OWNER -----
CONTRACTOR -----
0 23.07.2014
Abbreviations:
GI : Galvanised Iron
HT : High Tension
IR : Insulation Resistance
LT : Low Tension
ITP No.
INSPECTION & TEST
PLAN
CABLE LAYING Raipur/CUT/13B1A46-
00-QA-E-ITP-005
Page 3 of 6
CONTENTS
GENERAL NOTE
The enclosed ITP's shall be followed for the works to be performed by the contractor. The
provisions indicated for stagewise inspection by IOT are the minimum and the Engineer-
In-Charge may decide to increase Hold Points/ Witness Points. Activities for which ITP's
are not given, contractor to develop and get the same approved by IOT well before start of
the work.
Contractor to submit required reporting formats and job procedures for each activity listed in ITP's
and submit to IOT for approval, well before commencement of the activity. If the contractor
has to deviate from the given ITP for a valid reason, he shall obtain prior written approval
of IOT. Contractor to carry out 100% examination of all activities.
LEGEND
HP : Hold Point ;
W : Witness Point ;
Responsibility for execution of the inspection/testing is with the Contractor; IOT only verifies
examination or testing done by the Contractor at important stages
ITP No.
INSPECTION & TEST
PLAN
CABLE LAYING Raipur/CUT/13B1A46-
00-QA-E-ITP-005
Page 5 of 6
Sl.
Activity IOTAEC IOT
No.
1. Survey the cable route as per AFC drawings, identify any possible WC W
obstruction like road/pipe rack crossing, heat sources etc. and finalize
the cable route
6. Verify the dimensions of buried trench as per IFC drawings (in case WC S
of buried cables)
10. Provide cable tags at specified locations and end cap provided in WC Rw
each cable.
11. Record IR value of cables of first layer after sand filling. WC W
12. Provide second layer of sand, and ensure proper clearance between WC S
HT/LT cables (wherever applicable)
16. Ensure cable trenches in hazardous areas are filled with sand WC S
ITP No.
INSPECTION & TEST
PLAN
CABLE LAYING Raipur/CUT/13B1A46-
00-QA-E-ITP-005
Page 6 of 6
Sl.
Activity IOTAEC IOT
No.
18. Back fill the trenches with earth and compact properly after ensuring the WC S
completion of earthing works, if any as per earthing layout drawings.
19. Install cover slabs and seal the trenches in plant/offsite areas after WC S
ensuring the completion of earthing works, if any.