Gujarat State Civil Supplies Corporation Ltd.

MEASUREMENT
Name Of Work :- Construction of 2000 M . T. Godown Buildinng Office and Ancillary
Work At - Sutrapada, Una & Gir Gadhada Dist - Gir Somnath and Junagadh
( Khadia) Dist - Junagadh

Name of Agency :- M/S Arjun Construction Company

Sutrapada Measurment ( 5 th R A Bill )

Item No. No. L B D Qty Unit


ITEM NO - 6
Providing and Laying Cement concrete 1;3;6 ( 1- Cement ; 3- Course Sand ; 6- hand
broken stone aggregate 40 mm Nominal size and Curing Complete excluding cos of
formwork in (A) Foundation and Plinth.

Flooring Concrete 1 1 52.75 21.35 0.15 168.93

Total 168.93 Cum

ITEM NO - 11
Filing Foundation and plinth with sand under floors including watering remming and
consolidating dressing etc comp.
godowen in side 1 1 52.75 21.35 0.18 202.71

Total 202.71 Cum

ITEM NO - 12
Appliying General insectide pest control treatment to floor cupbord etc including
labour and materials etc.complete.

1 1 53.65 22.25 1193.71

Total 1193.71 Sqm


ITEM NO - 13
Providing and laying trimix vacume dewatering processcement concrete work
ordinary M- 200 and curing complete including compaction & Finishing of cement
concrete road by Trimix process providing extra labour charge for trimix vaccum
dewatring servise process on cement concrete road surface by using vaccum
dewatring pump floter surface vibrator including making groove 5mm width and
filling with polynile kpolynier and rough finish to surface as per instruction including
levelling etc complete for Trimix Floor Surface.

godowen in side 1 1 52.75 21.35 0.15 168.93

Total 168.93 Cum


ITEM NO - 14
Page 1 of 11
Item No. No. L B D Qty Unit
Providing and Laying Controlled Cement Concrete M - 200 and with curing etc comp.
Including the cost of formwork but excluding cost of rainforcement for
rainforcement concrete for Columns, Pilers, and strust, At - Ground Floor

1 40 0.45 0.45 0.50 4.05 Cum

Page 2 of 11
Item No. No. L B D Qty Unit
ITEM NO - 15
Providing and Laying Controlled Cement Concrete M - 200 and with curing etc comp.
Including the cost of formwork but excluding cost of rainforcement for
rainforcement concrete for Columns, Pilers, and strust, At - First Floor

1 40 0.45 0.45 1.50 12.15

12.15 Cum
ITEM NO - 17
Providing and Laying Controlled Cement Concrete M - 200 and curing complete
Including the cost of formwork but excluding cost of rainforcement for reinforced
concrete work in LINTAL Ground Floor.

front side & back side 1 24 3.35 0.23 0.30 5.54


Left & Right Side 1 7 3.35 0.23 0.30 1.61
1 4 2.85 0.23 0.30 0.78
rolling shutter 1 5 3.35 0.23 0.45 1.73

Total 9.66 Cum

ITEM NO - 18
Providing and Laying Controlled Cement Concrete M - 200 and with curing etc comp.
Including the cost of formwork but excluding cost of rainforcement for
rainforcement concrete work in Chhaja for All Floors.

windo chhaja 1 20 2.20 0.45 0.115 2.27


Rolling shutter chhaja 1 5 2.50 1.20 0.115 1.72

Total 3.99 Cum

ITEM NO - 19
Providing and Laying Controlled Cement Concrete M - 200 and with curing etc comp.
Including the cost of formwork but excluding cost of rainforcement for
rainforcement concrete work in Vertical and Horizontal Fins / Padadi for all Floors

windo projection 1 20 2.2 0.83 0.10 3.65

3.65 Cum
ITEM NO - 20
Providing TMT Bar Fe 500/500D Reinforcement for R.C.C Work including bending
binding and placing in Position complete up to floor two level.

Attach Separate Sheet = 24079.85 Kg

Page 3 of 11
Item No. No. L B D Qty Unit
ITEM NO - 21
Providing and Laying brick work using common burnt building conventional type
brick having crusing strength not less than 35 Kg./sq cm in super structure in cement
morter 1;6 ( 1 - cement ; 6 fine sand) for GROUND FLOOR including the cost of all
materials and labour charge etc complete.

Horizontal wall 2 14 3.35 0.23 2.60 56.09


vertical wall 2 4 3.35 0.23 2.60 16.02
2 2 2.85 0.23 2.60 6.81

Total 78.92 A
Deduction
W 1 20 2.00 0.23 0.60 5.52
shutter 1 5 2.55 0.23 2.60 7.62

Total 13.14 B

Net Total = A - B 65.78 Cum

PART - 5

ITEM NO - 128
Box cutting the road surface to proper slop and camber for making a base for road
work including removing the excavated stuff with disposing on the road slop as
directed up to 50mt lead.

main road 1 1 52.80 7.50 0.30 118.8


side road 1 1 22.25 8.00 0.30 53.4
1 1 22.25 7.50 0.30 50.06
back side road 1 1 69.15 6.20 0.30 128.61
front side road 1 1 69.15 7.50 0.30 155.58
office road 1 1 27.50 4.00 0.30 33.00

Total 539.45 Cum


ITEM NO - 129
Providing and laying Compacted Water bound Macadem of compacted 150mm
( average ) thick Grade - II as per MORT&H specification using crushed MT metal of
size 45mm to 63mm with using 13% stone screening 13.2 mm nominal size and
binding materials @ 7% stone dust as filler including spreading in uniform thickness
watering and consolidation with vibratory roller etc complete.

main road 1 1 52.80 7.50 0.20 79.2


side road 1 1 22.25 8.00 0.20 35.6
1 1 22.25 7.50 0.20 33.37
back side road 1 1 69.15 6.20 0.20 85.74
front side road 1 1 69.15 7.50 0.20 103.72
office road 1 1 27.50 4.00 0.20 22.00
Page 4 of 11
Item No. No. L B D Qty Unit

Total 359.63 Cum

Page 5 of 11
Item No. No. L B D Qty Unit
ITEM NO - 130
Suppling Stacking and Spreading Murrum including compacting etc completed.

50 % of Item No - 129 1 1 359.63 0.50 179.81

Total 179.81 Cum

ITEM NO - 131
Providing and Laying foundation cement concrete 1;3;6 ( 1 - cement , 3 - coarse
sand , 6 aggregate) 20mm nominal size) graded concrete and curing complete.

main road 1 1 52.80 7.50 0.20 79.2


side road 1 1 22.25 8.00 0.20 35.6
1 1 22.25 7.50 0.20 33.37
back side road 1 1 69.15 6.20 0.20 85.74
front side road 1 1 69.15 7.50 0.20 103.72
office road 1 1 27.50 4.00 0.20 22.00

Total 359.63 Cum

ITEM NO - 132
Providing and Laying Controlled cement concrete M - 250 and curing etc. comp
excluding the cost of form work and reinforcement for RCC work for interial road.

main road 1 1 52.80 7.50 0.20 79.2


side road 1 1 22.25 8.00 0.20 35.6
1 1 22.25 7.50 0.20 33.37
back side road 1 1 69.15 6.20 0.20 85.74
front side road 1 1 69.15 7.50 0.20 103.72
office road 1 1 27.50 4.00 0.20 22.00

Total 359.63 Cum

ITEM NO - 133
Compaction and finishing of cement concrete road by Trimix process providing extra
labour charge for trimix ( vacuum dewatering service) process on cement concrete
road surface by using vacuum dewatering pump flotter surface vibrator including
making groove 5mm width and filing with polyvynile polymer and rough finished to
surface as per instruction leveling etc. complete.

main road 1 1 52.80 7.50 396


side road 1 1 22.25 8.00 178
1 1 22.25 7.50 166.87
back side road 1 1 69.15 6.20 428.73
front side road 1 1 69.15 7.50 518.62
Page 6 of 11
Item No. No. L B D Qty Unit
office road 1 1 27.50 4.00 110

Total 1798.22 sqm

Page 7 of 11
Item No. No. L B D Qty Unit

ITEM NO - 134
Providing I .S. I Mark Fe - 500/500D Reinforcement for R.C.C Work including bending
binding and placing in position up to floor two level for All Floor

Attach Sheet = 10531.69 Kg

Page 8 of 11
Providing I .S. I Mark Fe - 500/500D Reinforcement for R.C.C Work including bending binding and placing in position up
Item No. 20 to floor two level for All Floor

Items Shape Cutting Dia. Of steel


Dia. in No. Length
No. No. 8mm 10mm 12mm 16mm 20mm 25mm
mm in
32mm (6.32)
meter (0.39) (0.62) (0.89) (1.58) (2.47) (3.85)
8mm 10mm 12mm 16mm 20mm 25mm 32mm
LINTAL & CHHAJA STEEL - - - - - - -
- - - - - - -
Horizontal - - - - - - -
Top 12 2 1 2 53.99 - - 215.96 - - - -
Bot 16 2 1 2 53.99 - - - 215.96 - - -
Ring 8 2 1 537 0.56 601.44 - - - - - -
Extra Bar 16 2 1 13 2.55 - - - 66.30 - - -
16 2 1 2 1.28 - - - 5.12 - - -
Laping 12 2 1 5 0.60 - - 6.00 - - - -
16 2 1 5 0.80 - - - 8.00 - - -
- - - - - - -
- - - - - - -
Vertical - - - - - - -
Top 12 2 1 2 22.67 - - 90.68 - - - -
Bot 16 2 1 2 22.67 - - - 90.68 - - -
Ring 8 2 1 226 0.56 253.12 - - - - - -
Extra Bar 16 2 1 5 2.55 - - - 25.50 - - -
16 2 1 2 1.28 - - - 5.12 - - -
Laping 12 1 1 2 0.60 - - 1.20 - - - -
16 1 1 2 0.80 - - - 1.60 - - -
- - - - - - -
- - - - - - -
Windo chhipya chhipya 8 20 1 15 1.71 513.00 - - - - - -
8 20 1 15 1.13 339.00 - - - - - -
Dist bar 8 20 1 7 2.10 294.00 - - - - - -
- - - - - - -
Page 9 of 11
Items Shape Cutting Dia. Of steel
Dia. in No. Length
No. No. 8mm 10mm 12mm 16mm 20mm 25mm
mm in
32mm (6.32)
meter (0.39) (0.62) (0.89) (1.58) (2.47) (3.85)
8mm 10mm 12mm 16mm 20mm 25mm 32mm
Rolling Shutter Chhipya - - - - - - -
Top bar Extra 16 5 1 2 4.40 - - - 44.00 - - -
Ring 8 5 1 34 3.67 623.90 - - - - - -
Dist bar 8 5 1 12 2.50 150.00 - - - - - -
- - - - - - -
Trimix Flooring - - - - - - -
- - - - - - -
- - - - - - -
Main steel 10 1 1 440 21.35 - 9394.00 - - - - -
10 1 1 178 52.75 - 9389.50 - - - - -
lap 10 1 1 440 0.60 - 264.00 - - - - -
10 1 4 178 0.60 - 427.20 - - - - -
outer road
back side road 10 1 15 52 4.50 - 3510.00 - - - - -
10 1 15 40 6.10 - 3660.00 - - - - -
Front side road 10 1 15 64 4.50 - 4320.00 - - - - -
10 1 15 40 7.50 - 4500.00 - - - - -
- - - - - - -
length 2774.46 35464.70 313.84 462.28 0.00 0.00 0.00
kg/m 0.39 0.62 0.89 1.58 2.47 3.85 6.32
kg. 1082.03 21988.11 279.31 730.4 0 0 0
Total kg. 24079.85

Page 10 of 11
Providing I .S. I Mark Fe - 415 TMT bar Reinforcement for R.C.C Work including bending binding and
Item No. 134 placing in position up to floor two level for All Floor

Sh Dia. Of steel
Dia.
Item ap in No. No. Cutting
No. Length in 8mm
meter 10mm 12mm 16mm 20mm 25mm 32mm (6.32)
mm (0.39) (0.62) (0.89) (1.58) (2.47) (3.85)
e
8mm 10mm 12mm 16mm 20mm 25mm 32mm
- - - - - - -
Trimix Road - - - - - - -
- - - - - - -
- - - - - - -
Main Road Main steel 10 1 11 68 5.00 - 3740.00 - - - - -
10 1 11 45 7.40 - 3663.00 - - - - -
Side road Main steel 10 1 6 71 4.35 - 1853.10 - - - - -
10 1 6 41 7.90 - 1943.40 - - - - -
10 1 6 68 4.35 - 1774.80 - - - - -
10 1 6 42 7.40 - 1864.80 - - - - -
Office road 10 1 5 39 5.40 - 1053.00 - - - - -
10 1 5 51 3.90 - 994.50 - - - - -
lap 10 1 2 100 0.50 - 100.00 - - - - -

length 0.00 16986.60 0.00 0.00 0.00 0.00 0.00


kg/m 0.39 0.62 0.89 1.58 2.47 3.85 6.32
kg. 0 10531.69 0 0 0 0.00 0
Total kg. 10531.69