NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT – SEPTEMBER ‘19


Name of Work: -

Construction of Two Tunnel (Two tubes of Four lane each (in km 1+040 to km 2+790)
1.75km and km 3+440 to 12+360 (8.92km) for Missing Link under Capacity
Augmentation of Mumbai-Pune Expressway in the state of Maharashtra under EPC
Mode -Package-I.


PROJECT ALIGNMENT

MAHARASHTRA STATE ROAD DEVELOPMENT


Authority:
CORPORATION LTD. (MSRDC)
Authority Engineer: M/s GEODATA-LOUIS BERGER CONSORTIUM

EPC Contractor: M/s NAVAYUGA ENGINEERING COMPANY LTD.


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 1

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

S.No TABLE OF CONTENTS Page No


PROJECT DETAILS
1 INTRODUCTION 5
1.1 PROJECT DESCRIPTION 5
1.2 SCOPE OF THE PROJECT 5
1.3 PROJECT MILESTONES 6
1.4 SALIENT FEATURES 9
1.5 DETAILS OF CONSULTANT APPROVALS 10
FINANCIAL DETAILS
2.1 DETAILS OF PERFORMANCE SECURITY 12
STATUS OF PRECONSTRUCTION ACTIVITIES
3 SUMMARY OF PROGRESS 14
3.1 TUNNEL – I 14
3.2 TUNNEL - II 14
3.3 ADIT - I 15
3.4 ADIT - II 15
3.5 PROGRESS AT EACH LOCATION 15
3.6 MUCK DISPOSAL AREA 16
3.7 STATUS OF ESTABLISHMENT WORKS 16
3.8 STATUS OF PERMITS, LICENSES AND POLICIES 16
3.9 ENCUMBRANCES/INVENTORY 17
STATUS OF DESIGN AND DRAWINGS
4 STATUS OF DESIGN AND DRAWINGS 19
STATUS AND PROGRESS OF PROJECT AT TUNNEL-T2
STRIP CHART, RFI LOG SHEET AND LINE DIAGRAM ATTACHED AS
5 30
ANNEXURE-I, II, II & IV RESPECTIVELY
MAJOR PENDING ISSUES
6.1 LOCATION TUNNEL-T1 32
6.2 LOCATION ADIT-I 32
6.3 LOCATION ADIT-II 32
6.4 LOCATION TUNNEL-T2 32
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 2

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

6.5 ADDITIONAL LAND REQUIREMENT 33


DETAILS OF LAB EQUIPMENTS AVAILABLE AT SITE
7.1 DETAILS OF LAB EQUIPMENTS AVAILABLE AT SITE 35
7.2 CALIBRATION DETAILS FOR LABORATORY EQUIPMENTS 37
QA / QC RECORDS
8 STATUS OF APPROVALS 40
MONTHLY QUALITY CONTROL TESTS AS ON OCTOBER 2019
8.1 43
ATTACHED AS ANNEXURE-VI
STATUS OF MANPOWER
9 STATUS OF MANPOWER 45
9.1 MANPOWER ENGAGED ON DATE 46
9.2 ORGANIZATION CHART ATTACHED AS ANNEXURE-VII 47
DETAILS OF MAJOR EQUIPMENTS ON SITE
10 MAJOR EQUIPMENTS AVAILABLE ON SITE 49
WEATHER RECORD
11 WEATHER RECORD FOR THE MONTH OF OCTOBER’19 51
SAFETY REPORT
12 SAFETY REPORT FOR THE MONTH OF OCTOBER’19 54
12.1 MONTHLY MAN-HOUR DETAILS 54
12.2 ACCIDENT STATISTICS 54
12.3 TOOLBOX DETAILS 54
12.4 FIRE EXTINGUISHER AND FIRST AID 54
12.5 SHE ACTIVITIES PLANNED FOR THE MONTH OF NOVEMBER’19 56
12.6 MONTHLY HEALTH, SAFETY AND ENVIRONMENT REPORT 57
PROJECT PHOTOGRAPHS
13 LOCATION 59
13.1 ESTABLISHMENT WORKS-SITE OFFICE 59
13.2 ESTABLISHMENT WORKS-BATCHING PLANT 59
13.3 ESTABLISHMENT WORKS-LABORATORY 60
13.4 TUNNEL T-2 EXIT- EXECUTIVE ENGINEER SITE VISIT ON 03.10.2019 61
13.5 TUNNEL T-2-PROFILE MARKING FOR CROSS PASSAGE TUNNEL 62
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 3

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

13.6 TUNNEL T-2 EXIT – DRILLING 62


TUNNEL T-2 EXIT- LOADING AND CHARGING AT MAIN TUNNEL AND
13.7 63
CROSS PASSAGE TUNNEL
13.8 TUNNEL T-2 EXIT-MUCKING 64
13.9 TUNNEL T-2 EXIT- SCALING 65
13.10 TUNNEL T-2 EXIT- SHOTCRETING 65
13.11 TUNNEL T-2 EXIT- ROCKBOLTS 66
13.12 TUNNEL T-2 EXIT- DEWATERING AT T-2 EXIT (RHS) 67
13.13 TUNNEL T-2 EXIT- WORKABILITY TEST 67
13.14 TUNNEL T-2 EXIT- ROCK BOLT PULL OUT TEST 68
TUNNEL T-2 EXIT- COMPRESSION STRENGTH TESTING IN SITE
13.15 69
LABORATORY
13.16 TUNNEL T-2 EXIT- POLY FIBRE WASHING TEST 70
13.17 TUNNEL T-2 EXIT- FLEXURAL STRENGTH TEST 71
13.18 TUNNEL T-2 EXIT- UNCONFINED COMPRESSION STRENGTH TEST 72
ADIT-I -COMMENCEMENT OF ADIT-I OPEN EXCAVATION BY
13.19 SUPERINTENDENT ENGINEER AND EXECUTIVE ENGINEER ON 73
03.102019
ANNEXURES 75-146
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 4

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

PROJECT DETAILS
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 5

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

1. INTRODUCTION

1.1 PROJECT DESCRIPTION

Maharashtra State Road Development Corporation Limited (MSRDC) has


awarded “The Project Highway consists of Construction of Two Tunnel (Two Tubes of Four
Lane each on Km 1+040 to Km 2+790) 1.75km and Km 3+440 to 12+360 (8.92km) for Missing
Link Under Capacity Augmentation of Mumbai Pune Expressway In The State of
Maharashtra Under EPC Mode – Package-I” on EPC basis to M/s Navayuga Engineering
Company Limited.

The LOA for the project is 30.08.2018. The EPC agreement was signed on 11.10.2018 by
Maharashtra State Road Development Corporation Limited (MSRDC) and M/s Navayuga
Engineering Company Limited. The appointed date was declared as 21.02.2019 and the
scheduled completion date is 20.02.2022.

1.2 SCOPE OF THE PROJECT

The Scope of work broadly include the following:


Construction of Two Tunnel (Two Tubes of Four Lane each (on Km 1+040 to Km 2+790)
1.75km and Km 3+440 to 12+360 (8.92km) for Missing Link Under Capacity Augmentation
of Mumbai Pune Expressway.

Tunnel 1 (LHS)
Length 1750 m (including approaches)
Proper Tunnel: – 1660 m (from km 1090 to km 2750)
Entry Approach – 50 m (from km 1040 to km 1090)
Exit Approach – 40 m (from km 2750 to km 2790)
Tunnel 1 (RHS)
Length 1690 m (including approaches)
Proper Tunnel: – 1620 m (from km 1130 to km 2750)
Entry Approach – 30 m (from km 1100 to km 1130)
Exit Approach – 40 m (from km 2750 to km 2790)
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 6

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

Tunnel 2 (LHS)

Length 9860 m (including approaches)


Proper Tunnel: – 8890 m (from km 3470 to km 12360)
Entry Approach – 30 m (from km 3440 to km 3470)
Exit Approach – 940 m (from km 12360 to km 13300)

Tunnel 2 (RHS)

Length 9930 m (including approaches)


Proper Tunnel: – 8830 m (from km 3470 to km 12300)
Entry Approach – 40 m (from km 3430 to km 3470)
Exit Approach – 1060 m (from km 12300 to km 13360)
Cross section for all the tunnels (Excavation Line) = 212 Sqm
Perimeter for all main tunnel (Excavation Line) = 60 m
Height for all the tunnels (Excavation Line) = 10.49 m

1.3 PROJECT MILESTONES:

Schedule-J

I. Project Completion Schedule

During Construction period, the Contractor shall comply with the requirements set forth
Schedule J for each of the Project Milestones and the Scheduled Completion Date. Within
15 (fifteen) days of the date of each Project Milestone, the Contractor shall notify the
Authority of such compliance along with necessary particulars thereof.

II. Project Milestone I

 Project Milestone I shall occur on the date falling on the 220th (two hundred and
Twentieth) day from Appointed Date (the Project Milestone I).
 Prior to the occurrence of Project Milestone-I, the Contractor shall have commenced
construction of the Project Expressway and submitted to the Authority duly and
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 7

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

validly prepared Stage Payment Statements for an amount not less than 10% (ten
per cent) of the Contract Price.

III. Project Milestone II

 Project Milestone II shall occur on the date falling on the 435th (four hundred and
thirty fifth) day from Appointed Date (the Project Milestone II).
 Prior to the occurrence of Project Milestone-II, the Contractor shall have
commenced construction of the Project Expressway and submitted to the Authority
duly and calidly prepared Stage Payment Statements for an amount not less than
30% (thirty per cent) of the Contract Price.

IV. Project Milestone III

 Project Milestone III shall occur on the date falling on the 660th (six hundred and
Sixtieth) day from Appointed Date (the Project Milestone III).
 Prior to the occurrence of Project Milestone-III, the Contractor shall have
commenced construction of the Project Expressway and submitted to the Authority
duly and calidly prepared Stage Payment Statements for an amount not less than
55% (fifty five per cent) of the Contract Price.

V. Project Milestone IV

 Project Milestone IV shall occur on the date falling on the 875th (eight hundred and
seventy fifth) day from Appointed Date (the Project Milestone IV).
 Prior to the occurrence of Project Milestone-IV, the Contractor shall have
commenced construction of the Project Expressway and submitted to the Authority
duly and calidly prepared Stage Payment Statements for an amount not less than
80% (eighty per cent) of the Contract Price.

VI. Scheduled Completion Date

 The Scheduled Completion Date shall occur on the date falling on the 1095th (One
thousand and ninety fifth) day from the Appointed Date.
 On or before the Scheduled Completion Date, the Contractor shall have completed
construction in accordance with this Agreement.
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 8

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

VII. Extension of time


Upon extension of any or all the aforesaid Project Milestones or the Scheduled
Completion Date, as the case may be, under and in accordance with the provisions of this
Agreement, the Project Completion Schedule shall be deemed to have been amended
accordingly.

Project Milestone – I : 220th day from the Appointed date i.e 29.09.2019
Project Milestone – II : 435th day from the Appointed date i.e 01.05.2020
Project Milestone – III : 660th day from the Appointed date i.e 12.12.2020
Project Milestone – IV : 875th day from the Appointed date i.e 15.07.2021
Scheduled Completion Date : 1095th day from the Appointed date i.e 20.02.2022

Regarding Milestone I:

 As per Schedule-J Milestone-I shall occur on 220th day from the Appointed date i.e
29.09.2019. But the due to the reasons mentioned below the same could not be
achieved.
S.No Location Reasons
1 T-1 Start LHS
2 T-1 Start RHS
3 T-1 End LHS
The ROW is not provided.
4 T-1 End RHS
5 T-2 Start LHS
6 T-2 Start RHS
7 T-2 End LHS
ROW available since 10-05-2019 and
8 T-2 End RHS
Work is in progress at this location
9 Adit-1
The ROW is not provided.
10 Adit-2
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 9

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

 It is evident from above tabulation that the requirements of Article 8.2 are yet to be
fulfilled by the Authority and the work could not be initiated at 9 portals out of 10
due to which the achievement of Milestone-I is not possible.

 Hence it is hereby notified as required under Article 10.5.2, that the milestones
specified in schedule-J cannot be achieved due to the reasons specified in Article
10.5.1(a) of the contract and hence we request the Authority to defer the Milestone-I
as mentioned in Schedule-J to a date which may be decided after the fulfilment of the
requirements of article 8.2 of the Contract.

1.4 SALIENT FEATURES

Date of Project was awarded (LOA) : 30.08.2018


Date of EPC Agreement : 11.10.2018
Appointed Date : 21.02.2019
Date of Completion : 20.02.2022
EPC Cost : Rs 2697,39,00,000.00
Maintenance Period : 4 Years from the Date of Completion
Defects Liability Period : 4 Years from the Date of Provisional Certificate
Main Tunnel Length : 1.75 Kms(T1) & 8.92 Kms(T2)
Adit I Length as per Agreement : 832.5 Metres
Adit I Length as per Site Condition : 2397.63 Metres
Adit II Length as per Agreement : 925 Metres
Adit II Length as per Site Condition : 1018.25 Metres
Design Director : Mr. Ranjith Soman
Design Consultant : M/s Beaver Infra Consultants Pvt Ltd
Proof Consultant : M/s IIT (BHU) Varanasi
Safety Consultant : M/s Shweta Technophile Consultants Pvt Ltd
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 10

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

1.5 Details of Consultant Approvals

S.No Description Name of Firm Approved Vide Letter


1 Design Consultant M/s Beaver Infra MSRDC/YCEWML/46/2018/8692
Consultants Pvt Ltd dated: 12.12.2018
2 Proof Consultant M/s IIT (BHU) Varanasi MSRDC/YCEWML/25/2018 part-
VI/2019/5521 dated: 29.08.2019
3 Safety Consultant M/s Shweta Technophile SO-0012G0000 MGT dated: 15.03.2019
Consultants Pvt Ltd
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 11

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

FINANCIAL DETAILS
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 12

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

2.1 DETAILS OF PERFORMANCE SECURITY:

S.No Performance Value (in Rs.) Bank Issued Issued on Validity


Security
1 0999518BG0001624 134,86,95,000.00 State Bank of 01.10.2018 26.03.2023
India, Mumbai
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 13

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

STATUS OF
PRECONSTRUCTION
ACTIVITIES
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 14

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

3. SUMMARY OF PROGRESS

3.1 TUNNEL – I
T-1 RHS Start: Reserve forest clearance is obtained from the forest department. But tree
cutting permission was not received from the concerned department and ROW not Handed
over till date.
T-1 RHS END: Reserve forest clearance is obtained from the forest department. But tree
cutting permission was not received from the concerned department and ROW not Handed
over till date.
T-1 LHS Start: Reserve forest clearance is obtained from the forest department. But tree
cutting permission was not received from the concerned department and ROW not Handed
over till date.
T-1 LHS END: Reserve forest clearance is obtained from the forest department. But tree
cutting permission was not received from the concerned department and ROW not Handed
over till date.

3.2 TUNNEL – II

T-2 RHS Start: Reserve forest clearance is obtained from the forest department. But tree
cutting permission was not received from the concerned department and ROW not Handed
over till date.
T-2 RHS END:
1. The heading excavation work at Tunnel-II End RHS from Portal Face (Ch:12+300)
was started on 05.08.2019. As on 31.10.2019, 354.2 meters of heading excavation was
completed.
2. Tree cutting permission for Balance portion was not received till date.

T-2 LHS Start: Reserve forest clearance is obtained from the forest department. But tree
cutting permission was not received from the concerned department and ROW not Handed
over till date.

T-2 LHS END: Tree cutting permission was not received from the concerned department
and ROW not Handed over till date.
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 15

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

3.3 ADIT-I

Field surveys were carried out at the location of Adit-1 entry during the past few
months. The survey has established that there is a huge difference of over 210 meters in the
Ground levels specified in the tender drawings and the actual ground levels at the location
of Adit-1 entry. Due to this huge difference in the GLs, the execution of Adit-1 as specified
in the tender drawings/Schedule-B is a technical impossibility. The Change of location and
design of Adit-1 is necessary as the location and design specified in the Schedule-B is not
technically feasible.
After conducting joint surveys by Authority representatives, TL, AE and NECL, new
entry location of the Adit-1 and its cross section have been developed and the same has been
submitted to Authority vide letter Ref No: NEC/MPEW/2019-20/221 dated: 01.10.2019.

As per discussions held in the several meetings and directions given by the
Authority/ Authority Engineer, agreement registration of land required for the entry to
Adit-1 is in progress as the new design being proposed/developed.

Open Excavation was started on 03.10.2019 at Adit-I location.

3.4 ADIT-II
Land Acquisition by MSRDC is in process. Site not handed over yet.

3.5 PROGRESS AT EACH LOCATION:


S.No Location August’19 September’19 October’19 Total Running
Distance (in Metres)
1 T-1 LHS - - - -
2 T-1 RHS - - - -
3 T-2 LHS - - - -
4 T-2 RHS 69 134.3 150.9 354.2
5 ADIT-I - - - -
6 ADIT-II - - - -
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 16

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

3.6 MUCK DISPOSAL AREA:

Land for muck disposal at Pimploli is handed over by MSRDC on 04.05.2019. But due
the lack of Tree cutting permission at T-2 Exit LHS side construction of slip road to muck
disposal area could not be commenced.

3.7 STATUS OF ESTABLISHMENT WORKS:


S.No Description of work Status of Completion Remarks
/ Permits
1 Construction of Site Office Completed
2 Construction of Store Completed
3 Construction of Laboratory Minor Works in
Progress
4 Erection of Batching Plant (AJAX Completed Consent to
FIORI 30 CUM) establish obtained

3.8 STATUS OF PERMITS, LICENSES AND POLICIES:

S.No Description Status Remarks

1 Labour License Obtained Valid upto


31/12/2019
2 Explosive License Obtained Valid upto
23/12/2019
3 Pollution Control Board Consent to establish Commissioning of
obtained project or 5 years
whichever is earlier
4 Inventory Inventory for Signed and
Tunnel-2 End point submitted.
(2 Km) completed
5 Workman Compensation (WC) Policy Obtained Valid upto
23/06/2020
6 Building and Other Construction Obtained Valid upto
Workers Act (BOCW) 09/07/2022
7 Contractor’s All Risk Policy (CAR) Obtained Valid upto
09/08/2022
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 17

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

3.9 ENCUMBRANCES / INVENTORY:

Encumbrance data has been collected through joint survey at T-2 End from Chainage
58+000 to 60+000 (2 Kms). The Inventory has been mutually signed and submitted to parties
(Navayuga Engineering Co Ltd, IRB Infrastructure Developers Ltd, STUP Consultants Pvt
Ltd, Geodata-Louis Berger JV & MSRDC Ltd) involved in joint survey for further action.
Inventory attached as Annexure-I along with this report.
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 18

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

STATUS OF DESIGN AND


DRAWINGS
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 19

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

4. STATUS OF DESIGN AND DRAWINGS:

S.No Drawing No. Description Drawing Submitted Approval Remarks


by AE
R0 R1
1 BIC-MPEW-P&P- PLAN & PROFILE LHS 26-02-19 28-05-19
LHS-01 SIDE
2 BIC-MPEW-P&P- PLAN & PROFILE LHS 26-02-19 28-05-19
LHS-02 SIDE
3 BIC-MPEW-P&P- PLAN & PROFILE LHS 26-02-19 28-05-19
LHS-03 SIDE
4 BIC-MPEW-P&P- PLAN & PROFILE LHS 26-02-19 28-05-19
LHS-04 SIDE
5 BIC-MPEW-P&P- PLAN & PROFILE LHS 26-02-19 28-05-19
LHS-05 SIDE
6 BIC-MPEW-P&P- PLAN & PROFILE LHS 26-02-19 28-05-19
LHS-06 SIDE
7 BIC-MPEW-P&P- PLAN & PROFILE LHS 26-02-19 28-05-19
LHS-07 SIDE
8 BIC-MPEW-P&P- PLAN & PROFILE LHS 26-02-19 28-05-19
LHS-08 SIDE
9 BIC-MPEW-P&P- PLAN & PROFILE LHS 26-02-19 28-05-19
LHS-09 SIDE
10 BIC-MPEW-P&P- PLAN & PROFILE LHS 26-02-19 28-05-19
LHS-10 SIDE
11 BIC-MPEW-P&P- PLAN & PROFILE LHS 26-02-19 28-05-19
LHS-11 SIDE
12 BIC-MPEW-P&P- PLAN & PROFILE LHS 26-02-19 28-05-19
LHS-12 SIDE
13 BIC-MPEW-P&P- PLAN & PROFILE LHS 26-02-19 28-05-19
LHS-13 SIDE
14 BIC-MPEW-P&P- PLAN & PROFILE LHS 26-02-19 28-05-19
LHS-14 SIDE
15 BIC-MPEW-P-T2 PLAN FOR TUNNEL-T2 26-02-19 28-05-19
EXIT-01 EXIT LOCATION

16 BIC-MPEW-P&P- PLAN & PROFILE RHS 26-02-19 28-05-19


RHS-01 SIDE
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 20

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

17 BIC-MPEW-P&P- PLAN & PROFILE RHS 26-02-19 28-05-19


RHS-02 SIDE
18 BIC-MPEW-P&P- PLAN & PROFILE RHS 26-02-19 28-05-19
RHS-03 SIDE
19 BIC-MPEW-P&P- PLAN & PROFILE RHS 26-02-19 28-05-19
RHS-04 SIDE
20 BIC-MPEW-P&P- PLAN & PROFILE RHS 26-02-19 28-05-19
RHS-05 SIDE
21 BIC-MPEW-P&P- PLAN & PROFILE RHS 26-02-19 28-05-19
RHS-06 SIDE
22 BIC-MPEW-P&P- PLAN & PROFILE RHS 26-02-19 28-05-19
RHS-07 SIDE
23 BIC-MPEW-P&P- PLAN & PROFILE RHS 26-02-19 28-05-19
RHS-08 SIDE
24 BIC-MPEW-P&P- PLAN & PROFILE RHS 26-02-19 28-05-19
RHS-09 SIDE
25 BIC-MPEW-P&P- PLAN & PROFILE RHS 26-02-19 28-05-19
RHS-10 SIDE
26 BIC-MPEW-P&P- PLAN & PROFILE RHS 26-02-19 28-05-19
RHS-11 SIDE
27 BIC-MPEW-P&P- PLAN & PROFILE RHS 26-02-19 28-05-19
RHS-12 SIDE
28 BIC-MPEW-P&P- PLAN & PROFILE RHS 26-02-19 28-05-19
RHS-13 SIDE
29 BIC-MPEW-P&P- PLAN & PROFILE RHS 26-02-19 28-05-19
RHS-14 SIDE
30 BIC-MPEW-P-T2 PLAN AND CROSS 26-02-19 28-05-19
EXIT-02 SECTIONS AT T2 EXIT
LOCATION
31 BIC/MSRDC/MPEW/P PLAN AND CROSS 26-02-19 28-05-19
A/02 SECTIONS AT T2 EXIT
LOCATION
32 BIC/MSRDC/MPEW/P PRIMARY LINING 30-07-19
A/04 SUPPORT OF PORTAL
AREA
33 BIC/MSRDC/MPEW/T LATTICE GIRDER OF 30-07-19
/47 (Sheet 01 of 04) PORTAL AREA
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 21

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

34 BIC/MSRDC/MPEW/T INITIAL CONSTRUCTION 30-07-19


/47 (Sheet 02 of 04) PLAN FOR T-2 EXIT
LOCATION
35 BIC/MSRDC/MPEW/T INITIAL CONSTRUCTION 30-07-19
/47 (Sheet 03 of 04) PLAN FOR T-2 EXIT
LOCATION
36 BIC/MSRDC/MPEW/T INITIAL CONSTRUCTION 30-07-19
/47 (Sheet 04 of 04) PLAN FOR T-2 EXIT
LOCATION
37 BICPL/MPEW/DR/T- DETAILED DESIGN 10-07-19
1&2/R0 REPORT FOR TUNNEL IN
MISSING LINK
38 BIC-MPEW-P&P- PLAN & PROFILE LHS 10-07-19
LHS-01 SIDE

39 BIC-MPEW-P&P- PLAN & PROFILE LHS 10-07-19


LHS-02 SIDE

40 BIC-MPEW-P&P- PLAN & PROFILE LHS 10-07-19


LHS-03 SIDE

41 BIC-MPEW-P&P- PLAN & PROFILE LHS 10-07-19


LHS-04 SIDE

42 BIC-MPEW-P&P- PLAN & PROFILE LHS 10-07-19


LHS-05 SIDE

43 BIC-MPEW-P&P- PLAN & PROFILE LHS 10-07-19


LHS-06 SIDE

44 BIC-MPEW-P&P- PLAN & PROFILE LHS 10-07-19


LHS-07 SIDE

45 BIC-MPEW-P&P- PLAN & PROFILE LHS 10-07-19


LHS-08 SIDE
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 22

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

46 BIC-MPEW-P&P- PLAN & PROFILE LHS 10-07-19


LHS-09 SIDE

47 BIC-MPEW-P&P- PLAN & PROFILE LHS 10-07-19


LHS-10 SIDE

48 BIC-MPEW-P&P- PLAN & PROFILE LHS 10-07-19


LHS-11 SIDE

49 BIC-MPEW-P&P- PLAN & PROFILE LHS 10-07-19


LHS-12 SIDE

50 BIC-MPEW-P&P- PLAN & PROFILE LHS 10-07-19


LHS-13 SIDE

51 BIC-MPEW-P&P- PLAN & PROFILE LHS 10-07-19


LHS-14 SIDE

52 BIC-MPEW-P-T2 PLAN FOR TUNNEL-T2 10-07-19


EXIT-01 EXIT LOCATION

53 BIC-MPEW-P&P- PLAN & PROFILE RHS 10-07-19


RHS-01 SIDE

54 BIC-MPEW-P&P- PLAN & PROFILE RHS 10-07-19


RHS-02 SIDE

55 BIC-MPEW-P&P- PLAN & PROFILE RHS 10-07-19


RHS-03 SIDE

56 BIC-MPEW-P&P- PLAN & PROFILE RHS 10-07-19


RHS-04 SIDE

57 BIC-MPEW-P&P- PLAN & PROFILE RHS 10-07-19


RHS-05 SIDE
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 23

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

58 BIC-MPEW-P&P- PLAN & PROFILE RHS 10-07-19


RHS-06 SIDE

59 BIC-MPEW-P&P- PLAN & PROFILE RHS 10-07-19


RHS-07 SIDE

60 BIC-MPEW-P&P- PLAN & PROFILE RHS 10-07-19


RHS-08 SIDE

61 BIC-MPEW-P&P- PLAN & PROFILE RHS 10-07-19


RHS-09 SIDE

62 BIC-MPEW-P&P- PLAN & PROFILE RHS 10-07-19


RHS-10 SIDE

63 BIC-MPEW-P&P- PLAN & PROFILE RHS 10-07-19


RHS-11 SIDE

64 BIC-MPEW-P&P- PLAN & PROFILE RHS 10-07-19


RHS-12 SIDE

65 BIC-MPEW-P&P- PLAN & PROFILE RHS 10-07-19


RHS-13 SIDE

66 BIC-MPEW-P&P- PLAN & PROFILE RHS 10-07-19


RHS-14 SIDE

67 BIC-MPEW-P-T2 PLAN AND CROSS 10-07-19


EXIT-02 SECTIONS AT T2 EXIT
LOCATION
68 BIC-MSRDC-MPEW- PLAN AND CROSS 10-07-19
P-T2 EXIT-02 SECTIONS AT T2 EXIT
LOCATION
69 BIC/MSRDC/MPEW/T NATM TUNNEL GENERAL 10-07-19
/01 NOTES SHEET 1 OF 2
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 24

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

70 BIC/MSRDC/MPEW/T NATM TUNNEL GENERAL 10-07-19


/02 NOTES SHEET 2 OF 2

71 BIC/MSRDC/MPEW/P PRIMARY LINING 10-07-19


A/03 SUPPORT DETAILS OF
PORTAL AREA
72 BIC/MSRDC/MPEW/P SECONDARY LINING 10-07-19
A/04 SUPPORT DETAILS OF
PORTAL AREA
73 BIC/MSRDC/MPEW/T LATTICE GIRDER 10-07-19
/05 DETAILS OF PORTAL
AREA
74 BIC/MSRDC/MPEW/T GAD FOR ADIT 1 & 2 10-07-19
/06 PORTAL AREA

75 BIC/MSRDC/MPEW/T SUPPORT DETAILS FOR 10-07-19


/07 ADIT 1 &2 PORTAL AREA

76 BIC/MSRDC/MPEW/T GAD MAIN FOR MAIN 10-07-19


/08 TUNNEL FOR “CLASS - A”
ROCK TYPE
77 BIC/MSRDC/MPEW/T SUPPORT DETAILS OF 10-07-19
/09 MAIN TUNNEL FOR
“CLASS - A” ROCK TYPE
78 BIC/MSRDC/MPEW/T GAD FOR CROSS- 10-07-19
/10 PASSAGE TUNNEL FOR
“CLASS - A” ROCK TYPE
79 BIC/MSRDC/MPEW/T SUPPORT DETAILS OF 10-07-19
/11 CROSS-PASSAGE TUNNEL
FOR “CLASS - A” ROCK
TYPE
80 BIC/MSRDC/MPEW/T GAD FOR ADIT TUNNEL 10-07-19
/12 FOR “CLASS - A” ROCK
TYPE
81 BIC/MSRDC/MPEW/T SUPPORT DETAILS OF 10-07-19
/13 ADIT TUNNEL FOR
“CLASS - A” ROCK TYPE
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 25

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

82 BIC/MSRDC/MPEW/T GAD FOR LAY-BAY 10-07-19


/14 TUNNEL FOR “CLASS - A”
ROCK TYPE
83 BIC/MSRDC/MPEW/T SUPPORT DETAILS OF 10-07-19
/15 LAY-BAY TUNNEL FOR
“CLASS - A” ROCK TYPE
84 BIC/MSRDC/MPEW/T GAD MAIN FOR MAIN 10-07-19
/16 TUNNEL FOR “CLASS - B”
ROCK TYPE
85 BIC/MSRDC/MPEW/T SUPPORT DETAILS OF 10-07-19
/17 MAIN TUNNEL FOR
“CLASS - B” ROCK TYPE
86 BIC/MSRDC/MPEW/T GAD FOR CROSS- 10-07-19
/18 PASSAGE TUNNEL FOR
“CLASS - B” ROCK TYPE
87 BIC/MSRDC/MPEW/T SUPPORT DETAILS OF 10-07-19
/19 CROSS-PASSAGE TUNNEL
FOR “CLASS - B” ROCK
TYPE
88 BIC/MSRDC/MPEW/T GAD FOR ADIT TUNNEL 10-07-19
/20 FOR “CLASS - B” ROCK
TYPE
89 BIC/MSRDC/MPEW/T SUPPORT DETAILS OF 10-07-19
/21 ADIT TUNNEL FOR
“CLASS - B” ROCK TYPE
90 BIC/MSRDC/MPEW/T GAD FOR LAY-BAY 10-07-19
/22 TUNNEL FOR “CLASS - B”
ROCK TYPE
91 BIC/MSRDC/MPEW/T SUPPORT DETAILS OF 10-07-19
/23 LAY-BAY TUNNEL FOR
“CLASS - B” ROCK TYPE
92 BIC/MSRDC/MPEW/T GAD MAIN FOR MAIN 10-07-19
/24 TUNNEL FOR “CLASS - C”
ROCK TYPE
93 BIC/MSRDC/MPEW/T SUPPORT DETAILS OF 10-07-19
/25 MAIN TUNNEL FOR
“CLASS - C” ROCK TYPE
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 26

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

94 BIC/MSRDC/MPEW/T GAD FOR CROSS- 10-07-19


/26 PASSAGE TUNNEL FOR
“CLASS - C” ROCK TYPE
95 BIC/MSRDC/MPEW/T SUPPORT DETAILS OF 10-07-19
/27 CROSS-PASSAGE TUNNEL
FOR “CLASS - C” ROCK
TYPE
96 BIC/MSRDC/MPEW/T GAD FOR ADIT TUNNEL 10-07-19
/28 FOR “CLASS - C” ROCK
TYPE
97 BIC/MSRDC/MPEW/T SUPPORT DETAILS OF 10-07-19
/29 ADIT TUNNEL FOR
“CLASS - C” ROCK TYPE
98 BIC/MSRDC/MPEW/T GAD FOR LAY-BAY 10-07-19
/30 TUNNEL FOR “CLASS - C”
ROCK TYPE
99 BIC/MSRDC/MPEW/T SUPPORT DETAILS OF 10-07-19
/31 LAY-BAY TUNNEL FOR
“CLASS - C” ROCK TYPE
100 BIC/MSRDC/MPEW/T GAD MAIN FOR MAIN 10-07-19
/32 TUNNEL FOR “CLASS - D”
ROCK TYPE (LHS & RHS)
101 BIC/MSRDC/MPEW/T PRIMARY LINING 10-07-19
/33 SUPPORT DETAILS OF
MAIN TUNNEL FOR
“CLASS - D” ROCK TYPE
102 BIC/MSRDC/MPEW/T SECONDARY LINING 10-07-19
/34 SUPPORT DETAILS OF
MAIN TUNNEL FOR
“CLASS - D” ROCK TYPE
103 BIC/MSRDC/MPEW/T GAD MAIN FOR CROSS- 10-07-19
/35 PASSAGE TUNNEL FOR
“CLASS - D” ROCK TYPE
(LHS & RHS)
104 BIC/MSRDC/MPEW/T PRIMARY SUPPORT 10-07-19
/36 DETAILS FOR CROSS
PASSAGE TUNNEL FOR
“CLASS - D” ROCK TYPE
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 27

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

105 BIC/MSRDC/MPEW/T SECONDARY SUPPORT 10-07-19


/37 DETAILS FOR CROSS
PASSAGE TUNNEL FOR
“CLASS - D” ROCK TYPE
106 BIC/MSRDC/MPEW/T GAD FOR ADIT TUNNEL 10-07-19
/38 FOR “CLASS - D” ROCK
TYPE
107 BIC/MSRDC/MPEW/T PRIMARY SUPPORT 10-07-19
/39 DETAILS FOR ADIT
TUNNEL FOR “CLASS - D”
ROCK TYPE
108 BIC/MSRDC/MPEW/T SECONDARY SUPPORT 10-07-19
/40 DETAILS FOR ADIT
TUNNEL FOR “CLASS - D”
ROCK TYPE
109 BIC/MSRDC/MPEW/T GAD AND PLAN FOR 10-07-19
/41 LAYBAY FOR “CLASS - D”
ROCK TYPE
110 BIC/MSRDC/MPEW/T PRIMARY LINING 10-07-19
/42 SUPPORT OF LAYBAY FOR
“CLASS - D” ROCK TYPE
111 BIC/MSRDC/MPEW/T SECONDARY LINING 10-07-19
/43 SUPPORT OF LAYBAY FOR
“CLASS - D” ROCK TYPE
112 BIC/MSRDC/MPEW/T SUMMARY OF PRIMARY 10-07-19
/44 AND SECONDARY
SUPPORTS FOR ALL
CLASS ROCK TYPES
(SHEET 1 OF 2)
113 BIC/MSRDC/MPEW/T SUMMARY OF PRIMARY 10-07-19
/44 AND SECONDARY
SUPPORTS FOR ALL
CLASS ROCK TYPES
(SHEET 2 OF 2)
114 BIC/MSRDC/MPEW/T TEMPORARY 10-07-19
/45 (SHEET 01 OF 04) CONSTRUCTION PLAN
FOR TUNNEL T-2 EXIT
LOCATION
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 28

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

115 BIC/MSRDC/MPEW/T TEMPORARY 10-07-19


/45 (SHEET 02 OF 04) CONSTRUCTION PLAN
FOR TUNNEL T-2 EXIT
LOCATION
116 BIC/MSRDC/MPEW/T TEMPORARY 10-07-19
/45 (SHEET 03 OF 04) CONSTRUCTION PLAN
FOR TUNNEL T-2 EXIT
LOCATION
117 BIC/MSRDC/MPEW/T TEMPORARY 10-07-19
/45 (SHEET 04 OF 04) CONSTRUCTION PLAN
FOR TUNNEL T-2 EXIT
LOCATION
118 BIC/MSRDC/MPEW/T INSTRUMENTATION FOR 10-07-19
/46 MONITORING IN
TUNNELS
119 BIC/MSRDC/MPEW/T TUNNEL T1 START AREA 10-07-19
/47 (RHS)

120 BIC/MSRDC/MPEW/T TUNNEL T1 END AREA 10-07-19


/48 (RHS)

121 BIC/MSRDC/MPEW/T TUNNEL T1 START AREA 10-07-19


/49 (LHS)

122 BIC/MSRDC/MPEW/T TUNNEL T1 END AREA 10-07-19


/50 (LHS)

123 BIC/MSRDC/MPEW/T TUNNEL T2 START AREA 10-07-19


/51 (LHS)

124 BIC/MSRDC/MPEW/T TUNNEL T2 START AREA 10-07-19


/52 (RHS)

125 BIC/MSRDC/MPEW/T PERMANENT 10-07-19


/53 EXCAVATION PLAN FOR
T-2 EXIT
126 BIC/MSRDC/MPEW/T PERMANENT 10-07-19
/54 EXCAVATION PLAN &
CROSS-SECTIONS FOR T-2
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 29

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

EXIT

127 BIC/MSRDC/MPEW/T CROSS-SECTIONS AT T-2 10-07-19


/55 EXIT LOCATION

128 BIC/MSRDC/MPEW/T CROSS-SECTIONS AT T-2 10-07-19


/56 EXIT LOCATION
(CH:12+300) MONITORING
PLAN AT OPEN CUT
PORTION
129 BIC/MSRDC/MPEW/T PORTAL BACK SLOPE AT 10-07-19
/57 CH: 12+300

130 BIC/MSRDC/MPEW/T CROSS SECTION OF SUB- 10-07-19


/58 STATION WITH CROSS-
PASSAGE FOR CLASS-C
ROCK TYPE
131 BIC/MSRDC/MPEW/T GAD FOR HORIZONTAL 10-07-19
/59 (SHEET 01 OF 02) SLABING PORTION

132 BIC/MSRDC/MPEW/T SUPPORT DETAILS OF 10-07-19


/59 (SHEET 02 OF 02) HORIZONTAL SLABING
PORTION
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 30

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

STATUS & PROGRESS OF


THE PROJECT
(Strip Charts, RFI Log Sheet
and Line Diagram attached as
Annexure-II, Annexure-III &
Annexure-IV respectively)
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 31

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

MAJOR PENDING ISSUES


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 32

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

6. MAJOR PENDING ISSUES:

6.1 LOCATION TUNNEL-T1:

Forest Clearance obtained, But Tree cutting permission by Forest Department is


pending at Tunnel -1 start & end portion. The same has been conveyed to Authority &
Authority Engineer vide our Letter: NEC/MPEW/2018-19/155 dated: 22.07.2019 and
NEC/MPEW/2018-19/181 dated: 14.08.2019.

6.2 LOCATION ADIT-I:

Land Acquisition is still in progress. The ROW is not handed over till date.

6.3 LOCATION ADIT-II:

Land Acquisition by MSRDC is still in progress. The ROW is not handed over till
date. The same has been conveyed to the Authority & the Authority Engineer vide our
Letter: NEC/MPEW/2018-19/155 dated: 22.07.2019 and NEC/MPEW/2018-19/181 dated:
14.08.2019.

6.4 LOCATION TUNNEL-T2:

 Localites from Dongargaon obstructed blasting work creating hindrance to the


progress of the project which has been addressed to The Authority vide Letter No.
NEC/MPEW/2018-19/098 dated 31.05.2019.

 Concerns from Dongargaon localites was addressed by Mr. Sanjay Gangurde,


Executive Engineer, MSRDC vide meeting held in NEC Site Office, Lonavala on
31.08.2019. Dongargaon localites claimed that the blasting work has damaged their
roof and walls and NEC has to compensate for it.

 ROW at Tunnel -2 start is not handed over yet. Tree cutting permission for balance
portion of Tunnel-2 end is pending from Forest Department due to which
construction of slip road for muck disposal activities could not be commenced and
hence large amount of muck is being deposited in the Kusgaon Camp area itself.
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 33

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

 The same has been conveyed to Authority & Authority Engineer vide our Letters:
NEC/MPEW/2018-19/155 dated: 22.07.2019 and NEC/MPEW/2018-19/181 dated:
14.08.2019.

 As per Clause 14, Revised Schedule B of Volume-III, abandoned quarry plots at


Kusgaon village, upto an extent of 48 Hectares and at Waksai and Devghar villages
upto an extent of 6 hectares has been identified as Muck Disposal areas. But the muck
disposal area at Pimploli has been handed over to us which is about 10-15 Kms one-
way from the Portal face (T-2 Exit). Dumpers carrying muck has to travel around 20-
30 Kms to collect the muck, dispose and return back to the work front. This
enormously increases the cost of mucking activities. By stating the above reasons,
NECL has requested to The Authority and The Authority Engineer vide letter no.
NEC/MPEW/2019-20/228 dated 09.10.2019 for handing over the muck disposal areas
at Kusgaon, Waksai and Devghar at the earliest to reduce the cost and time of the
project.

6.5 ADDITIONAL LAND REQUIREMENT:

Field surveys were carried out at the exit of Tunnel T-1 and T-2 entry and Adit-1 on
15.04.2019. The survey has established that there is a huge difference in the Ground levels
specified in the Tender drawings and the actual ground levels at site. This difference is over
40 meters at the tunnel entry/exit.

As per the meeting held with The Authority on 25th September-2019, AE and NECL
informed that the location of the tunnel portals at the locations specified in the tender
drawings/Schedule-B is a technical impossibility and hence the tunnel portals are to be
located at locations that are technically feasible. The approaches from the tunnel portals to
the contract chainages would involve construction of high embankments of upto 40-45
metres height. Construction of such high embankments is technically impossible within the
proposed ROW and hence it requires additional land.

The same has been conveyed to The Authority vide our letter no. NEC/MPEW/2019-
20/219 dated 01.10.2019.
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 34

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

DETAILS OF LAB
EQUIPMENT AVAILABLE
ON SITE
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 35

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

7.1 Details of Lab Equipments available on Site:


S.No Sub. Equipment
Name Unit Available Remarks
No

A: GENERAL
1 Electronic Balance
1.1 600 gms Capacity Electronic Balance Accuracy Least count
0.01gm Nos 1

1.2 30 Kg Capacity Electronic Balance Accuracy 1gm Nos 1


1.3 10 Kg Capacity Electronic Balance Accuracy 1gm Nos 1
1.4 5 Kg Capacity Electronic Balance Accuracy 0.5gm Nos 1
2 IS Sieves
2.1 IS Sieves 200MM Internal dia ( 1 set) Set 1
2.2 IS Sieves 300MM Internal dia ( 1 set) Set 1
2.3 IS Sieves 450MM Internal dia ( 1 set) Set 1
B: FOR SOIL
3 3.1 Modified Proctor Have Compaction Test apparatus with
complete set up (2250cc) Set 1

3.2 Modified Proctor Lite Compaction Test apparatus with


complete set up (1000cc) Set 1

3.3 Liquid Limit Device (Casagrande Apparatus) Nos 1


3.4 Liquid Limit Device (Cone Penetrometer) Nos 1
3.5 Core Cutters Nos 1
3.6 Core Cutter Dolly Nos 3
3.7 Pycnometer Bottles Nos 1
3.8 Scoops 500 gm Nos 1
3.9 Spatula 8" Nos 1

3.10 California Bearing Ratio Apparatus (Mechanical/ Electrically Nos 1


operated)
3.11 California Bearing Ratio Mould Nos 12
3.12 CBR Base Plate Nos 6
3.13 Surcharge Weight Nos 20
3.14 Proving Ring 30 KN Nos 2
3.15 Proving Ring 50 KN Nos 1
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 36

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

3.16 Rapid Moisture meter complete with chemicals Nos 2


3.17 Rubber Hammer Nos 1
3.18 Thermostatically controller of hot air oven 50 or 300c Nos 1
C: FOR CEMENT
4 4.1 Concrete Cube Mould size 150*150*150mm Nos 147
4.2 Compression Testing Machine (CTM) Nos 2
4.3 Concrete Baby pan Mixer Nos 2
4.4 Slump cone Apparatus Set 11
4.5 Aggregate Impact value Apparatus Nos 2
4.6 Aggregate Crushing value Apparatus Nos 2
4.7 Flakiness Index Gauge Test apparatus Nos 2
4.8 Elongation Index Gauge test apparatus Nos 2
4.9 Bulk density Cylinder capacity 3 lit Nos 1
4.10 Bulk Density Cylinders Capacity 15 lit Nos 2
4.11 Vibrating Machine (Mortar cubes) Nos 1
4.12 Concrete Cube Mould size 70.6*70.6.70.6mm Nos 32
4.13 Pycnometer Bottle- 1 liter cap. (Specific Gravity Test) Nos 3
4.14 Wire Basket for sp.gr. Test Density test Nos 2
4.15 Le-Chateliers Mould Nos 5
General Item as per size Requirement
5 5.1 Measuring Jars (PVC) Set 1
5.2 Measuring Jars (Borosil) Set 1
5.3 ENAMEL Trays Set 1
5.4 CBR Filter paper size 150mm dia Nos 50
5.5 Core cutting Machine with Bit Set 2
5.6 Rock Bolt Pull-out testing apparatus Set 1
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 37

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

7.2 Calibration Details for Laboratory Equipment:

Next
S.No Name of Equipment Qty. Date of Calibration Calibration
Due on
1 Compression Testing Machine 1 12.08.2019 12.08.2020
2 Electronics Weighing balance (30 Kg) 1 12.08.2019 12.08.2020
3 Electronics Weighing balance (30 Kg) 1 12.08.2019 12.08.2020
4 Hot air Oven 1 12.08.2019 12.08.2020
5 Digital Temp Controller of Thin Film Oven 1 12.08.2019 12.08.2020
6 Water Bath 1 12.08.2019 12.08.2020
Pull Out machine Pressure Gauge (Upto 30
7 tonnes) 1 12.08.2019 12.08.2020
8 Sieve Shaker (Motorized) 1 12.08.2019 12.08.2020
9 Density Bucket (15 L) 1 12.08.2019 12.08.2020
10 Density Bucket (3 L) 1 12.08.2019 12.08.2020
11 Pycnometer Bottle 1 12.08.2019 12.08.2020
12 Wire Bucket 1 12.08.2019 12.08.2020
13 Marsh Cone 1 12.08.2019 12.08.2020
14 Proctor Compaction Mould 1 12.08.2019 12.08.2020
15 Sand Replace Test Apparatus (Light) 1 12.08.2019 12.08.2020
16 Sand Replace Test Apparatus (Field) 1 12.08.2019 12.08.2020
17 Cement Mortar Cube Vibrating Machine 1 12.08.2019 12.08.2020
18 Aggregate Impact Value Apparatus 1 12.08.2019 12.08.2020
19 Measuring Cylinder(100ml) 1 14.08.2019 14.08.2020
20 Measuring Cylinder(500ml) 1 14.08.2019 14.08.2020
21 Measuring Cylinder(1000ml) 1 14.08.2019 14.08.2020
22 Measuring Cylinder(250ml) 1 14.08.2019 14.08.2020
Specific Gravity Hydrometer (1.00 to 1.500
23 Range) 1 14.08.2019 14.08.2020
24 Vernier Caliper(0-200mm) 1 14.08.2019 14.08.2020
25 Dial Gauge(0-25mm) 1 14.08.2019 14.08.2020
26 Test Sieve (Brass) 4.75mm 1 14.08.2019 14.08.2020
27 Test Sieve (Brass) 2.36mm 1 14.08.2019 14.08.2020
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 38

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

28 Test Sieve (Brass) 1.18mm 1 14.08.2019 14.08.2020


29 Test Sieve (Brass) 600 Mic 1 14.08.2019 14.08.2020
30 Test Sieve (Brass) 425Mic 1 14.08.2019 14.08.2020
31 Test Sieve (Brass) 300 Mic 1 14.08.2019 14.08.2020
32 Test Sieve (Brass) 150 Mic 1 14.08.2019 14.08.2020
33 Test Sieve (Brass) 75 Mic 1 14.08.2019 14.08.2020
34 Test Sieve (Brass) 90 Mic 1 14.08.2019 14.08.2020
35 Test Sieve (Brass) 2 mm 1 14.08.2019 14.08.2020
36 Test Sieve (GI) 80 mm 1 14.08.2019 14.08.2020
37 Test Sieve (GI) 75 mm 1 14.08.2019 14.08.2020
38 Test Sieve (GI) 63 mm 1 14.08.2019 14.08.2020
39 Test Sieve (GI) 53 mm 1 14.08.2019 14.08.2020
40 Test Sieve (GI) 50 mm 1 14.08.2019 14.08.2020
41 Test Sieve (GI) 40 mm 1 14.08.2019 14.08.2020
42 Test Sieve (GI) 31.5 mm 1 14.08.2019 14.08.2020
43 Test Sieve (GI) 25 mm 2 14.08.2019 14.08.2020
44 Test Sieve (GI) 20 mm 1 14.08.2019 14.08.2020
45 Test Sieve (GI) 16 mm 1 14.08.2019 14.08.2020
46 Test Sieve (GI) 12.5 mm 1 14.08.2019 14.08.2020
47 Test Sieve (GI) 10 mm 1 14.08.2019 14.08.2020
48 Test Sieve (GI) 6.3 mm 1 14.08.2019 14.08.2020
49 Test Sieve (GI) 4.75 mm 1 14.08.2019 14.08.2020
50 Test Sieve (GI) 2.36 mm 1 14.08.2019 14.08.2020
51 Rapid Moisture Meter 1 14.08.2019 14.08.2020
52 Cube Mould(150mm×150mm×150mm) 24 13.08.2019 13.08.2020
53 Cube Mould(70.6mm×70.6mm×70.6mm) 9 13.08.2019 13.08.2020
54 Vicat Apparatus 1 13.08.2019 13.08.2020
55 Flakiness Gauge 1 13.08.2019 13.08.2020
56 Elongation Gauge 1 13.08.2019 13.08.2020
57 Slump Cone 2 Nos 1 13.08.2019 13.08.2020
58 Aggregate Crushing Value 1 13.08.2019 13.08.2020
59 Core Cutter With dolly 1 13.08.2019 13.08.2020
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 39

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

QA / QC RECORDS
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 40

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

8. Status of Approvals:
S.No Letter No Letter Description Status
Dated

NABL ACCREDITED THIRD PARTY LABORATORY


1 UO3359/XL0135/0235 21.02.2019 Buildcon Material Testing & Services Pvt Ltd Approved
2 SO-0033 G1000 DES 22.04.2019 M/s Spectro SSA Lab Pvt Ltd Approved
3 SO-0061 A1000 COT 27.05.2019 CSRL-Structwel Lab Pvt.Ltd Approved
WATER
S.No Letter No Letter Description Status
Dated
4 SO-0046 G1000 COT 13.05.2019 Bore Well ( Near Batching Plant ) Approved
ADMIXTURE& ACCELERATOR
S.No Letter No Letter Description Status
Dated
Submitting of Credentials of Admixture
BASF
NEC/MPEW/2018-
5 29.03.2019 SIKA
19/048
FOSROC Pending
MAPEI
BUILDTECH
NEC/MPEW/2018-
6 13.05.2019
19/082 FAIR MATE
CAC (Concrete Additives & Chemicals
7 SO-0019 G1000 COT 03.04.2019 Approved
Pvt.Ltd )
8 SO-0040 G1000 COT 02.05.2019 KUNAL ConchemPvt. Ltd-ADMIXTURE Approved
9 SO-0043 G1000 COT 09.05.2019 KUNAL ConchemPvt. Ltd-ACCELERATOR Approved
MACRO SYNTHETIC FIBRE
S.No Letter No Letter Description Status
Dated
10 SO-0067 G1000 COT 28.05.2019 Buildtech Product India Pvt Ltd(HICOPLA) Approved
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 41

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

CEMENT & RESIN CAPSULE


S.No Letter No Letter Description Status
Dated
11 SO-0067 G1000 COT 28.05.2019 Buildtech Product India Pvt Ltd Approved
Submitting of Credentials of Cement & Resin
NEC/MPEW/2018-
12 11.05.2019 capsule
19/080 KUNAL
Pending
Submitting of Credentials of Cement & Resin
NEC/MPEW/2018-
13 25.07.2019 capsule
19/151 TECHNO PRECISION
CEMENT
S.No Letter No Letter Description Status
Dated
14 SO-0065 G1000 COT 28.05.219 Ultratech Cement (OPC 53 GRADE) Approved
Source Approval Construction materials Pending
NEC/MPEW/2018-
15 18.01.2019
19/024 Ambuja 53 Grade OPC

NEC/MPEW/2018- Submission of credentials Pending


16 02.08.2019
19/169 ACC Limited, 53 Grade OPC
COARSE AGGREGATES
S.No Letter No Letter Description Status
Dated
17 SO-0075 G1000 COT 04.06.2019 Talegaon (Mangrul) Approved
MACRO SYNTHETIC FIBER
S.No Letter No Letter Description Status
Dated
Credentials of Macro Synthetic Fiber
NEC/MPEW/2018-
18 11.05.2019 BAJAJ Pending
19/079
KUNAL

NEC/MPEW/2018- Credentials of Macro Synthetic Fiber


19 30.05.2019 Pending
19/097 ELKEM
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 42

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

STEEL
S.No Letter No Letter Description Status
Dated
NEC/MPEW/2018- Submitting of M-25 TMT Bar Testing Approved
20 12.06.2019
19/105 SAIL
METHOD STATEMENT
S.No Letter No Letter Description Status
Dated
21 NEC/MPEW/2018- 05.07.2019 Submission of Revised Method Statement for Pending
19/141 Shotcrete
22 NEC/MPEW/2018- 05.07.2019 Submission of Revised Method Statement for Pending
19/140 Rock Bolt
23 NEC/MPEW/2018- 26.07.2019 Submission of Method Statement for Revision in
19/158 Forepoling Progress
24 NEC/MPEW/2018- 09.08.2019 Submission of Method statement for Tunnel Revision in
19/178 Excavation Progress
25 NEC/MPEW/2018- 27.08.2019 Submission of method statement for Lattice Pending
19/190 Girder With AE
26 NEC/MPEW/2018- 30.10.2019 Submission of method statement for Open Pending
19/240 Excavation in Adit-I With AE
27 NEC/MPEW/2018- 31.10.2019 Submit Method Statement for Cross Passage Pending
19/241 With AE
QUALITY ASSURANCE PLAN

S.No Letter No Letter Description Status


Dated
28 SO-0091 G1000 22.06.2019 Quality Assurance Plan Approved
COT
ENVIRONMENTAL MANAGEMENT PLAN
S.No Letter No Letter Description Status
Dated
29 SO-0111 G1000 23.07.2019 Environmental Management Plan Approved
SEE
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 43

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

HEALTH AND SAFETY PLAN

S.No Letter No Letter Description Status


Dated
30 SO-0105 G1000 09.07.2019 Health and Safety Plan Approved
SOH
TRAFFIC MANAGEMENT PLAN
S.No Letter No Letter Description Status
Dated
31 SO-0114 G1000 15.07.2019 Traffic Management Plan Approved
SOH
MIX DESIGN
S.No Letter No Letter Description Status
Dated
32 SO-0096 G1000 29.06.2019 Submission of Mix Design for Shotcrete-M-30 Approved
COT
33 SO-0095 G1000 29.06.2019 Submission of Mix Design for M-15 PCC Approved
COT
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 44

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

8.1 Monthly Quality Control Tests as on October 2019: (Attached as Annexure-VI)


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 45

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

STATUS OF MANPOWER
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 46

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

9. STATUS OF MANPOWER:

Details of Key Persons


Contact
S.No Name Designation Email-ID Remarks
Details
m.jayaram@navayuga.com
1 Mr. M. Jayaram Director

2 Mr. Ranjit Soman Design Director 9029083536 ranjith.beaver@gmail.com

3 Mr. T. Srinivas Kumar Construction Magnate 9704567176 tsk.nec@gmail.com

Vice President
4 Mr. Raghavendra raghavendra.pk@navayuga.com

5 Mr. K. Anil Kumar Project Manager 9817466777 anilkumark@navayuga.com

6 Mr. B.D. Patni Geological Expert 9910033404 bdpatni@rediffmail.com

Project Manager (Tunnel-1


7 Mr. Shyam Kurode 9820021190 s.kurode@gmail.com
& Adit-1)
8 Mr. S.B. Sajane Project Manager (Design) 8378986591 sbsajane@gmail.com

9 Mr. R. Suresh Kumar Deputy Manager (Tunnel) 9805196999 sureshkuttyrr@gmail.com

10 Mr. Babu Ramesh Deputy Manager (P & E) 7004999534 rameshbabunec@gmail.com

11 Mr. Ashutosh Singh Sr.Manager (Admin & 7458015319 ashutosh471@gmail.com


Liaison)

12 Mr. K.N.V Rama Kumar Manager (Electrical) 7896675502 missinglinkmep@gmail.com

Deputy Manager
13 Mr. Prashanth Kumar 9886199766 s.prashanthn@gmail.com
(Electrical)
14 Mr. Amar Pal Manager (QA/QC) 9880767630 amar.pal564@gmail.com

15 Mr. K. Srinivas Manager (Plant & 9880767630 kadiyalasrinivas72@gmail.com


Equipment)

16 Mr. P.Prasad Manager (Safety) 7981010598 prasadsafety1980@gmail.com


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 47

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

17 Mr. Ch. V. Ramana Asst. Manager (Materials) 7873326287 stores1299@necltd.com

18 Mr. Arun Kumar Nayak Sr.Engineer (Civil) 8763923332 arun.nayak260@gmail.com

19 Mr. K. Ravikanth Sr.Engineer (Civil) 9908872591 ravikanth.kotta@gmail.com

necl1299@gmail.com
20 Mr. P. Mahesh Reddy Sr.Engineer (Planning) 9985552777

necl1299@gmail.com
21 Mr. D. V. R. R. Srinivas Sr.Engineer (Planning) 7995914939

necsurvey1299@gmail.com
22 Mr. Asish Kumar Jana Sr.Engineer (Survey) 9660829074

23 Mr. Vikranth Mishra Site.Engineer (Survey) 7205433170 necsurvey1299@gmail.com

24 Mr. Kapil Dev Sr. Geologist 8005726741 necgeology.pune@gmail.com

25 Mr. Deepak Joshi Sr. Geologist 9305454738 necgeology.pune@gmail.com

26 Mr. Shivlal Dheemar Safety Officer 6206894098 deogharsafety@gmail.com

9.1 MANPOWER ENGAGED AS ON DATE:

S.No Description Unit Manpower Engaged at


Site
1 Staff (Local & HO) Nos 79
2 Drivers, Operators & Helpers Nos 147
3 Fabrication Team Nos 8
4 Tunnel Working Team Nos 56
5 Civil Works (Miscellaneous) Nos 45
TOTAL MANPOWER ENGAGED AT SITE 270
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 48

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

9.2 ORGANIZATION CHART (Attached as Annexure-VII)


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 49

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

DETAILS OF MAJOR
EQUIPMENT ON SITE
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 50

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

10. MAJOR EQUIPMENT AVAILABLE ON SITE

S.No Description of the Equipment Unit Qty Remarks


1. Boomer L2D Nos 1
2. Boomer XE3C Nos 1
3. ROC Drill Rig Nos 2
4. Meyco Potenza Nos 1
5. Sika Concrete Sprayer Nos 1
6. JCB 3DX Nos 2
7. Dumper Nos 16
8. Transit Mixer 6 CUM Nos 3
9. Generator 15 KVA Nos 1
10. Generator 30 KVA Nos 1
11. Generator 320 KVA Nos 1
12. Generator 125 KVA Nos 3
13. Generator 600 KVA Nos 2
14. Excavator Rock Breaker Nos 1
15. TATA Excavator 200 Nos 1
16. Volvo Excavator EX 290 BLC Nos 2
17. CAT Wheel Loader Nos 2
18. Volvo Loader 220G Nos 1
19. Volvo Excavator EC 300 DL Nos 2
20. Excavator ZAXIS 210 LCH Nos 3
21. Hydraulic Mobile Crane 14 Ton Nos 2
22. Air Compressor 450 HP Nos 2
23. Air Compressor 350 HP Nos 2
24. Batching Plant (30 Cum) Nos 2
25. Bolero Camper Nos 2
26. Water Tanker 10KL Nos 1
27. Grouting Pump Nos 3
28. Ambulance Nos 2
29. Four Wheelers Nos 8
30. Two Wheelers Nos 5
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 51

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

WEATHER RECORD
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 52

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

11. WEATHER RECORD FOR OCTOBER ‘19:

WEATHER RECORD
Month: October ' 19
TEMPERATURE [C] RAINFALL CUMMULATIVE
DATE
Minimum Maximum [mm] RAINFALL [mm]

01-Oct-19 20 31 9.6 0
02-Oct-19 20 31 0.8 0.8
03-Oct-19 21 31 0.1 0.9
04-Oct-19 21 31 12.3 13.2
05-Oct-19 20 31 14.6 27.8
06-Oct-19 20 30 10 37.8
07-Oct-19 22 31 15.6 53.4
08-Oct-19 21 32 17.8 71.2
09-Oct-19 22 32 34.8 106
10-Oct-19 21 30 9.2 115.2
11-Oct-19 21 31 12.9 128.1
12-Oct-19 21 32 8.6 136.7
13-Oct-19 22 33 5.2 141.9
14-Oct-19 21 33 19.3 161.2
15-Oct-19 20 32 0 161.2
16-Oct-19 18 31 0 161.2
17-Oct-19 18 31 0 161.2
18-Oct-19 21 27 13.4 174.6
19-Oct-19 21 25 36 210.6
20-Oct-19 21 23 92.1 302.7
21-Oct-19 20 28 30.9 333.6
22-Oct-19 21 30 37 370.6
23-Oct-19 22 29 98.9 469.5
24-Oct-19 22 27 10.6 480.1
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 53

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

25-Oct-19 22 25 1.1 481.2


26-Oct-19 21 28 3.9 485.1
27-Oct-19 20 30 1.2 486.3
28-Oct-19 19 32 0.4 486.7
29-Oct-19 21 31 2.6 489.3
30-Oct-19 20 31 12.3 501.6
31-Oct-19 20 28 1.3 502.9
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 54

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

SAFETY REPORT
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 55

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

12. Safety Report for the Month of October-2019:

12.1 Monthly Man-Hour details:

For the month of October’19, total manpower deployed for the project was 371.
Man-hours worked for this month was 74200 Hours.

12.2 Accident Statistics:

On 24.10.2019, a container lorry collided with the hard barrications erected on the
shoulder of Mumbai-Pune Expressway causing damages to 10 No’s of barrication boards.
The incident has been officially informed to the concerned police station vide a complain
letter.

12.3 Toolbox details:

Toolbox talk is performed before the start of each shift where the workers are made
aware and instructed to follow the safety precautions for the activities to be done on that
shift. Toolbox talk is signed and documented properly vide F/MPEW/1299/HSE/002.
Photographs are attached in the project photographs chapter and the documents are
attached as Annexure-VIII.

12.4 Fire Extinguishers and First Aid:


Fire Extinguisher suitable for class for Fire: A, B and C has been placed at NEC Site
Office, Store, D.G at camp site and D.G at work front.
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 56

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

First Aid Box has been placed at NEC Site office and at site.
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 57

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

12.5 SHE activities planned for the month of November-2019:


 Daily HSE Inspection for ongoing activities.
 Mock drill.
 Noise Monitoring.
 On the Job Training.
 Illumination Monitoring.
 Inspection of Fire point and Fire Extinguishers.
 Inspection of Plant and Machinery.
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 58

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

12.6 Monthly Health, Safety and Environment Report:

HSE Report NEC/HSE/FR/21/004 has been attached as Annexure-IX.


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 59

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

PROJECT PHOTOGRAPHS
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 60

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

13 LOCATION:

13.1 ESTABLISHMENT WORKS: Site Office

13.2 ESTABLISHMENT WORKS: Erection of Batching Plant


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 61

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

13.3 ESTABLISHMENT WORKS: Laboratory


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 62

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

13.4 TUNNEL-T2 EXIT: Executive Engineer Site Visit on 03.10.2019


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 63

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

13.5 TUNNEL-T2 EXIT: Profile Marking for Cross Passage tunnel

13.6 TUNNEL-T2 EXIT: Drilling


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 64

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

13.7 TUNNEL – T2 EXIT: Loading and Charging at Main Tunnel and Cross Passage
tunnel
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 65

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

13.8 TUNNEL-T2 EXIT: Mucking


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 66

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

13.9 TUNNEL-T2 EXIT: Scaling

13.10 TUNNEL-T2 EXIT: Shotcreting


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 67

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

13.11 TUNNEL-T2 EXIT: Rock Bolts


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 68

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

13.12 TUNNEL-T2 EXIT: Dewatering at T-2 Exit (RHS)

13.13 TUNNEL-T2 EXIT: Workability Test


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 69

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

13.14 TUNNEL-T2 EXIT: Rock Bolt Pull Out Test


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 70

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

13.15 TUNNEL-T2 EXIT: Compression Strength Testing in Site Laboratory


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 71

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

13.16 TUNNEL-T2 EXIT: Poly Fibre Washing Test


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 72

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

13.17 TUNNEL-T2 EXIT: Flexural Strength Test


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 73

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

13.18 TUNNEL-T2 EXIT: Unconfined Compression Strength (UCS Test)


NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 74

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

13.19 ADIT-I: Commencement of Adit-I Open Excavation by Superintendent Engineer


and Executive Engineer on 03.10.2019
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 75

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

ANNEXURES
NAVAYUGA ENGINEERING COMPANY LIMITED

MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2019 Page 76

CONSTRUCTION OF TWO TUNNEL (TWO TUBES OF FOUR LANE EACH (IN KM 1+040
TO KM 2+790) 1.75KM AND KM 3+440 TO 12+360 (8.92KM) FOR MISSING LINK UNDER
PROJECT NAME
CAPACITY AUGMENTATION OF MUMBAI PUNE EXPRESSWAY IN THE STATE OF
MAHARASHTRA UNDER EPC MODE – PACKAGE-I

S.No ANNEXURE DESCRIPTION NO.


1 T-2 Exit Inventory (Expressway Ch: 58+000 to 60+000) I
2 Strip Chart for Project Activities at Tunnel-T2 End for October'19 II
3 T1 Strip Chart for October '19 II
4 T2 Strip Chart for October '19 II
5 Tree cutting Strip Chart for October '19 II
6 RFI Log Sheet for Project Activities at T-2 Exit for October '19 III
7 Project Line Diagram IV
8 Land Acquisition Status V
9 Statement of Monthly Quality Control Test on Materials till October 2019 VI
10 Organization Chart - MPEW - Final for October '19 VII
11 Tool Box Talk F/MPEW/1299/HSE/002 VIII
12 Monthly HSE Report IX
T-2 Exit
T-2 Exit
T-2 Exit
T-2 Exit
T-2 Exit
T-2 Exit
T-2 Exit
T-2 Exit
T-2 Exit
T-2 Exit
T-2 Exit
T-2 Exit
T-2 Exit
T-2 Exit
in
in

Legend
LHS T-2

RHS T-2

Chainage
Chainage

KMs(LHS)

KMs(RHS)
Trees
Trees

Expressway
Expressway

Description
Description
58+125 58+100

Description

Trees aready removed


58+175 58+150

Trees yet to be removed


58+225 58+200
58+275 58+250
58+325 58+300
58+375 58+350
58+425 58+400
58+475 58+450
58+500 58+500
58+550 58+550
58+600 58+600
58+650 58+650
58+700 58+700
58+750 58+750
58+800 58+800
58+850 58+850
58+900 58+900
58+950 58+950
59+000 59+000
59+050 59+050
59+100 59+100
59+150 59+150
59+200 59+200
59+250 59+250
STRIP CHART FOR TREE CUTTING AT T-2

59+300 59+300
59+350 59+350
59+400 59+400
59+450 59+450
59+500 59+500
59+550 59+550
59+600 59+600
59+650 59+650
59+700 59+700
59+750 59+750
59+800 59+800
59+850 59+850
59+900 59+900
59+950 59+950
59+975 60+000
Trees
Trees
Expressway

Description
Description

in
in

LHS T-2

RHS T-2

Chainage
Chainage

KMs(LHS)

KMs(RHS)
ANNEXURE-II
4. STRIP CHART FOR PROJECT ACTIVITIES AT T-2 END (RHS) ANNEXURE-II

BACK SLOPE APPROACH ROAD


12+280 12+290 CHAINAGE 12+300 12+310 12+320 12+330 12+340 12+350 12+360 12+370 12+380 12+390 12+400 12+410 12+420 12+430 12+440 12+460
9,10,12,14,16,18,
1,2,9,10,12,14 18,23,28,29,31,32 21,22,23,24,25,26 15,17,19,21,22,23 11,13,15,17,
PORTAL 20,30,31,32,33,34 8,11,13 3,8 3,4 4,5 4,5,6 5,6,7
,16,18 ,33,34,35,36 ,27,34,35,37 ,24,25,35,37 19,25,37
,36
1,2,4,5,6 1,3,4,5,7 3,4 4,8 8
1,6 1,2,6 2,4,5,6 2,4,5 2,4 3 7 5,7 5,7 5 5
1,2 1,2

12 Mtr

12 Mtr
DIMENSION

T-2 Portal
17 Mtr

15.6 Mtr

15.6 Mtr

15.6 Mtr
Legend Description Legend Description Legend Depth(Mtr)
1 Blasting performed on 01.07.2019 at Ch: 12+293 to 12+296 28 Blasting performed on 21.07.2019 at Ch: 12+311.3 0-6
2 Blasting performed on 02.07.2019 at Ch: 12+293 to 12+296 29 Blasting performed on 22.07.2019 at Ch: 12+303 6-14
3 Blasting performed on 02.07.2019 at Ch: 12+365 to 12+375 30 Blasting performed on 23.07.2019 at Ch: 12+300 14-21
4 Blasting performed on 03.07.2019 at Ch: 12+375 to 12+386 31 Blasting performed on 23.07.2019 at Ch: 12+300 to 12+304
5 Blasting performed on 04.07.2019 at Ch: 12+388 to 12+396 32 Blasting performed on 24.07.2019 at Ch: 12+300 to 12+306.5
6 Blasting performed on 04.07.2019 at Ch: 12+396 to 12+404 33 Blasting performed on 28.07.2019 at Ch: 12+300 to 12+307
7 Blasting performed on 05.07.2019 at Ch: 12+404.5 34 Blasting performed on 29.07.2019 at Ch: 12+307 to 12+315
8 Blasting performed on 08.07.2019 at Ch: 12+350 to 12+353 35 Blasting performed on 30.07.2019 at Ch: 12+315 to 12+325
9 Blasting performed on 08.07.2019 at Ch: 12+293 to 12+301 36 Blasting performed on 31.07.2019 at Ch: 12+300 to 12+303
10 Blasting performed on 09.07.2019 at Ch: 12+293 to 12+300 37 Blasting performed on 31.07.2019 at Ch: 12+325 to 12+335
11 Blasting performed on 09.07.2019 at Ch: 12+347 1 Fixing of Wire Mesh performed on 04.07.2019 at Ch: 12+293 to 12+298
12 Blasting performed on 10.07.2019 at Ch: 12+296 2 Fixing of Wire Mesh performed on 05.07.2019 at Ch: 12+293
13 Blasting performed on 11.07.2019 at Ch: 12+344 3 Fixing of Wire Mesh performed on 15.07.2019 at Ch: 12+300 to 12+304
14 Blasting performed on 11.07.2019 at Ch: 12+293 to 12+295.5 4 Fixing of Wire Mesh performed on 24.07.2019 at Ch: 12+293 to 12+300
15 Blasting performed on 12.07.2019 at Ch: 12+338 5 Fixing of Wire Mesh performed on 24.07.2019 at Ch: 12+293 to 12+317
16 Blasting performed on 12.07.2019 at Ch: 12+296 6 Fixing of Wire Mesh performed on 26.07.2019 at Ch: 12+293
17 Blasting performed on 14.07.2019 at Ch: 12+334 7 Fixing of Wire Mesh performed on 28.07.2019 at Ch: 12+300
18 Blasting performed on 15.07.2019 at Ch: 12+298 to 12+308 8 Fixing of Wire Mesh performed on 29.07.2019 at Ch: 12+322 to 12+326
19 Blasting performed on 15.07.2019 at Ch: 12+332 1 Fixing of Rock Bolts performed on 04.07.2019 at Ch: 12+293
20 Blasting performed on 16.07.2019 at Ch: 12+300 2 Fixing of Rock Bolts performed on 12.07.2019 at Ch: 12+300 to 12+330
21 Blasting performed on 16.07.2019 at Ch: 12+329 3 Fixing of Rock Bolts performed on 15.07.2019 at Ch: 12+332
22 Blasting performed on 17.07.2019 at Ch: 12+327 4 Fixing of Rock Bolts performed on 15.07.2019 at Ch: 12+318 to 12+330
23 Blasting performed on 17.07.2019 at Ch: 12+315 to 12+322 5 Fixing of Rock Bolts performed on 22.07.2019 at Ch: 12+310 to 12+318 & 12+368 to 12+390
24 Blasting performed on 18.07.2019 at Ch: 12+324.4 6 Fixing of Rock Bolts performed on 23.07.2019 at Ch: 12+296 to 12+300 & 12+300 to 12+304
25 Blasting performed on 18.07.2019 at Ch: 12+322.5 to 12+335 7 Fixing of Rock Bolts performed on 28.07.2019 at Ch: 12+350 to 12+368
26 Blasting performed on 19.07.2019 at Ch: 12+319.8 1 Shotcreting performed on 05.07.2019 at Ch: 12+293
27 Blasting performed on 20.07.2019 at Ch: 12+315.3 2 Shotcreting performed on 13.07.2019 at Ch: 12+293
RHS Tube-1 LHS Tube-1

KMs
KMs

ge in
ge in

Chaina
Chaina

Heading
Heading

Description
Description

Shotcrete+Bolts
Shotcrete+Bolts

Excavation Heading
Excavation Heading

PQC
Ventilation
PQC
Ventilation

Excavation Benching
Excavation Benching

Tunnel Electrical
Tunnel Electrical

Benching Shotcrete+Bolts
Benching Shotcrete+Bolts
1+130 1+090
1+145 1+105
1+160 1+121
1+175 1+136
1+190 1+152
1+205 1+167
1+220 1+183
1+235 1+198
1+250 1+214
1+265 1+229
1+280 1+245
1+295 1+260
1+310 1+275
1+325 1+291
1+340 1+306
1+355 1+322
1+370 1+337
1+385 1+353
1+400 1+368
1+415 1+384
1+430 1+399
1+445 1+414
1+460 1+430
1+475 1+445
1+490 1+461
1+505 1+476
TUNNEL -1 STRIP CHART

1+520 1+492
1+535 1+507
1+550 1+523
1+565 1+538
1+580 1+554
1+595 1+569
1+610 1+584
1+625 1+600
1+640 1+615
1+655 1+631
1+670 1+646
1+685 1+662
1+700 1+677
1+715 1+693
1+730 1+708
1+745 1+723
1+760 1+739
1+775 1+754
1+790 1+770
1+805 1+785
1+820 1+801
1+835 1+816
1+850 1+832
1+865 1+847
1+880 1+863
1+895 1+878
1+910 1+893
1+925 1+909
ANNEXURE-II
1+940 1+924
1+955 1+940
1+970 1+955
1+985 1+971
2+000 1+986
2+015 2+002
2+030 2+017
2+045 2+032
2+060 2+048
2+075 2+063
2+090 2+079
2+105 2+094
2+120 2+110
2+135 2+125
2+150 2+141
2+165 2+156
2+180 2+172
2+195 2+187
2+210 2+202
2+225 2+218
2+240 2+233
2+255 2+249
2+270 2+264
2+285 2+280
2+300 2+295
2+315 2+311
2+330 2+326
2+345 2+341
TUNNEL -1 STRIP CHART

2+360 2+357
2+375 2+372
2+390 2+388
2+405 2+403
2+420 2+419
2+435 2+434
2+450 2+450
2+465 2+465
2+480 2+481
2+495 2+496
2+510 2+511
2+525 2+527
2+540 2+542
2+555 2+558
2+570 2+573
2+585 2+589
2+600 2+604
2+615 2+620
2+635 2+635
Heading
Heading

Description
Description

Shotcrete+Bolts
Shotcrete+Bolts

Excavation Heading
Excavation Heading

PQC
Ventilation
PQC
Ventilation

Excavation Benching
Excavation Benching

Tunnel Electrical
Tunnel Electrical

Benching Shotcrete+Bolts
Benching Shotcrete+Bolts
ANNEXURE-II
RHS Tube-2 RHS Tube-2 LHS Tube-2 LHS Tube-2

KMs
KMs
KMs
KMs

ge in
ge in
ge in
ge in

Chaina
Chaina
Chaina
Chaina

Heading
Heading
Heading
Heading

Description
Description
Description
Description

Shotcrete+Bolts
Shotcrete+Bolts
Shotcrete+Bolts
Shotcrete+Bolts

Excavation Heading
Excavation Heading
Excavation Heading
Excavation Heading

Tunnel Electrical
Tunnel Electrical
Tunnel Electrical
Tunnel Electrical

Ventilation
Ventilation
Ventilation
Ventilation

Excavation Benching
Excavation Benching
Excavation Benching
Excavation Benching

PQC
Benching Shotcrete+Bolts
PQC
Benching Shotcrete+Bolts
PQC
Benching Shotcrete+Bolts
PQC
Benching Shotcrete+Bolts
7+900 3+580 8+065 3+520
8+170 3+625 8+110 3+565
8+215 3+670 8+155 3+610
8+260 3+715 8+200 3+655
8+305 3+760 8+245 3+700
8+350 3+805 8+290 3+745
8+395 3+850 8+335 3+790
8+440 3+895 8+380 3+835
8+485 3+940 8+425 3+880
8+530 3+985 8+470 3+925
8+575 4+030 8+515 3+970
8+620 4+075 8+560 4+015
8+665 4+120 8+605 4+060
8+710 4+165 8+650 4+105
8+755 4+210 8+695 4+150
8+800 4+255 8+740 4+195
8+845 4+300 8+785 4+240
8+890 4+345 8+830 4+285
8+935 4+390 8+875 4+330
8+980 4+435 8+920 4+375
9+025 4+480 8+965 4+420
9+070 4+525 9+010 4+465
9+115 4+570 9+055 4+510
9+160 4+615 9+100 4+555
9+205 4+660 9+145 4+600
9+250 4+705 9+190 4+645
TUNNEL -2 STRIP CHART

9+295 4+750 9+235 4+690


9+340 4+795 9+280 4+735
9+385 4+840 9+325 4+780
9+430 4+885 9+370 4+825
9+475 4+930 9+415 4+870
9+520 4+975 9+460 4+915
9+565 5+020 9+505 4+960
9+610 5+065 9+550 5+005
9+655 5+110 9+595 5+050
9+700 5+155 9+640 5+095
9+745 5+200 9+685 5+140
9+790 5+245 9+730 5+185
9+835 5+290 9+775 5+230
9+880 5+335 9+820 5+275
9+925 5+380 9+865 5+320
9+970 5+425 9+910 5+365
10+015 5+470 9+955 5+410
10+060 5+515 10+000 5+455
10+105 5+560 10+045 5+500
10+150 5+605 10+090 5+545
10+195 5+650 10+135 5+590
10+240 5+695 10+180 5+635
10+285 5+740 10+225 5+680
10+330 5+785 10+270 5+725
10+375 5+830 10+315 5+770
10+420 5+875 10+360 5+815
10+465 5+920 10+405 5+860
10+510 5+965 10+450 5+905
ANNEXURE-II
10+555 6+010 10+495 5+950
10+600 6+055 10+540 5+995
10+645 6+100 10+585 6+040
10+690 6+145 10+630 6+085
10+735 6+190 10+675 6+130
10+780 6+235 10+720 6+175
10+825 6+280 10+765 6+220
10+870 6+325 10+810 6+265
10+915 6+370 10+855 6+310
10+960 6+415 10+900 6+355
11+005 6+460 10+945 6+400
11+050 6+505 10+990 6+445
11+946 6+550 11+035 6+490

354.2
354.2
354.2
354.2
11+959 6+595 11+080 6+535
11+977 6+640 11+125 6+580
12+038 6+685 11+170 6+625
12+048 6+730 11+215 6+670
12+061 6+775 11+260 6+715
12+068 6+820 11+305 6+760
12+088 6+865 11+350 6+805
12+097 6+910 11+395 6+850
12+100 6+955 11+440 6+895
12+104 7+000 11+485 6+940
12+114 7+045 11+530 6+985
12+159 7+090 11+575 7+030
12+167 7+135 11+620 7+075
12+187 7+180 11+665 7+120
12+207 7+225 11+710 7+165
TUNNEL -2 STRIP CHART

12+180 7+270 11+755 7+210


12+193 7+315 11+800 7+255
12+202 7+360 11+845 7+300
12+211 7+405 11+890 7+345
12+220 7+450 11+935 7+390
12+225 7+495 11+980 7+435
12+231 7+540 12+025 7+480
12+240 7+585 12+070 7+525
12+252 7+630 12+115 7+570
12+260 7+675 12+160 7+615
12+270 7+720 12+205 7+660
12+280 7+765 12+250 7+705
12+290 7+810 12+295 7+750
12+300 7+855 12+360 7+795
0
0
0
0

7+840
7+885
7+930
7+975
8+020
Heading
Heading
Heading
Heading

Description
Description
Description
Description

Shotcrete+Bolts
Shotcrete+Bolts
Shotcrete+Bolts
Shotcrete+Bolts

Excavation Heading
Excavation Heading
Excavation Heading
Excavation Heading

Tunnel Electrical
Tunnel Electrical
Tunnel Electrical
Tunnel Electrical

Ventilation
Ventilation
Ventilation
Ventilation

Excavation Benching
Excavation Benching
Excavation Benching
Excavation Benching

PQC
Benching Shotcrete+Bolts
PQC
Benching Shotcrete+Bolts
PQC
Benching Shotcrete+Bolts
PQC
Benching Shotcrete+Bolts
ANNEXURE-II
Adit-I

KMs
ge in
Chaina

Heading
Description

Shotcrete+Bolts
Excavation Heading

PQC
Ventilation
Excavation Benching

Tunnel Electrical
Benching Shotcrete+Bolts
0+000
+24
+47
+71
+95
+119
+142
+166
+190
+213
+237
+261
+284
+308
+332
+356
+379
+403
+427
+450
+474
+498
+521
+545
+569
Adit-I (Strip Chart)

+593
+616
+640
+664
+687
+711
+735
+758
+782
+806
+830
+853
+877
+901
+924
+948
+972
+995
1+019
1+043
1+067
1+090
1+114
1+138
1+161
1+185
1+209
1+232
1+256
ANNEXURE-II
1+280
1+304
1+327
1+351
1+375
1+398
1+422
1+446
1+469
1+493
1+517
1+541
1+564
1+588
1+612
1+635
1+659
1+683
1+706
1+730
1+754
1+778
1+801
1+825
1+849
1+872
1+896
1+920
Adit-I (Strip Chart)

1+943
1+967
1+991
2+015
2+038
2+062
2+086
2+109
2+133
2+157
2+180
2+204
2+228
2+252
2+275
2+299
2+323
2+346
2+370
2+398
Heading
Description

Shotcrete+Bolts
Excavation Heading

PQC
Ventilation
Excavation Benching

Tunnel Electrical
Benching Shotcrete+Bolts
ANNEXURE-II
Adit-I

KMs
ge in
Chaina

Heading
Description

Shotcrete+Bolts
Excavation Heading

PQC
Ventilation
Excavation Benching

Tunnel Electrical
Benching Shotcrete+Bolts
0+000
+10
+21
+31
+42
+52
+62
+73
+83
+94
+104
+114
+125
+135
+146
+156
+166
+177
+187
+198
+208
+218
+229
+239
+250
Adit-II (Strip Chart)

+260
+270
+281
+291
+302
+312
+322
+333
+343
+354
+364
+374
+385
+395
+406
+416
+426
+437
+447
+458
+468
+478
+489
+499
+510
+520
+530
+541
+551
ANNEXURE-II
+562
+572
+582
+593
+603
+614
+624
+634
+645
+655
+666
+676
+686
+697
+707
+718
+728
+738
+749
+759
+770
+780
+790
+801
+811
+822
+832
+842
Adit-II (Strip Chart)

+853
+863
+874
+884
+894
+905
+915
+926
+936
+946
+957
+967
+978
+988
+998
1+009
1+019
1+030
1+040
1+051
Heading
Description

Shotcrete+Bolts
Excavation Heading

PQC
Ventilation
Excavation Benching

Tunnel Electrical
Benching Shotcrete+Bolts
ANNEXURE-II
ANNEXURE-III

RFI LOG SHEET FOR PROJECT ACTIVITIES AT T2 EXIT - October'19

Revision Remarks
S.No Date RFI No. Location/Chainage Description

1 NEC/GDLBJV/RFI/427 T-2 Exit(RHS)12096.7-12093 First Layer Shotcrete

Drilling ,Loading and


2 NEC/GDLBJV/RFI/428 T-2 Exit(RHS)12163.7
Blasting .
T-2 Exit(RHS)12167.3-
3 NEC/GDLBJV/RFI/429 First Layer Shotcrete
12163.7
T-2 Exit(RHS)12163.7-
4 NEC/GDLBJV/RFI/430 First Layer Shotcrete
12160.4
01-10-2019
Drilling ,Loading and
5 NEC/GDLBJV/RFI/431 T-2 Exit(RHS)12093
Blasting .
Installation of
6 NEC/GDLBJV/RFI/432 T-2 Exit(RHS)12096
Rockbolts
Drilling ,Loading and
7 NEC/GDLBJV/RFI/433 T-2 Exit(RHS)12160.4
Blasting .
Drilling ,Loading and
8 NEC/GDLBJV/RFI/435 T-2 Exit(RHS)12089.4
Blasting .
Installation of
9 NEC/GDLBJV/RFI/436 T-2 Exit(RHS)12094,12092
Rockbolts
Drilling ,Loading and
10 NEC/GDLBJV/RFI/437 T-2 Exit(RHS)12089.4
Blasting .
Drilling ,Loading and
11 NEC/GDLBJV/RFI/439 T-2 Exit(RHS)12156.7
Blasting .

12 NEC/GDLBJV/RFI/440 T-2 Exit(RHS)12093-12086.2 First Layer Shotcrete


03-10-2019
Drilling ,Loading and
13 NEC/GDLBJV/RFI/441 T-2 Exit(RHS)12086.2
Blasting .
T-2 Exit(RHS)12160.4-
14 NEC/GDLBJV/RFI/442 First Layer Shotcrete
12156.7
T-2 Exit(RHS)12156.7-
15 NEC/GDLBJV/RFI/442 First Layer Shotcrete
12152.9
Drilling ,Loading and
16 NEC/GDLBJV/RFI/443 T-2 Exit(RHS)12152.9
Blasting .
Drilling ,Loading and
17 NEC/GDLBJV/RFI/444 T-2 Exit(RHS)12149.1
Blasting .
Drilling ,Loading and
18 NEC/GDLBJV/RFI/445 T-2 Exit(RHS)12083.1
Blasting .
T-2 Exit(RHS)12152.9-
19 NEC/GDLBJV/RFI/446 First Layer Shotcrete
12169.1

2nd Layer Shotcrete on


20 NEC/GDLBJV/RFI/447 T-2 Exit(RHS)12160-12152.91
both chainages

T-2 Exit(RHS)12090,88,86,88 Installation of


21 NEC/GDLBJV/RFI/448
Rockbolts
04-Oct-19
T-2 Exit(RHS)12158-12156 Installation of
22 NEC/GDLBJV/RFI/449
Rockbolts

T-2 Exit(RHS)12145.3 Drilling ,Loading and


23 NEC/GDLBJV/RFI/450
Blasting .
ANNEXURE-III

T-2 Exit(RHS)12086.2-
24 NEC/GDLBJV/RFI/451 12083.1 First Layer Shotcrete

T-
2Exit(RHS)12146,12148,1215 Installation of
25 NEC/GDLBJV/RFI/452
0,12152,12154 Rockbolts

T-2 Exit(RHS)12083.1-
26 NEC/GDLBJV/RFI/453 12079.5 First Layer Shotcrete

T-2 Exit(RHS)12082 Installation of


27 NEC/GDLBJV/RFI/454
Rockbolts
28 NEC/GDLBJV/RFI/455 T-2 Exit(RHS)12149-12145.3 First Layer Shotcrete
2nd Layer Shotcrete
29 NEC/GDLBJV/RFI/456 T-2 Exit(RHS)12152.9-12149
(RHS)
2nd Layer Shotcrete
30 NEC/GDLBJV/RFI/456 T-2 Exit(RHS)12149-12145.3
(RHS)
Drilling ,Loading and
31 NEC/GDLBJV/RFI/457 T-2 Exit(RHS)12079.5
Blasting.
T-2 Exit(RHS)120831.1 -
2nd Layer Shotcrete
32 NEC/GDLBJV/RFI/458 12079.5
(RHS)
05-Oct-19 T-2 Exit(RHS)12079.5-
33 NEC/GDLBJV/RFI/459 1st layer shotcrete
12075.7
Installation of
34 NEC/GDLBJV/RFI/460 T-2 Exit(RHS)12144
Rockbolts
Drilling ,Loading and
35 NEC/GDLBJV/RFI/461 T-2 Exit(RHS)12141.4
Blasting.
Drilling ,Loading and
36 NEC/GDLBJV/RFI/462 T-2 Exit(RHS)12137.6
Blasting.
T-2 Exit(RHS)12145.3 to 1st Layer Shotcrete
37 NEC/GDLBJV/RFI/463
12141.4 (RHS)
T-2 Exit(RHS)12145.3- 2nd Layer Shotcrete
38 NEC/GDLBJV/RFI/464
12141.4 (RHS)
T-2 Exit(RHS)12134 Installation of
39 NEC/GDLBJV/RFI/465
,12136,12138,12140,12142 Rockbolts
Drilling ,Loading and
40 NEC/GDLBJV/RFI/466 T-2 Exit(RHS)12133.7
Blasting.
Drilling ,Loading and
41 NEC/GDLBJV/RFI/467 T-2 Exit(RHS)12075.7
Blasting.
Installation of Rock
42 NEC/GDLBJV/RFI/468 T-2 Exit(RHS)12132-12131.5
bolt.
Drilling ,Loading and
43 NEC/GDLBJV/RFI/469 T-2 Exit(RHS)12130
Blasting
T-2 Exit(RHS)12075.7- 1st Layer Shotcrete
44 NEC/GDLBJV/RFI/470
12071.9 (RHS)
Installation of Rock
45 NEC/GDLBJV/RFI/471 T-2 Exit(RHS) 12076-12078
bolts.
Drilling ,Loading and
46 NEC/GDLBJV/RFI/472 T-2 Exit(RHS)12071.9
Blasting
T-2 Exit(RHS)12137.6- 1st Layer Shotcrete
47 NEC/GDLBJV/RFI/473
06-Oct-19 12133.7 (RHS)
1st Layer Shotcrete
48 NEC/GDLBJV/RFI/474 T-2 Exit(RHS)12133.7-12130
(RHS)
ANNEXURE-III

1st Layer Shotcrete


49 NEC/GDLBJV/RFI/475 T-2 Exit(RHS)12130-12126.4
(RHS)
T-2 Exit(RHS)12068.2 to 1st Layer PFRS
50 NEC/GDLBJV/RFI/476
12071.9 Shotcrete (RHS)
T-2
Installation of Rock
51 NEC/GDLBJV/RFI/477 Exit(RHS)12072,12074,12070,
bolts.
12080
Drilling ,Loading and
52 NEC/GDLBJV/RFI/478 T-2 Exit(RHS)12068.2
Blasting
Installation of Rock
53 NEC/GDLBJV/RFI/479 T-2 Exit(RHS)12128,12126
bolts.
Drilling ,Loading and
54 NEC/GDLBJV/RFI/480 T-2 Exit(RHS)12126.41
Blasting
T-2 Exit(RHS)12068.2 to 1st Layer PFRS
55 NEC/GDLBJV/RFI/481
12064.2 Shotcrete (RHS)
T-2 Exit(RHS)12068.2- 2nd Layer PFRS
56 NEC/GDLBJV/RFI/482
12071.9 Shotcrete (RHS)
T-2 Exit(RHS)12071.9 - 2nd Layer Shotcrete
57 NEC/GDLBJV/RFI/483
12075.7 (RHS)
2nd Layer Shotcrete
58 NEC/GDLBJV/RFI/484 T-2 Exit(RHS)12124,12122
(RHS)
07-Oct-19
Installation of Rock
59 NEC/GDLBJV/RFI/485 T-2 Exit(RHS)12218 to 12216
bolt( LHS Half face)
2nd Layer Shotcrete
60 NEC/GDLBJV/RFI/486 T-2 Exit(RHS)12126.4-12130
(RHS)
2nd Layer PFRS
61 NEC/GDLBJV/RFI/487 T-2 Exit(RHS)12130-12133.71
Shotcrete (RHS)
T-2 Exit(RHS)12133.7- 2nd Layer Shotcrete
62 NEC/GDLBJV/RFI/488
12137.6 (RHS)
Drilling , Loading ,
63 NEC/GDLBJV/RFI/489 T-2 Exit(RHS) 12122.5
Blasting
Drilling , Loading ,
64 NEC/GDLBJV/RFI/490 T-2 Exit(RHS)12118.6
Blasting
T-2 Exit(RHS) 12126.4- 1st Layer PFRS
65 NEC/GDLBJV/RFI/491
12122.5 Shotcrete (RHS)
T-2 Exit(RHS) 12122.5 - 1st Layer Shotcrete
66 NEC/GDLBJV/RFI/492
12118.6 (RHS)
T-2 Exit(RHS)12118.6 to 1st Layer Shotcrete
67 NEC/GDLBJV/RFI/493
12114.6 (RHS)
Drilling , Loading ,
68 NEC/GDLBJV/RFI/494 T-2 Exit(RHS)12114.6
Blasting
T-2
Installation Of
69 NEC/GDLBJV/RFI/495 Exit(RHS)12066,68,70,72,76,8
Rockbolts
0
08-Oct-19
T-2 Exit(RHS)12114.6- 1st Layer Shotcrete
70 NEC/GDLBJV/RFI/496
12110.5 (RHS)
T-2 Exit(RHS)12122.5- 2nd Layer Shotcrete
71 NEC/GDLBJV/RFI/497
12118.6 (RHS)
T-2 Exit(RHS)12118.6- 2nd Layer Shotcrete
72 NEC/GDLBJV/RFI/498
12114.6 (RHS)
T-2 Exit(RHS)12126.4- 2nd Layer Shotcrete
73 NEC/GDLBJV/RFI/499
12122.5 (RHS)
T-2
Installation of Rock
74 NEC/GDLBJV/RFI/500 Exit(RHS)12112,12114,12116,
bolts.
12118,12120,12122,12124
ANNEXURE-III

Drilling ,Loading and


75 NEC/GDLBJV/RFI/501 T-2 Exit(RHS)12110.5
Blasting
Drilling ,Loading and
76 NEC/GDLBJV/RFI/502 T-2 Exit(RHS)12064.2
Blasting
Drilling ,Loading and
77 NEC/GDLBJV/RFI/503 T-2 Exit(RHS)12106.7
Blasting
T-2 Exit(RHS)12110.5-
78 NEC/GDLBJV/RFI/504 Shotcrete 1st layer
12102.9
T-2 Exit(RHS)12064.2- 1st Layer Shotcrete
79 09-Oct-19 NEC/GDLBJV/RFI/505
12060.6 (RHS)
Installation of Rock
80 NEC/GDLBJV/RFI/506 T-2 Exit(RHS)12064
bolts.
Drilling ,Loading and
81 NEC/GDLBJV/RFI/507 T-2 Exit(RHS)12060.61
Blasting
Drilling ,Loading and
82 NEC/GDLBJV/RFI/508 T-2 Exit(RHS)12102.91
Blasting
Installation of Rock
83 NEC/GDLBJV/RFI/509 T-2 Exit(RHS)12062,12060
bolts.
Drilling ,Loading and
84 NEC/GDLBJV/RFI/510 T-2 Exit(RHS)12056.9
Blasting
Installation of Rock
85 NEC/GDLBJV/RFI/511 T-2 Exit(RHS)12100,12102
bolts.
T-2 Exit(RHS)12060.6- 1st Layer Shotcrete
86 NEC/GDLBJV/RFI/512
12053.2 (RHS)
Drilling ,Loading and
87 NEC/GDLBJV/RFI/513 T-2 Exit(RHS)12053.2
Blasting
Installation of Rock
88 NEC/GDLBJV/RFI/514 T-2 Exit(RHS)12058
bolts.
1st Layer Shotcrete
89 NEC/GDLBJV/RFI/515 T-2 Exit(RHS)12102.9-12099
(RHS)
T-2 Exit(RHS)12099 to 1st Layer Shotcrete
90 NEC/GDLBJV/RFI/516
12095.2 (RHS)
T-2 Exit(RHS)12114.6 to
91 NEC/GDLBJV/RFI/517 2nd Layer Shotcrete
12110.5
Installation of Rock
92 NEC/GDLBJV/RFI/518 T-2 Exit(RHS)12106,12104
bolts.
Drilling ,Loading and
93 NEC/GDLBJV/RFI/519 T-2 Exit(RHS)12095.2
Blasting
T-2 Exit(RHS)12200 to
94 NEC/GDLBJV/RFI/520 2nd Layer Shotcrete
122160

95 NEC/GDLBJV/RFI/521 T-2 Exit(RHS)12420 to 12470 1st Layer Shotcrete

Installation of Rock
96 NEC/GDLBJV/RFI/522 T-2 Exit(RHS)12056,12054
10-Oct-19 bolts.
Drilling ,Loading and
97 NEC/GDLBJV/RFI/523 T-2 Exit(RHS)12049.6
Blasting
Drilling ,Loading and
98 NEC/GDLBJV/RFI/524 T-2 Exit(RHS)12095.2
Blasting
Drilling ,Loading and
99 NEC/GDLBJV/RFI/525 T-2 Exit(RHS)12091.3
Blasting
100 NEC/GDLBJV/RFI/526 T-2 Exit(RHS)12390-12370 2nd Layer Shotcrete
T-2 Exit(RHS)12053.2 -
101 NEC/GDLBJV/RFI/527 1st Layer Shotcrete
12049.61
1st Layer PFRS
102 NEC/GDLBJV/RFI/528 T-2 Exit(RHS) 12049.6-12046
Shotcrete
ANNEXURE-III

Installation of Rock
103 NEC/GDLBJV/RFI/529 T-2 Exit(RHS) 12052
bolts.
Drilling ,Loading and
104 NEC/GDLBJV/RFI/530 T-2 Exit(RHS) 12046
Blasting
T-2 Exit(RHS) 12099-
105 NEC/GDLBJV/RFI/531 1st Layer Shotcrete
12095.21
T-2 Exit(RHS) 12095.2-
106 NEC/GDLBJV/RFI/532 1st Layer Shotcrete
12091.3
T-2 Exit(RHS) 12091.3-
107 NEC/GDLBJV/RFI/533 1st Layer Shotcrete
12087.5
T-2 Exit(RHS) 12064.2-
108 NEC/GDLBJV/RFI/533 2nd Layer Shotcrete
12060.6
T-2 Exit(RHS) 12066.6-
109 NEC/GDLBJV/RFI/534 2nd Layer Shotcrete
12056.9
Drilling ,Loading and
110 NEC/GDLBJV/RFI/534 T-2 Exit(RHS) 12087.5
Blasting.
T-2 Exit(RHS) 12056.9-
111 NEC/GDLBJV/RFI/535 2nd Layer Shotcrete
12053.2

112 NEC/GDLBJV/RFI/535 T-2 Exit(RHS) 12046-12042.3 1st Layer Shotcrete

Installation of Rock
113 NEC/GDLBJV/RFI/536 T-2 Exit(RHS) 12050,12048
bolts
T-2 Exit(RHS) 12053.2-
114 NEC/GDLBJV/RFI/536 2nd Layer Shotcrete
12049.6

115 NEC/GDLBJV/RFI/537 T-2 Exit(RHS) 12049.2-12046 2nd Layer Shotcrete

T-2 Exit(RHS) 12068.2-


116 NEC/GDLBJV/RFI/537 2nd Layer Shotcrete
12064.2
T-2 Exit(RHS) Installation of Rock
117 NEC/GDLBJV/RFI/538
12094,12092,12090,12088 bolts
Drilling ,Loading and
118 11-Oct-19 NEC/GDLBJV/RFI/539 T-2 Exit(RHS) 12083.7
Blasting.
Drilling ,Loading and
119 NEC/GDLBJV/RFI/540 T-2 Exit(RHS) 12042.3
Blasting.
T-2 Exit(RHS) 12042.3- 1st layer PFRS
120 NEC/GDLBJV/RFI/541
12038.6 Shotcrete activity
Installation of Rock
121 NEC/GDLBJV/RFI/542 T-2 Exit(RHS) 12046
bolts
Drilling ,Loading and
122 NEC/GDLBJV/RFI/543 T-2 Exit(RHS) 12038.6
Blasting.
T-2 Exit(RHS) 12087.5- 1st layer PFRS
123 NEC/GDLBJV/RFI/544
12083.7 Shotcrete activity
T-2 Exit(RHS) 12083.7- 1st layer PFRS
124 NEC/GDLBJV/RFI/545
12080 Shotcrete activity
Drilling ,Loading and
125 NEC/GDLBJV/RFI/546 T-2 Exit(RHS) 12080
Blasting.
1st layer PFRS
126 NEC/GDLBJV/RFI/547 T-2 Exit(RHS) 12098.6-12035
Shotcrete activity
Installation of Rock
127 NEC/GDLBJV/RFI/548 T-2 Exit(RHS) 12044,12042
bolts
Drilling ,Loading and
128 NEC/GDLBJV/RFI/549 T-2 Exit(RHS) 12035
Blasting
1st layer PFRS
129 NEC/GDLBJV/RFI/550 T-2 Exit(RHS) 12080-12076.2
Shotcrete activity
ANNEXURE-III

2nd layer PFRS


130 NEC/GDLBJV/RFI/551 T-2 Exit(RHS) 12083.7-12080
Shotcrete activity
T-2 Exit(RHS)12087.5- 2nd layer PFRS
131 NEC/GDLBJV/RFI/552
12083.7 Shotcrete activity
12-Oct-19
T-2 Exit(RHS)12086 Installation of Rock
132 NEC/GDLBJV/RFI/553
,12084,12082 bolts
Drilling ,Loading and
133 NEC/GDLBJV/RFI/554 T-2 Exit(RHS)12076.2
Blasting
Installation of Rock
134 NEC/GDLBJV/RFI/555 T-2 Exit(RHS)12040,12038
Bolts
Drilling ,Loading and
135 NEC/GDLBJV/RFI/556 T-2 Exit(RHS)12031.3
Blasting
1st layer PFRS
136 NEC/GDLBJV/RFI/557 T-2 Exit(RHS)12076.2-12120
Shotcrete activity
2nd layer PFRS
137 NEC/GDLBJV/RFI/558 T-2 Exit(RHS)12080 - 12076.2
Shotcrete activity
1st layer PFRS
138 NEC/GDLBJV/RFI/559 T-2 Exit(RHS)12027.6- 12035
Shotcrete activity

T-2 Installation of Rock


139 NEC/GDLBJV/RFI/560
Exit(RHS)12036,12034,12032 Bolts

Drilling ,Loading and


140 NEC/GDLBJV/RFI/561 T-2 Exit(RHS)12027.6
Blasting
T-2
Installation of Rock
141 NEC/GDLBJV/RFI/562 Exit(RHS)12080,12078,12076,
Bolts
12074
Drilling ,Loading and
142 13-Oct-19 NEC/GDLBJV/RFI/563 T-2 Exit(RHS)12072.4
Blasting
T-2 Exit(RHS)12160.4- 2nd layer PFRS
143 NEC/GDLBJV/RFI/564
12182.1 Shotcrete activity
1st layer PFRS
144 NEC/GDLBJV/RFI/565 T-2 Exit(RHS)12027.6- 12024
Shotcreting
T-2 Exit(RHS)12030 ,12028 Installation of Rock
145 NEC/GDLBJV/RFI/566
,12026 Bolts
Drilling ,Loading and
146 NEC/GDLBJV/RFI/567 T-2 Exit(RHS)12024
Blasting
Drilling ,Loading and
147 NEC/GDLBJV/RFI/568 T-2 Exit(RHS)12068.6
Blasting
1st layer PFRS
148 NEC/GDLBJV/RFI/569 T-2 Exit(RHS) 12024-12020.3
Shotcreting
Installation of Rock
149 NEC/GDLBJV/RFI/570 T-2 Exit(RHS) 12024,12022
Bolts
T-2 Exit(RHS) Installation of Rock
150 NEC/GDLBJV/RFI/571
12072,12070,12068,12066 Bolts
T-2 Exit(RHS) 12072.4- 1st layer PFRS
151 NEC/GDLBJV/RFI/572
12068.6 Shotcreting
T-2 Exit(RHS) 12068.6- 1st layer PFRS
152 NEC/GDLBJV/RFI/573
12064.8 Shotcreting
14-Oct-19
Drilling ,Loading and
153 NEC/GDLBJV/RFI/574 T-2 Exit(RHS) 12064.8
Blasting
Drilling ,Loading and
154 NEC/GDLBJV/RFI/575 T-2 Exit(RHS) 12018.1
Blasting
Installation of Rock
155 NEC/GDLBJV/RFI/576 T-2 Exit(RHS) 12064,12062
Bolts
ANNEXURE-III

Drilling ,Loading and


156 NEC/GDLBJV/RFI/591 T-2 Exit(RHS)12020.31
Blasting
Drilling ,Loading and
157 NEC/GDLBJV/RFI/577 T-2 Exit(RHS) 12061
Blasting
T-2 Exit(RHS) 12020.3- 1st layer PFRS
158 NEC/GDLBJV/RFI/578
12018.1 Shotcreting
T-2 Exit(RHS) 12018.1-
159 NEC/GDLBJV/RFI/579 1st layer Shotcreting
12014.8
T-2 Exit(RHS) Installation of Rock
160 NEC/GDLBJV/RFI/580
12022,12020,12018 Bolts
Drilling ,Loading and
161 NEC/GDLBJV/RFI/581 T-2 Exit(RHS) 12014.8
Blasting
Installation of Rock
162 NEC/GDLBJV/RFI/582 T-2 Exit(RHS) 12060,12058
Bolts
1st layer PFRS
163 NEC/GDLBJV/RFI/583 T-2 Exit(RHS) 1206-12058
Shotcreting
2nd layer PFRS
164 15-Oct-19 NEC/GDLBJV/RFI/584 T-2 Exit(RHS) 12061-12076.2 Shotcrete activity
(4Cycles)
Drilling ,Loading and
165 NEC/GDLBJV/RFI/585 T-2 Exit(RHS) 12058
Blasting
Applying Shotcrete on
166 NEC/GDLBJV/RFI/586 T-2 Exit(RHS) 12370-12340
wiremesh
T-2 Exit(RHS) 12011.4- 1st layer PFRS
167 NEC/GDLBJV/RFI/587
12014.8 Shotcreting
Drilling ,Loading and
168 NEC/GDLBJV/RFI/588 T-2 Exit(RHS) 12011.4
Blasting
Drilling ,Loading and
169 NEC/GDLBJV/RFI/589 T-2 Exit(RHS) 12054.1
Blasting
Final Layer Shotcrete
170 NEC/GDLBJV/RFI/590 T-2 Exit(RHS) 12051-12045
Crown Portion
Drilling ,Loading and
171 NEC/GDLBJV/RFI/591 T-2 Exit(RHS) 12020.31
Blasting
T-2 Exit(RHS) 12011.4- 1st layer PFRS
172 NEC/GDLBJV/RFI/592
12008.2 Shotcreting
T-2 Exit(RHS) Installation of Rock
173 NEC/GDLBJV/RFI/593
12016,12014,12012 Bolts
Drilling ,Loading and
174 NEC/GDLBJV/RFI/594 T-2 Exit(RHS) 12008.2
Blasting .
T-2 Exit(RHS) Installation of Rock
175 NEC/GDLBJV/RFI/595
12056,12054,12052,12050 Bolts
1st layer PFRS
176 NEC/GDLBJV/RFI/596 T-2 Exit(RHS) 12058-12054.1
Shotcreting
T-2 Exit(RHS) 12054.1- 1st layer PFRS
177 NEC/GDLBJV/RFI/597
12050.2 Shotcreting
Drilling ,Loading and
178 16-Oct-19 NEC/GDLBJV/RFI/598 T-2 Exit(RHS) 12050.2
Blasting .
T-2 Exit(RHS) 12008.2- 1st layer PFRS
179 NEC/GDLBJV/RFI/599
12005.7 Shotcreting
T-2 Exit(RHS) 12011.4- 2nd layer PFRS
180 NEC/GDLBJV/RFI/600
12008.2 Shotcreting
Installation of Rock
181 NEC/GDLBJV/RFI/601 T-2 Exit(RHS) 12010,12008
Bolts
Drilling ,Loading and
182 NEC/GDLBJV/RFI/602 T-2 Exit(RHS) 12205.7
Blasting
ANNEXURE-III

Installation of Rock
183 NEC/GDLBJV/RFI/603 T-2 Exit(RHS) 12050,12048
Bolts
Drilling ,Loading and
184 NEC/GDLBJV/RFI/604 T-2 Exit(RHS) 12046.4
Blasting .
Finishing layer
185 NEC/GDLBJV/RFI/605 T-2 Exit(RHS) 12039-12043
Shotcreting
T-2 Exit(RHS) 12005.7- 1st layer PFRS
186 NEC/GDLBJV/RFI/606
12003.1 Shotcreting
T-2 Exit(RHS) 12008.2- 2nd layer PFRS
187 NEC/GDLBJV/RFI/607
12005.7 Shotcreting
Drilling ,Loading and
188 NEC/GDLBJV/RFI/608 T-2 Exit(RHS) 12003.1
Blasting .
Installation of
189 NEC/GDLBJV/RFI/609 T-2 Exit(RHS) 12046.44
Rockbolts
T-2 Exit(RHS) 12050.2- 1st layer PFRS
190 NEC/GDLBJV/RFI/610
12046.4 Shotcreting
17-Oct-19 T-2 Exit(RHS) 12046.4- 1st layer PFRS
191 NEC/GDLBJV/RFI/611
12042.6 Shotcreting
Drilling ,Loading and
192 NEC/GDLBJV/RFI/612 T-2 Exit(RHS) 12042.6
Blasting
193 NEC/GDLBJV/RFI/613 T-2 Exit(RHS) 12087.5 Erection Of Girders
Installation of
194 NEC/GDLBJV/RFI/614 T-2 Exit(RHS) 12006,12004
Rockbolts.
Drilling ,Loading and
195 NEC/GDLBJV/RFI/615 T-2 Exit(RHS) 12000.4
Blasting
Drilling ,Loading and
196 NEC/GDLBJV/RFI/616 T-2 Exit(RHS) 12042.6
Blasting
T-2 Exit(RHS) 12003.1- 1st layer PFRS
197 NEC/GDLBJV/RFI/617
12000.4 Shotcreting
T-2 Exit(RHS) 12000.4- 1st layer PFRS
198 NEC/GDLBJV/RFI/618
11997.3 Shotcreting
Installation of
199 NEC/GDLBJV/RFI/619 T-2 Exit(RHS) 12002,12000
Rockbolts.
Drilling ,Loading and
200 NEC/GDLBJV/RFI/620 T-2 Exit(RHS) 11997.3
Blasting
Installation of
201 NEC/GDLBJV/RFI/621 T-2 Exit(RHS) 12042,12040
Rockbolts.
T-2 Exit(RHS) 12182.1- 2nd layer PFRS
202 NEC/GDLBJV/RFI/622
12160.4 Shotcreting
T-2 Exit(RHS) 12110.5- 2nd layer PFRS
203 NEC/GDLBJV/RFI/622
121099 Shotcreting
2nd layer PFRS
204 NEC/GDLBJV/RFI/622 T-2 Exit(RHS) 12141.3-137.6
Shotcreting
18-Oct-19
Drilling ,Loading and
205 NEC/GDLBJV/RFI/623 T-2 Exit(RHS) 12038.8
Blasting
T-2 Exit(RHS) 11997.3-
206 NEC/GDLBJV/RFI/624 1st layer Shotcreting
11994.1
T-2 Exit(RHS) 12000.4 - 2nd layer PFRS
207 NEC/GDLBJV/RFI/625
11997.3 Shotcreting
Installation of
208 NEC/GDLBJV/RFI/626 T-2 Exit(RHS) 11998,11996
Rockbolts
Drilling ,Loading and
209 NEC/GDLBJV/RFI/627 T-2 Exit(RHS) 11994.1
Blasting
Installation of
210 NEC/GDLBJV/RFI/628 T-2 Exit(RHS) 12038,12036
Rockbolts
ANNEXURE-III

2nd layer PFRS


211 NEC/GDLBJV/RFI/629 T-2 Exit(RHS) 12058-12035
Shotcreting
Drilling ,Loading and
212 NEC/GDLBJV/RFI/630 T-2 Exit(RHS) 12035.0
Blasting
T-2 Exit(RHS) 11994.1- 2nd layer PFRS
213 NEC/GDLBJV/RFI/631
11997.3 Shotcreting
T-2 Exit(RHS) 11994.1- 1st layer PFRS
214 NEC/GDLBJV/RFI/632
11990.5 Shotcreting
Installation of
215 NEC/GDLBJV/RFI/633 T-2 Exit(RHS) 11994
Rockbolts
Drilling ,Loading and
216 NEC/GDLBJV/RFI/634 T-2 Exit(RHS) 11990.5
Blasting
T-2 Exit(RHS) Installation of
217 NEC/GDLBJV/RFI/635
12036,12034,12032,12030 Rockbolts
Drilling ,Loading and
218 NEC/GDLBJV/RFI/636 T-2 Exit(RHS) 12031.5
Blasting
19-Oct-19
T-2 Exit(RHS) 12042.6- 1st layer PFRS
219 NEC/GDLBJV/RFI/637
12028.3 Shotcreting
Drilling ,Loading and
220 NEC/GDLBJV/RFI/638 T-2 Exit(RHS) 12028.3
Blasting
T-2 Exit(RHS) 11990.5- 1st layer PFRS
221 NEC/GDLBJV/RFI/639
11986.8 Shotcreting
Installation of
222 NEC/GDLBJV/RFI/640 T-2 Exit(RHS) 11992
Rockbolts
Drilling ,Loading and
223 NEC/GDLBJV/RFI/641 T-2 Exit(RHS) 11986.8
Blasting
Drilling ,Loading and
224 NEC/GDLBJV/RFI/642 T-2 Exit(RHS) 12024.8
Blasting
T-2 Exit(RHS) Installation of
225 NEC/GDLBJV/RFI/643
12028,12026,12024,12022 Rockbolts
Installation of
226 20-Oct-19 NEC/GDLBJV/RFI/644 T-2 Exit(RHS) 11990,11988
Rockbolts
Drilling ,Loading and
227 NEC/GDLBJV/RFI/645 T-2 Exit(RHS) 12021.3
Blasting
Installation of
228 NEC/GDLBJV/RFI/646 T-2 Exit(RHS) 11956
Rockbolts
Drilling ,Loading and
229 NEC/GDLBJV/RFI/647 T-2 Exit(RHS) 11983.3
Blasting
Installation of
230 NEC/GDLBJV/RFI/648 T-2 Exit(RHS) 12020,12018
Rockbolts
Drilling ,Loading and
231 NEC/GDLBJV/RFI/649 T-2 Exit(RHS) 12018
Blasting
T-2 Exit(RHS) 11986.8- 1st layer PFRS
232 NEC/GDLBJV/RFI/650
11983.31 Shotcreting
T-2 Exit(RHS) 11983.3- 1st layer PFRS
233 21-Oct-19 NEC/GDLBJV/RFI/651
11979.8 Shotcreting
Installation of
234 NEC/GDLBJV/RFI/652 T-2 Exit(RHS) 11984,11982
Rockbolts
Drilling ,Loading and
235 NEC/GDLBJV/RFI/653 T-2 Exit(RHS) 11979.8
Blasting
T-2 Exit(RHS) 12028.3- 1st layer PFRS
236 NEC/GDLBJV/RFI/654
12014.51 Shotcreting
Drilling ,Loading and
237 NEC/GDLBJV/RFI/655 T-2 Exit(RHS) 12014.5
Blasting
ANNEXURE-III

2nd layer PFRS


238 NEC/GDLBJV/RFI/656 T-2 Exit(RHS) 12035-12014.5
Shotcreting
T-2 Exit(RHS) 11979.8- 1st layer PFRS
239 NEC/GDLBJV/RFI/657
11976.5 Shotcreting
T-2 Exit(RHS) 11979.8- 2nd layer PFRS
240 NEC/GDLBJV/RFI/658
11983.3 Shotcreting
T-2 Exit(RHS) 11986.8- 2nd layer PFRS
241 NEC/GDLBJV/RFI/659
11983.31 Shotcreting
Installation of
242 NEC/GDLBJV/RFI/660 T-2 Exit(RHS) 11980,11978
Rockbolts
Drilling ,Loading and
243 NEC/GDLBJV/RFI/661 T-2 Exit(RHS) 11976.5
Blasting
T-2 Exit(RHS) Installation of
244 NEC/GDLBJV/RFI/662
12016,12014,12012 Rockbolts
T-2 Exit(RHS) 12014.5- 1st layer PFRS
245 NEC/GDLBJV/RFI/663
12010.9 Shotcreting
Drilling ,Loading and
246 NEC/GDLBJV/RFI/664 T-2 Exit(RHS) 12010.9
Blasting
T-2 Exit(RHS) 11976.5- 1st layer PFRS
247 22-Oct-19 NEC/GDLBJV/RFI/665
11972.8 Shotcreting
T-2 Exit(RHS) 11979.8- 2nd layer PFRS
248 NEC/GDLBJV/RFI/666
11976.8 Shotcreting
Installation of
249 NEC/GDLBJV/RFI/667 T-2 Exit(RHS) 11976,11974
Rockbolts
Drilling ,Loading and
250 NEC/GDLBJV/RFI/668 T-2 Exit(RHS) 11972.8
Blasting
Installation of
251 NEC/GDLBJV/RFI/669 T-2 Exit(RHS) 12010,12008
Rockbolts
T-2 Exit(RHS) 12014.5- 2nd layer PFRS
252 NEC/GDLBJV/RFI/670
12010.9 Shotcreting
T-2 Exit(RHS) 12010.9- 2nd layer PFRS
253 NEC/GDLBJV/RFI/671
12007.4 Shotcreting
T-2 Exit(RHS) 12007.4- 1st layer PFRS
254 NEC/GDLBJV/RFI/672 R0
12010.9 Shotcreting
Drilling ,Loading and
255 NEC/GDLBJV/RFI/673 T-2 Exit(RHS) 12007.4
Blasting
T-2 Exit(RHS) 11972.8- 1st layer PFRS
256 NEC/GDLBJV/RFI/674
11969.1 Shotcreting
T-2 Exit(RHS) 11976.5- 2nd layer PFRS
257 NEC/GDLBJV/RFI/675
11972.8 Shotcreting
T-2 Exit(RHS) Installation of
258 NEC/GDLBJV/RFI/676
11974,11972,11970 Rockbolts
Drilling ,Loading and
259 NEC/GDLBJV/RFI/677 T-2 Exit(RHS) 11969.1
Blasting
T-2 Exit(RHS) Installation of
260 NEC/GDLBJV/RFI/678
12006,12004,12008,12002 Rockbolts
T-2 Exit(RHS) 12007.4- 1st layer PFRS
261 NEC/GDLBJV/RFI/679
12003.7 Shotcreting
Drilling ,Loading and
262 23-Oct-19 NEC/GDLBJV/RFI/680 T-2 Exit(RHS) 12003.7
Blasting
T-2 Exit(RHS) 11965.7- 1st layer PFRS
263 NEC/GDLBJV/RFI/681
11969.1 Shotcreting
T-2 Exit(RHS) 11972.5- 2nd layer PFRS
264 NEC/GDLBJV/RFI/682
11969.1 Shotcreting
ANNEXURE-III

Installation of
265 NEC/GDLBJV/RFI/683 T-2 Exit(RHS) 11972,11970
Rockbolts
Drilling ,Loading and
266 NEC/GDLBJV/RFI/684 T-2 Exit(RHS) 11965.7
Blasting
Drilling ,Loading and
267 NEC/GDLBJV/RFI/685 T-2 Exit(RHS) 12000
Blasting
2nd layer PFRS
268 NEC/GDLBJV/RFI/686 T-2 Exit(RHS)
Shotcreting
1st layer PFRS
269 NEC/GDLBJV/RFI/687 T-2 Exit(RHS) 11969.1-11962
Shotcreting
T-2 Exit(RHS) 11965.7- 2nd layer PFRS
270 NEC/GDLBJV/RFI/688
11969.1 Shotcreting
2nd layer PFRS
271 NEC/GDLBJV/RFI/689 T-2 Exit(RHS) 11969.1-11996
Shotcreting
T-2 Exit(RHS) Installation of
272 NEC/GDLBJV/RFI/690
11970,11968,11966 Rockbolts
1st layer PFRS
273 NEC/GDLBJV/RFI/691 T-2 Exit(RHS) 11996.2-12000
Shotcreting
1st layer PFRS
274 NEC/GDLBJV/RFI/692 T-2 Exit(RHS) 12000-12003.7
Shotcreting
24-Oct-19
Installation of
275 NEC/GDLBJV/RFI/693 T-2 Exit(RHS) 11966
Rockbolts
Drilling ,Loading and
276 NEC/GDLBJV/RFI/694 T-2 Exit(RHS) 11962.0
Blasting
2nd layer PFRS
277 NEC/GDLBJV/RFI/695 T-2 Exit(RHS) 12128-12105
Shotcreting
2nd layer PFRS
278 NEC/GDLBJV/RFI/696 T-2 Exit(RHS) 12000-12007.4
Shotcreting
Installation of
279 NEC/GDLBJV/RFI/697 T-2 Exit(RHS) 12002,12000
Rockbolts
Drilling ,Loading and
280 NEC/GDLBJV/RFI/698 T-2 Exit(RHS) 11996.2
Blasting
1st layer PFRS
281 NEC/GDLBJV/RFI/699 T-2 Exit(RHS) 11962-11959.3
Shotcreting
2nd layer PFRS
282 NEC/GDLBJV/RFI/700 T-2 Exit(RHS) 11965.7-11962
Shotcreting
Installation of
283 NEC/GDLBJV/RFI/701 T-2 Exit(RHS) 11964
Rockbolts
T-2 Exit(RHS) Installation of
284 NEC/GDLBJV/RFI/702
11994,11996,11998 Rockbolts
1st layer PFRS
285 NEC/GDLBJV/RFI/703 T-2 Exit(RHS) 11996.2-11992
Shotcreting
2nd layer PFRS
286 NEC/GDLBJV/RFI/704 T-2 Exit(RHS) 11996.2-12000
Shotcreting
25-Oct-19
2nd layer PFRS
287 NEC/GDLBJV/RFI/705 T-2 Exit(RHS) 12000-12003.7
Shotcreting
Drilling ,Loading and
288 NEC/GDLBJV/RFI/706 T-2 Exit(RHS) 11959.3
Blasting
T-2 Exit(RHS) 11959.3- 1st layer PFRS
289 NEC/GDLBJV/RFI/707
11956.1 Shotcreting
2nd layer PFRS
290 NEC/GDLBJV/RFI/708 T-2 Exit(RHS) 11959.3-11962
Shotcreting
Drilling ,Loading and
291 NEC/GDLBJV/RFI/709 T-2 Exit(RHS) 11956.1
Blasting
ANNEXURE-III

Drilling ,Loading and


292 NEC/GDLBJV/RFI/710 T-2 Exit(RHS) 11988.7
Blasting
T-2 Exit(RHS) 11956.1- 1st layer PFRS
293 NEC/GDLBJV/RFI/711
11952.5 Shotcreting
T-2 Exit(RHS) 11959.3- 2nd layer PFRS
294 NEC/GDLBJV/RFI/712
11956.1 Shotcreting
T-2 Exit(RHS) Installation of
295 NEC/GDLBJV/RFI/713
11962,11960,11958,11956 Rockbolts
Installation of
296 NEC/GDLBJV/RFI/714 T-2 Exit(RHS) 11992
Rockbolts
297 NEC/GDLBJV/RFI/715 T-2 Exit(RHS) 12340-12330 Shotcrete
Drilling ,Loading and
298 NEC/GDLBJV/RFI/716 T-2 Exit(RHS) 11952.5
Blasting
27-Oct-19 1st layer PFRS
299 NEC/GDLBJV/RFI/717 T-2 Exit(RHS) 11952.5-11949
Shotcreting
T-2 Exit(RHS) 11956.1- 2nd layer PFRS
300 NEC/GDLBJV/RFI/718
11952.9 Shotcreting
Drilling ,Loading and
301 NEC/GDLBJV/RFI/719 T-2 Exit(RHS) 11984.9
Blasting
T-2 Exit(RHS) 11988.7- 1st layer PFRS
302 NEC/GDLBJV/RFI/720
11984.9 Shotcreting
1st layer PFRS
303 NEC/GDLBJV/RFI/721 T-2 Exit(RHS) 11992-11988.7
Shotcreting
Drilling ,Loading and
304 NEC/GDLBJV/RFI/722 T-2 Exit(RHS) 11981.2
Blasting
305 NEC/GDLBJV/RFI/723 T-2 Exit(RHS) 12297-12282 Shotcrete
T-2 Exit(RHS) Installation of
306 NEC/GDLBJV/RFI/724
11954,11952,11950 Rockbolts
T-2 Exit(RHS) Installation of
307 NEC/GDLBJV/RFI/725
11990,11988,11986,11984 Rockbolts
28-Oct-19 T-2 Exit(RHS) 11984.9- 1st layer PFRS
308 NEC/GDLBJV/RFI/726
11981.2 Shotcreting
T-2 Exit(RHS) 11988.7- 2nd layer PFRS
309 NEC/GDLBJV/RFI/727
11981.2 Shotcreting
2nd layer PFRS
310 NEC/GDLBJV/RFI/728 T-2 Exit(RHS) 11988.7-11992
Shotcreting
Drilling ,Loading and
311 NEC/GDLBJV/RFI/729 T-2 Exit(RHS) 11949
Blasting
Drilling ,Loading and
312 NEC/GDLBJV/RFI/730 T-2 Exit(RHS) 11977.4
Blasting
Drilling ,Loading and
313 NEC/GDLBJV/RFI/731 T-2 Exit(RHS) 11980-12020
Blasting
29-Oct-19 T-2 Exit(RHS)
Installation of
314 NEC/GDLBJV/RFI/732 11982,11980,11980,11978,119
Rockbolts
76
T-2 Exit(RHS) 11981.2-
315 NEC/GDLBJV/RFI/733 Shotcrete
11977.4
T-2 Exit(RHS) 11977.4-
316 NEC/GDLBJV/RFI/734 Shotcrete
11973.61
Drilling ,Loading and
317 NEC/GDLBJV/RFI/735 T-2 Exit(RHS) 11097-11085
Blasting
Drilling ,Loading and
318 30-Oct-19 NEC/GDLBJV/RFI/736 T-2 Exit(RHS) 12017-12003
Blasting
ANNEXURE-III

Drilling ,Loading and


319 NEC/GDLBJV/RFI/737 T-2 Exit(RHS) 12002-12008
Blasting
Drilling ,Loading and
320 NEC/GDLBJV/RFI/738 T-2 Exit(RHS)11945.8
Blasting
1st layer PFRS
321 NEC/GDLBJV/RFI/739 T-2 Exit(RHS) 11949-11945.8
Shotcreting
T-2 Exit(RHS) 11945.8- 1st layer PFRS
322 NEC/GDLBJV/RFI/740
11942.7 Shotcreting
31-Oct-19
Installation of
323 NEC/GDLBJV/RFI/741 T-2 Exit(RHS) 11948
Rockbolts
Drilling ,Loading and
324 NEC/GDLBJV/RFI/742 T-2 Exit(RHS) 11942.7
Blasting
Drilling ,Loading and
325 NEC/GDLBJV/RFI/743 T-2 Exit(RHS) 12022-12017
Blasting
START OF THE PROJECT
T-1 Start 1+130 T-1 Start 1+090

LHS T-1

RHS T-1

TUNNEL-1
TOWARDS PUNE
T-1 End 2+635 T-1 End 2+635

T-2 Start 3+580 T-2 Start 3+520

Ch: 5+550

H/S-I
2397.3m
PROJECT LINE DIAGRAM

TUNNEL-2

Ch: 9+300
H/S-II

1051m

LHS T-2

RHS T-2

T-2 End 12+300 T-2 End 12+360


TOWARDS MUMBAI

Existing Expressway Merging Existing Expressway Merging


Point 13+200 Point 13+160
END OF THE PROJECT
ANNEXURE-IV
START OF THE PROJECT

F2
F1
T-1 Start 1+100 / T-1 Start 1+130 T-1 Start 1+040 / T-1 Start 1+090
TOWARDS MUMBAI

LHS T-1

RHS T-1

TUNNEL-1
T-1 End 2+790 / T-1 End 2+635
T-1 End 2+790 / T-1 End 2+635

F4
F3

VIADUCT-2

F6
F5

T-2 Start 3+440 / T-2 Start 3+520


T-2 Start 3+430 / T-2 Start 3+580
832.5 / 2397.63m
Adit-I
F9

Ch:5+800 / Ch: 5+800


LEGEND:
TUNNEL-2
LHS T-2

AA/ BB
STATUS OF LAND ACQUISITION

RHS T-2
925 / 1030m
Adit-II
F10

Ch: 9+250 / Ch: 9+300


F7

T-2 End 12+300 / T-2 End 12+300 T-2 End 12+360 / T-2 End 12+360

Ch:12+670
F8

ROW NOT HANDED OVER

ROW NOT HANDED OVER


WORK FRONT AVAILABLE
TOWARDS PUNE

T-2 End Approach 12+300 T-2 Approach End 12+360


SCHEDULE-B / AS PER SITE CHAINAGES

/ T-2 End Approach 12+300 / T-2 Approach End 12+360


END OF THE PROJECT
TREE CUTTING PERMISSION NOT RECEIVED &
ANNEXURE-V
9.2 ORGANIZATION CHART WITH KEY PERSONS ANNEXURE-VII

M. Jayaram
(Director)

Ranjit Soman
Raghavendra
(Design Director) T. Srinivas Kumar
(Project Controller- Vice
9029083536 (Construction Magnet)
President)

K. Anil Kumar
(Sr. Project Manager)
9817466777

Execution Planning & Monitoring Quality Control Electrical Dept., Survey Department

P. Mahesh Reddy Amar Pal K.N.V Ramkumar Asish Kumar Jana


Tunnel 2 - End point Tunnel 2 - Adit-2 Tunnel 2 - Adit-1 Tunnel 1 (Sr. Engineer) (Manager) Manager (Electrical) (Sr. Engineer)
9985552777 9880767630 7896675502 9660829074

R Suresh Kumar Shyam Korde Prashanth Kumar


D.V.R.R. Srinivas
(Deputy Manager) (Project Manager) Senior Engineer Deputy Manager(Electrical) Senior Surveyor/Surveyor - 8
(Sr.Engineer) 7995914939
9805196999 9820021190 9886199766
Planning Engineer - 2 Site Engineer - 2 Site Engineer - 4 Asst. Surveyor - 5
Ravi Kanth Arun Kumar Nayak
Nadeem Ahmed Amit
(Sr. Engineer) (Sr. Engineer) Lab Asst., - 4 Electricians - 10
(Sr.Engineer) (Sr.Engineer)
9908872591 8763923332

Site Engineer - 4 Site Engineer - 2 Site Engineer - 2 Site Engineer - 4

Supervisor - 4 Supervisor - 4 Supervisor - 4 Supervisor - 4

Geology Dept. Safety Dept. Stores Accounts Mechanical Dept.(P&E) Administration

Ashutosh Singh
Ch.V.Ramana Anirban Ghosh Babu Ramesh
B.D. Patni P.Prasad Sr. Manager
(Asst. Manager) Asst. Manager (Finance) (Deputy Manager) P.R.O-2
(Geological Expert) (Safety Manager) Liaison & Admin
7873326287 9784918022 7004999534
(7458015319)

Kapil Dev Shivlal Deemar K.Srinivas


(Sr.Geologist) (Safety Officer) Store In Charge - 4 Accounts Officer (Manager) Personnel officer-1
8005726741 6206894098
Rajeshwar Prasad Amit Singh
Material Purchaser - 2
(Fabrication) Site Engineer (Mech)
Deepak Joshi
(Geologist) Site Engineers
Safety Sup., - 6 Sr.Store Asst. / Store Asst.- 10 Accountant-2 Foreman HR Asst., - 4
9305454738 (Fabrication)

Tally /Record Entry-3 Accounts Asst-2 Foreman(Fabrication) - 2 Mechanics


ANNEXURE-IX

MONTHLY HEALTH,SAFETY AND ENVIRONMENT REPORT NEC/HSE/FR/21/004

Location : Lonavala
Name of the Project : Mumbai Pune Expressway Missing Link Project Package-1

Month & Year: October-2019

Date:-10/11/2019 Report Period From To 01.05.2019 to 31.10.2019

Upto Previous During this


Required Data Total upto date Month
month month
01. Average No. of Employee's / Workers 1234 371 1605 October
02. Manhours worked 250280 74200 324480 October
03.Number of HSE awareness programs conducted at site 2 1 3 October
04.Number of Safety Induction/ Intial orientation programme 5 5 10 October
04. Number of Tool Box Meetings conducted at site 45 15 60 October
05. Number of loss time Accidents (LTA) Fatal 0 0 0 October
06. Number of loss time Accidents ( LTA) Others 0 0 0 October
07. Number of Loss time Injuries ( LTI) 0 0 0 October
08. Number of Non Loss time Accidents 0 0 0 October
09. Number of First Aid Cases 0 0 0 October
10. Number of Near Miss incidents 1 0 1 October
11. Number of AE Safety Observations 108 17 125 October
12. Number of Environmental Incidents 0 0 0 October
13. Number of Govt Inspections (MSRDC visit) 3 1 4 October
14. Number of Audits conducted 0 0 0 October
15. Number of pending non conformances from audits 0 0 0 October