( CIN No U40109MH2005SGC153646)
From: To
Office of Additional Executive Engineer The Executive Engineer;
220/33 KV Sub-Station,M.S.E.T.C.L,Oni EHV O&M Division, MSETCL,
Tal-Rajapur, Dist-Ratnagiri, Pin:- 416705 Mirjole Road, MIDC, Ratnagiri
Phone : 02353-228361(O) Ph. No. 02352 – 231388.
Email : dyeeh461@mahatransco.in E-mail:eeratnagiri3220@mahatransco.in
Ref.No. Addl.E.E./220KV/Oni/T/370 Date:19/03/2017
Respected Sir,
In connection with the above subject, find enclosed herewith the LCM test report
carried out on 14.03.2017 on 198KV metal oxide gapless surge arresters of various
feeders/equipments at 220/33KV Oni Sub-Station.
Sd/-
Sub-Station incharge
220/33KV Oni Sub-Station
M.S.E.T.C.L
Encl:- 1. LCM Test Report
LCM TEST RESULTS
Name of Kit:- Doble LCM500
Serial no Kit:- 205 296
Test carried out on 20.11.2019 at 220/33KV Oni Sub-Station
Y-Ph
B-Ph
B-Ph
3. Name of Equipment:- 220/33KV 25MVA BBL T/F NO-1 (HV Side LA)
R-Ph
Y-Ph
B-Ph
4. Name of Equipment:- 220/33KV 25MVA VIJAI T/F NO-2 (HV Side LA)
R-Ph
Y-Ph
B-Ph