Site Execution Progress Report

Site
: TABOUK POWER PLANT

S. Progres s 
No. Percent age
AREA Activity %

CIVIL WORK & STRUCTURAL 98.42%

8 COTP Open Steel Structure Shed for 95%


one COTP
Slab On Grade Plinth or
18 Pavements for access etc. 75%

ELECTRICAL AND INSTRUMENTATION 93.19%

Instrument & Instrumentation & control cable 99%


control Cable laying & termination for
7 GT#07 & 08 complete
units

HVAC system cable laying and


termination

9 HVAC System 99%

11 Skids Fire fhigtng GT#07 & GT#08


GT#07 & GT08 fwd,additive,heater,trans former
& MCC room skid fire fighting 50%

17 Instrument & Instrumentation & control cable


control Cable laying & termination for
GT#9,10,11 complete 95%
units

GT#9,10 & 11
Skid Lighitng
19 fwd,selection,heater,tran 85%
GT#9,10 & 11
sformer & MCC room lighitng
GT#9,10 &11
fwd,selection,heater,tran
sformer & MCC room fire
Skids Fire fhigtng fighting
20 40%
GT#9,10,11

GT#14 & GT#15


Skids Fire fhigtng fwd,selection,heater,tran
29 70%
GT#14 & GT15 sformer & MCC room fire
fighting

GT#16 & GT#17


fwd,heater,transformer & MCC
Skids Fire fhigtng room fire fighting
38 95%
GT#16 & GT17

UPS COTP Installation of UPS with I&C


46 cable laying and termination 20%

All skids lighitng,MCC room


lighitng
48 COTP Lighitng 99%

45%
HVAC system cable laying and
COTP HVAC System
termination

All skid fire fighitng & MCC


49 COTP Fire fighitng 65%
room fighitng

MECHANICAL 90.00%

GT 9/10/11 Blinding of Valves feeding to 0%


distillate Headers from Tank 11
6 (8"
Valve 102 and 12" Valve#
04)
Blind distillate Return line
Valve# 100 to Tank 11, and
ensure Crude Return line
7 Valve# 101 to 0%
tank 11 is open.
Insulating the Piping from
16 Heaters to Selection 55%
Skid to GT
GT 7/8 Install 4" Valve, Close and Blind
20 the GT1&2 Return line to Tanks 30%
3&4
Add a TEE before the
newly added valve and
21 terminate the line distillate 30%
return header
before Valve# 34.
22 GT 14 & 15 Blind Valve# 29 to prevent
distillate return to Tank 3 & 4
(For Blind: 0%
Vlv #53, #35, #37, #31)

Insulating the Piping from


46 Heaters to Selection 50%
Skid to GT
FM200 System (Control 0%
Rooms)

50%
Foam System (Skids)
Fire Fighting All
Areas Transformer Cooling System
(Deluge Sprinkler System) 35%

0%
HPCO2 Work

Bulk Fuel Additive Skid SS


Bulk Storage Additive 50%
PIPING to Selection Skids
ution Progress Report

TARGET DATES Total


Percent age
Status Remarks %

In Progres s 90.10%

In Progress 15/06/19

In Progress
20/06/19

In Progres s

In Progres s Additve skid power


16/06/201 termination in
9 progress

One HAVC
unit ready in
working condition
20/06/201 while 2nd
In Progres s
9 commisoning
remaining

In Progres s 20/07/201
9

In Progres s 18/06/201
9

In Progres s 4 light fixture are


short and will be
installed once
delivered.how ever
10/07/201 each skid have
9 enough lighting
Completion date
will be provided
once GT
15/07/201 installation work is
In Progres s
9 completed

In Progres s 15-07- Completion depend


2019 on fire fighitng
material delivery

In Progres s 15/07/201 Completion depend


9 on fire fighitng
material delivery

In Progres s 20/06/201 As Per UPS


9 delivery date

In Progres s Only Vent & Air


compressor skid
25/06/201
remaining
9

In Progres s One HAVC


30/06/201 unit ready in
9 working condition

In Progres s 20/07/201 Completion depend


9 on fire fighitng
material delivery

In Progres s

20/07/19

Not yet started

Not yet started 10/07/19


In Progres s
10/07/19

In Progres s
10/07/19

In
Progres s 10/07/19

Not yet started


10/07/19

In Progres s
10/07/19

Not yet started 30/06/19

In
Progres s 30/06/19
In Progres s
30/06/19

Not yet started 30/06/19

In Progres
s 25/06/19