Documente Academic
Documente Profesional
Documente Cultură
Site
: TABOUK POWER PLANT
S. Progres s
No. Percent age
AREA Activity %
GT#9,10 & 11
Skid Lighitng
19 fwd,selection,heater,tran 85%
GT#9,10 & 11
sformer & MCC room lighitng
GT#9,10 &11
fwd,selection,heater,tran
sformer & MCC room fire
Skids Fire fhigtng fighting
20 40%
GT#9,10,11
45%
HVAC system cable laying and
COTP HVAC System
termination
MECHANICAL 90.00%
50%
Foam System (Skids)
Fire Fighting All
Areas Transformer Cooling System
(Deluge Sprinkler System) 35%
0%
HPCO2 Work
In Progres s 90.10%
In Progress 15/06/19
In Progress
20/06/19
In Progres s
One HAVC
unit ready in
working condition
20/06/201 while 2nd
In Progres s
9 commisoning
remaining
In Progres s 20/07/201
9
In Progres s 18/06/201
9
In Progres s
20/07/19
In Progres s
10/07/19
In
Progres s 10/07/19
In Progres s
10/07/19
In
Progres s 30/06/19
In Progres s
30/06/19
In Progres
s 25/06/19