VODAFONE NPT Acceptance Testing Document.

_________________________________________________________________________________________

ECI–NPT-1200/1020/1050/1010
Station/Location: - ____________________________________________________

NE Name as in Plan: - ____________________________________________________

NE ID: - ____________________________________________________

NE Embedded Version: - ____________________________________________________

NE Boot version: - ____________________________________________________

Shelf Type & Serial Number: - ______________________________________________

Communication IP: - ____________________________________________________

NE/Loopback IP: - ____________________________________________________

Date of Testing: - ____________________________________________________

Management Type (OSFP / DCC):- ______________________________________________

ECI Representative(s) Vodafone Representative(s)

Name: - ______________________ Name: - ________________________

Mobile: - ______________________ Mobile: - ________________________

Designation: - ______________________ Designation: - ______________________

Date: - ______________________ Date: - ______________________

NOTE: All readings to be recorded against each test in the document. Wherever it is NOT
APPLICABLE please mention N/A.

PAGE 1 OF 18
VODAFONE NPT Acceptance Testing Document.

_________________________________________________________________________________________

1 Commissioning Tests

Overview
This chapter describes general commissioning procedures for the NPT-1200/1050/1020 and
provides a basis for preparing tests in specific networks.

The commissioning procedures include:


 Site commissioning tests, performed at the Site level to ensure proper functionality
of the site.
 Equipment commissioning tests, performed at the Site level to ensure proper data
functionality of the Node.

NOTE: Personnel involved in the execution and supervision of commissioning


tests must be familiar with the applicable safety precautions and requirements.

Test Equipment
The following test equipment is required for the commissioning procedures:

 Optical Power Meter (OPM)

 Set of optical attenuators with various values

 Variable optical attenuator

 FC-to-LC adapters

 LC/FC optical patch cords

 Multimeter.

Suitable equipment is available from a wide range of manufacturers and therefore no specific
models are listed. You can use any equipment that meets applicable international standards and
has satisfactory measurement accuracy over the range of operating parameters and
environmental conditions that apply to the specific network. If necessary, contact ECI’s Field
Engineering Department for specific recommendations.

PAGE 2 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

1. Visual Inspection and Mechanical Checks


1.1. Documentation check

Inventory Serial Number records attached Yes No

1.2. Visual Inspection

1.2.1 Rack firmly Installed Yes No

1.2.2 Sub rack equipped to job specification Yes No

1.2.3 Ensuring dummy plates installation for empty slots Yes No

1.2.4 Rack Alarm unit fitted properly Yes No

1.2.5 All the power cables properly routed & terminated Yes No
with suitable lugs
1.2.6 All patch cords routed and terminated properly at Yes No
relevant ODF
1.2.7 All patch cords & CAT5/6 routed through PVC Yes No
channel
1.2.8 All patch cords/CAT5-6 cables are properly labeled Yes No
with printed stickers
1.2.8 Storage of patch cords properly done Yes No

1.2.9 All alarms LED/Lamps are in healthy condition Yes No

1.2.10 X-Rap to Rack Grounded Yes No

1.2.11 Mux to Rack Earth bar Grounded Yes No

1.2.12 Rack Earth Bar to Room Earth Bar Grounded Yes No

1.3 Mechanical defects

1.3.1 All screw & nuts properly mounted Yes No

3.2 No physical damage to rack/sub rack or its Yes No


component

Remarks:-

PAGE 3 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

2. Inventory Details:
2.1 Checking Cards and Modules Installed in Each Shelf
This check is performed to confirm that the required cards and modules have been installed in each
site, and to record their options, revisions, boot version, and serial numbers.

The following table provides a typical form for recording the cards and modules installed in a NPT
shelf.

Table 2-1: Card and module inventory

Embedded
Card/Module type Slot Boot version Serial number
Version.

PAGE 4 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

3. POWER SUPPLY TEST:


3.1 Circuit breaker

At
AT XRAP/DCDB==NPT1200
xRAP/DCDB==NPT1010/1020/1050
MCB
Measured Voltage MCB Rating Measured Voltage
Rating
Power
10A
Supply A 32A/50A
Power 10A
32A/50A
Supply B

3.2 Specifications

Operating range -40 to -72 V


Idealistic Preferred Voltage -48 to -55 V
NPT-1200 MCB rating at XRAP/DCDB 50 Amp
NPT-1010/1050/1020 MCB rating at
XRAP/DCDB 10 Amp

3.3 Redundancy check

I/p O/P I/p O/P Alarm Alarm MUX Result


Power Power Power PWR on INF on INF State OK /
A on A on B on B on card A card B Not
XRAP XRAP XRAP XRAP OK
Test from MCB A -40 to 0V -40 to -40 to power no Working
XRAP/DCDB - OFF -70 V -70 V -70 V fail alarm
(both MCB MCB B alarm
in ON state - ON
at Power MCB A -40 to -40 to -40 to 0V no power Working
Supply) - ON -70 V -70 V -70 V alarm fail
MCB B alarm
- OFF

PAGE 5 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

3.4 DC and ground cables:

1) Power Plant to DCDB to xRAP – As Specified Yes No


2) Power Plant to xRAP – As Specified Yes No
3) Grounding cable from Yes No
Shelter Grounding Bar to Rack ground bar – As Specified
Grounding cable from Yes No
Rack ground bar to NPT-1200/1020 – As Specified
NPT 1200 Recommended 16sqmm Cable
NPT 1020/1050 Recommended 10sqmm Cable
NPT 1010 Recommended 10sqm Cable

4. Measuring Optical Levels


These measurements check optical signal levels at the various equipment ports. Before
performing any other commissioning test, proper optical levels within the limits specified in the
NPT-1200/1050/1020 Product Line System Specifications must be achieved for each optical
component.

Perform these measurements using an OPM configured according to the wavelength at the
measurement port. For reliable measurement, do not connect the OPM directly to a port but use
a two-meter fiber. When measuring high optical power levels, use attenuators to ensure that the
power does not exceed the maximum OPM input level.

The measured power levels:


 Must be within the range of minimum and maximum levels specified in the NPT Product Line
General
Description for the transceiver plug-in type installed on the corresponding port.
 Must be within the expected range according to the optical network plan.
It is usually sufficient to measure the optical levels at the receive ports only. A good port-receive
level indicates that the components in the optical path up to that port are properly connected and
operating normally. If the result is not satisfactory, perform additional measurements at the
transmit port in the remote site.

PAGE 6 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

Slot
Port SFP Wave Tx. Tx. Patch Error
numb Typ Length Power Power Receiver Rx ALS Cord Free
er e (dBm) (dBm) Sensitivity ( Check BER for
dBm)
Example By of for 3
LCT Module Insertion minutes
LR by Loss ( (OK/
Power OK / NOT
Meter NOT OK) OK )

PAGE 7 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

5. Maintenance Functions
5.1 Alarm Indications on Data Cards: for one port of each slot.

Card Type & Slot Number


ID Description

Link Fail.
5.1.1 (Electrical
port)
5.1.2 LOS (SFP)

Type
5.1.3
mismatch

5.1.4 Card Out

5.2 On Craft Terminal verify severity:

Critical/Major, Minor, Warning, Intermediate.

□ OK □ Not OK

5.3 Alarm Acknowledge:

Acknowledge all the alarms and verify cleared alarms disappear from the Current Alarm Window,
all the active alarm are acknowledge but still on the Current Alarm Window

□ OK □ Not OK

PAGE 8 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

6. Equipment Protection:
UNIT Force Manual JOJI Reset Button
Switch Switch
CPTS/CPS Switching OK □ OK □
A>B (Force Switch) Not OK□ Not OK □
CPTS/CPS Switching OK □
A->B (Manual Switch) Not OK□
CPTS/CPS Switching OK □
A->B (JOJI CPTS/CPS A) Not OK □
CPTS/CPS Switching OK □ OK □
B->A(Force Switch) Not OK□ Not OK □
CPTS/CPS Switching OK □
B->A (Manual Switch) Not OK□
CPTS/CPS Switching OK □
B->A (JOJI CPTS/CPS B) Not OK □

During CPTS/CPS switching as above check the manageability after switching completion

Result:

Manageability: □ YES □ NO

7. E1 Testing:
Take a Terminal Loop on the port and test the E1 on E1 BER meter.
E1 Tested (OK / E1 Tested (OK / E1 Tested (OK /
NOT OK) NOT OK) NOT OK)
1 22 43
2 23 44
3 24 45
4 25 46
5 26 47
6 27 48
7 28 49
8 29 50
9 30 51
10 31 52
11 32 53
12 33 54
13 34 55
14 35 56
15 36 57
16 37 58
17 38 59
18 39 60
PAGE 9 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

19 40 61
20 41 62
21 42 63

8. Ethernet (Opt/Elect port) Testing:


A. Testing of 1G/10G Optical Ethernet Port : Loop back the port and check the physical status of
the port
B. Testing of 1G Electrical Port : Connect the laptop to the physical port and check the port
physical status

Card Slot No Port No Card Slot No Port No

11. Artemis & MXD8: (Applicable only if it’s DWDM Site)


Insert the MXD8 is the ARTEMIS shelf to check the insertion loss

1. Measure the output power of the channel OTR/OTP


2. Connect the configured channel OTR /OTP to the channel port of the MXD8.
3. Connect Power meter to Line out of MXD and measure the power
4. You should receive power lesser than 2-4 db than the actual measured value of OTR/OTP

OTP10D_AL22(XCVR FOP DWDM 1559.79NM Power Range : 0 to +3 db


10GBS SFP+ 80KM LINEAR)
OTR10_AL21 CARD ASSY Power Range : 0 to +3 db

PAGE 10 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

10. Power ON and OFF Test:


Post completion of full configuration and tests the node has to be switched OFF and Switched ON.
Ensure all the configs are retained by the system and there is no loss of information.

Configuration Status: □ Retained

11. Measuring the Configured Frequency


Measuring the frequency of the OTR’s via NMS once configured on field during installation

Slot ( Card type) OTR Type Frequency

12. Amplifier Gain Check


Check the Amplifier Input and Output Power and Gain from NMS

Slot ( Card type) Amplifier Input Power Output Power Gain

PAGE 11 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

PAGE 12 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

PAGE 13 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

PAGE 14 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

PAGE 15 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

PAGE 16 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

Annex-H – Model Name and Node number table

Below tables represents model name and its abbreviation for


ECI Access Nodes (NPT 1020, 1021, 1050, 1200, 1600, 1800, 1010).

ECI Access Model Name Abbreviation Example


NPT 1020 Access N20 : PJ_MHLI_CH094_M01_C_X_EN20001
NPT 1021 Access N2 : PJ_MHLI_CH094_M01_C_X_EN21001
NPT 1050 Access N50 : PJ_MHLI_CH094_M01_C_X_EN50001
NPT 1200 Access N12 : PJ_MHLI_CH094_M01_C_X_EN12001
NPT 1600 Access N16 : PJ_MHLI_CH094_M01_C_X_ EN16001
NPT 1800 Access N18 : PJ_MHLI_CH094_M01_C_X_ EN18001
NPT 1010 Access N10 : PJ_MHLI_CH094_M01_C_X_ EN10001

Node Naming Format Description


Following shall be the Node name format capturing State, City, City location, Site type, Node
type, Subrack location, Vendor, Node name and node quantity.

Format - STATE_CITY_CITY LOCATION/SITE ID_SITE TYPE_NODE TYPE_SUBRACK


LOCATION/BG MEDIA_VENDORNODE NAMENODE QTY

XX_YYYY_SSSSS_TTT_Z_N_VMMMJJJ

XX - State
YYYY - City / Town
SSSSS - City Location
TTT - Site Type
Z - Node Type
N - Subrack Location/BG MEDIA
V - Vendor
MMM - Model Name
JJJ - Node No

PAGE 17 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

NOC Acceptance Document


To be Filled from NOC

Note: 1) Wherever it is NOT APPLICABLE please mention NA.


2) Record Observation/Deviations against each
prameters.

Verified
Verified by ECI Remark
Sl.No. Verifications Points by NOC
NE NMS Name as per plan
NE ID as per plan
No Duplicate NE ID
Site Name in system
NE
location/sitename
NE Time
NE Version
NE Consistancy in EMS

MCC IP & Subnet mask as per


plan
PE ID as per plan
MPLS ID as per plan
CCN should be enabled
OSPF area ID as
per plan only for
IP/DCN Check OSPF Area ID should be as per the connected
plan ports
NO duplicate PE ID in one MPLS
ID
GNE IP / Subnet as per plan with
proper ping response
Loop Back IP/ Subnet as per
plan with proper ping response

Sync defined as per plan


Sync ESMC Enable on WAN Ports
Check Priority as per plan

Next Hop MAC defined on WAN


port
CAC should be set as per
Guideline
COS should be set as per
Guideline
Topology
EXP BIT should be set on default
Create DiffServ Block and
Assigne B.W on MOE Port
Topology created with correct
ports as per the connectivity in
plan
PAGE 18 OF 18
VODAFONE NPT Acceptance Testing Document.

__________________________________________________________________________________________

ALS should be ON on each WAN


Optical Port
Optical Power Sheet

Eg. DHGE_8 card


not available on
Card Equipage
All cards inserted & equipped as TS7, while it is
per plan mentioned in plan

No alarms present
Masking/Non reporting of
Alarms
alarms on the connected port as
per the profile.

Power Supply NO Single Power supply


Observations