october

Sr no Improvement Projects Activities New plan date Last plan date First plan date Status / remarks
ohmmeter modification from Vendor 10-10-2018 5.10.2018 unit under develoment
testing of ohmemeter unit with the help of NM automation 11-10-2018 6.10.2018 unit under develoment
integration with PLC, with help of NM automation 11-10-2018
alarm limits programming from John sir 12-10-2018
mounting of resistance head, by kotian 10-10-2018 follow up with bhrama
encoder mounting on the head, from bhraman sign 10.10.2018
trials and testing 12-10-2018

Resistance
1 parameter weld defect detection

Wire straightner design by akshay 05-10-2018 25.09.2018 in process


wire straigtner manufacturing by bharama singh 17-10-2018
logic modification for error by gajendra 10-10-2018 already done, under trials
wire straigtner installation, by bhrama 17-10-2018
testing and trials 19-10-2018

Voltage, current,
2 wirfeed parameter based weld defect detection

material checking by gajendra 03-10-2018 done


cross slides on ws 01 reception from drupe 20-10-2018
cross slides installation on ws 01 by kotian and waman 20-10-2018
camera installation on ws 01 20-10-2018
stepper motor for slides on ws 01 by waman 20-10-2018
panel wiring by waman 25-10-2018
panel mounting on ws01 by waman 25-10-2018
ws 01 trials and testing 27-10-2018
ws 20/06 pc installation 03-10-2018
wireless arrangement on ws 01, 06, 20 30-10-2018
common cockpit
integration of ws 01 and ws 04 on same pc, scada development by gajendra 30-10-2018
integration of ws 06 and ws 20 on same pc, scada development by gajendra 30-10-2018
ws 15, ws 21 separate PC 30-10-2018
Dahej
cross slide from drupe 21-10-2018
cross slides installation 22-10-2018
camera installation 23-10-2018
stepper motor for slides on ws 01 by waman 24-10-2018
panel wiring by waman 25-10-2018
panel mounting by waman 26-10-2018
trials and testing 27-10-2018
3 Seam Tracker

mechanical reuirement finalization with prasad sir. 03-10-2018 need meeting with prasad sir.
mechanical deisgn with prasad sir 20-10-2018
arrangement for valves and sensors, stand 20-10-2018
plc and controller finalization, with reddy sir 02-10-2018 done
wiring diagram by waman 10-10-2018
panel drawing by waman 10-10-2018
panel preparation by wmana 20-10-2018
temperature sensors 20-10-2018
plc logic 21-10-2018
HMI programming 22-10-2018 9820186987
integration of valve, hmi and plc over panel 25-10-2018
trials and testing 25-10-2018

7 preheat controller

IO listing 03-10-2018 done


signal flow diagram 03-10-2018 done
communication flow diagram 03-10-2018 done
electrical drawing 05-10-2018 Drawing are made on paper
panel layout 05-10-2018
panel cutouts and wiring by waman 08-10-2018
mounting of ink controller 10-10-2018
pumch marker system mounting 15-10-2018
PLC programming by gajendra 10-10-2018
hmi programmimg 10-10-2018
robot integration with robo 18-10-2018
Track and panel wiring 26-10-2018
auto flushing system 03-11-2018
auto flushing system mounting 11-11-2018

trials

8 Shell Marking

10
10

11

12

13

14

15

16

15