Hallare Building ( 6th Storey Building with basement and roof deck )
Minutes of meeting
Updates on Project:
Bricks installation ongoing, done installing in ground floor
Ramp preparation and backfilling ongoing
Workers on site 12
Electrical Permit for follow-up, B.O already inspected the building for the permit application.
Electrical panels next week to start; fabrication haven’t started yet waiting for the payment but Sir john already
given a 50% down payment to the Sub-contractor.
Elevator hoist beam already done installing waiting for the Supplier to check the work done so that they can
start installing the elevator.
Sir John requested new system of billing – Php 120,000 per week