Bill of Quantities
Water Supply Extension to Innamaluwa and Kithulhitiyawa
Central Province, Sri Lanka
1. General
The Contractor’s attention is specifically directed to the Conditions of Contract, Specification and the Drawings,
which are to be read in conjunction with the Bill of Quantities and the Preamble.
3. Method of Measurement
The Works as executed will be measured for payment in accordance with the method adopted in the Bill of
Quantities and under the item as set forth therein. The net measurement or weight of the finished work in place
will always be taken, and except where otherwise stated or where separate items are provided, no allowance
will be made for cutting, waste, laps, circular work, etc., and no deductions will be made for grout nicks, joggle
holes, rounded arises or for shrinkage for fitting ironwork and the like.
Payment will be made only for those materials, which are specified and permanently installed in the works to
the approval of the Engineer. Construction materials supplied and delivered to the site by the Contractor which
become surplus to the requirements of the works shall become the property of the Contractor who shall
reimburse the Employer any money that was paid to the Contractor for the supply and delivery to site of the
surplus materials.
The Bidder shall indicate the total amount for each item (i.e. the quantity multiplied by the rate) to the nearest
cent when inserting the figures in the BOQ.
i. All the bonds and guarantees related to all the works under this contract
ii. All site investigations, which may be necessary;
iii. All setting out and survey work;
iv. Temporary fencing, watching, and lighting;
v. Paying fees and giving notice to authorities;
vi. Payment of all patent rights and royalties;
Page 1 of 71
vii. Reinstatement of the site;
viii. Safety precautions and all measures to prevent and suppress fire and other hazards;
ix. Workers camps may be located within the site depending on the availability of space and there are no issues
for the possession of the site, once the contract is signed. Women shall be given equal pay for work of
equal value;
x. Workers camps should be provided with sanitary amenities as per the standards given in the IFC (2009)
Worker’s Accommodation: Processes and standards. At least 1 toilet per 15 workers should be provided
with separate facilities for males and females and site should be kept clean and solid waste and waste
water disposal should be carried out as per the CEA regulations. All toilets should be kept 50 m away
from drinking water sources;
xi. Interference to the works by persons, vehicles, and the like using the existing facilities;
xii. Works in connection with the protection and safety of adjacent structures;
xiii. Supplying, maintaining and removing on completion Contractor’s own accommodation, offices including
Engineer’s office, stores, workshops, transport, welfare services and all charge in connection therewith;
except those for which a separate BOQ item is provided;
xiv. Working in the dry except where otherwise permitted by the specification;
xv. Maintaining access roads;
xvi. The supply, inspection, sampling and testing of materials and of the Works under construction, including the
provision and use of equipment;
xvii. Except where separate items are provided for bringing plant to the site and removing on completion, for
providing, transporting to site, setting to work operating (including all fuel and consumable stores),
maintaining and removing from the site upon completion all construction plant and equipment
necessary for the execution of the work, including the cost of all tests and other requirements in respect
to such plant and equipment;
xviii. The recruitment, bringing to and from the site, accommodating and feeding and all incidental costs and
expenses involved in the provision of all necessary skilled and unskilled labour and supervision, except
for whom a separate BOQ item is provided;
xix. All statutory taxes and levy, surcharges etc. including stamp duty payable on the contract, which will have
to be borne by the Contractor.\
xx. All costs of supplying water and electricity to the site for the completion of works.
xxi. All costs of providing safe accommodation to the Employees.
xxii. Final cleaning and handing over of facility in a good condition including submission of as built drawings.
xxiii. Marking the trace of the pipe line and obtain the approval from the Engineer. If it is along the road before
marking, obtain the offset from the centre of the road from RDA or PRDA or other road maintenance
authority as applicable
xxiv. The maximum length of open trench excavation which can be left ahead of pipe line is only 20m. Pipe laying
should be done on a bedding of well graded sand height 100 to 150mm above the trench bottom or as
shown in the drawings. Backfilling up to 300mm above crown of the pipes to be done with soft material
free of stones of size more than 2.5cm. Backfilling should be done leaving the joints open until the
pressure testing is over.
xxv. The cost of repairing damages to the existing road surface outside the pipe trenching or any structure due
to carrying out work of the contract, shall be borne by the contractor.
xxvi. Locations of air valves and scour valves should be indicated by standard concrete markers giving the etc.
xxvii. Testing of materials, pressure and leak testing and completed works as per the ICTAD (SCA/3/2)
specifications
xxviii. Management of traffic, safety control measures, erecting barricading and sign boards
xxix. Provision of temporary accesses to residents’ property during construction
xxx. Contractor when operating on a road shall not work in a continuous stretch more than 500m long and two
such working stretches shall have a gap of 500m to minimize road users’ inconvenience. The schedule
of work shall be submitted to the road maintenance authority and get concurrence for work. A copy
should be sent to the Engineer
xxxi. Any unsuitable material for use in works shall be taken away from the site by the contractor
xxxii. The Contractor shall establish stores facility for handling, storage and issuing of supply items such as uPVC
/DI/GI pipes/fittings/specials brought to the site and shall maintain above stores. He shall employ an
experienced store keeper for proper record keeping purposes. The PVC pipes supplied shall be under proper
cover, not exposed to elements, and not get flooded. This facility shall be accessible to the Engineer and
have security, fencing, lighting etc;
Page 2 of 71
No claim will be considered for further payment in respect of any work or method of execution, which may be
described in the Contract or is inherent in the construction of the work and detailed on the drawings on account
of
(1) any omission from the wording of the items or from a clause in the Preamble or
(2) no mention of such work or method of execution having been in the Preamble
Items against which no rates or sum is entered by the Contractor, whether quantities are stated or not, will not
be paid for when executed, but will be regarded as covered by other rates in the Bills of Quantities.
The quantities set out in the Bills of Quantities are the estimated quantities of the work and they shall not be
taken as the actual and correct quantities of the works to be executed by the contractor in fulfillment of his
obligation under the contact.
The Contractor shall be deemed to have taken into account all recognized holidays, festivals, religious and
other customs in his Bid Prices and his Construction Programmes.
However, the Contractor shall ascertain the exact nature and extent of work to be performed by reference to
the Drawings, Specifications and Conditions of Contract as the case may be.
Provisional Sums are represented by the words “Provisional Sum” or “PS” entered under the description.
The Bidder shall indicate a percentage figure and the amount in the appropriate BOQ item provided, based on
the total sum of all such “Provisional Sums”, to cover up his overhead costs, profits and any other related costs
involved in executing the work under provisional sum items.
The total payment to the Contractor under this BOQ item will be assessed by applying the percentage rate
indicated by Contractor on the actual total amount of Provisional Sums spent in the Contract.
No claim will be entertained in respect of overhead charges or any other costs, which may allegedly result from
the omission of all, or part of the work covered by such “Provisional Quantity” Items.
Certain manpower inputs by the Contractor for certain specific positions will be paid under the BOQ items if
provided for this purpose. Any other manpower inputs by the Contractor will not be paid under these items.
Page 3 of 71
10. Payment of Lump Sums for General and Other Items
Lump Sum items stipulated in Bill No. 1 and where the Bidder includes additional items for complying with the
general conditions etc. will be paid on the basis of a proportion of respective lump sum in the same ratio as the
value of the work completed bears to the total value of the Contract.
Lump Sum items stipulated in Bill No. 1 which are related to a specific work will be paid on the basis of the
proportion of actual work done to the total work of that specific item as assessed by the Engineer.
Items with quantities and units will be paid against number of units used and/or incorporated in the works.
12. Demolition
The rates and prices for demolition shall include for;
14. Earthworks
(1) Excavation in all Material except Rock
The rates and prices for excavations shall be for all types of material encountered except rock including ground
conditions above or below water level. The Contractor must make due allowance for the possibility of
permission not being granted to the use of explosives for blasting and other operations.
(a) For structures, volume of material excavated measured as the product of the horizontal area of the base
of permanent work to be constructed and the mean depth below ground level, or measured as the volume
to be occupied by permanent work below ground level, whichever is the greater.
In no case shall any of the following quantities be included in the measurement for payment.
i. Quantity outside the vertical planes of neat outline of foundation structures unless shown
otherwise on the drawings.
ii. Quantity of excavation and/or backfill for water supply pipe lines, sewer pipelines, and storm
drainage except as allowed for in pipeline construction as specified.
iii. Quantity of any excavation performed prior to the taking of measurements of the undisturbed
natural ground.
iv. Quantity of any material re-handled, except where the drawings indicate or the Engineer directs
the excavation after embankment has been placed.
v. Removal of slides, cave-ins, silting or filling due to the action of the elements or weather and/or
carelessness of the Contractor.
Page 4 of 71
(b) For unsuitable material, volume of excavated material shall be measured as volume of material (below
base of the permanent works) directed to be removed by the Engineer. However, this does not include
removal of material rendered unsuitable due to contractor's method of excavation.
No allowance is made for bulking or for any extra transport required due to bulking. The rates shall include, if
separate items are not provided but not by way of limitation, for:
i. excavation to the correct depth and preserving the bottoms of excavations in a state suitable for
the reception of concrete or other foundation work, and no payment will be made for any concrete
or any bedding required for filling over-excavated volumes or disturbed areas to the net
dimensions as indicated on the Drawings,
ii. any additional excavation required for shuttering, working space, temporary or permanent
shoring, and subsequent refilling and ramming and disposal of surplus and back fills behind
structures,
iii. provision of storage areas for the temporary storage of any material required for back filling which
cannot be stored alongside the excavation for any reason, together with the cost of transporting,
loading including disposal of surplus and unloading such material and all other charges incurred
in this respect,
iv. trimming the bottoms of excavations including bottoming to falls, and trimming to sloping surfaces
where required or indicated on the Drawings,
v. taking all precautions by supporting faces of excavation to ensure the safety of the workmen and
to prevent damage to adjacent walls, building and all other structures and services, including
permanent and/or temporary shoring of trenches,
vi. keeping the site and trenches and all other excavations free from water from whatever cause
arising,
vii. for clearing any scrub or other vegetable growth including all trees and for disposing of the whole
of the cleared material to tip provided by the Contractor,
viii. all temporary and permanent measures required to protect and support all existing pipes, cables
and services, including all chambers, gullies and foundations thereto, or repair or replace them
should they become damaged due to the Contractor’s activities,
ix. all barriers, lighting, warning signs and any other measures necessary to ensure complete safety
around the area of the works,
x. reinstatement except where separate items are included.
Excavation in rock, which shall, in all cases, be measured extra over measurement under 1(a) or 1(b) above by
volume from the level at which rock is encountered. For work described under 1(a) and 1(b), measurement
shall be as specified therein.
(3) Fill
Fill shall be measured as the net volume above ground level of the permanent earthwork to the dimensions
shown on the Drawings or ordered by the Engineer, irrespective of source of material. The rate shall include
for selection, handling, placing, compaction of excavated or imported material and cost of control and material
selecting tests (field and laboratory). Costs incurred in connection with the remedial work ordered by the
Engineer consequent to the results of control tests falling below the minimum specified shall be borne by the
Contractor.
15. Concrete
The rates for concrete are to include for
i all costs incurred in determining the mixes to satisfy the Specification ( including any admixtures);
ii. supplying all material (including any admixtures), storing, mixing, transporting, placing and
compaction (whether by hand or vibration);
iii. excavation as required below previously filled levels and back filling (except where separate items
are provided);
iv. roughening the surface of previously executed work as required in order to provide the necessary
bond with new concrete;
v. achieving specified tolerance;
vi. forming sloping, falls and the like;
Page 5 of 71
vii. forming holes or boxing out for pipes, bolts, frames for covers and other steel work;
viii. building in cable conduit, pipes, junction boxes etc;
ix. forming 25mm chamfers on all external arises to exposed concrete;
x. forming all construction joints, keys, stop ends, temporary stops and shuttering of other than
permanently exposed faces (except where separate items are provided);
xi. curing the concrete and all measures to protect freshly poured concrete from direct sunlight and wave
action;
xii. troweling, rubbing down etc. and making good the concrete surfaces to provide the specified finishes;
xiii. the cost of control testing throughout the period of concreting and for the testing of concrete and
remedial work ordered by the Engineer consequent to the results of control tests falling below the
minimum specified;
xiv. overtime working to maintain continuity of casting;
xv. a daily return to the Engineer showing the quantities of cement and the volume of concrete placed
and compacted in position, of each class of concrete in each section of the works and temporary
works.
xvi. and other such related works
The measurement of concrete shall be by cubic metre, square metre or linear metre of completed structure as
in the Bill of Quantities. Where volumetric measure is used, no deductions will be made for channels, recesses
or rebates less than 600mm girth, for splays or chamfers less than 300mm measured on the splay nor for holes
or ducts formed in the concrete less than 1m girth. Fillets less than 300mm on the splay will be measured.
Note: Hand mixing will not be allowed for structural concrete works.
i. general formwork, working in narrow spaces and small quantities, for setting up, strutting and
supporting at any height, together with any necessary strutting and supporting through lower floors,
applying mould oil, use of polythene, easing, striking and removing, cleaning preparing for reuse,
and removal , including all props, stays, struts, wedges, bolts etc;
ii. all fillets to form grooves, rebates, throats, splays or chamfers, raking, circular cutting, cutting
around all pipes, sleeves, conduits etc;
The unit of measurement for steel reinforcement is the Kilogram (kg.) and the weight of steel has been
calculated net with no allowance made for wastage or laps and the cost of these will be deemed to be covered
in the rates.
The weight of steel supports, spacer bars and ties, but including stirrups and binders, used to locate and hold
the reinforcement in place is not included in the quantity and the cost of these will be deemed to be covered in
the rates.
18. Timber
The rates for timber shall include for all handling, labour and waste, for all chamfers and nosing and for
protective treatment except where otherwise provided. The rates for timber for permanent works are to allow
for the use of new properly seasoned new timber.
Page 6 of 71
19. Brickwork
The basis of measurement for brickwork walls shall be the overall area of the walls measured in plane elevation,
no allowance being made for setbacks, recesses and nibs.
Rates for brickwork shall include for bricks of the thickness stated bounded in cement mortar, damp proof
course, finishing around all openings vertical expansion joints as required, building in electrical conduit and
small pipes and tubes, galvanized wire ties to steel work and concrete.
Unit Abbreviation
Meter m, lm
Square meter m2 or sq m
Cubic meter m3 or cu m
Cube Cube, cu
Kilo gran kg
Tonne t
Linear Feet Ft, L.ft,
Number no
Provisional Sum PS
Lump Sum LS
Square Feet sq.ft
pound(112) cwt
Month mon
Labour day L.day
Man Month MM
Sri Lanka Rupees LKR
Cents. Cts.
i General
Reference should be made to Clause 13.6 of the General Conditions of Contract. Work shall not be executed
on a day work basis except by written order of the Engineer. Contractors shall enter rates for day work items in
schedules, which rates shall apply to any quantity of day work ordered by the Engineer.
Page 7 of 71
The Contractors shall price all items in the day work schedule for Labour, Constructional Plant and
Material.
Labour
The contractor is to enter hereunder the individual rates for labour for skilled and unskilled workers and gangers
employed on day works solely on the direction of the Engineer. The quantities given below are all provisional
and these rates shall include to cover all costs of the Contractor including the amount of wages paid to such
labour, transportation time, overtime, subsistence allowance, and any sums paid to or on behalf of such labour
for social benefits in accordance with law of the country, as well as Contractor's profit, overheads,
superintendence, liabilities and insurance and allowance to labour, timekeeping and clerical and office work,
the use of consumable stores, water, lighting and power use and repair of staging, scaffolding, workshops and
stores, portable power tools, manual plant and tools; supervision by the Contractor's staff, foremen and other
supervisory personnel; and charges incidental to the foregoing.
Constructional Plant
The Contractor shall be entitled to payments in respect of Constructional Plant already on Site and employed
on day work at the rental rates entered by him in the "Schedule of Day work Rates: Constructional Plant”.
The rates shall be deemed to include due and complete allowance for depreciation, interest, indemnity and
insurance, repairs, maintenance, supplies, fuel, lubricants, and other consumable, and all overhead profit and
administrative costs related to the use of such plant. The cost of drivers, operators and assistants will be paid
for separately as described under the section on Day work: Labour.
In calculating the payment due to the Contractor for Constructional Plant employed on day work, only the actual
number of working hours will be eligible for payment, except that where applicable and agreed with the
Engineer, the traveling time from the part of the Site where the Constructional Plant was located when ordered
by the Engineer to be employed on day work and the time for return journey thereto shall be included for
payment.
Materials
The contractor shall be entitled to payments in respect of materials used for day work at the rates entered by
him in the "Schedule of Day work Rates: Materials" together with an additional percentage payment on the
basic rate to cover overhead charges and profit as follows:
i The basic rates for materials shall be calculated on the basis of the invoiced price, freight, insurance,
handling expenses, damages, losses, etc., and shall provide for delivery to store for stock piling at the
Site as directed by the Engineer. The contractor may allow an additional percentage payment on the
actual cost of materials to allow for his handling and storage costs, overhead profit. The percentage
mark-up cost shall be inserted by the Contractor in the appropriate item in the Day work Schedule.
ii The cost of hauling materials for use on work ordered to be carried out as day work from the store or
stockpile on the Site to the place where it is to be used will be paid in accordance with the terms for
Labour and Constructional Plant.
Page 8 of 71
PURA NEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT
ADDITIONAL FINANCING
CONTRACT NO: - CP-AF-WS-CKD-10B
SUPPLY & LAYING OF uPVC/ DI/ GI/ PE PIPES FITTINGS AND SPECIALS FOR WATER SUPPLY
EXTENSION TO INAMALUWA & KITHULHITIYAWA (RURAL AREAS)
BILL OF QUANTITES
GRAND SUMMARY
Supply & delivery of uPVC/DI/GI Pipes fittings & Specials for Inamaluwa &
BILL NO.02
Kithulhitiyawa
Laying of uPVC/DI/GI Pipes fittings & Specials for Inamaluwa &
BILL NO.03
Kithulhitiyawa
SUB TOTAL - 01
Any Discounts
SUB TOTAL - 02
……………………………………………………………………………………………………………………………………………………………………………….
……………………………………………………………………………………………………………………………………………………………………………….
……………………………………………………………………………………………………………………………………………………………………………….
……………………………………………… ………………………………….
Page 9 of 71
PURA NEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT
ADDITIONAL FINANCING
CONTRACT NO: - CP-AF-WS-CKD-10B
SUPPLY & LAYING OF uPVC/ DI/ GI/ PE PIPES FITTINGS AND SPECIALS FOR WATER SUPPLY
EXTENSION TO INAMALUWA & KITHULHITIYAWA (RURAL AREAS)
BILL OF QUANTITES
BILL NO: 01 -GENERAL
CESM
Item Rate Amount
M3 Description Unit Qty
No (Rs.) (Rs.)
Code
Allow for all Costs and Expenses for
Complying with the General Conditions of
Contract and Specifications.
Page 10 of 71
CESM
Item Rate Amount
M3 Description Unit Qty
No (Rs.) (Rs.)
Code
Total of Page No.10 brought forward
Page 11 of 71
PURA NEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT
ADDITIONAL FINANCING
CONTRACT NO: - CP-AF-WS-CKD-10B
SUPPLY & LAYING OF uPVC/ DI/GI/ PE PIPES FITTINGS AND SPECIALS FOR WATER SUPPLY
EXTENSION TO INAMALUWA & KITHULHITIYAWA (RURAL AREAS)
Bill No. 02-Supply and delivery of uPVC/DI/GI Pipes, Fittings & Specials for Inamaluwa & Kithulhitiyawa.
Sub Item No. 02.1-Supply and delivery of uPVC Pipes, Fittings & Specials for Inamaluwa.
Note
1.0 All the uPVC fittings shall be injection moulded type except for bends.
2.0 Joint rings shall be of EPDM or SBR
3.0 Flanges shall be of PNT10 for type PNT7 (or equivalent) fittings and PNT16 for type PNT11 (or equivalent) fittings
For PNT7 uPVC Fittings If fittings are imported, they shall be of PNT 8 as per ISO 1452 and as per the
4.0
specification
5.0 For PNT11 uPVC Fittings
If fittings are imported, they shall be of PNT 12.5 as per ISO 1452 and as per the specification
6.0 If DI fittings are offered in lieu of PVC fittings the additional fittings required to join DI to PVC shall be supplied and
all the items shall conform to the specifications.
7.0 Supplies should conform with the temperature correction, if imported and comply with BS 4346
8.0 All rates & prices shall be exclusive of VAT, which should only be shown separately in the summary. As for the Bid
evaluation purposes these rates & prices will be considered to be exclusive of VAT.
After receiving the material to site and after submission of relevant quality tests reports and satisfying specification
9.0 requirements in section 06, 80% of the amount will be paid. Balance 20% of will be released after completion of
pressure testing, cleaning & disinfection, soil compaction testing and temporary road reinstatement etc.
Item Rate Amount
Description Unit Qty
No. (Rs.) (Rs.)
uPVC Pressure Class of PNT11 Socket and Spigot 6m
Long Straight Pipes with Sockets Suitable for
Mechanical Joints (Excluding Joints Rings
&Lubricant).
2.1.1 63mm dia. m 32500
2.1.2 90mm dia. m 60000
2.1.3 110mm dia. m 7000
2.1.4 160mm dia. m 3500
2.1.5 225mm dia. m 3500
EPDM Joint Rings for Mechanical Jointing of the
Above Pipes (Includes 10% extra).
2.1.6 63mm dia. nr 5960
2.1.7 90mm dia. nr 10700
2.1.8 110mm dia. nr 1280
2.1.9 160mm dia. nr 640
2.1.10 225mm dia. nr 640
Total of Page No. 12 carried forward
Page 12 of 71
Item Rate Amount
Description Unit Qty
No. (Rs.) (Rs.)
Total of Page No. 12 brought forward
Page 13 of 71
Item Rate Amount
Description Unit Qty
No. (Rs.) (Rs.)
Total of Page No. 13 brought forward
uPVC, Pressure Class of PNT11 All Socket Tees
Suitable for Mechanical Joints (Excluding Joint
Rings & Lubricant).
2.1.36 63 x 63mm dia. nr 74
2.1.37 90 x 63mm dia. nr 105
2.1.38 90 x 90mm dia. nr 170
Page 14 of 71
Item Rate Amount
Description Unit Qty
No. (Rs.) (Rs.)
Total of Page No. 14 brought forward
EPDM Joint Rings for Mechanical Jointing of the
Above Reducers (Includes 10% Extra).
2.1.64 63mm dia. nr 33
Page 15 of 71
PURA NEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT
ADDITIONAL FINANCING
CONTRACT NO: - CP-AF-WS-CKD-10B
SUPPLY & LAYING OF uPVC/ DI/GI/ PE PIPES FITTINGS AND SPECIALS FOR WATER SUPPLY
EXTENSION TO INAMALUWA & KITHULHITIYAWA (RURAL AREAS)
Bill No. 02-Supply and delivery of uPVC/DI/GI Pipes, Fittings & Specials for Inamaluwa & Kithulhitiyawa.
Sub Item No. 02.2 - Supply and delivery of DI Pipes, Fittings, Specials & DI Valves for Inamaluwa.
Note
1.0 All spigot and socket pipes shall be of class C-40
2.0 All flange pipes shall be of class C-40
3.0 All fittings shall be of class C-40
4.0 All tees and crosses shall be of class C-40
5.0 All flanges shall be PN 16 unless otherwise stated
Item Rate Amount
Description Unit Qty.
No. (Rs) (Rs)
CLASS C-40; SPIGOT & SOCKET PIPES
Spigot and Socket Straight Pipes(Excluding Joint Rings )
2.2.1 80 mm dia. m 1000
2.2.2 100 mm dia. m 150
2.2.3 150 mm dia. m 75
2.2.4 200 mm dia. m 75
EPDM Joint Rings for Above Spigot & Socket Pipes
(Including 10% Extra)
2.2.5 80 mm dia. nr. 184
2.2.6 100 mm dia. nr. 28
2.2.7 150mm dia. nr. 14
2.2.8 200 mm dia. nr. 14
DI Double Socketed Bends (Excluding Joint Rings and
Lubricant)
2.2.9 80 mm dia. 11 ¼ deg. nr. 8
2.2.10 80 mm dia. 22 ½ deg. nr. 8
2.2.11 80 mm dia. 45 deg. nr. 5
2.2.12 80 mm dia. 90 deg. nr. 2
2.2.13 100 mm dia. 11 ¼ deg. nr. 2
2.2.14 100 mm dia. 22 ½ deg. nr. 2
2.2.15 100 mm dia. 45 deg. nr. 2
2.2.16 100 mm dia. 90 deg. nr. 2
2.2.17 150 mm dia. 11 ¼ deg. nr. 2
2.2.18 150 mm dia. 22 ½ deg. nr. 2
2.2.19 150 mm dia. 45 deg. nr. 2
2.2.20 150 mm dia. 90 deg. nr. 2
Total of Page No. 16 carried forward
Page 16 of 71
Item Rate Amount
Description Unit Qty.
No. (Rs) (Rs)
Total of Page No. 16 brought forward
Page 17 of 71
Item Rate Amount
Description Unit Qty.
No. (Rs) (Rs)
Total of Page No. 17 brought forward
2.2.48 200mm dia. (1000 mm long) nr. 2
2.2.49 200 mm dia. (1500 mm long) nr. 2
2.2.50 200 mm dia. (2000 mm long) nr. 2
2.2.51 200 mm dia. (3000 mm long) nr. 2
Page 18 of 71
Item Rate Amount
Description Unit Qty.
No. (Rs) (Rs)
Total of Page No. 18 brought forward
Page 19 of 71
PURA NEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT
ADDITIONAL FINANCING
CONTRACT NO: - CP-AF-WS-CKD-10B
SUPPLY & LAYING OF uPVC/ DI/GI/ PE PIPES FITTINGS AND SPECIALS FOR WATER SUPPLY
EXTENSION TO INAMALUWA & KITHULHITIYAWA (RURAL AREAS)
Bill No. 02-Supply and delivery of uPVC/DI/GI Pipes, Fittings & Specials for Inamaluwa & Kithulhitiyawa.
Sub Item No. 02.2 - Supply and delivery of DI Pipes, Fittings Specials & DI Valves for Inamaluwa.
Note:
1.0 All valves shall be suitable for operation with a valve key unless otherwise stated.
2.0 All flanges shall be of PN 16.
VALVES ;
SLUICE VALVES
AIR VALVES
Screw Down Type Single Orifice Air Valve with
Isolating Cock. (Including 10% Extra)
2.2.107 25mm dia. nr 273
Page 20 of 71
PURA NEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT
ADDITIONAL FINANCING
CONTRACT NO: - CP-AF-WS-CKD-10B
SUPPLY & LAYING OF uPVC/ DI/GI/ PE PIPES FITTINGS AND SPECIALS FOR WATER SUPPLY
EXTENSION TO INAMALUWA & KITHULHITIYAWA (RURAL AREAS)
Bill No. 02-Supply and delivery of uPVC/DI/GI Pipes, Fittings & Specials for Inamaluwa & Kithulhitiyawa.
Sub Item No. 02.3 - Supply and delivery of GI Pipes, Fittings & Specials for Inamaluwa.
Note:
1.0 All pipes, fittings & specials shall be of high class and heavy duty.
Item Rate Amount
Description Unit Qty.
No. (Rs) (Rs)
HIGH CLASS ,HEAVY DUTY GI PIPES,
FITTINGS AND SPECIALS
GI Screwed Pipes Suitable for GI Sockets/Screw
Flanges
2.3.1 50 mm dia. 1.0m long pipe nr 40
Screw Flanges
2.3.7 50 mm dia. nr. 700
Bends
Screw Sockets
Page 21 of 71
PURA NEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT
ADDITIONAL FINANCING
CONTRACT NO: - CP-AF-WS-CKD-10B
SUPPLY & LAYING OF uPVC/ DI/GI/ PE PIPES FITTINGS AND SPECIALS FOR WATER SUPPLY EXTENSION
TO INAMALUWA & KITHULHITIYAWA (RURAL AREAS)
Bill No. 02-Supply and delivery of uPVC/DI/GI Pipes, Fittings & Specials for Inamaluwa & Kithulhitiyawa.
Sub Item No. 02.4 - Supply and delivery of uPVC Pipes, Fittings & Specials for Kithulhitiyawa.
Note
1.0 All the uPVC fittings shall be injection moulded type except for bends.
2.0 Joint rings shall be of EPDM or SBR
3.0 Flanges shall be of PNT10 for type PNT7 (or equivalent) fittings and PNT16 for type PNT11 (or equivalent) fittings
4.0 For PNT7 uPVC Fittings If fittings are imported, they shall be of PNT 8 as per ISO 1452 and as per the specification
Page 22 of 71
Item Rate Amount
Description Unit Qty
No. (Rs.) (Rs.)
Total of Page No.22 brought forward
Page 23 of 71
Item Rate Amount
Description Unit Qty
No. (Rs.) (Rs.)
Total of Page No.23 brought forward
Page 24 of 71
PURA NEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT
ADDITIONAL FINANCING
Sub Item No. 02.5 - Supply and delivery of DI Pipes, Fittings, Specials & DI Valves for Kithulhitiyawa.
Note
Page 25 of 71
Item Rate Amount
Description Unit Qty.
No. (Rs) (Rs)
Total of Page No.25 brought forward
Page 26 of 71
Item Rate Amount
Description Unit Qty.
No. (Rs) (Rs)
Total of Page No.26 brought forward
Page 27 of 71
PURA NEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT
ADDITIONAL FINANCING
CONTRACT NO: - CP-AF-WS-CKD-10B
SUPPLY & LAYING OF uPVC/ DI/GI/ PE PIPES FITTINGS AND SPECIALS FOR WATER SUPPLY
EXTENSION TO INAMALUWA & KITHULHITIYAWA (RURAL AREAS)
Bill No. 02-Supply and delivery of uPVC/DI/GI Pipes, Fittings & Specials for Inamaluwa & Kithulhitiyawa.
Sub Item No. 02.5 - Supply and delivery of DI Pipes, Fittings, Specials & DI Valves for Kithulhitiyawa.
Note:
1.0 All valves shall be suitable for operation with a valve key unless otherwise stated.
VALVES ;
SLUICE VALVES
AIR VALVES
Page 28 of 71
PURA NEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT
ADDITIONAL FINANCING
CONTRACT NO: - CP-AF-WS-CKD-10B
SUPPLY & LAYING OF uPVC/ DI/GI/ PE PIPES FITTINGS AND SPECIALS FOR WATER SUPPLY
EXTENSION TO INAMALUWA & KITHULHITIYAWA (RURAL AREAS)
Bill No. 02-Supply and delivery of uPVC/DI/GI Pipes, Fittings & Specials for Inamaluwa & Kithulhitiyawa.
Sub Item No. 02.6 - Supply and delivery of GI Pipes, Fittings & Specials for Kithulhitiyawa.
Note:
1.0 All pipes, fittings & specials shall be of high class and heavy duty.
Page 29 of 71
PURA NEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT
ADDITIONAL FINANCING
CONTRACT NO: - CP-AF-WS-CKD-10B
SUPPLY & LAYING OF uPVC/ DI/ GI/ PE PIPES FITTINGS AND SPECIALS FOR WATER SUPPLY
EXTENSION TO INAMALUWA & KITHULHITIYAWA (RURAL AREAS)
Bill No. 02 - Supply & Delivery of uPVC ,DI ,GI Pipes, Fittings & Specials for Inamaluwa & Kithulhitiyawa
2.1
Supply & delivery of uPVC Pipes fittings & Specials for Inamaluwa
(Page No. 15)
2.2
Supply & delivery of DI Pipes fittings & Specials for Inamaluwa
(Page No. 20)
2.3
Supply & delivery of GI Pipes fittings & Specials for Inamaluwa
(Page No. 21)
2.4
Supply & delivery of uPVC Pipes fittings & Specials for Kithulhitiyawa
(Page No. 24)
2.5
Supply & delivery of DI Pipes fittings & Specials for Kithulhitiyawa
(Page No. 28)
2.6
Supply & delivery of GI Pipes fittings & Specials for Kithulhitiyawa
(Page No. 29)
Page 30 of 71
PURA NEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT
ADDITIONAL FINANCING
CONTRACT NO: - CP-AF-WS-CKD-10B
SUPPLY & LAYING OF uPVC/ DI/ GI/ PE PIPES FITTINGS AND SPECIALS FOR WATER SUPPLY
EXTENSION TO INAMALUWA & KITHULHITIYAWA (RURAL AREAS)
Bill No. 01 - Laying of uPVC ,DI ,GI ,PE Pipes, Fittings & Specials for Inamaluwa & Kithulhitiyawa.
Sub Item No. 01.1 - Laying of uPVC ,DI ,GI ,PE Pipes, Fittings & Specials for Inamaluwa.
Note
Rate to include bush clearing, removing trees, trench excavation, excavation for trial pit if required,
delivering material to the site, trimming, laying, cutting, grinding, jointing of pipes, backfilling &
1.0 compaction with selected excavated material up to the finished surface of the reinstatement, disposal
of surplus excavated materials, laying of polythene/metallic marker tape, cleaning, disinfection and
pressure testing of pipes
Pipes not in Trenches shall cover the whole of the works and rates shall comprise delivering, placing
2.0 in position, construction & fixing to the supports with Pipe brackets as per the Drawings and
Specifications.
uPVC pipes in trenches depth not exceeding 1.5 m for road crossings, laid perpendicular to the main
3.0 line will be measured in meters. Tees and associated Fittings, Valves and Specials will be measured
separately as detailed in the plan drawings
During the period of pipe laying contract, the contractor should provide necessary traffic control
4.0
devices and safety arrangements at site (barricades, night lamps, warning boards, sign boards etc.).
All safety arrangements for workers should be provided by the contractor (helmets, boots, jackets
5.0
etc.)
Contractor should be capable to do the pipe laying works even in the night time depending on the
6.0
site conditions and as directed by the Engineer.
All testing equipment, tools, other necessary items should be supplied by the contractor and if found
8.0 any leakage during the pressure test of the pipe line, the contractor should repair it and complete the
test at his own expense.
Damages to the existing properties, culverts, pipe lines, during site works should be rectified by the
9.0
contractor by his own expense.
Page 31 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
CLASS I-PIPE WORK-PIPES
LAYING, JOINTING AND FIXING OF
PVC/DI SOCKET & SPIGOT PIPES AND
FITTINGS
Rate to include for excavation in any material
other than rock requiring blasting (the depth
of excavation to be accordingly to keep
minimum cover of 1.0 m for the pipe),
backfilling & compaction of pipe trenches(the
excess excavated material should be disposed
from site as directed), cutting and grinding of
pipes, laying and jointing of pipes, cleaning &
disinfection of pipes and pressure testing of
pipes (Only 70% of the rate for pipe laying
will be considered for payment unless the
related pressure testing and disinfection are
completed as per the instruction of the
Engineer.)
uPVC Pressure class PNT11 socketed and
spigot pipes with push fit joints in trenches
depth not exceeding 1.5m
3.1.1 I 512 63mm dia. pipe (PNT11 ) m 30400
Page 32 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 32 brought forward
Page 33 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No.33 brought forward
Page 34 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 34 brought forward
160 mm dia.
225 mm dia.
3.1.53 J412 11 ¼ deg. Bend nr 25
3.1.54 J412 22 ½ deg. Bend nr 16
3.1.55 J412 45deg. Bend nr 4
Page 35 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 35 brought forward
Repair Coupling
3.1.89 J391 63mm dia. tapered core and steel tapered flange nr 30
3.1.90 J391 90mm dia. tapered core and steel tapered flange nr 400
DI Double Socket Bend. Suitable for
Mechanical Joints (Including Joints Rings)
Rate to Include for Concrete Thrust Blocks,
Anchor Blocks Where Necessary to withstand
10 Bar Pressure and All Necessary Items of
Work Required to Complete the Fixing.
DI 80 mm dia.
3.1.91 J311 11 ¼ deg. Bend nr 8
DI 100 mm dia.
Page 36 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 36 brought forward
DI 150 mm dia.
3.1.99 J311 11 ¼ deg. Bend nr 2
3.1.100 J311 22 ½ deg. Bend nr 2
3.1.101 J311 45deg. Bend nr 2
3.1.102 J311 90deg. Bend nr 2
DI 200 mm dia.
3.1.103 J312 11 ¼ deg. Bend nr 2
3.1.104 J312 22 ½ deg. Bend nr 2
3.1.105 J312 45deg. Bend nr 2
3.1.106 J312 90deg. Bend nr 2
DI Double Flange Bends, Make-up Pipes, Tees
with Flange Joints. Rate to Include for
Concrete Thrust Blocks, Anchor Blocks Where
Necessary to withstand 10 Bar Pressure and
All Necessary Items of Work Required to
Complete the Fixing.
DI Double Flange Straight Pipes
3.1.107 J381 80mm dia. 1.0m long DI D/F pipe nr 5
3.1.108 J381 80mm dia. 1.5m long DI D/F pipe nr 10
3.1.109 J381 80mm dia. 2.0m long DI D/F pipe nr 10
3.1.110 J381 80mm dia. 3.0m long DI D/F pipe nr 8
3.1.111 J381 80mm dia. 4.0m long DI D/F pipe nr 5
3.1.112 I 312 80mm dia. 5.5m long DI D/F pipe nr 4
3.1.113 J381 100mm dia. 1.0m long DI D/F pipe nr 3
3.1.114 J381 100mm dia. 1.5m long DI D/F pipe nr 3
Page 37 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 37 brought forward
Page 38 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 38 brought forward
DI Flange Adaptors
3.1.170 J351 80mm dia. flange adaptor to suit 90mm dia. pipe. nr 3
100mm dia. flange adaptor to suit 110mm dia.
3.1.171 J351 nr 1
pipe.
150 mm dia. Flange adoptor to suit 160mm dia.
3.1.172 J351 nr 1
pipe.
200 mm dia. Flange adoptor to suit 225mm dia.
3.1.173 J351 nr 1
pipe.
DI Couplings
3.1.174 J391 80mm dia. coupling to suit 90mm dia. pipe. nr 344
Page 39 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 39 brought forward
Bends
Fixing of Valves
Rate to include for additional excavation,
preparation of surfaces, disposal of excavated
materials, supporting sides of excavation,
backfilling, thrust blocks for fittings and all
necessary items of work required for
completion of work
Section Valves / Inline Valves (Detail as Shown
in Drawing WT 407/SV/01A.
Type B1
Mechanical Coupling
3.1.194 J391 100 mm dia. (to suit 110mm dia. uPVC pipe) nr 2
3.1.195 J391 150mm dia. (to suit 160mm dia. uPVC pipe) nr 2
3.1.196 J391 200mm dia. (to suit 225mm dia. uPVC pipe) nr 2
Page 40 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 40 brought forward
Flange Adaptors
3.1.201 J351 80 mm dia. nr 34
3.1.202 J351 100 mm dia. nr 2
AIR VALVE
Fixing Air Valves Complete as Shown In Detail
on Drawing No:WT405/AV/01. Rate to Include
for Suitable Support Blocks
TYPE A1 for PVC pipes.
Air Valves
25 mm dia. Single orifice screwed down type air
3.1.213 J861 valve with isolating cock as described in the nr 117
drawing.
Couplings
3.1.214 J391 80 mm dia. (to suit 90mm dia. PVC pipe) nr 140
3.1.215 J391 100 mm dia. (to suit 110mm dia. PVC pipe) nr 18
3.1.216 J391 63mm dia. tapered core and steel tapered flange nr 76
DI Plain Ended Pipe 3000mm Long
Approximately
3.1.217 J381 80mm dia. nr 70
Page 41 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No.41 brought forward
Page 42 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 42 brought forward
Fixing of Washout Valves Complete as Shown
in Detail on Drawing No: WT406/WV/05
TYPE B1 for PVC Pipes.
90x90mm dia. Socketed tees.(Rate to include for
3.1.240 J421 providing suitable support block as per the nr 40
drawing)
110x90mm dia. Socketed tees.(Rate to include for
3.1.241 J421 providing suitable support block as per the nr 5
drawing)
160x90mm dia. Socketed tees.(Rate to include
3.1.242 J421 for providing suitable support block as per the nr 3
drawing)
225x90mm dia. Socketed tees.(Rate to include
3.1.243 J422 for providing suitable support block as per the nr 3
drawing)
3.1.244 J411 90mm dia. 22 ½ deg. bend nr 51
3.1.245 J481 90mm dia. PVC 2000mm long pipe nr 51
3.1.246 J351 80 mm dia. Flange adaptor nr 51
80mm dia. DI Flange and plain ended 2000mm
3.1.247 J381 nr 51
(approximately) long pipe
3.1.248 J391 90 mm dia. tapered core & steel tapered flange nr 51
3.1.249 J811 80mm dia. Flange sluice valve nr 51
Fixing of Washout Valves Complete as Shown
in Detail on Drawing No: WT406/WV/10A
TYPE C3 for63 mm dia. PVC Pipes.
63x63mm dia. socketed tee.(Rate to include for
3.1.250 J421 providing suitable support block as per the nr 25
drawing)
3.1.251 J411 63mm dia. 22 ½ deg. PVC bend nr 25
3.1.252 J391 63mm dia. tapered core & steel tapered flange nr 50
3.1.253 J481 63mm dia. PVC 2000mm long pipe nr 25
3.1.254 J811 50mm dia. Flange sluice valve nr 25
CLASS K : PIPE WORK
CHAMBER AND PIPE WORK
ANCILLARIES
Construction of Valve Chambers and Pipe
Work Ancillaries
Rate to include for excavation, preparation of
surfaces, disposal of excavated materials,
supporting sides of excavation, back filling,
concrete, reinforcement, formwork, joints and
fixing all other related items. As per the
drawing.
Section Valve Chamber for PVC Pipe Lines.
Valve chamber as shown in detail Drawing No:
WT 407/SV/01A type B1, Chamber size
3.1.255 K232 1200x1300 should be concrete grade 25 as shown nr 5
in detail Drawing. Rate to exclude supply of
Manhole cover.
Valve chamber as shown in detail Drawing No:
WT 407/SV/01A type B1, Chamber size
3.1.256 K232 1300x1400 should be concrete grade 25as shown nr 1
in detail Drawing. Rate to exclude supply of
Manhole cover.
Page 43 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 43 brought forward
Page 44 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 44 brought forward
Culvert crossing
Width of culvert opening is given below as "L".
Additional horizontal pipe length piece plus
inclined portion if applicable shall be
considered to calculate overall crossing length.
Rate to include for laying & jointing or fixing
in position DI/PVC pipes, fittings, specials,
valves as shown in drawing, excavation,
providing suitable anchor blocks, concrete
support columns, repairing culvert and all
other necessary works to complete the
crossing. Contractor should submit the
proposal with shop drawings and required to
get the Engineer's approval prior to commence
the work.
Crossing Type A1 for PVC Main as Shown on
Drawing No WT401/CC/01
3.1.264 K611 50mm dia.GI pipe (L –2.0 m ) nr 7
3.1.265 K611 50mm dia.GI pipe (L –3.0 m ) nr 10
3.1.266 K621 50 mm dia. GI pipe (L – 4.0m ) nr 3
Page 45 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Page 46 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 46 brought forward
Page 47 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 47 brought forward
Bridge Crossing.
Page 48 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 48 brought forward
Channel Crossing
Marker Post
Page 49 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 49 brought forward
Road Reinstatement
Temporary Road Reinstatement to be Done in
Accordance with Specification and the
Guidance of RDA. Refer Drawing no
WT/403/BT/02 - TYPE III
Rate to include for breaking up and temporary
reinstatement of RDA/PRDA/Pradeshiya Saba
roads carriageway (Asphalt / Tarred/
Concrete/ concrete block paved roads) and
maintenance until handover.
3.1.353 L711 63mm dia. Pipes (PNT11 ) m 3000
3.1.354 L711 90 mm dia. Pipes (PNT11 ) m 6000
3.1.355 L711 110 mm dia. Pipes (PNT11 ) m 700
3.1.356 L711 160 mm dia. Pipes (PNT11 ) m 300
3.1.357 L711 225 mm dia. Pipes (PNT11 ) m 300
3.1.358 L711 80mm dia. DI pipes. m 100
3.1.359 L711 100mm dia. DI pipes. m 15
3.1.360 L711 150 mm dia. DI pipe m 10
3.1.361 L711 200 mm dia. DI pipe m 10
CLASS L: PIPE WORK SUPPORT AND
PROTECTION ANCILLARIES TO LAYING
AND EXCAVATION
Rate to Include for Excavation, Preparing of
Surfaces, Disposal of Excavated Material,
Supporting Sides of Excavation.
Extras to excavation and backfilling Depth not
exceeding 1.5m
In pipe trenches: excavation of rock (control
3.1.362 L111 blasting). Payment will be made only for trench m3 1300
width .
In pipe trenches: excavation of rock (chemical
3.1.363 L111 blasting) (Provisional). Payment will be made m3 200
only for trench width..
In manhole: excavation of rock (control blasting).
3.1.364 L121 m3 50
Payment will be made only for chamber width .
In manhole: excavation of rock (chemical
3.1.365 L121 blasting). Payment will be made only for chamber m3 30
width .
In pipe trenches: backfilling with imported soil
3.1.366 L116 m3 4000
where necessary.
In Pipe trenches: backfilling material quarry dust.
3.1.367 L116 m3 800
.
In pipe trenches: backfilling with imported sand
3.1.368 L116 m3 10
where necessary as per the engineer's instructions.
In Pipe trenches: backfilling material ABC where
3.1.369 L116 m3 10
necessary as per the engineer's instructions.
Page 50 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 50 brought forward
Bedding Type A
Bedding Type B
Bedding Type C
Page 51 of 71
CESMM3 Rate Amount
Item no Description Unit Qty
Code (Rs.) (Rs.)
Total of Page No. 51 brought forward
Pipe Beddings (As per the Detail Drawing no.
WT403/BT/02 ) for PVC Laying
Bedding Type D
Compaction should be done without Using
Heavy Compacting Equipment.
3.1.385 L511 63mm dia. uPVC m 1625
3.1.386 L511 90mm dia. uPVC / 80mm dia. DI Pipes m 3000
3.1.387 L511 110mm dia. uPVC / 100mm dia. DI Pipes m 350
3.1.388 L511 160mm dia. uPVC / 150mm dia. DI Pipes m 175
3.1.389 L512 225mm dia. uPVC / 200mm dia. DI Pipes m 175
Breaking of Asphalt Concrete/concrete surfaces
3.1.390 L112&4 m 200
by using asphalt cutter for trench excavation. .
Suitable Earth work supports where necessary for
PVC/DI/GI pipe laying depth not exceeding
3.1.391 1900 m 200
1.5m. Rate to include both sides of trench and
fixing & removing of supports..
Breaking of rubble walls during pipe laying works
3.1.392 E14&E15 m3 10
as per the Engineer instructions. .
Provision for de-watering by using 2 inch pump
3.1.393 hr. 40
where necessary
Provision for supplying and laying of 8mm thick
mild steel plate (M S plate) for covering trench
3.1.394 Item 1
opening during pipe laying works in order to
ensure convenient access to the general public
Provision for cleaning and applying all exposed
DI pipes and specials with two coats of black
3.1.395 m 500
colour approved paint after completion of pipe
laying .(diameter from 80mm to 200mm)
Miscellaneous
150-225 Random Rubble Stone Work,
Vertical, Laid in Cement and Sand (1:5)
3.1.396 U831 300mm thick . m2 35
Page 52 of 71
PURA NEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT
ADDITIONAL FINANCING
CONTRACT NO: - CP-AF-WS-CKD-10B
SUPPLY & LAYING OF uPVC/ DI/ GI/ PE PIPES FITTINGS AND SPECIALS FOR WATER SUPPLY
EXTENSION TO INAMALUWA & KITHULHITIYAWA (RURAL AREAS)
Bill No. 03 - Laying of uPVC ,DI ,GI ,PE Pipes, Fittings & Specials for Inamaluwa & Kithulhitiyawa.
Sub Item No. 03.2 - Laying of uPVC ,DI ,GI ,PE Pipes, Fittings & Specials for Kithulhitiyawa.
Note
Rate to include bush clearing, removing trees, trench excavation, excavation for trial pit if required,
delivering material to the site, trimming, laying, cutting, grinding, jointing of pipes, backfilling &
1.0 compaction with selected excavated material up to the finished surface of the reinstatement,
disposal of surplus excavated materials, laying of polythene/metallic marker tape, cleaning,
disinfection and pressure testing of pipes
Pipes not in Trenches shall cover the whole of the works and rates shall comprise delivering,
2.0 placing in position, construction & fixing to the supports with Pipe brackets as per the Drawings
and Specifications.
uPVC pipes in trenches depth not exceeding 1.5 m for road crossings, laid perpendicular to the
3.0 main line will be measured in meters. Tees and associated Fittings, Valves and Specials will be
measured separately as detailed in the plan drawings
During the period of pipe laying contract, the contractor should provide necessary traffic control
4.0
devices and safety arrangements at site (barricades, night lamps, warning boards, sign boards etc.).
All safety arrangements for workers should be provided by the contractor (helmets, boots, jackets
5.0
etc.)
Contractor should be capable to do the pipe laying works even in the night time depending on the
6.0
site conditions and as directed by the Engineer.
All testing equipment, tools, other necessary items should be supplied by the contractor and if found
8.0 any leakage during the pressure test of the pipe line, the contractor should repair it and complete
the test at his own expense.
Damages to the existing properties, culverts, pipe lines, during site works should be rectified by the
9.0
contractor by his own expense.
Page 53 of 71
CESMM Rate Amount
Item no Description Unit Qty
3Code (Rs.) (Rs.)
Page 54 of 71
CESMM Rate Amount
Item no Description Unit Qty
3Code (Rs.) (Rs.)
Total of Page No. 54 brought forward
Page 55 of 71
CESMM Rate Amount
Item no Description Unit Qty
3Code (Rs.) (Rs.)
Total of Page No. 55 brought forward
63 mm dia.
90 mm dia.
110 mm dia.
Page 56 of 71
CESMM Rate Amount
Item no Description Unit Qty
3Code (Rs.) (Rs.)
Total of Page No. 56 brought forward
Repair Coupling
3.2.46 J391 63mm dia. tapered core and steel tapered flange nr 30
3.2.47 J391 90mm dia. tapered core and steel tapered flange nr 50
3.2.48 J391 110mm dia. tapered core and steel tapered flange nr 20
DI 80 mm dia. .
DI 100 mm dia. .
Page 57 of 71
CESMM Rate Amount
Item no Description Unit Qty
3Code (Rs.) (Rs.)
Total of Page No. 57 brought forward
Page 58 of 71
CESMM Rate Amount
Item no Description Unit Qty
3Code (Rs.) (Rs.)
Total of Page No. 58 brought forward
DI Flange Adaptors
3.2.85 J351 80mm dia. flange adaptor to suit 90mm dia. pipe. nr 50
3.2.86 J351 100mm dia. flange adaptor to suit 110mm dia. pipe. nr 35
DI Couplings
Bends
Page 59 of 71
CESMM Rate Amount
Item no Description Unit Qty
3Code (Rs.) (Rs.)
Total of Page No. 59 brought forward
Fixing of Valves
Type B1
Mechanical Coupling
3.2.102 J391 100 mm dia. (to suit 110mm dia. uPVC pipe) nr 4
Flange Adaptors
3.2.109 J391 63mm dia. tapered core and steel tapered flange nr 4
Page 60 of 71
CESMM Rate Amount
Item no Description Unit Qty
3Code (Rs.) (Rs.)
Total of Page No. 60 brought forward
AIR VALVE
Fixing Air Valves Complete as Shown In Detail
on Drawing No:WT405/AV/01. Rate to Include
for Suitable Support Blocks
TYPE A1 for PVC pipes.
Air Valves
25 mm dia. Single orifice screwed down type air
3.2.113 J861 nr 14
valve with isolating cock as described in the drawing.
Couplings
3.2.115 J391 100 mm dia. (to suit 110mm dia. PVC pipe) nr 6
3.2.116 J391 63mm dia. tapered core and steel tapered flange nr 6
DI Plain Ended Pipe 3000mm Long
Approximately
3.2.117 J381 80mm dia. nr 8
Page 61 of 71
CESMM Rate Amount
Item no Description Unit Qty
3Code (Rs.) (Rs.)
Total of Page No. 61 brought forward
3.2.133 J391 63mm dia. tapered core & steel tapered flange nr 4
Page 62 of 71
CESMM Rate Amount
Item no Description Unit Qty
3Code (Rs.) (Rs.)
Total of Page No. 62 brought forward
Culvert crossing
Width of culvert opening is given below as "L".
Additional horizontal pipe length piece plus
inclined portion if applicable shall be considered
to calculate overall crossing length. Rate to
include for laying & jointing or fixing in position
DI/PVC pipes, fittings, specials, valves as shown
in drawing, excavation, providing suitable anchor
blocks, concrete support columns, repairing
culvert and all other necessary works to complete
the crossing. Contractor should submit the
proposal with shop drawings and required to get
the Engineer's approval prior to commence the
work.
Crossing Type A1 for PVC Main as Shown on
Drawing No WT401/CC/01
3.2.142 K611 50mm dia.GI pipe (L –2.0 m ) nr 5
Page 63 of 71
CESMM Rate Amount
Item no Description Unit Qty
3Code (Rs.) (Rs.)
Total of Page No. 63 brought forward
Page 64 of 71
CESMM Rate Amount
Item no Description Unit Qty
3Code (Rs.) (Rs.)
Total of Page No. 64 brought forward
Bridge Crossing .
Page 65 of 71
CESMM Rate Amount
Item no Description Unit Qty
3Code (Rs.) (Rs.)
Total of Page No. 65 brought forward
Marker Post
Page 66 of 71
CESMM Rate Amount
Item no Description Unit Qty
3Code (Rs.) (Rs.)
Total of Page No. 66 brought forward
CLASS L: PIPE WORK SUPPORT AND
PROTECTION ANCILLARIES TO LAYING
AND EXCAVATION
Rate to Include for Excavation, Preparing of
Surfaces, Disposal of Excavated Material,
Supporting Sides of Excavation.
Extras to excavation and backfilling Depth not
exceeding 1.5m
In pipe trenches: excavation of rock (control
3.2.201 L111 blasting). Payment will be made only for trench m3 125
width .
In pipe trenches: excavation of rock (chemical
3.2.202 L111 blasting) (Provisional). Payment will be made only m3 20
for trench width..
In manhole: excavation of rock (control blasting).
3.2.203 L121 m3 5
Payment will be made only for chamber width .
Page 67 of 71
CESMM Rate Amount
Item no Description Unit Qty
3Code (Rs.) (Rs.)
Total of Page No. 67 brought forward
Bedding Type C
Bedding Type D
Page 68 of 71
CESMM Rate Amount
Item no Description Unit Qty
3Code (Rs.) (Rs.)
Total of Page No. 68 brought forward
Miscellaneous
150-225 Random Rubble Stone Work, Vertical,
Laid in Cement and Sand (1:5)
3.2.227 U831 300mm thick . m2 35
Page 69 of 71
PURA NEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT
ADDITIONAL FINANCING
CONTRACT NO: - CP-AF-WS-CKD-10B
SUPPLY & LAYING OF uPVC/ DI/ GI/ PE PIPES FITTINGS AND SPECIALS FOR WATER SUPPLY
EXTENSION TO INAMALUWA & KITHULHITIYAWA (RURAL AREAS)
Bill No. 03 - Laying of uPVC, DI ,GI ,PE Pipes, Fittings & Specials for Inamaluwa & Kithulhitiyawa
Sub Item
Description Amount (Rs.)
No.
3.1
Laying of uPVC / DI /GI Pipes , Fittings & Specials for Inamaluwa
Page No. 52
3.2
Laying of uPVC / DI /GI Pipes , Fittings & Specials for Kithulhitiyawa
Page No. 69
Page 70 of 71
PURA NEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT
ADDITIONAL FINANCING
CONTRACT NO: - CP-AF-WS-CKD-10B
SUPPLY & LAYING OF uPVC/DI/ GI/ PE PIPES FITTINGS AND SPECIALS FOR WATER SUPPLY
EXTENSION TO INNAMALUWA AND KITHULHITIYAWA(RURAL AREAS)
BILL NO. 04 - DAY WORKS
Page 71 of 71