Method Statement for Bending and Installation of
Downspout for Toll Plaza
PROJECT: Cavite – Laguna Expressway Project
Document Number: MS-MEPF- Rev 0 27-MAY-2019
Table of contents
1. SCOPE OF WORKS.................................................................................................................4
2. CONSTRUCTION PROCEDURE.............................................................................................4-8
4. ENVIRONMENT………………………………………………………………………………………………………………9-10
5. PERSONNEL………………………….........................................................................................10-11
6. SUB-CONTRACTOR / SUPPLIERS......................................................................................11-12
8. MATERIALS.........................................................................................................................12
12. REFERENCES......................................................................................................................14
Page 3 of 14
Method Statement for Bending and Installation of
Downspout for Toll Plaza
PROJECT: Cavite – Laguna Expressway Project
Document Number: MS-MEPF- Rev 0 27-MAY-2019
DLL & Sons Company Asia Ltd., will be responsible for the delivery, bending, lifting
and installation of pipes and fittings necessary for the downspout of each Toll Plaza.
2. Check all pipes and fittings to be used for joint are free from defects, dents
or deformities and are straight. Remove pipes and fittings with defects and
replace with acceptable materials.
4. Remove foreign matter or dirt from inside of the pipe and fittings before fit
up.
6. For longer work breaks, place suitable stoppers (plug or cap) to prevent
debris, earth or water from entering pipe open ends.
1. Fabricate the pipe bender assembly by obtaining the actual curvature of the
toll plaza post/column. Make a curve pattern initially, then fabricate the pipe
bender using this pattern. Be sure to reinforce every segment of the
assembly to withstand bending force
2. Insert the whole length of pipe (6m) in the assembly and start bending the
pipe either manually or by using hydraulic jack (hydraulic jack shall only be
an additional accessory of the pipe bender; it can be added or be removed)
(see Figure 1a & Figure 1b).
Page 4 of 14
Method Statement for Bending and Installation of
Downspout for Toll Plaza
PROJECT: Cavite – Laguna Expressway Project
Document Number: MS-MEPF- Rev 0 27-MAY-2019
Page 5 of 14
Method Statement for Bending and Installation of
Downspout for Toll Plaza
PROJECT: Cavite – Laguna Expressway Project
Document Number: MS-MEPF- Rev 0 27-MAY-2019
3. Individually bend the pipe and acquire the required quantity of downspout
for each toll plaza.
Page 6 of 14
Method Statement for Bending and Installation of
Downspout for Toll Plaza
PROJECT: Cavite – Laguna Expressway Project
Document Number: MS-MEPF- Rev 0 27-MAY-2019
C. Installation Works
1. Lift the bended pipe using a hoist and align it with the toll plaza post/column.
2. While properly aligned mark the location and distances of the pipe support.
3. With proper coordination to DMCI personnel and the Toll Plaza building
subcontractor, tack weld the base of the clamp to the building structure. Be
sure to correctly position the clamp to line up according to the curvature of
the bend pipe and toll plaza column/post (see Figure 2).
4. Once properly placed, fully weld the base of the clamp support with the
building structure (see Figure 3).
Page 7 of 14
Method Statement for Bending and Installation of
Downspout for Toll Plaza
PROJECT: Cavite – Laguna Expressway Project
Document Number: MS-MEPF- Rev 0 27-MAY-2019
6. Begin layout of pipe and fittings. Tack weld initially the fittings required for
the downspout. Works shall be carried out in accordance with the approved
shop drawings.
7. For proper welding procedure, refer and follow Method Statement for
Welding of Drain Pipes for Bridges.
The installation of downspout for toll plaza will have a health and safety risk for the
immediate personnel involved and the community. The following are the identified
risk and potential hazards.
1. Dust
2. Poor illumination
3. Uneven surface
4. Ergonomic
5. Suspended load
6. Floor openings
7. Electrocution
Page 8 of 14
Method Statement for Bending and Installation of
Downspout for Toll Plaza
PROJECT: Cavite – Laguna Expressway Project
Document Number: MS-MEPF- Rev 0 27-MAY-2019
8. Fire
DMCI shall mitigate the negative effect of the construction and installation of drain
pipes for bridges on the health and safety by observing the following:
5. All lifting activities shall have a critical lifting plan and coordinated
accordingly.
6. All floor openings shall be closed fixed. If closing is not an option installation
of hard barricades shall be put in place.
4.0 Environment
The installation of downspout for toll plaza will have a potential impact on the
immediate surroundings. DMCI have identified the following as the impact of the
said activity:
1. Dust
2. Eye sore
DMCI shall mitigate the negative effect of the construction and installation of drain
pipes for bridges on the environment by observing the following:
2. Barriers and perimeter enclosure shall be installed prior to start of the activity
to lessen the visual impact of the construction activity.
Page 9 of 14
Method Statement for Bending and Installation of
Downspout for Toll Plaza
PROJECT: Cavite – Laguna Expressway Project
Document Number: MS-MEPF- Rev 0 27-MAY-2019
5.0 Personnel
A. Project Engineer
B. Safety Officer
The organization chart allocates the position of the Safety personnel that reports
immediately to the Project Manager. The Safety personnel has also direct
communication lines with the supervisors to ensure a continuous follow up of the
eventual safety and environmental impacts of the works executed at any time
and place.
C. Project Foreman
Page 10 of 14
Method Statement for Bending and Installation of
Downspout for Toll Plaza
PROJECT: Cavite – Laguna Expressway Project
Document Number: MS-MEPF- Rev 0 27-MAY-2019
D. Scaffolders
E. Welders
6.0 Subcontractors/Suppliers
1 Subcontractors
DMCI will work with the owner to ensure that owner-furnished materials and
equipment meet the technical requirements of the project. In addition, DMCI will
Page 11 of 14
Method Statement for Bending and Installation of
Downspout for Toll Plaza
PROJECT: Cavite – Laguna Expressway Project
Document Number: MS-MEPF- Rev 0 27-MAY-2019
provide the owner with request of materials indicating specs, quantity and
delivery schedules so that the owner-furnished materials and equipment do not
delay or otherwise affect the construction process. If the installation of materials
and equipment are DMCI’s responsibility, DMCI will inspect the materials and
equipment when delivered and properly store them in the storage provided until
needed. Records of receipt and inspection of materials and equipment will be
forwarded to the owner.
All equipment to be utilized in this project so as to expedite the operation and give
precise output shall comply with the requirements, technical standard, and safety
regulation. Tabulated list of equipment will be provided to the client for reference.
Equipment shall be operated only by a knowledgeable and well-trained personnel
equipped with proper gear.
8.0 Materials
All materials to be utilized in this project shall be approved by the client. All
necessary material submittal, data sheets and test result shall be readily available
and shall be submitted to the client for approval.
All materials should have appropriate and proper handling and shall be stored on the
designated area of storage upon delivery at the site in such a way that it is free from
any deleterious materials that can affect the quality of the material.
DMCI performs final inspection and testing on all completed work, specified
requirements and DMCI’s quality assurance procedures prior to turning the
Page 12 of 14
Method Statement for Bending and Installation of
Downspout for Toll Plaza
PROJECT: Cavite – Laguna Expressway Project
Document Number: MS-MEPF- Rev 0 27-MAY-2019
completed work over to the respective parties. Records are kept for all final
inspection and testing.
Start-up and testing procedures for materials, equipment and the systems it is
comprised will be performed in accordance with the technical specifications and
DMCI quality assurance procedures. In an event of starting up an equipment
supplied by other contractor a manufacturer’s representative is required to be on
site to inspect the installation, perform final adjustments, perform required tests
and/or start-up the equipment or system when required by contract for technical
reasons or for warranty compliance.
All inspection and test records will be maintained by DMCI along with records of
any corrective action taken. Copies of the inspection and test records will be
provided to the owner, owner’s representative or architect/engineer in
accordance with the contract documents.
DMCI will ensure that all requirements to put warranties and guarantees in force
are met. Copies of all warranties and guarantees will be provided to the owner in
accordance with the contract documents.
Nonconforming material, equipment and work in place will be corrected in one of the
following:
Page 13 of 14
Method Statement for Bending and Installation of
Downspout for Toll Plaza
PROJECT: Cavite – Laguna Expressway Project
Document Number: MS-MEPF- Rev 0 27-MAY-2019
12.0 References
Page 14 of 14