Sunteți pe pagina 1din 1

Following documents are required to arrange prior to start Excavation activity

1.All employees should carry valid site ID along with the valid Iqama all the time.

2.Heavy equipment Operator should carry Saudi Arabian Operator license along with the third party
certification.

3. Heavy equipment should have valid third party certification.

4. All heavy equipment should be accompanied by a Competent banksman/Signal man.

5. A copy of all permits, Approved RFI from Royal Commission along with the supporting documents at
the site location.