Sunteți pe pagina 1din 4

Plaster Quantitiy

Sr. No. Description Quantity Unit


1 Proportion of Mortar 1 6
2 Area of Plastering 100 sq. m
3 Thickness of Plastering 12 mm
4 Volume of Plaster 1.2 cu. M

5 Adding 50% for voids and 10% for uneveness 1.92 cu. M
*Dry Mortar*
Cement 0.2743 cu. M
6
Cement bags 8 numbers
1.646 cu. M
7 Sand
0.58 brass

Cost of Material
Sr. No. Description Quantity Unit Rate
1 Cement 8 number 350.00
2 Sand 1.646 cu. M 1,000.00
Total Cost of Materials
Total Cost
2,800.00
1,645.71
4,445.71
Concrete Quantity
Volume of Work 0.12 cu. M
Proportion of Concrete 1 2 4

1 Dry Volume 0.1824 cu. M


2 Cement 0.03 cu. M
3 Cement Bags 1 numbers
0.05 cu. M
4 Sand
0.02 brass
0.10 cu. M
5 Aggregate
0.04 brass

Cost Material
Sr. No. Description Quantity Unit Rate Total Cost
1 Cement Bags 1 Numbers 350.00 350.00
2 Sand 0.05 cu. M 1,000.00 52.11
3 Aggregate 0.10 cu. M 600.00 62.54
Total Cost of Materials 464.65
Note: 45 -52 of total vol of work

vol of 1 bag of cement .035 cu m


1 cu m equals 0.354 brass

S-ar putea să vă placă și