SRI AVANTIKA POWER PROJECTS (P) LTD.

SAPTADHARA SMALL HYDRO ELECTRIC PROJECT ( 3 X 6 MW)


FORTNIGHT SCHEDULE ( CIVIL, H&M, E&M)
Target Vs Achieved
Months Fortnight (02.09.2019 to 15.09.2019)
Weeks D1 (02) D2 (03) D3 (04) D4 (05) D5 (06) D6 (07) D7 (08) W1 D1 (09) D2 (10) D3 (11) D4 (12) D5 (13) D6 (14) D7 (15) W2

HOLIDAY

HOLIDAY
Achieved

Achieved

Achieved

Achieved

Achieved

Achieved

Achieved

Achieved

Achieved

Achieved

Achieved

Achieved

Achieved

Achieved
Target

Target

Target

Target

Target

Target

Target

Target

Target

Target

Target

Target

Target

Target
S. Duratio Total Achive Balance
NO
DISCRIPTION n (Days)
From To Unit
Qty. d Qty. Qty.

1 DIVERSION WEIR

i Balance excavation Completed 7030 7030 Nil

ii PCC and Anchoring etc. Completed 165 165 Nil

iii Non Over Flow Completed 1900 1900 Nil

RCC of Over flow (Opening of River


iv 15 01.11.2019 15.11.2019 m3 3060 2810 250
Flow Portion Only )

2 HEAD REGULATOR & SCOUR PIPE

RCC Concretting including raft, side wall,


i Completed 601 601 NIL
slab and gate groove etc.
Transition wall & Both Side Side Wall
ii (RRM 1:3 CM) 45 Completed 1150 1150 NIL

iii Toe wall Completed 1050 1050 NIL

3 APPROACH CHANNEL

Balance excavation(including driling


i 105 Completed 19000 19000 0
blasting,with maintaining side slope 1:1

RR Masonary Work from Head Regulator


ii 90 01.04.2019 30.06.2019 m3 4000 990 3010
to Approach Channel

iii Lining concretting 91 15.05.2019 15.08.2019 m3 1115 0 1115

4 FORE BAY

Excavation including Drilling ,Blasting &


i Completed 2803 2803 0
maintaining.

ii RCC Concretting including raft, side wall 120 9.05.2019 8.09.2019 m3 1440 269 1171

5 PENSTOCK

Excavation of penstock line including


i Anchor block and saddle support 64 11.02.2019 15.04.2019 4000 4000 0
Including Drilling & Blasting

Anchor blocks 1-7 and saddle support STRI STRI STRI STRI
ii 50 11.03.2019 30.08.2019 m3 900 567 333 5 Puja 5 R 5 0 5 R 5 R 5 R 30 0 5 0 5 R 5
KE
5
KE
5
KE
5
KE
30 0
first stage RCC
STRI STRI STRI STRI
iii Errection of steel linear (Penstock) 169 1.03.2019 17.08.2019 m 630 122.5 507.5 2.5 Puja 2.5 R 2.5 0 2.5 R 2.5 R 2.5 R 15 0 5 0 5 R 5
KE
5
KE
5
KE
5
KE
30 0

2nd Stage RCC Concerting and Saddle STRI STRI STRI STRI
iv 184 31.03.2019 30.09.2019 m3 1250 592 658 5 Puja 5 R 5 0 5 R 5 R 5 R 30 0 5 0 5 R 5
KE
5
KE
5
KE
5
KE
30 0
Support Manually)

The concreting around penstock bends STRI STRI STRI STRI


v 131 22.03.2019 31.07.2019 m3 592 76 516 10 Puja 10 R 10 3 10 R 10 R 10 R 60 3 10 10 10 R 10
KE
10
KE
10
KE
10
KE
60 10
8/1,8/2 and 8/3 and the slope portion.
The concreting around the Y pieces of
vi 143 25.03.2019 15.08.2019 m3 402 25 377
penstock (Including Step Concreting)

6 POWER HOUSE

Concreting in the machine hall area along


i 39 1.08.2019 9.09.2019 m3 150 15 135
with equipment erection

Side long wall EL. 283.10 to 295.00 up to


ii 75 Completed 1110 1110 0
service bay EL.295.00 and stair case

Filling of Service Bay(Back side) &


Approach Road to Service Bay &
iv
Formation of service bay with details
works.

iva Soil Filling (cantilever slab-2, & DT,s) 110 Completed 3000 3000 0

ivb Slab Concreting (Service Bay) 60 1.03.2019 30-04-2019 60 60 0

Draft tube wall section D-D and section E-


v 40 Completed 800 800 0
E EL. 281.897- 295.00, 284.411-295.00

Finishing Work of Power House


vi (including Painting,Flooring,Interior of 45 1.09.2019 15.11.2019
Control Room, Brick Masonary etc.)

vii Pre-Feb. Super Structure Above El. 295 45 20.05.2019 5.07.2019 MT 79 0 79

viii Flood protection Wall 40 25.03.2019 30.04.2019 2700 2700 0


STRI
ix Slab at 287 (Storage room Floor) 5 02.09.2019 13.09.2019 30 0 30 10 0 10 R 10
KE
30 0

7 TRC.

i TRC excavation Blasting 75 15.02.2019 30-06-2019 m3 15271 11650 3621

Supporting wall including raft concretting STRI STRI STRI STRI


ii 90 1.06.2019 30.08.2019 m3 600 157 443 2.5 Puja 2.5 R 2.5 R 2.5 R 2.5 R 2.5 R 15 5 0 5 R 5
KE
5
KE
5
KE
5
KE
30 0
EL (side Wall)285.20 to 295.00 m

8 MISCELLANEOUS WORK

Catch water drain, permanent drain ,


i Retaining wall ,cross drainage work , as 72 15.02.2019 30.06.2019 20 20 0
per site condition
From Start point of Service Bay &
ii Existing Catch Drain (Box- 60 1.03.2019 30.06.2019 m3 55 20 35
shaped)(Including PCC & RRM)
CONSOLIDATION GROUTING &
9
CURTAIN GROUTING
Power House (According to Site
i
Condition)
10 TRP

i TRP excavation Completed 0

Supporting wall including raft concret EL


ii Completed 0
(side Wall) 285.20 to 295.00 m

11 SWITCHYARD

i Excavation of Foundation Of Switch Yard 10 1.09.2019 10.09.2019

ii Concreting of footing 20 11.09.2019 30.09.2019

12 33 KV TRANSMISSION LINE

i Survey 15 Completed km 18.5 18.5 0

ii Designing and Drawing 15 15.05.2019 30.05.2019

iii Land acquisition 30 15.05.2019 28.06.2019

iv Concreting of Foundation 60 1.06.2019 30.07.2019

v Erection of tower 60 1.07.2019 30.08.2019

vi Stringing 90 1.08.2019 30.10.2019

13 H&M WORKS

A Head regulator & Scour pipe

Vertical Gate and Hoist Pipe ( 02 Nos. Set


i 25 25.06.2019 20.07 2019
)

ii Trash rack erection ( 02 Nos. Set ) 3 20.05 2019 23.07 2019

iii Stoplog Gate Installation ( 02 Nos. Set ) 15 23.05 2019 07.09 2019

iv Scour Sluic Gate ( 01 No. Set ) 7 07.06 2019 14.09 2019

B FOREBAY

i Intake Gate at Fore bay( 01 No. Set ) 15 15.06.2019 29.09 2019

ii Stoplog Gate Installation ( 01 No. Set ) 5 01.07.2019 05.09 2019

iii Trash Rack at Fore bay( 01 No. Set ) 10 06.07.2019 15.09. 2019

C DRAFT TUBE

Draft Tube Gates & Hoist Unit-1


i 15 16.07.2019 31.07 2019
( 01 No. Set )
Draft Tube Gates & Hoist Unit-2
ii 15 01.08.2019 15.08 2019
( 01 No. Set )
Draft Tube Gates & Hoist Unit-3
iii 15 16.08.2019 31.08 2019
( 01 No. Set )

14 E&M WORKS

i Refurbishment of Materials 90 28/2/2019 29.05.2019


ii Installation of EOT Crane 28 1.05.2019 10.07.2019

iii Installation of Draft Tube (Unit-1, 2 & 3) 15 11.05.2019 25.07.2019

iv Installation of MIV (Unit-1, 2 & 3) 15 26.05.2019 9.07.2019

v Installation of Turbines with accessories 60 10.06.2019 9.08.2019

vi Installation Generator with accessories 60 15.06.2019 15.08.2019

Installation of Switchyard Equipment


vii 60 1.05.2019 1.07.2019
(Transformer,equipments,etc)
Conection of 33 KV Transmission Line to
viii 2 10.07.2019 12.07.2019
Govindpally Substation
TURBINE & GENERATOR
15
TESTING

A UNIT# 1

Erection & Commissioning of Unit-1 (Dry


i and Wet tests, Load Tests, Synchronation, 30 25.08.2019 25.09.2019
etc)

B UNIT# 2

Erection & Commissioning of Unit-2 (Dry


i and Wet tests, Load Tests, Synchronation, 30 20.09.2019 20.10.2019
etc)

C UNIT # 3

Erection & Commissioning of Unit-2 (Dry


i and Wet tests, Load Tests, Synchronation, 30 10.10.2019 10.11.2019
etc)
COMMERCIAL OPERATION DATE
16 5 11.11.2019 31.12.2019
( COD )

Note: Reasons for shortfall highlighted by developer are below Excavation(Cum) Excavation(Cum)
R - stand for work hampered due to Rainfall, Puja- Stand for Festivel,Strike-Stand for 135 3 180 10
1
Worked Hampered by Local Worker Concreting(Cum) Concreting(Cum)
15 0 30 0
2 Excavation Work Not Targeted Due to Monsoon Penstock Erection (m) Penstock Erection (m)
3 Concreting shortfall is due to Rainfall and Local Worker Strike
4 Penstock Erection shortfall is due to Rainfal and Local Worker Strike