unit Quantity Productivity Productivity unit Duration Productivity/ Persons FXG= Final Duration
(Days) Day/ Person (No.) DAYS
(ROUNDED)
Sl.no Description
1 Land Acquisition 60
2 Statutory Clearence Approval 45
3 Design Brief 3
4 Proposal 15
5 Approvals 30
6 Site Preparation 10
7 Setting Out 2
SUBSTRUCTURE
8 Excavation Cum 185.472 0.8 CUM/D/2 231.84 0.4 20 8 23
9 Rubble Soaling SQM 39.52 0.2 SQM/D/2 197.6 0.1 20 2 20
10 P.C.C. Cum 5.928 0.65 CUM/D/4 9.12 0.163 10 1.63 4
R.C.C. footing
11 Shuttering 4
12 CBT of Concrete 2
13 Pouring of Concrete Cum 20.7 0.6 CUM/D/4 34.5 0.15 8 1.2 17
14 Curing of Concrete 7
15 De-Shuttering 2
R.C.C. columns
16 Shuttering 4
17 CBT of Concrete 2
18 Pouring of Concrete Cum 3.024 0.6 CUM/D/4 5.04 0.15 8 1.2 3
19 Curing of Concrete 7
20 De-Shuttering 2
21 Murum filling. Cum 44.85 0.5 CUM/D/3 89.7 0.167 6 1.00 45
RCC Ground Beams
22 Shuttering 4
23 CBT of Concrete 2
24 Pouring of Concrete CUM 6.6 0.6 CUM/D/4 11 0.15 8 1.2 6
25 Curing of Concrete 7
26 De-Shuttering 2
27 Brick Masonary in Plinth CUM 5.106 1.25 CUM/D/4 4.0848 0.313 4 1.252 4
RCC Plinth Beams
28 Shuttering 4
29 CBT of Concrete 2
30 Pouring of Concrete CUM 9.9 0.6 CUM/D/4 16.5 0.15 8 1.2 8
31 Curing of Concrete 7
32 De-Shuttering 2
33 PCC and DPC CUM 29.25 0.65 CUM/D/4 45 0.163 8 1.30 22
SUPERSTRUCTURE
RCC Columns Till First Slab
34 Shuttering 4
35 CBT of Concrete 2
36 Pouring of Concrete CUM 8.2 0.6 CUM/D/4 13.66667 0.15 10 1.5 5
37 Curing of Concrete 7
38 De-Shuttering 2
RCC Slab & Floor Beams
39 Shuttering 4
40 CBT of Concrete 2
41 Condute 2
42 Pouring of Concrete CUM 29.25 0.6 CUM/D/4 48.75 0.15 10 1.5 20
43 Curing of Concrete 7
44 De-Shuttering 2
45 Brick Masonry till sill level CUM 10 1.25 CUM/D/4 8 0.313 8 2.504 4
46 Placement of Windows and Door Frames NO. 16 7
47 Brick Masonry till lintel level CUM 32 1.25 CUM/D/4 25.6 0.313 8 2.504 13
Placment of Lintel and Chajja
48 Shuttering 2
49 CBT of Concrete 2
50 Pouring of Concrete CUM 0.864 0.6 CUM/D/4 1.44 0.15 2 0.3 3
51 Curing of Concrete 7
52 De-Shuttering 1
53 Brick Masonry Beam Level & in Parapet CUM 14 1.25 CUM/D/4 11.2 0.313 8 2.504 6
54 Waterproofing of Terrace SQM 160 15
55 External Plaster SQM 268.8 3 SQM/D/6 89.6 0.5 18 9 30
56 Internal Plaster SQM 252 4 SQM/D/4 63 1 18 18 14
57 Electrification 32
58 Plumbing 21
59 Flooring SQM 195 4 SQM/D/3 48.75 1.333 8 10.664 18
60 Internal Painting SQM 252 8 SQM/D/3 31.5 2.667 8 21.336 12
61 External Painting SQM 268.8 6 SQM/D/4 44.8 1.5 8 12 22
62 Placing Doors and Windows NO. 16 7
63 Snag list 10
64 Handover 8
TOTAL
DURATION
667
Project : Bunglow
Measurement Sheet
Sr. No Item No L/ rL
SUB - STRUCTURE
1 Excavation 16 2.8
2 Rubble Soaling 230mm thk 16 1.9
3 P.C.C. 16 1.9
4 R.C.C. footing 16 1.8
5 R.C.C. columns 16 0.6
6 RCC Plinth Beams (pb1,pb3,pb8,pb15) 4 3.9
7 RCC Plinth Beams (pb5,sb1,pb10,pb13) 4 5
8 RCC Plinth Beams (pb23,pb21,pb19,pb17) 4 3.9
9 RCC Plinth Beams (pb4,pb2) 2 3.2
10 RCC Plinth Beams (pb7,pb9) 2 5
11 RCC plinth Beams (pb16,pb14,pb12,pb18) 4 6.6
12 RCC Plinth Beams (pb6,pb22) 2 5.5
13 RCC Plinth Beams (pb11,pb20) 2 2.6
14 Brick Masonary in Plinth 1 74
15 Murum filling (back Filling) 1 15
16 Soiling 230mm thk for ground level pcc 1 15
17 PCC and DPC 1 15
18 Ground Beam 1 147
SUPERSTRUCTURE
19 RCC Columns Till First Slab 16 0.6
20 RCC Slab (S1-S9) 1 15
21 Brick Masonry till sill level 230mm 1 64
22 Brick Masonry till sill level 115mm 1 30
23 Placement of Windows and Door Frames 16 1
24 Brick Masonry till lintel level 115 mm 1 30
25 Brick Masonry till lintel level 230 mm 1 64
26 Placment of Lintel and Chajja 1 14.4
27 Brick Masonry Beam Level 230mm thk 1 64
28 Brick Masonry Beam Level 115mm thk 1 30
29 Waterproofing of Terrace 1 16
30 External Plaster 1 64
31 Internal Plaster 1 60
32 Electrification
33 Plumbing
34 Flooring 1 15
35 Painting Internal 1 60
36 Painting External 1 64
37 Placing Doors and Windows 16 1
B H/D unit quantity