elements. Expenses
incurred during the course of a project are recorded in specific job cost
accounts to be compared with the original cost estimates in each category.
6. Thus, individual job cost accounts generally represent the basic unit for cost
control. Alternatively, job cost accounts may be disaggregated or divided
into work elements which are related both to particular scheduled activities
and to particular cost accounts.
8. With this information, actual materials usage and labor employed can be
compared to the expected requirements. As a result, cost overruns or savings
on particular items can be identified as due to changes in unit prices, labor
productivity or in the amount of material consumed.
UNIT-5
COST CONTROL, MONITORING AND ACCOUNTING
9. The number of cost accounts associated with a particular project can vary
considerably. For constructors, on the order of four hundred separate cost
accounts might be used on a small project. These accounts record all the
transactions associated with a project.
10. Thus, separate accounts might exist for different types of materials, equipment
use, payroll, project office, etc. Both physical and non-physical resources are
represented, including overhead items such as computer use or interest
charges.
12. Particular cost accounts are used to indicate the expenditures associated with
specific projects and to indicate the expenditures on particular items
throughout an organization.
13. Converting a final cost estimate into a project budget compatible with an
organization's cost accounts is not always a straightforward task.
14. One particular problem in forming a project budget in terms of cost accounts is
the treatment of contingency amounts. These allowances are included in
project cost estimates to accommodate unforeseen events and the resulting
costs.
BudgetedCost
The budgeted cost is derived from the detailed cost estimate prepared at the start of
the project. The factors of cost would be referenced by cost account and by a prose
description.
Estimatedtotalcost
The estimated or forecast total cost in each category is the current best estimate of
costs based on progress and any changes since the budget was formed. Estimated
total costs are the sum of cost to date, commitments and exposure.
CostCommittedandCostExposure!!
Estimated cost to completion in each category in divided into firm commitments and
estimated additional cost or exposure. Commitments may represent material orders or
subcontracts for which firm dollar amounts have been committed.
CosttoDate
The actual cost incurred to date is recorded in column and can be derived from the
financial record keeping accounts.
UNIT-5
COST CONTROL, MONITORING AND ACCOUNTING
Overor(Under)
This is an indicator of the extent of variance from the project budget; items with
unusually large overruns would represent a particular managerial concern.
6. Overruns in cost might be due to lower than expected productivity, higher than
expected wage rates, higher than expected material costs, or other factors.
Even further, low productivity might be caused by inadequate training, lack of
required resources such as equipment or tools, or inordinate amounts of re-
work to correct quality problems. Review of a job status report is only the first
step in project control.
7. The estimates are used to identify the actual progress and status of a expense
category. Using a linear extrapolation of costs, the forecast total cost, Cf , is:
Where Ct is the cost incurred to time t and pt is the proportion of the activity
completed at time t.
8. Alternatively, the use of measured unit cost amounts can be used for
forecasting total cost. The basic formula for forecasting cost from unit costs is:
Where Cf is the forecast total cost, W is the total units of work, and ct is the
average cost per unit of work experienced up to time t.
UNIT-5
COST CONTROL, MONITORING AND ACCOUNTING
9. The unit cost may be replaced with the hourly productivity and the unit cost per
hour (or other appropriate time period), resulting in the equation
Where the cost per work unit (ct) is replaced by the time per unit, ht, divided by
the cost per unit of time, ut.
where forecast total cost, Cf, is the sum of cost incurred to date, Ct, and the
cost resulting from the remaining work (W - Wt) multiplied by the expected cost
per unit time period for the remainder of the activity, ct.
11. Each of the estimating methods described above require current information on
the state of work accomplishment for particular activities. There are several
possible methods to develop such estimates, including:
UnitsofWorkCompleted
For easily measured quantities the actual proportion of completed work
amounts can be measured.
IncrementalMilestones
Particular activities can be sub-divided or "decomposed" into a series of
milestones, and the milestones can be used to indicate the percentage of work
complete based on historical averages.
Opinion
Subjective judgments of the percentage complete can be prepared by
inspectors, supervisors or project managers themselves. Clearly, this estimated
technique can be biased by optimism, pessimism or inaccurate observations.
Knowledgeable estimators and adequate field observations are required to
obtain sufficient accuracy with this method.
UNIT-5
COST CONTROL, MONITORING AND ACCOUNTING
Costratio
The cost incurred to date can also be used to estimate the work progress. This
method provides no independent information on the actual percentage
complete or any possible errors in the activity budget: the cost forecast will
always be the budgeted amount.
Project managers are involved with assessment of the overall status of the project,
including the status of activities, financing, payments and receipts. These various
items comprise the project and financing cash flows.
These components include costs incurred, billings and receipts for billings to owners
(for contractors), payable amounts to suppliers and contractors, financing plan cash
flows (for bonds or other financial instruments), etc.
Costs
this is a summary of charges as reflected by the job cost accounts, including
expenditures and estimated costs. This row provides an aggregate summary of the
detailed activity cost
information Billings
This row summarizes the state of cash flows with respect to the owner of the facility;
this row would not be included for reports to owners.
Payables
The Payables row summarizes the amount owed by the contractor to material
suppliers, labor or sub-contractors.
Receivables
This row summarizes the cash flow of receipts from the owner. Note that the actual
receipts from the owner may differ from the amounts billed due to delayed payments
or retainage on the part of the owner
Cash Position
UNIT-5
COST CONTROL, MONITORING AND ACCOUNTING
This row summarizes the cash position of the project as if all expenses and receipts
for the project were combined in a single account.
Schedule Control:
3. The methods used for forecasting completion times of activities are directly
analogous to those used for cost forecasting. For example, a typical estimating
formula might be:
5. For example, Figure 12-2 shows the originally scheduled project progress
versus the actual progress on a project. This figure is constructed by summing
up the percentage of each activity which is complete at different points in time;
this summation can be weighted by the magnitude of effort associated with each
activity. In Figure 12-2, the project was ahead of the original schedule for a
period including point A, but is now late at point B by an amount equal to the
horizontal distance between the planned progress and the actual progress
observed to date.
UNIT-5
COST CONTROL, MONITORING AND ACCOUNTING
6. Schedule adherence and the current status of a project can also be represented
on geometric models of a facility.
2. On "fast track" projects, initial construction activities are begun even before
the facility design is finalized. In this case, special attention must be placed on
the coordinated scheduling of design and construction activities.
6. In essence, duration and cost estimates for future activities should be revised in
light of the actual experience on the job. Without this updating, project
schedules slip more and more as time progresses. To perform this type of
updating, project managers need access to original estimates and estimating
assumptions.
7. Beyond the direct updating of activity durations and cost estimates, project
managers should have mechanisms available for evaluating any type of
schedule change.
2. A numbering or identifying system for work elements would include both the
relevant cost account and the associated activity. In some cases, it might also
be desirable to identify work elements by the responsible organization or
individual.
8. Until data collection is better automated, the use of work elements to control
activities in large projects is likely to be difficult to implement. However,
certain segments of project activities can profit tremendously from this type of
organization.
UNIT-5
COST CONTROL, MONITORING AND ACCOUNTING
10. Moreover, the benefits from integration of schedule and cost information are
particularly noticeable in materials control since delivery schedules are
directly affected and bulk order discounts might be identified. Consequently,
materials control systems can reasonably encompass a "work element"
accounting system.
11. In the absence of a work element accounting system, costs associated with
particular activities are usually estimated by summing expenses in all cost
accounts directly related to an activity plus a proportion of expenses in cost
accounts used jointly by two or more activities.
12. The basis of cost allocation would typically be the level of effort or resource
required by the different activities.