Documente Academic
Documente Profesional
Documente Cultură
MINISTRY OF WATER
CONTRACTOR:
NOVEMBER 2019
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP QUALITY ASSURANCE
QUALITY ASSURANCE
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP TABLE OF CONTENTS
TABLE OF CONTENTS
1 INTRODUCTION........................................................................................................ 1-1
1.1 Background of the Project...........................................................................................1-1
1.2 Scope of Work............................................................................................................ 1-1
1.3 Main Objective of the Project......................................................................................1-1
1.4 Expected Results of the Project..................................................................................1-1
1.5 Presentation of the Detailed Design Report-WTP.......................................................1-2
2 DESCRIPTION OF THE PROJECT AREA.................................................................2-3
2.1 Location and Topography............................................................................................2-3
2.2 Vegetation................................................................................................................... 2-3
2.3 Climate....................................................................................................................... 2-3
3 THE DESIGN PROCESS...........................................................................................3-4
3.1 Design parameters.....................................................................................................3-4
3.1.1 Design Flows Criteria..................................................................................................3-4
3.1.2 Treated Water Quality Criteria.....................................................................................3-4
3.2 approach to design work.............................................................................................3-5
3.2.1 Review of Existing Documents...................................................................................3-5
3.2.2 Site Visit...................................................................................................................... 3-5
3.2.3 Topographical Survey.................................................................................................3-5
3.2.4 Geotechnical Survey...................................................................................................3-5
4 DESIGN OF WATER TREATMENT PLANT...............................................................4-1
4.1 Detailed Design.......................................................................................................... 4-1
4.1.1 Design Basis............................................................................................................... 4-1
4.1.2 General Layout........................................................................................................... 4-1
4.1.3 Coagulation/Flocculation.............................................................................................4-1
4.1.4 Flocculator Unit........................................................................................................... 4-2
4.1.5 Chemical Dosing.........................................................................................................4-3
4.1.6 Clarification Basins.....................................................................................................4-4
4.1.7 Rapid Sand Filters......................................................................................................4-5
4.1.8 Clear and Backwash Water Reservoir........................................................................4-7
4.1.9 Disinfection................................................................................................................. 4-7
4.1.10 Sludge Treatment and Disposal..................................................................................4-7
4.1.11 Clear and Backwash Water Pump Station..................................................................4-8
4.1.12 Chemical Building.......................................................................................................4-9
4.1.13 Site Drainage.............................................................................................................. 4-9
4.1.14 Administrative Building, Staff House and Guard House..............................................4-9
4.2 Structural design.......................................................................................................4-10
PAGE II
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP TABLE OF CONTENTS
PAGE III
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP TABLE OF CONTENTS
LIST OF ANNEXES
No. Content
3-1 Topographical Survey Data
3-2 Geotechnical Investigation Report
4-1 WTP Design Calculations
4-2 General Site Layout for WTP
4-3 Hydraulic Profile Drawing of WTP
LIST OF ABBREVIATIONS
PAGE IV
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP
1 INTRODUCTION
The Government of the United Republic of Tanzania (GoT) has set aside funds towards
improvement of water supply in Bunda town.
The implementation of the project is based on the principles of the National Water Policy
(NAWAPO) and will provide clean and safe water to the residents of Bunda Township. The
Proposed Bunda Township Water Supply Project involves abstracting raw water from Lake
Victoria to a proposed Water Treatment Plant (WTP) for treatment for subsequent transmission
to the town. The capacity of the WTP is 9,405 m3/day and is the proposed intake is 9,900
m3/day.
The project is financed through the Water Sector Development Programme (WSDP). The
contracting authority is the Ministry of Water (MoW) ("Client") and the beneficiary is Bunda
Urban Water Supply and Sanitation Authority ("Beneficiary") and the works are carried out by
Shanxi Construction Engineering Corporation & Mineral Co. Limited ("Contractor").
The overall scope of work for water supply improvement project in Bunda Township involves
design and construction of new intake works, modifications of existing raw water pumping
station and ancillaries, new water treatment plant, upgrading of existing booster stations, new
buildings and associated components.
The main objective of GoT is to provide Bunda town with clean and safe water supply for
improved health of Bunda population in accordance with the principles of the National Water
Policy (NAWAPO.
PAGE 1
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP
Construction of New Buildings namely WTP Administration Building, WTP Staff House,
WTP Guard House, and UWSA Office Block.
Design Report in two parts, one part for intake works and the other part for the WTP works. This
report covers the WTP part and shows the detailed designs and calculations of the various
components of the water treatment process.
PAGE 2
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP
Bunda District
Bunda District in Mara Region is located between latitude 10 30’ and 20 45’ South of Equator
and, between longitude 330 39’ to 340 05’ East of Greenwich. It is bordered by Serengeti
District in the east, Musoma District in the north, Magu District in the south, and shores of Lake
Victoria in the west.Bunda District.
Bunda District in Mara Region is located between latitude 10 30’ and 20 45’ South of Equator
and, between longitude 330 39’ to 340 05’ East of Greenwich. It is bordered by Serengeti
District in the east, Musoma District in the north, Magu District in the south, and shores of Lake
Victoria in the west.
Bunda District covers an area of 3,088 km 2 of which 200 km2 is Lake Victoria water. Average
annual rainfall ranges between 900 – 1300 mm in the western part of the district, and between
700 – 900 mm in the eastern part. Temperatures range between 17° – 31°C and the average
altitude of the district is 1300 masl.
Bunda Town
Bunda Town is the administrative and commercial centre of Bunda District. It was declared a
township in the Government Notice No. 353 of 17th September 2004. The town is located within
Bunda Ward, covering an area of approximately 86 km2 consisting of five urban areas namely
Bunda Mjini, Nyasura Balili, Nyamakokoto and Majengo, and four villages of Bunda Stoo, Balili,
Migungani, and Manyamanyama with a total of 14 sub-villages.
2.2 VEGETATION
Bunda town is mostly covered with natural vegetation, but there are large areas for cultivation.
The most prevalent landscape seen in the natural vegetation is the “savannah type” most
commonly found in areas that receive annual rainfall between 900-1200 mms/year. The plains
consist of predominant forest vegetation, but mostly scattered woodlands and wooded
grasslands
2.3 CLIMATE
The climate is tropical. The summers here have a good deal of rainfall, while the winters have
very little. The average annual temperature is 22.4 °C in Bunda. About 963 mm of precipitation
falls annually. The driest month is July, with 10 mm of rain. Most of the precipitation here falls in
April, averaging 163 mm. October is the warmest month of the year. The temperature in October
averages 23.4 °C. July is the coldest month, with temperatures averaging 21.3 °C. There is a
difference of 153 mm of precipitation between the driest and wettest months. Throughout the
year, temperatures vary by 2.1 °C.
PAGE 3
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP
The new Raw Water Intake and the new Water Treatment Facilities are designed for a Design
Flow of 450 m3/hour (four hundred and fifty cubic meters per hour), which shall apply for water
conveyed from the Raw Water Intake.
The net water production of the new Water Treatment Facilities is designed to be be 430
m3/hour (four hundred and thirty cubic meters per hour), which shall apply for water conveyed
from the Clear and Backwash Water Pump Station.
The net water production of the Water Treatment Plant shall meet the water quality standards
according to the WHO “Guidelines for Drinking Water Quality”, 3rd edition, Year 2004, which are
presented in the following table:
Table 3-1 Water Quality Standards – WHO Guidelines (3rd edition, Year 2004)
Parameter Symbol Unit WHO Guideline Value
Toxic
Lead Pb mg/l 0.01
Arsenic As mg/l 0.01
Selenium Se mg/l 0.01
Chromium Cr mg/l 0.05
Cyanide CN mg/l 0.07
Cadmium Cd mg/l 0.003
Barium Ba mg/l 0.7
Mercury Hg mg/l 0.001
Affecting Human Health
Fluoride F mg/l 1.5
Nitrate NO3 mg/l 50
Nitrite NO2 mg/l 3
Organoleptic
Colour TCU 15
Turbidity NTU 5
Taste - not objectionable
Odour - not objectionable
Salinity and Hardness
pH - 6.5 – 9.5
Total Filterable Residue mg/l 1,500
Calcium Ca mg/l 200
Magnesium Mg mg/l 150
Sulphate SO4 mg/l 400
Chloride Cl mg/l 600
PAGE 4
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP
The following relevant project documents have been reviewed during the design process:
Bidding Documents Employer’s particular requirement and Drawings
Detailed Design Report for Proposed Bunda Township Water Supply Project; and
MoW Design Manual for Water Supply and Waste Water Disposal
During the design process, the Contractor’s representative and the Supervising Consultant
made two joint site visits to the project area. The aim of the site visits was to have a joint
understanding of the site conditions and assess suitability of the proposed sites.
After assessing and confirming the treatment plant site, topographical surveys were carried out
using the latest survey equipment. The surveys were undertaken in accordance with the Land
Surveying and Mapping Standards of Tanzania. The survey field work involved measuring
ground levels at the proposed site of the WTP.
With the survey data, contour lines were generated at a suitable interval to determine location of
the various components of the WTP. Temporary benchmarks/ survey control points were also
established for reference and control of the construction works.
Topographical survey data consisting of all the topographical works carried out is in Annex 3-1.
The primary objective of the geotechnical survey was to provide all the necessary soil data
required for the design of the WTP. The soil data is important to check the stability of the WTP
site and any possible ground movements that would affect the operation of the constructed
PAGE 5
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP
WTP structures. The data is also important for the design team to take necessary measures by
ensuring that sound structural elements are designed for all the structures. All field work for
geotechnical survey has been completed and samples have already been submitted to Dar es
Salaam Institute of Technology (DIT) in Dar Es Salaam for laboratory testing. All tests were
carried in accordance with BS 1377. DIT is accredited and registered with the Engineers
Registration Board of Tanzania (ERB) to undertake testing of engineering construction
materials.
A separate Geotechnical Survey Report consisting of all the geotechnical survey works carried
out will be submitted separately.
PAGE 6
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP
4.1.3 Coagulation/Flocculation
Raw water conveyed from the Raw Water Pump Station will be discharged at the head of the
water treatment works of the new WTP. For this purpose, a reinforced concrete structure will be
constructed at the new WTP which comprises: (a) an inlet chamber into which the raw water
discharges, (b) chambers for chemical dosing and hydraulic mixing, and (c) chambers for
flocculation through baffled walls. This structure is specified as the Flocculator Unit.
The water treatment plant comprises a raw water coagulation channel followed by a sinuous
channel for water flocculation purposes. The channels have the following dimensions:
Coagulation channel
Channel length: approximately 5.0 m
Channel width: approximately 0.5 m
Channel depth: averaged to 0.5 m (variable from 1.16 m to 0.186 m)
Channel volume: Calculated as 1.25 m3.
Flocculation channel (Horizontal flow baffle walls sinuous channel)
Total channel length: approximately 375 m
Channel width: approximately 0.45 for the first 147.6 meters and 0.5m for 131.2 meters
and 0.6m for the last 98.4 meters
Channel depth: approximately 1.0 m.
PAGE 1
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP
As a general design criterion, the value of the velocity gradient "G" is between 500 and 700 sec-
1 The G value or in other words the velocity gradient, is the energy required per unit volume of
treated water, and is expressed as: G = (P/µV)^0.5 sec-1 whereby; P is the required power in
watts, µ is the value of the dynamic viscosity of water at 20°C normally 0.0010087 Pa *sec, and
V is the volume of water in the channel calculated above as 1.25 m3. For a value of G of 500
sec-1 the power required is worked out to be 315.2 watts.
The power required shall be obtained from the potential energy "P" vested in the flowing water
by use of the following relationship: - Power P = ɤQh, where ɤ is the product of water density
"p" normally 1000kg/m3 and the value of acceleration due to gravity "g" with a value of 9.8
m/sec2 , hence the value of ɤ is 9,800 Newtons/m3 Since the value of P is known, ɤ is known,
and Q is 0.125m3/sec, the value of "h" (The head loss required in order for the water to provide
the required potential energy) works out to be 0.257 meters.
The inlet pipes shall be DI DN 400 from raw water at the inlet of the coagulation chamber. For
the given flow rate 0.125m3/sec, the velocity shall be about 0.99 m/sec. The energy that shall
be dissipated by the velocity of the water at inlet shall be calculated as V2/2g, and this will work
out to be 0.025 meters head. This will make the extra required head loss to be (0.257 - 0.025m)
or 0.232 meters. Therefore, the water in the coagulation channel shall be subjected to a drop of
0.232 meters.
The details of the coagulation channel are as shown in the drawing no. SCEMC-WTP-GA-0001
Annex 4-1, S/No.2 presents the detailed calculations for the coagulation chamber.
The energy input shall be obtained from the potential energy of the flowing water, in order to
avoid continuous use of electricity for running static mixers. However, a proper coagulant dosing
equipment is important in order to assure optimum floc formation which is necessary for efficient
removal of the water turbidity.
PAGE 2
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP
Average water depth in channel is 0.8 m.
If the width of the baffle shall be 8.2 m, then 23 baffles shall be required.
Velocity shall be 0.125/(0.52x0.8) equal to 0.3 m/sec which is within 0.1 – 0.3 m/sec.
In order to reduce the value of G near the settling tank, the channel width shall be
changed to 500mm and then 600mm, average flow velocity round the baffle ends shall
become 0.21 m/sec.
The value of G is obtained by the relationship: (G = (P/(V*µ))^0.5)
The energy input is obtained from the same relationship as in coagulation. However, the
head loses are from friction of moving water in the channel, and especially at the bends
at the end of each baffle where the water takes a 180° bend. The head losses 'hfb' at
each bend is evaluated as hfb = 3.2xV2/2g, whereby V is the velocity of flow at the bend,
and g is the value of gravity (9.8 m/sec2)
The spacing between the side wall and the end of baffle has been kept as 600, 750 and
900 mm. This will give a velocity of 0.21 m/sec, which is also less than 0.3m/sec.
The value of 3.2xV2/2g becomes 7.1926x10-3, and when multiplied by 3.2 becomes
0.023 meters for one bend, and 0.529 meters for 23 baffles.
Total head losses to be compensated therefore become 0.48 m.
The power input then become 191 watts (from P = ɤQh)
The value of G works out to be 35.5<75 sec-1 and Gt value of 42,652<105
Annex 4-1, S/No.2 presents the detailed calculations for the flocculator unit.
The details of the flocculator unit are as shown in the drawing no. SCEMC-WTP-GA-0002
PAGE 3
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP
directly into a pressure pipe, this dosing arrangement allows for easy visual inspection of the
dosing rates. Any potential blockage of pipes would be immediately identified.
The Design
The use of tube settlers will allow a surface loading rate of 4 m³/m²h. This surface loading rate
will be achieved by constructing 2 square-shaped clarifiers. Each clarifier will be 7.5 m long on
each side. The inverted pyramidal-shaped hopper of the clarifiers will have a depth of 6.5 m, in
order to provide space for sludge settling at the bottom.
The tube settler modules, laid on concrete beams, will be made out of polypropylene, have a
height of 0.8 m and an angle of inclination of 60°. The entire area of the clarifier will be covered
by tube settlers, except from the space necessary for the inlet valve and pipe. In emergency
case or for a total emptying of the tanks, the tube settler modules can be lifted out of the tanks
using an auto crane.
The transition between the flocculators and clarifiers is designed to minimize floc shear. In order
to ensure even distribution of the influent in the clarifier, the downward pointing inlet pipe will be
vertical and centered. Its size and outlet shape should be carefully adjusted in order to provide
an appropriate velocity (around 0.6 m/s) – high enough to maintain the sludge blanket in
suspension, but not too high which would disturb sludge settling at the bottom of the clarifier.
Collection of the settled water would be achieved by collection troughs with v-notched weirs on
both sides. A maximum allowable weir load of 5 m³/m/h is adopted, with four troughs, each 7.5
m long, mounted in each clarifier.
Excess sludge will be allowed to settle at the bottom of the clarifiers, below a horizontal circular
steel plate fixed at an elevation of 1.5 m above clarifier bottom. It will be removed through a
PAGE 4
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP
sludge pipe, by the manual opening of a valve according to scheduled time intervals, and
transferred by gravity to the sludge drying beds.
Each valve will be opened and closed manually according to a scheduled operation programme.
During de-sludging, the valve must be only half open, to make sure that the velocity in the
sludge pipe is not too high. The valve would be fully opened only in case of emergency.
Besides, the opening time must be short, because the sludge hopper has a limited volume and
will be emptied very quickly (1-2 minutes), meaning that non-settled sludge would be drawn out
afterwards, thus causing water losses.
A flushing system is also be provided to allow for periodic cleaning of the sludge hoppers, in
case the accumulated sludge becomes too thick and cannot flow by gravity anymore. The entire
flushing system consists of the connecting pipe to the service water network, one valve and a
flushing ring-shaped pipe with holes where the water can splash out. The flushing ring will be
fixed close to the hopper bottom and next to the inlet of the sludge abstraction pipe.
Annex 4-1, S/No.3 presents the detailed calculations for the clarifier unit.
The details of the clarifier unit are as shown in the drawing no. SCEMC-WTP-GA-0003
PAGE 5
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP
The Design
The design calculation in this case is based on a filtration flow rate of 6 m 3/(m2*h) i.e. 6m/h. This
means the need of 75 m2 for a flow of 450 m3/hr.
This will be done by 4 identical filter units, each being 3.6 m wide and 5.6 m long. During
periodic backwashing of one filter, the filtration rate will increase to 7.5 m/h, which is acceptable
for the expected clarified water quality.
The type of filter employed will be “influent flow controlled” with rising water level during
proceeding filtration time. Influent flow control will be established by installation of an adjustable
sharp crested weir at the inlet of each filter box. Once the weirs have been equally levelled
during the construction phase, no further adjustment is necessary.
The water depth on top of a filter will vary from 0.1 m right after filter backwash (controlled by
the level of clear water pipe in clear water collection trough) up to a maximum of 2.3 m
(2300mm) when the next backwash cycle starts. A minimum water depth must be ensured on
top of the filter in order to avoid the development of negative pressures within the sand bed. The
maximum water depth before backwashing is recommended to be between 2 m and 3 m, in
order to avoid too frequent backwash while keeping the overall filter battery height within
acceptable range.
The filter medium will be quartz sand with an effective size of 0.9 mm and a uniformity
coefficient smaller than 1.4 in order to avoid stratification of non-uniform sand grains during
backwash. Filter media height will be 1.0 m, on top of a stratified 0.3 m height gravel layer.
The filter media bed will be split into two equal parts of 1.8 m by 5.6 m, with the inlet/backwash
water collecting channel being located in the middle of the filter. To avoid sand losses during
backwash due to filter bed expansion, the crest of the collecting channel will be located 0.5 m
above the top of the filter medium.
The filter floor will be equipped with polyethylene or PVC filter nozzles with a slot width of less
than 0.4 mm. The minimum number of nozzles should be 56-64 per m² in order to allow even
distribution of air and water during backwash.
Backwashing will consist of a sequence of three steps:
Air scour at a rate of 60 m/h for 5 minutes.
Combined air scour (60 m/h) and wash-water at a rate of 15 m/h for 5 minutes.
Water rinsing at a rate of 30 m/h for minimum 5 minutes and maximum 10 minutes.
The solids-loaded backwash water will be collected from the rapid sand filters and conveyed by
gravity flow to the sludge drying beds.
Backwash water will be supplied from backwash pumps which are 2 duty , 1 standby with
capacity of 300m3/h and a head of 15m (1.5bar).
Each filter will have its own filter control desk with a synoptic showing the status of the filter unit
valves and air scour blowers. Each filter unit valve will include an electrically-driven valve
actuator wired to the filter control. The backwash sequence will be operated manually, either by
push-button operation at the filter control desk, or by manual operation of the filter unit valves
and air blowers. A clock timer will be provided at each filter control desk to allow manual push-
button operation according to the sequence specified above. The flow from the backwash
PAGE 6
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP
compartment of the Tank will be controlled by two different valve settings of the valve controlling
discharge from the backwash compartment, one setting for the combined air scour step and
another setting for the water rinsing step, each of which will have their own push-button control
at the filter control desk.
The top area of the filter battery with the filter control desks will be covered by a common roof
which will protect the filter control desks against rain and sun radiation.
The filter backwash water will be discharged to a system of sludge drying beds. Overflow of
supernatant water from the drying beds will be led to a channel which will discharge to the
natural drainages.
Annex 4-1, S/No.4 presents the detailed calculations for the clarifier unit.
The details of the clarifier unit are as shown in the drawing no. SCEMC-WTP-GA-0004
4.1.9 Disinfection
The provision of safe drinking water requires final disinfection of the treated water to treat the
remaining microbiological water pollution.
It is recommended to ensure water disinfection of the filtered water by means of chlorination
using hydrated Calcium Hypochlorite as chlorine raw product.
For purpose of disinfection, Chlorine will be dosed at a maximum dosage of 2 mg/l.
PAGE 7
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP
The filter media of each sludge drying bed will comprise a top layer of coarse sand to a depth of
30 cm, followed by layer of fine gravel (3 − 6 mm) to a depth of 30 cm, followed by medium
gravel (10 − 12 mm) surrounding a DN250 perforated Steel pipe with drilled holes of 10 mm
diameter spaced at 50 cm intervals center-to-center.
The total depth of one drying bed will be at least 1.0 m above the filter media. About 0.5 m will
be provided for sludge accumulation and storage, and about 0.5 m will be reserved to
accumulate the daily quantity of sludge and backwash water, during periods having the highest
turbidity of the raw water quality.
The drainage water will percolate through the gravel and sand layers into perforated collection
pipes at the bottom of the drying bed. The pipes are sloped towards an outlet channel, from
where the water is conveyed by gravity flow in a common drainage pipe for final disposal. The
drainage pipes can be closed with gate valves.
Above the gate valves, stop logs will be arranged, which have the purpose to define the level of
overflow of supernatant water. Different levels can be adjusted by adding/removing some logs.
The feeding of the influent to the drying beds will be done via a distribution system, including
one inlet chamber which connects to the distribution channels of two individual drying beds by
pipe work. This inlet chamber will include penstocks which can be opened and closed to divide
the flow between the two drying beds. This inlet chamber will also include an overflow weir
which discharges the overflow into a drainage conduit away from the sludge drying beds.
The feeding of the drying beds will be done via the distribution channel of each drying bed, with
each distribution channel having two penstocks discharging onto the surface of the drying bed.
The middle drying bed connected to the inlet chamber will connect to the drying bed on the
other side of its distribution channel. The influent can be discharged to this third drying bed, by
closing the penstock to the inlet of the first drying bed in the inlet chamber, opening the
penstock to the inlet of the middle drying bed in the inlet chamber, closing the two penstocks in
the distribution channel of the middle drying bed, and opening the penstock which connects to
the pipe work connected to the distribution channel of the third drying bed.
The gradients of the bottoms of each distribution channel of each drying bed will have minimum
slope of 1% to achieve the function specified above.
Annex 4-1, S/No.7 presents the detailed calculations for the clarifier unit.
The details of the sludge drying beds are as shown in the drawing no. SCEMC-WTP-GA-0006
PAGE 8
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP
Back wash water suction pipe will be DN150 extended from DN250 suction manifold. The pipe
will branch within the pump house into two, each DN150 complete with DN150 flanged gate
valve, supplying water to individual back wash water pumps.
DN100 non return and gate valves together with pressure gauges will be connected to each
pump to safeguard against hydraulic surges, isolation and monitoring of pump pressure
respectively.
PAGE 9
CONSTRUCTION OF WATER TREATMENT PLANT DETAILED DESIGN REPORT
IN BUNDA TOWNSHIP
The WTP Administration Building will include: two office rooms; one laboratory room; one
workshop room; one bathroom with two urinals and two toilets; and parking space for one
normal-size vehicle underneath a veranda, all under a common roof.
The WTP Staff House will include two apartments, each including: one bedroom; one living
room; one bathroom with sink, toilet and shower; and one kitchen room, connecting to a
covered veranda, all under a common roof.
The WTP Guard House will comprise one room with three windows.
Structural design and drawings were prepared on the basis of the following design codes and
references.
Electrical works for the new works and facilities comprise the following:
Electrical Works at Raw Water Intake Pump Station
Electrical Works at Water Treatment Plant (WTP)
Electrical Works at Booster Pump Stations
Design of electrical works is ongoing and will be submitted in the final version of this report.
PAGE 10