Documente Academic
Documente Profesional
Documente Cultură
Client Approval:
Date:
1475-CP-001-E E
257422914.doc
ERROR: REFERENCE SOURCE NOT FOUND ERROR: REFERENCE SOURCE NOT FOUND
ERROR: REFERENCE SOURCE NOT FOUND
TABLE OF CONTENTS
1 INTRODUCTION
2 PROCESS DESCRIPTION
3 GENERAL
4.1 Crushing
4.2 Fine Ore Bin, HPGR, Grinding and Gravity
4.3 Flotation
4.4 Reagents and Consumables
4.5 Services
4.6 Gravity Concentrate Leaching
4.7 Flotation Concentrate Leaching
4.8 Carbon Stripping
4.9 Electrowinning
4.10 Cyanide Detoxification
5.1 General
5.2 Crushing
5.3 Fine Ore Bin, HPGR, Grinding and Gravity
5.4 Flotation
5.5 Reagents and Consumables
5.6 Gravity and Flotation Concentrate Leaching
5.7 Carbon Stripping
5.8 Electrowinning
5.9 Cyanide Detoxification
6.1 Crushing
6.2 Fine Ore Bin, HPGR, Grinding and Gravity
6.3 Flotation
6.4 Reagents and Consumables
6.5 Gravity and Flotation Concentrate Leaching
6.6 Carbon Stripping
6.7 Electrowinning
6.8 Cyanide Detoxification
7.1 Crushing
7.2 Grinding and Gravity
7.3 Flotation
7.4 CIL and Detox
7.5 Acid Wash Procedures
7.6 Elution Procedures
2 PROCESS DESCRIPTION
Processing of gold bearing ore includes the following activities:
Crushing
Flotation
257422914.doc Page 1
Coarse concentrates from the gold trap are sorted to recover coarse gold nuggets. After sorting,
coarse concentrates are crushed using the concentrate roll crusher and fed to the goldroom
gravity spinner. Goldroom gravity spinner tails, with accumulated spinner and centrifugal
concentrator concentrates, are fed to the goldroom fine screen. Oversize concentrates are re-
crushed and fed to the Concentrate Roll Crusher and fed back to the goldroom gravity spinner.
Fine concentrates are fed to the concentrate jig. Jig concentrates are upgraded using two
shaking tables and the concentrate calcined for direct smelting. Jig and table tails (middlings)
are leached in a proprietary system (Intensive Leach Reactor or ILR) where gold dissolves under
aggressive reaction conditions in an enclosed rotating drum. Cyanide and sodium hydroxide
solutions are added to the ILR. Solution containing solubilised gold (electrolyte) is circulated
through an electrowinning cell and recycled to the ILR.
The overflow of the conditioning tank feeds the flotation cells. Flotation concentrate slurry is
pumped to the concentrate thickener. Tails slurry is pumped to the sand cyclone. Fines are
removed in the cyclone overflow. The cyclone underflow (sands) slurry is diluted and pumped to
a section of the tailings storage facility. The cyclone overflow slurry gravitates to the flotation tail
thickener to remove excess water. Thickener underflow is pumped to the flotation tailings
storage facility. Supernatant water is decanted from settled solids and pumped back to the
process water tank.
The flotation concentrate slurry is thickened to remove excess water and combined with tails
slurry from the ILR. The combined slurry, screened to remove trash, is mixed with lime slurry
and pumped to the CIL circuit. Sodium cyanide is added to the slurry before is enters the
agitated CIL tanks. Dissolved gold is adsorbed onto activated carbon granules. After acid
treatment of the loaded carbon, gold is stripped (eluted) from the activated carbon into a gold
bearing solution (eluate). The eluate is circulated through a separate dedicated electrowinning
cell. Barren activated carbon is processed through a kiln to restore the gold adsorption capacity
and added back to the agitated leach tanks.
The leached slurry discharged from the agitated CIL tanks is treated in a cyanide detoxification
system to reduce the cyanide concentration to below permitted limits and pumped to a separate
tailings storage facility.
Goldroom activities include upgrading of the gravity concentrates and monitoring of
electrowinning from the electrolytes from the ILR and elution systems. Gold in the electrolytes
plated onto cathodes is periodically removed by washing cathodes with a high-pressure water
spray. Washings are filtered and dried in an oven with the shaking table concentrates and
smelted with fluxes into doré bullion.
The reagent area includes facilities for the offloading, mixing, storage and distribution of flotation
collector, activator, frother, flocculant, hydrated lime, sodium hydroxide, sodium cyanide, sodium
metabisulphite and hydrochloric acid. The actual reagents used will vary from time to time
depending on cost, performance and availability.
3 GENERAL
257422914.doc Page 2
Standard personal computers (PC) are located in the Main Control Room (MCR) and the
Crusher Control Room (CCR), and networked to the PLCs. The computers operate a
Supervisory Control and Data Acquisition (SCADA) program for control and monitoring of the
relevant sections of the plant. The SCADA is configured to provide outputs to alarms, control the
function of selected process equipment, and provide logging and trending facilities to assist in
analysis of the operating plant.
The CCR and MCR are purpose built structures, located in the crushing and mill buildings
respectively. The CCR houses one control room operator station and the MCR houses one
control room operator station, one engineering station and a printer. The control room operator
station provides the following functions:
Graphic (mimic) displays of all plant areas, showing equipment status (ready, not-
ready or running) and analogue values for critical process variables
Alarm display and logs, showing the alarm tag number, title, date and time
Trend displays with flexible time and process variable axes for any analogue process
variable
Loop displays showing controller settings and trending of process variable, set-point
and output
The control room operator stations are supplied from an uninterruptible power supply (UPS) unit
with twenty minutes standby capability.
Drives that form part of a vendor package shall be controlled from the vendor’s control panel. As
a minimum, ‘Run’ and ‘Fault’ signals from each vendor control panel are made available to the
SCADA system via the PLC.
The PLCs perform the control of the plant with the SCADA system providing an interface to the
PLCs which:
257422914.doc Page 3
COLOUR DENOTATION
YELLOW Drive Fault , Drive Isolated - LOS, Lanyard or De-
contactor operated
ORANGE Drive ready, but with unhealthy process interlocks
RED Drive and interlocks ready - stopped able to be started
GREEN Running
All controlled valves are shown in graphical format. The colour of the symbol represents the
state of the valve as follows:
COLOUR DENOTATION
257422914.doc Page 4
The control loops described can be found on the Piping and Instrumentation Diagrams (P&IDs)
attached in Appendix 1.
3.2 Drives
Certain equipment is started by PLC controlled group sequences wherever possible, e.g. the
crushing section. Using the sequences allows the control room operator to start or shut down
sections of the plant faster, without risk associated with distractions.
Equipment drives have three modes of operation: namely “AUTO”, “MANUAL” and
“MAINTENANCE”.
Certain drives that are not necessarily associated to a group sequence may need to be set to
“AUTO” mode such as sump pumps, so that they will automatically start and stop based on the
activation of a level switch or other such field device.
Drives that do not require “AUTO” mode will have the AUTO mode selection disabled in the PLC
code. These drives will not have the AUTO mode pushbutton shown on the Citect SCADA motor
faceplate.
AUTO mode cannot be selected on the drive faceplate when the drive is faulted.
In AUTO mode, all process interlocks must be satisfied for the drive to run.
In AUTO mode, the operator may initiate a start and stop the drive from the Citect SCADA
system. The drive will run, provided that the process interlocks are satisfied. The drive will be
switched from AUTO to MANUAL mode if the Citect stop pushbutton is initiated, as well as
stopping the drive.
In AUTO mode, the operator may also start and stop the drive from the Local Control Station
(LCS). The drive will run provided that the process interlocks are satisfied.
Switching of the drive mode from AUTO to MANUAL will keep the drive at its current state (i.e.
drive will stay running).
Switching of the drive mode from AUTO to MAINTENANCE will stop the drive.
In MANUAL mode, the operator may also start and stop the drive from the Local Control Station
(LCS). The drive will run provided that the process interlocks are satisfied.
Switching of the drive mode from MANUAL to AUTO will keep the drive at its current state (i.e.
drive will stay running).
257422914.doc Page 5
Switching of the drive mode from MANUAL to MAINTENANCE will stop the drive.
In this mode, all process interlocks are bypassed and not effective. It is assumed that in
MAINTENANCE mode the field operator will be in full control and supervising the drive.
When switching a drive into MAINTENANCE mode the drive will be stopped.
In MAINTENANCE mode a “spanner” symbol appears adjacent to the drive shown on the mimic
display.
The selection of either mode is made via three separate push buttons on the equipment motor
control faceplates. A coloured border appears around the selected mode push button to denote
that it is selected.
The Local Control Station stop button is always functional regardless of mode selected.
Safety interlocks such as conveyor pull wires, which must remain operational at all times, are
hardwired. All other interlocks are implemented in the PLC.
257422914.doc Page 6
3.2.6 Symbols
Symbols appear adjacent to the drives as well as other control equipment to denote an abnormal
control condition.
These symbols are shown and described on the SYMBOLS LEGEND page.
3.3 Alarms
Alarms are categorised according to relative importance as follows:
1. CRITICAL = RED TEXT
These are those alarms that may cause harm to personnel or equipment damage if condition
remains unattended.
2. PROCESS = YELLOW
These are process type alarm conditions, such as equipment stopping, levels, or other field
devices that stop or have certain effect on the process plant areas and require operator
intervention.
3. EVENT= GREEN
257422914.doc Page 7
These are warning and notification type alarms. The alarm advises the operator that certain
conditions have changed on his plant and may require action or intervention. In some instances
an EVENT type alarms could lead to a PROCESS alarm if the alarm remains unattended.
A schedule of alarms and their category is presented in Appendix 1.
3.4.1 Conveyors
Conveyors are fitted with speed sensors to detect low speed or belt slip, limit switches to detect
belt drift, pull-wire switches to stop the conveyor in an emergency and start-up sirens and
flashing light beacons to advise of an imminent start.
3.4.2 Chutes
Where applicable, chutes are fitted with a laser (or suitable alternative) level switch or transmitter
to alarm on blockage at high level and stop equipment feeding the chute.
3.4.4 Samplers
Slurry samplers are provided at the following locations:
Sampler Sampler Type Location
Flotation feed sampler Airlift Conditioning tank
Flotation tail samplers Double Stage cross-cut Flotation cell 5 outlet
Flotation concentrate sampler Single Stage cross-cut Concentrate thickener
underflow pump delivery
CIL tail sampler Airlift CIL tank 7
Detox tail sampler Airlift Detox tank
Final CIL tail sampler Poppet valve Delivery of CIL tails pumps
257422914.doc Page 8
The airlift sample consists of an airlift with a timer controlled solenoid valve that opens the air
supply on a controlled preset frequency and delivers sample into a suitably located container.
Sample frequency can be adjusted by changing the solenoid valve timer settings via the
SCADA.
The double stage cross cut sampler consists off an electrical motor driven sample cutter that
travels through the process stream. Primary sample is delivered into a surge launder to smooth
out the flow. The primary sample is passed through a Vezin type secondary sampler. The
sample is collected in a sample collection bucket. The reject primary sample from the secondary
sampler is fed to the flotation tailings concentrator. Sample frequency can be adjusted by
changing the sampler timer settings via the SCADA.
The single stage cross-cut sampler consists of a flexible pipe section normally discharging into a
funnel. The pipe is fixed to a pneumatically actuated ram that periodically moves the mouth of
the hose over a static sample collection slot in the funnel. The sample is collected via the slot
and gravitates into a sample collection bucket. Sample frequency can be adjusted by changing
the sampler timer setting at the field mounted sampler control panel.
The final CIL tail sampler consist of an actuated poppet type sampling valve on the CIL tails
pump delivery pipeline with a timer controlled solenoid valve that opens the air supply on a
controlled preset frequency and delivers sample into a suitably located container. Sample
frequency can be adjusted by changing the solenoid valve timer settings via the SCADA.
All samplers are interlocked so they do not operate without process flow.
Manually operated valves are provided as sample points on the ILR and CIL electrowinning cell
feed and tail pipelines.
257422914.doc Page 9
3.4.10 General Monitoring
Selected critical equipment drives are monitored for motor current. They are:
Primary crusher
Secondary crusher
HPGR
Ball mill
Mill pump
Cyclone pump
3.4.12 Thickeners
Nuclear density meters are installed on the thickener underflow pump delivery pipelines. The
density meter can control the thickener underflow pump variable speed, i.e. slowing the pump if
the density drops and speeding up the pump if the density rises.
If the density of underflow slurry drops below the minimum acceptable, e.g. if the thickener feed
is interrupted due to a stoppage in the upstream process, the PLC alarms. The SCADA advises
the control room operator to close the remotely controlled actuated underflow pump delivery
valve feeding the downstream process and open the remotely controlled actuated recycle valve
diverting slurry back to the thickener feed. The PLC detects if the thickener is in this
recirculation mode for longer than a period of 15 minutes an alarm pops up at the SCADA
screen to ensure the control room operator stops flocculant solution addition.
257422914.doc Page 10
A magnetic flow meter on the delivery line from the underflow pump to the downstream process,
is installed after the valves used for diverting underflow slurry back to the thickener feed column.
The volumetric flow and nuclear slurry density measurement are integrated in the PLC to provide
indication and totalisation of the dry tonnage flowrate to the downstream process.
The thickeners are equipped with “mud-level cone” type interface detectors that warn the control
room operator via the SCADA if the bed level is rising so that corrective action can be taken
before a sliming condition occurs. Thickener rake torque measurement is displayed and logged
for trending on the SCADA system. An increase in solids loading raises the high and high-high
torque alarms that activate at the SCADA.
4.1 Crushing
Refer to P&ID 1475-P051 Crushing.
The crushing area is generally controlled from the crusher control room. The MCR can only
monitor operations in the crushing plant up to the discharge of crushed ore intro the fine ore bin.
Equipment is generally started and stopped as part of start-up and shutdown sequences.
The rate of tipping into the ROM bin is a controlled by the visual observation of the loader driver
in communication with the crusher operator. A level element in the ROM bin provides and
indication of the bin level. At a high level, the crusher operator manually activates a switch to
illuminate a red light to advise the loader driver that he may not tip. A high level alarm is
provided and a low-low level alarm is interlocked to stop the primary jaw crusher feeder. The
low-low level interlock ensures that material cannot normally be tipped into an empty bin and
damage the feeder.
The variable speed of the primary jaw crusher feeder is set to match the primary jaw crusher
capacity as observed by the crusher operator. A level detection element is installed in the
primary jaw crusher feed chute which stops the primary jaw crusher feeder in the event of high
level.
A self-cleaning belt magnet is installed at the discharge of crusher product conveyor (CV-001) for
tramp metal removal. The magnet is started and stopped as part of the crushing sequence.
A variable speed vibrating feeder delivers ore from the secondary crusher feed bin to the
secondary cone crusher. The feeder speed is controlled by a level element in the secondary
crusher feed bin. A level element in the crusher feed cavity stops the feeder at a high level.
A high level in the secondary crusher feed bin stops the primary crusher feeder. A high-high
level in the secondary crusher feed bin stops the secondary crusher feed bin conveyor. A metal
detector is installed on the secondary crusher bin feed conveyor. If crusher magnet 1 fails to
remove tramp metal or non-magnetic metal is present, the secondary crusher metal detector
activates the secondary crusher feed bin diverter gate in the secondary crusher feed bin, forcing
material to bypass the bin by diverting back to the crusher product conveyor for a set period.
This period is long enough to ensure any metal detected bypasses the bin. If the position switch
on the secondary crusher feed bin diverter gate does not register the gate has moved to the
divert position in time, the secondary crusher bin feed conveyor trips.
The secondary cone crusher has an alarm after a certain idling time (e.g. 30 minutes). The
control room operator is directed to shut-off the crusher if no feed is available.
257422914.doc Page 11
The primary jaw crusher has an automated pneumatic grease lubrication system running on a
timer. The secondary cone crusher has a low-pressure air seal system to protect the eccentric
and drive from dust. The crusher is equipped with a vendor supplied hydraulic positioning
system for raising and lowering the main shaft to adjust the crusher gap setting and for tramp
relief. An air-cooled lubrication system circulates and cleans oil for the crusher drive.
The dust collection system on the outlet of the primary and secondary crushers and fine ore bin
feed conveyor head pulley and the system at the secondary screen and HPGR are started and
stopped automatically as part of the crushing sequence.
The fine ore bin feed weightometer installed on the fine ore bin feed conveyor measures and
totalises the flowrate of crushed ore from the crushing plant fed to the fine ore bin. The
indication can be used by the control room or crusher operator as a guide to adjust the primary
jaw crusher feeder speed to control the feed to the crushing plant. A level element is installed in
the fine ore bin feed conveyor head chute which stops the conveyor in the event of a high level
in the fine ore bin.
257422914.doc Page 12
The crusher spillage pump delivers to the stormwater collection pond and the stormwater
collection pump delivers decanted water underground for disposal. High level switches in the
crusher building and at the stormwater collection pond provide an alarm to warn of flooding.
Ventilation in the crusher building is provided by the crusher area fan. At the entrance for
personnel to the building, a green light illuminates while the fan is running and a warning red
light illuminates if the fan is stopped.
257422914.doc Page 13
The HPGR is equipped with a dedicated PLC for management of key alarms, trip settings,
interlocks, start up, and shut down sequencing for the main and auxiliary drives. All alarms from
the vendor PLC control panel are repeated at the SCADA system via the relevant plant PLC.
The power, torque, current and speed of the two motors are displayed at the SCADA system.
A level switch is installed in the ball mill screen feed box which stops the mill feed conveyor in
the event of a high level caused by a blockage in the ball mill screen feed box.
257422914.doc Page 14
4.2.2 Grinding and Gravity
The ball mill screen underflow and ball mill discharge, via the trommel, flow to the mill pump
hopper. There is one operating mill pump, with an installed standby. The mill pump delivers via
the jig feed distributor to the three primary jigs operating in parallel. Each pump has actuated
valves for isolation of suction, discharge and gland water. The hopper level is measured and is
controlled automatically by adjusting the pump variable speed.
Water addition to the grinding and gravity section is sourced from the process water tank via the
process water pump.
A flow meter is installed on the water supply to the ball mill screen gold trap and ball mill screen
sprays. The desired flowrate is entered manually into the controller at the SCADA and the
flowrate controlled by an actuated valve.
A flow meter is also installed on the water supply to the ball mill feed chute. The desired flowrate
to provide the required mill discharge slurry density is entered manually into the controller at the
SCADA and the flowrate controlled by an actuated valve.
The mill feed chute seal and mill trommel spray water flows are controlled by manually adjusted
valves. A master actuated valve on the pipeline supplying mill feed dilution, mill feed chute seal
and mill trommel spray water is interlocked to the ball mill drive such that the mill cannot be
started unless the valve is open first and the water supply will be closed when the mill is
stopped.
Jig hutch water is set during commissioning using the vendor supplied magnetic flow meter at
the jig and manually adjusting a water flow control valve at the jig also supplied by the vendor.
Hutch water flow can be optimised thereafter by adjusting the valve position. Hutch water
flowrate is indicated at the SCADA. The jigs are equipped with their own panel mounted
controller to adjust the stroke and frequency of the pulsation.
Mill pump hopper dilution water is controlled by an actuated control valve. The valve position is
controlled by the output of the nuclear density meter installed on the mill pump delivery pipeline
feeding the jig feed distributor to give a consistent cyclone feed slurry density. Operators check
the density of jig feed, mill cyclone overflow, underflow and mill discharge every hour using a
Marcy density scale.
Concentrates accumulating in the ball mill screen gold trap are flushed out periodically to a
Concentrate Kibble in the goldroom by opening remotely actuated purge valves. The fail close
valves are set to open for a short pre-set period and can be opened on a set frequency basis
controlled by a timer or on an ad-hoc basis by the operator. The gold trap should be routinely
purged prior to a planned plant shutdown.
Concentrates from the jigs are discharged into the spinner feed distributor. Spinner tails are
returned to the spinner tails pump hopper. A slurry of coarse solids gravitates from the spinner
tails pump hopper to the mill pump hopper. Provision is made to divert the coarse solids slurry
to the cyclone pump hopper if required. Fine solids and water overflow the hopper into an
overflow compartment and are pumped using the spinner tails pump to the mill screen gold trap
to increase feed dilution. A high level overflow on the hopper overflows to the mill pump hopper.
Four spinners are installed in two parallel pairs of spinners in series. Normally the two spinners
in each pair operate as a primary and secondary stage device with the first unit’s tail feeding the
second unit. The feed valve to the first stage is actuated and closes when the first stage unit is
flushing; diverting slurry from the spinner feed distributor directly to the second stage unit until
flushing is complete. When the second stage unit is flushing, the actuated intermediate valve
closes and diverts the first stage unit tails directly to the mill pump hopper. Spinners are
equipped with their own panel mounted controller to allow setting of cycle times and the
sequential opening and closing of feed and flushing water valves.
257422914.doc Page 15
The centrifugal concentrator is located in the mill area. The centrifugal concentrator is controlled
by a Falcon “AutoPAC" control system. This is a stand-alone unit mounted near to the
centrifugal concentrator and allows setting of key operational parameters such as cycle time.
Manipulation of process variables is only possible at the “AutoPAC” system user interface. The
SCADA only displays whether the centrifugal concentrator system is healthy and the unit is
concentrating, flushing or running in flush inhibit mode.
An actuated knife gate valve is provided on the centrifugal concentrator feed line from the gravity
screen underpan. During the normal concentrating cycle, the valve feeding the concentrator is
open. For bypass during the concentrate flush cycle the valve is closed and the slurry level
backs up in the screen underpan until it reaches the level of the overflow pipe that diverts slurry
directly to the centrifugal concentrator tail pipe feeding the cyclone pump hopper. Should the
concentrator trip, the valve fails closed in order to bypass it until it can be restarted.
There is one operating cyclone pump, with an installed standby. The pump delivers to the mill
cyclone cluster. A duty and a standby cyclone are installed. Each pump has actuated valves for
isolation of suction, discharge and gland water.
The cyclone pump hopper level is measured and is controlled automatically by adjusting the
pump variable speed. A diaphragm-protected gauge on the cyclone feed distributor measures
the cyclone pressure. The cyclone isolation valves are manually opened and closed. A low level
alarm in the hopper opens an actuated valve adding process water to the hopper to assist in
start up of the circuit and prevent the pump from choking.
A flow meter is also installed on the water supply to the centrifugal concentrator, gravity screen
sprays and cyclone pump hopper. The flow meter is not used for control of water addition but is
provided for monitoring purposes.
Though the cyclone feed slurry density is ultimately controlled by the water addition to the jig
feed slurry at the mill pump hopper, the cyclone feed density is monitored by the control room
operator. A nuclear density meter is installed on the cyclone pump delivery pipe line and the
measured density is indicated at the SCADA.
A level measurement device is installed in the cyclone underflow launder to warn of a choked
mill feed chute. A high level alarm will override the level control on the mill and cyclone pump
hoppers and will trip the mill feed conveyor.
Concentrates flushed from the spinners and centrifugal concentrator are delivered to the gravity
concentrate surge tank. The tank is equipped with a level measurement device. The level
measurement prevents any of the spinners or centrifugal concentrator from flushing
concentrates if the tank level is too high. Concentrates are pumped from the tank to the gravity
concentrate tank in the goldroom by the gravity concentrate transfer pump. There is one
operating pump, with an installed standby. The pump suction and delivery arrangement is a
single flexible hose. To change over pumps, a security cleared operator will enter the security
cage and change over the suction and delivery lines.
As the flushing of concentrates to the surge tank is an intermittent process, the delivery of the
gravity concentrate transfer pump is normally set to recycle to the tank to maintain the
concentrate solids in suspension when the tank level is low. After any of the spinners or the
centrifugal concentrator flushes a batch of concentrate to the tank and the level in the tank rises,
the position of actuated valves on the pump delivery is reset to transfer concentrate slurry to the
gravity concentrate tank in the goldroom until the level drops. The PLC inhibits flushing of any of
the spinners or the centrifugal concentrator if the gravity concentrate surge tank is at a high
level.
Balls are added to the mill every shift by the mill operator. The ball addition rate is manually
controlled by the operator to ensure the correct mill power draw is achieved.
257422914.doc Page 16
Balls are delivered in drums and immediate usage requirements stored near the mill. The drums
are emptied manually into the ball kibble and this hoisted to the mill feed chute floor and emptied
into the mill feed chute.
Spillage from the grinding and gravity bunded area is pumped to the mill pump hopper by mill
spillage pump 1 or 2. The mill hoist is a travelling overhead gantry crane that services the
grinding facilities.
4.3 Flotation
4.3.2 Flotation
Refer to P&ID 1475-P057 Flotation 1.
The flotation activator, collector are added to the conditioning tank. Frothing agent is added to
the first flotation cell. The flotation reagent addition rate is ratio controlled by the integrated dry
tonnage flowrate measurement on the flotation feed thickener underflow pump delivery to the
conditioning tank. Facilities are provided for the addition of small extra quantities of collector
and frother to the feed to second and third banks of cells.
The flotation section consists of rougher cells in three banks in series of one, two and two cells
respectively. The concentrate froth launders gravitate to the flotation concentrate pump (one
duty/one standby). Concentrate is pumped to the concentrate thickener. The flotation
concentrate pumps are fixed speed. The flotation cell levels are controlled by actuated pinch
valves located in the discharge of the cell banks. Flotation cell 1, 3 and 5 levels are measured
by an ultrasonic level probe and used to adjust the position of the valve on the cell outlet.
Flotation tails from the final cell gravitate via the flotation tails primary sampler into the flotation
tail pump hopper. The flotation tail pumps (one duty/one standby) pump to either the sand
cyclone or directly to the flotation tail thickener feed box depending on whether the sand cyclone
is online or not. The primary flotation tails sample passes through the flotation tails secondary
sampler and into the flotation tail concentrator. The concentrator is installed to sample the
flotation tail slurry and detect any gravity recoverable free gold particles to identify any deficiency
in the operation of the gravity gold recovery section. Concentrator tails gravitate to the flotation
tails sampler transfer sump pump and are pumped to the flotation tails thickener feed box.
Concentrate is collected and transferred by hand to the plant laboratory.
The flotation tail pump hopper level is measured and is controlled automatically by adjusting the
flotation tail pump speed. Each pump has actuated valves for isolation of suction, discharge and
gland water.
The low-pressure airflow to the individual flotation cells is regulated by a vendor supplied flow
control valve and flow meter at each flotation cell.
257422914.doc Page 17
Spillage from the flotation bunded area is hosed to the flotation spillage pump and pumped to
the conditioning tank.
257422914.doc Page 18
Under Option 3, if both the sand plant and thickener are offline, due to the volume of dilute slurry
from the flotation tailings pumps the installed tails thickener underflow pumps will have
insufficient capacity for the unthickened flotation tailings slurry at the design plant feed rate. The
sand cyclone feed valve (XV4040) is closed and the bypass valve (XV4041) opened. To achieve
the thickener bypass, a tee section will be added into the thickener feed pipe prior to the
thickener feed box. This will feed the tailings thickener underflow pump suctions. A parallel
tailings thickener underflow pumping system is used with both of the flotation tail thickener
underflow pumps operating in parallel delivering separately via both tailings pipelines. A
reduced plant feedrate of 44 t/h is adopted to reduce the slurry volume pumped.
Water is reclaimed from the flotation tailings storage facility by a flotation tail decant pump.
Decant water is returned to the process water tank. A thermal flow switch is installed on the
decant pump delivery. If a no flow situation is detected by the switch, due to the process water
tank being full and the outlet float valve being closed, or the TSF being dry, the switch stops the
decant pump. The switch is linked to a timer and the pump will restart after a 20 minute delay.
Seepage water from the flotation tails storage facilities is collected in trenches. A pump is
located at the facility and seepage water pumped back onto the flotation tailings storage facility
by a seepage pump. The pumps are started and stopped automatically by a level switch in the
seepage trench.
Spillage from the flotation tails thickener bunded area is hosed to the flotation tail thickener
spillage pump and pumped back to the flotation tail thickener feed box. If the flotation tail
thickener is to be bypassed in the event of a breakdown, the delivery of the flotation tail pump
can be connected temporarily to the suction of the flotation tail thickener underflow pump.
4.3.5 Goldroom
The goldroom is manned during dayshifts only and all equipment is started and stopped locally.
257422914.doc Page 19
Goldroom fine screen oversize gravitates to the oversize concentrate bin and undersize to the
concentrate jig. Jig tails are discharged to the gravity middlings pump. Jig concentrates are fed
onto shaking table 1. Shaking table 1 middlings are fed to shaking table 2. Concentrates from
both tables are collected in buckets, excess water decanted and placed in trays in the calcine
oven for drying. Tailings from both shaking tables are combined with jig tails at the gravity
middlings pump and pumped to the ILR feed cone. The concentrate jig is equipped with a 1 mm
screen. Any coarse (i.e. +1 mm) concentrate accumulating in the jig is removed, collected in a
kibble and emptied into the oversize concentrate bin to be crushed and returned to the circuit.
Water is supplied to the jig and shaking tables from the goldroom water tank. The level of water
in the tank is controlled by a float valve to give a constant steady head of water. Water is
supplied to the gold room gold room spinner wetting box directly from the raw water supply.
The gravity concentrate tabling area is bunded to prevent escape of spilt high-grade
concentrates. The goldroom spillage pump is installed to return spilt high grade concentrates to
the gravity concentrate tank.
257422914.doc Page 20
4.4.1 Collector and Frother
Refer to P&ID 1475-P063 Reagents & Consumables Sheet 1 of 4.
Dithio-phosphate collector and frother are delivered in bulk-a-boxes. The handling and storage
is identical for both reagents.
Both bulk-a-boxes are connected to stand pipes. The stand pipe provides a reserve while an
empty bulk-a-box is changed. Duty and standby variable speed double diaphragm dosing
pumps connected to the stand pipes meter the reagent additions from the collector and frother
standpipes tanks to the conditioning tank and first flotation cell respectively. The pump speeds
are controlled by the flotation feed thickener underflow mass flow measurement. A low level
switch is installed in both stand pipes to indicate if the bulk-a-box is empty and alarms at the
SCADA screen if the level is low.
Spillage from the collector and frother storage area is hosed to the flotation bunded area.
257422914.doc Page 21
4.4.3 Flocculant
Refer to P&ID 1475-P064 Reagents & Consumables Sheet 2 of 4.
Flocculant powder is delivered in bulk by road tanker and pneumatically offloaded into the
storage vessel. Dry powder is dissolved in raw water to produce a solution at 0.2 % w/w for
subsequent dilution and use at the thickeners.
Dissolution of flocculant is a fully automatic operation, initiated by a signal from a low level
switch in the flocculant tank. The flocculant preparation plant is a vendor supplied package. The
operator is required to maintain an adequate amount of dry flocculant in the feed hopper. A low
level signal in the feed hopper alerts the operator.
The batch controller of the flocculant make-up system automatically controls the addition of
water, transfer of dry flocculant to the dispersion head, the mixing time for solution aging, and
the transfer to the flocculant tank. A single “general fault” alarm notifies the operator to check
the system.
The flocculant tank has a level switch, which initiates mixing and transfer and a level
measurement element, with a low-low level alarm to notify the operator of problems, and protect
the dosing pumps from running dry.
The operator must ensure that the hopper contains dry flocculant powder, the water supply
isolating valve is open and check that there is sufficient water pressure to the Auto Jet Wet by
observing the pressure gauge reading and ensure the power supply is on and the Duty Selector
Switch is set to "AUTO" mode. For further details, refer to the Ciba Specialty Chemicals
Operating, Maintenance & Installation Manual.
A dedicated flocculant dosing pump is provided for flocculant addition at each thickener. A
common standby is provided for the pumps delivering to the flotation feed and flotation tail
thickeners. A duty and a dedicated standby pump are provided for flocculant addition to the
concentrate thickener.
Strong flocculant solution (0.2%) is pumped into inline mixers, where process water is added to
the flocculant solution to dilute the concentration to 0.02% to ensure better dispersion in the
slurry stream. Each thickener’s flocculant pump delivers flocculant to a dedicated inline mixer.
The pumps are equipped with variable speed drives to allow the flocculant solution dosage to be
adjusted manually. Dilution is controlled by the operator. The operator adjusts the flocculant
dilution water valve and checks by inspection of rotameters, the flow of water and flocculant
respectively until the correct degree of dilution is achieved. Manual valve controlled addition
points are provided at each thickener feed pipe to ensure adequate dispersion of dilute
flocculant solution.
Flocculant spillage from the flocculant make up area is hosed to the flocculant spillage pump and
pumped to the flotation tailings thickener overflow launder.
257422914.doc Page 22
The main section of the tank is partially filled with raw water via an actuated valve and briquettes
are loaded into a cage located in the main compartment of the tank. The tank is topped up with
raw water. The cyanide agitator is started to dissolve the briquettes to make up a 20% solution.
On completion of mixing, the agitator is stopped. The suction manifold valve from the main
section of the tank is reopened to balance the level in the main section and now partially empty
reserve compartment. The valve from the reserve compartment is then closed.
Sodium cyanide solution is pumped through a ring main by the cyanide pumps (one operating,
one standby) to the CIL, elution tank and ILR and returned to the cyanide tank. Line pressure is
maintained by a manually operated diaphragm valve. The ring main return discharges into the
reserve compartment of the tank to ensure it is always full.
Cyanide solution is dosed to CIL tank 1 from an actuated flow control valve on the ringmain
pipeline. The position of the control valve is set by a cascade loop from the concentrate
thickener underflow mass flow system to the CIL cyanide addition flowmeter located upstream of
the flow control valve.
If cyanide is required at the elution tank, it is added by opening via remotely controlled actuated
valve from the cyanide ringmain. The required volume of cyanide solution flowing to the tank is
totalised by a flow meter and the remotely controlled actuated valve closed. Cyanide addition to
the ILR from the ringmain is controlled by the ILR PLC.
The cyanide tank is equipped with level measurement devices indicating at the SCADA in both
compartments. A high level alarm in the main compartment is interlocked to the water addition
valve and a low level alarms at the SCADA screen. A low-low level in the main compartment or
low level in the reserve compartment will trip the cyanide pump.
A duplex strainer is installed on the suction of the cyanide pumps.
Spillage from the cyanide make up tank bunded area is pumped to CIL tank 1 by reagents
spillage pump 2. Reagent hoist 2 services the cyanide make up facilities.
257422914.doc Page 23
Hydrochloric acid is received in a bulk-a-box at 33% w/w strength. The bulk-a-box functions as a
storage tank and is connected to a stand pipe. The stand pipe provides a reserve while an
empty bulk-a-box is changed. A low level switch is installed in the stand pipe to indicate if the
bulk-a-box is empty and alarms at the SCADA screen if the level is low.
The hydrochloric acid offload pump is a fixed speed pump and delivers to the acid wash tank.
The pump is normally left in “Maintenance” mode and started and stopped in the field. The start
button initiates a timer so that if the pump is not stopped manually before the timer expires the
pump will stop to prevent accidental overdosing.
Acid spillage from the laydown area is hosed to a spillage sump. A pneumatically operated
diaphragm pump (supplied by BML) will be installed to dispose of spillage.
4.4.7 SMBS
Refer to P&ID 1475-P067 Reagents & Consumables Sheet 4 of 4.
Sodium metabisulphite (SMBS) is delivered in 1000 kg bags and is dissolved in raw water to
produce a solution at 20% w/v for use at cyanide detoxification. SMBS solution make-up and
storage use the same tank. The tank is split by a vertical plate into the main make up and
storage compartment and a reserve compartment.
Normally SMBS solution is dosed from the main section of the tank. Make up of SMBS solution
is a manual operation, initiated by the operator when the tank is close to empty. While a fresh
batch of solution is made up, the dosing pump suction manifold valve from the main
compartment of the tank is closed and the valve from the reserve compartment opened.
The main section of the tank is partially filled with raw water via an actuated valve. The valve is
then closed and the SMBS agitator started by the operator who can then add a bag of SMBS
using the bag breaker. On completion of mixing, the agitator is stopped. The operator reopens
the water filling valve to fill the main compartment.
The suction manifold valve from the main section of the tank is reopened to balance the level in
the main section and now partially empty reserve compartment. The valve from the reserve
compartment is then closed.
The SMBS tank is equipped with a level measurement device indicating at the SCADA in both
the compartments. A high level alarm in the main compartment is interlocked to the water
addition valve. A low level in either compartment will alarm at the SCADA. A low-low level in the
main compartment or low level in the reserve compartment is interlocked to trip the SMBS pump.
A duplex strainer is installed on the suction of the SMBS pumps.
The variable speed SMBS pumps (one duty/one standby) deliver solution as required to the
detox tank. The flow rate of SMBS to the detox tank is controlled by varying the speed of the
SMBS pump. The pump speed is ratio controlled to the CIL tails volumetric flowrate measured
by a magnetic flow meter on the CIL tails pump delivery line.
Spillage from the SMBS make up area is pumped to the detox tank by reagents spillage pump 1.
Reagent hoist 1 services the SMBS make up facilities.
4.4.8 Lime
Refer to P&ID 1475-P066 Reagents & Consumables Sheet 4 of 4.
Hydrated lime is delivered by road tanker and pneumatically off-loaded into the lime silo. The
silo is equipped with a dust collector. The dust collector is cleaned by a reverse pulse of air
when a high pressure differential is detected over the bag filter.
Lime powder is slurried in the agitated lime tank and pumped via ringmain to the CIL and detox
tank by the lime pump (one duty/one standby). A diaphragm valve on the return line is used to
provide adequate pressure in the ringmain circulation line.
257422914.doc Page 24
Lime slurry is dosed to the CIL at the trash screen underflow and at the detox tank from actuated
pulsing control valves on the ringmain main pipeline.
The lime tank is equipped with an ultrasonic level measurement element. The level of the tank
will drop as lime slurry is dosed to the CIL and detox tank. At a low level set-point, the actuated
water addition valve is opened to refill the lime tank and the lime silo vibrated fluidiser and lime
feeder is started. At a high level set-point, the actuated water addition valve is closed and the
fluidiser and feeder stopped.
A “general fault” alarm notifies the operator to check the lime system.
Spillage from the lime make up area is pumped to the detox tank by reagents spillage pump 1.
4.5 Services
257422914.doc Page 25
The process water tank is supplied with water recycled from the overflows of the flotation feed
thickener, concentrate thickener and flotation tail thickeners, return decant water from the
Flotation Tails Storage facilities and make-up water from the mine water supply (underground
pumping). The addition of decant and make-up water from the mine water supply is controlled
by float valves in the tank. Water sources entering the tank are delivered into the connecting
process water stand pipe to minimise sanding of the tank from suspended solids in the thickener
overflow streams.
The process water tank is equipped with a hydrostatic level measurement device. A low level
alarms at the SCADA and a low-low level will then trip the HPGR feed conveyor.
The CIL water tank is supplied with return decant water from the CIL tails storage facility, and
make-up water from the mine water supply. The water in the CIL water tank is used as spray
and dilution water at the trash screen, loaded carbon screen and CIL tail screen.
The addition of decant and make-up water from the mine water supply is controlled by float
valves in the tank. The CIL water tank is equipped with a hydrostatic level measurement device.
A low level in the tank alarms at the SCADA.
The transfer water pump is started and stopped by the operator as required. The level in the
transfer water tank is topped up as required by opening a manual valve on the Bendigo water
supply line.
If contaminated transfer water is to be disposed of the operator closes the delivery line valve to
elution area and opens the recycle valve on the delivery back into the transfer water tank and a
bleed valve feeding a small amount of contaminated water to the carbon safety screen feed box
and starts the pump. The flow of contaminated water to disposal at the carbon safety screen
feed box is controlled manually using the bleed valve.
4.5.3 Air
Refer to P&ID 1475-P069 Services - Air.
Duty and standby low-pressure air flotation blowers supply the flotation cells. A local pressure
gauge indicator and a transducer indicating at the SCADA are fitted on the low-pressure air
main.
Compressor 1 and 2 operate in lead/lag mode and provide high-pressure compressed air for
general distribution. Air compressors are rotary screw type complete with vendor controller
package, which senses load and starts the second unit or puts the compressor on idle, as
required.
All high-pressure compressed air is filtered and dried to produce instrument quality air. All
compressed air is filtered using a “Class B” grade filter element in instrument air filter 1 and dried
to a 3 degree Celsius dew point using the refrigerant type air dryer. Dry air is filtered using a
“Class C” grade filter element in instrument air filter 2 and stored in the plant air receiver then
distributed to the plant. Duty and standby air filters are installed. An extra mill air receiver is
installed at the mill area to ensure a reliable compressed air supply is available for the mill and
jigs.
Air filters are equipped with their own vendor supplied high differential pressure indication to
warn when the filter cartridge element is blocked. Each air receiver is equipped with a pressure
gauge and pressure transducer indicating at the SCADA.
Compressed air is used for pneumatic tools, chute diverters, and valve and dart plug actuation.
Service points are provided throughout the plant.
The CIL LP air blower provides low pressure air that is used for airlifts and interstage screens.
Plant air (high pressure) can be used for additional CIL LP air if required.
257422914.doc Page 26
Oxygen is delivered in liquid form by road tanker and off-loaded into a bulk liquid storage vessel
equipped with a vaporising system. The bulk oxygen supply system feeds a plant reticulation
system that supplies oxygen to the CIL and detox tanks. The oxygen system includes a tank
pressure and discharge pressure control system and tank level and pressure indicators.
4.5.4 Other
Uncontaminated plant site run-off is collected in the stormwater collection pond. Collected run-
off water can be pumped either to the process water tank or to underground using the
stormwater collection pump.
257422914.doc Page 27
Flocculant solution is added to the ILR pump hopper and ILR thickener from a dosing tank
supplied by Gekko located at the ILR. The dosing tank is filled by the operator daily from the
flotation feed thickener dilute flocculant solution pipeline.
Concentrate thickener underflow slurry is pumped via flotation concentrate sampler to the trash
screen feed box. At the trash screen, material such as grit, woodchips, fibres, wire and plastic,
that would otherwise choke CIL interstage screens and contaminate loaded carbon recovered
from the CIL tanks, is removed. The trash screen underflow is pumped into CIL tank 1. The
screen spray water is manually controlled to achieve the required CIL slurry density.
Trash screen oversize reports to the trash basket. The basket is equipped with wedge wire
mesh panels to allow excess water to drain away, retaining the trash. The basket can be
removed with a forklift or hoisted with a crane and emptied. The empty basket can then be
replaced.
Lime slurry is added to the trash screen underpan by a pulsing valve on the lime ringmain pipe.
A pH meter is installed in CIL tank 1. The output of the pH meter is used to control the valve
pulse frequency.
The ILR may not operate when the trash screen or trash screen underflow pump is stopped as
ILR tails would blind the screen or overflow the trash screen underflow hopper.
257422914.doc Page 28
Slurry discharged from the final stage CIL tank gravitates to the cyanide detoxification tank.
A detector is provided on the CIL tank top floor level for monitoring of hydrogen cyanide gas with
local buzzer or horn alarms and SCADA alarms in case of high levels.
A laboratory is provided for CIL operators to check slurry densities, pH, and dissolved oxygen
(DO) levels and perform titrations to check reagent levels and prepare samples for the assay
laboratory. Manually taken slurry samples from the tanks are used to check the slurry density
using a Marcy scale. Manual samples are used to check carbon concentrations. Slurry samples
are taken from selected CIL tanks every 2 hours, filtered, the solution titrated for sodium cyanide,
and the slurry pH measured using a pH meter. Action can then be taken to increase or decrease
cyanide and pH modifier addition as needed.
The CIL spillage pump delivers to the spillage from the CIL bunded area back to the CIL tank 1.
257422914.doc Page 29
Periodically (typically every 3 to 4 acid washes) the dilute acid in the acid wash tank becomes
too contaminated for further use. Sufficient sodium hydroxide is pumped to the acid wash tank
to neutralise the spent acid. The acid wash pump is used to pump the discarded liquor to the
CIL tails pump hopper. Fresh raw water is used to refill the acid wash tank and sufficient fresh
concentrated hydrochloric acid is added to make up the required hydrochloric acid strength
(~3%). Water addition to the acid wash tank to make-up fresh dilute acid solution is controlled
by a manual valve.
The acid wash system requires operator intervention at various times during the sequence as all
valves are opened or closed manually.
4.8.2 Elution
Refer to P&ID 1475-P074 Elution.
The elution section uses the pressure Zadra method. The elution liquor, a dilute sodium
hydroxide-cyanide solution is pumped from the elution tank via the recovery heat exchanger and
elution heater into the elution column under elevated temperature. The heater burners heat the
eluate solution directly. Hot eluant solution exiting the elution column is cooled in the recovery
heat exchanger by contacting with fresh eluate solution being pumped into the heater.
To start an elution, the sodium hydroxide and cyanide concentrations in a sample of the eluate
solution in the elution tank are checked and if required, corrected by adding fresh reagents. The
eluate solution is pumped, using the elution pump, through the heat exchanger, heater, elution
column and elution strainers (one duty/one standby) to the CIL electrowinning cell. Barren
electrolyte is returned from the cell outlet to the elution tank.
On completion of an elution, carbon is transferred to the eluted carbon screen above the kiln
feed hopper. The transfer water pump pressurises the elution column and supplies transport
water to the outlet bend at the base of the column. A slurry of carbon in water is delivered to the
screen. Carbon drops into the hopper and excess water is drained back to the transfer water
tank.
Eluate solution can be reused for a number of elutions until the level of contamination becomes
unacceptable. The spent eluate is pumped to CIL via the spent eluate tank by the elution pump
after opening the spent eluate discharge valve (XV8730). The benefit of any available sodium
hydroxide and cyanide in the spent eluate is used and the carbon in the CIL can recover the
residual gold values. The elution heater is interlocked to the valve open position so the heater
cannot be operated without eluate flow nor eluate disposed of by accident during an elution.
To make a new batch of eluate solution, the elution tank is filled with raw water and sufficient
cyanide and sodium hydroxide solutions added. Water addition to the elution tank to make-up
fresh eluant solution is controlled by a manual valve.
The elution system requires operator intervention at various times during the sequence as all
valves are opened or closed manually.
The elution tank is equipped with a low level switch interlocked to trip the elution pump at low
level. The elution pump is a helical rotor type pump and cannot be run dry.
The elution column outlet is equipped with a pressure and temperature gauges. Pressure and
temperature gauges are supplied at the inlets and outlets of the heat exchanger. A temperature
gauge is installed at the elution tank.
The outlet of the heater is equipped with a temperature gauge as well as a temperature
measurement device. This is used to control the elution heating system. The heater system is
automated and has a local control panel. The elution column pressure is controlled by the
operator who manually adjusts the position of a throttling valve on the eluate outlet of the
recovery heat exchanger.
257422914.doc Page 30
4.8.3 Regeneration
Refer to P&ID 1475-P075 Regeneration.
When the elution sequence is complete, the operator can divert the transfer of carbon direct to
CIL via the regen carbon screen or to regeneration via the eluted carbon screen.
Screened eluted carbon is discharged into the kiln feed hopper. Carbon is fed to the
regeneration kiln situated on top of the CIL tanks by the kiln screw feeder.
Regenerated carbon from the kiln is quenched in the carbon quench pan and passes over the
regen carbon screen at the CIL. The screen removes excess water and carbon fines. Carbon is
discharged into the last CIL tank to replace loaded carbon transferred upstream.
Water and carbon fines passing through the eluted carbon screen gravitate to the transfer water
tank. Water and carbon fines passing through the regen carbon screen gravitate to the detox
tank.
The regeneration section operates intermittently depending on the availability and activity of
eluted carbon and the requirements for regenerated carbon to be added to the CIL.
Regeneration is performed as a manually controlled sequence and all valves are opened or
closed manually. Operator intervention or acknowledgement is required at various times during
the procedure. Kiln heating is controlled by the vendor’s instrumentation and control system. An
emergency drive system is incorporated to protect the heated kiln retort tube from distortion if
the main power supply is interrupted. Changeovers from mains supply to emergency supply and
vice versa are automatic and instantaneous. The battery supply will drive the tube for a
minimum period to allow the tube to cool to a safe temperature.
4.9 Electrowinning
Refer to P&ID 1475-P076 Electrowinning.
Gold in the ILR electrolyte and eluate is plated separately onto cathodes in the dedicated ILR
and CIL electrowinning cells.
Periodically, the operator uses the electrowinning hoist to remove the anodes from the cells after
isolating the rectifier and feed systems. The anodes are stored in an anode “horse” allowing the
operator to raise the cathodes utilising the same hoist. The gold sludge adhering to the cathode
mesh is removed by washing with a high-pressure water spray and collected in the body of the
electrowinning cell.
Rectifier voltage and current is displayed and adjusted at the rectifiers located adjacent to the
outside wall of the goldroom.
The plated precious metals are washed from the stainless steel mesh cathodes using the high-
pressure cathode wash pump directly into the cell. The pan filter dewaters the resultant sludge
that is collected and this is then dried in the calcine oven prior to mixing with fluxes and
placement into the smelting furnace.
To collect cathode sludge, after electrowinning is complete, the rectifier is switched off and
electrically isolated, the cells are drained via a decant line, to within 100 mm of the cell bottom to
discard the majority of the solution. This decant line is run to the electrowinning spillage pump
sump. The electrowinning spillage pump delivers to the elution tank Solution flow from the cell
during the decant draining step is controlled by a manual valve to ensure cell exit velocities are
low enough to avoid solids entrainment and to match the flow rate to the electrowinning spillage
pump capacity.
After draining, the fume hood is removed and the anode pack is carefully lifted from the cell with
the cathode hoist, hosing off any residual sludge that may have adhered to the anode plates into
the cell. The anode pack is then removed from the cell and placed in the anode holding frame,
freeing the overhead monorail and electric hoist for lifting and removal of the cathode pack.
257422914.doc Page 31
The vacuum system is then started and the receiver evacuated. The remaining cell solution is
drained to the vacuum filter and the operator matches the filter feed and vacuum receiver inlet
flows, to prevent filter overflows, by adjusting feed and discharge valves. Once the remaining
cell solution has been filtered, the vacuum system is regulated to accept the lower flow of solids
and wash water being drained from the cell during the cell cleaning step.
Using the cathode hoist, the cathode pack is carefully raised from the cell and each cathode is
progressively hosed off, into the cell, using the cathode wash pump. This stream of sludge and
wash water is filtered concurrently with the cell cleaning process. The vacuum receiver is sized
to contain the residual cell solution after decanting plus a nominal volume of wash water, such
that it should not be necessary to drain the receiver during the cell clean out process. This
volume is later drained from the receiver to the electrowinning spillage pump sump. If this
nominal volume of wash water is exceeded during the cell clean out process, it is necessary to
shut down the vacuum pump and drain the receiver. A high-level switch in the receiver will trip
the vacuum pump to protect against overfilling of the receiver and consequently filling the
vacuum pump with filtrate.
After filtering, the solids are recovered from the vacuum filter by tilting the filter pan and
shovelling to metal drying trays. The trays are manually lifted into a drying oven to remove any
remaining moisture.
Each electrowinning cell is fitted with a fume hood. This is arranged over the cell and connected
to a plenum chamber that in turn connects to the goldroom scrubber to scrub the fume and
vapours before discharge to atmosphere via the stack. Control of the airflows through this
venting system is by means of manually adjusted slide plate dampers. The anode and cathode
packs of the cell are fitted with a dedicated laminated busbar to conduct current. Air drawn into
the cell enters via spaces between the laminations of the cell’s cathode and anode busbars, thus
providing cooling.
The tails from the ILR electrowinning cell gravitate to the ILR cell tail pump hopper. The ILR cell
tail pump (one duty/one standby) delivers the cell tail solution back to the ILR thickener. The
level in the hopper is maintained by a float valve connected to the pump delivery.
A high level in the ILR cell tail pump hopper closes an actuated valve in the pregnant solution
pipeline from the ILR to prevent flooding in the goldroom.
257422914.doc Page 32
The free cyanide (CNfree) level in the detox tank feed slurry is routinely measured by the operator
by titration of slurry filtrate samples. The CN free level is input via the SCADA along with a ratio for
predicting weak acid dissociable cyanide (CNwad) levels based on actual CNwad compared to
actual CNfree measurements determined from operating experience.
The speed of the copper sulphate dosing pump adding solution to the detox tank is ratio
controlled from the CIL tails volumetric flowrate and manually input slurry density and the copper
sulphate addition rate set point in grams Cu2+ per cubic metre of solution.
Duplicate pH probes are installed in the detox tank. A selected probe provides input to the detox
pH control loop. The loop output controls a pulsing lime-dosing valve on the lime ringmain to
maintain a pH in the tank between 8.5 and 9.5. The signals from the two probes are compared
in the event one probe is out of calibration. If a significant difference in signal is detected, an
alarm advises the operator of the discrepancy. The most accurate pH probe is determined and
control switched to this probe. The inaccurate probe is cleaned, recalibrated or replaced so that
the readings from the two probes coincide.
Oxygen is added to the tank through a sparger system. Rotameters measure the gas-flow and
flow is adjusted by manual operated needle valves.
The detoxified slurry discharging from the tank passes through the CIL tail screen. Screen
oversize reports to the carbon basket. The carbon basket is equipped with wedge wire mesh
panels to allow excess slurry to drain away, retaining the carbon. The basket can be removed
with a forklift or hoisted with a crane and emptied. The empty basket can then be replaced.
Screen undersize gravitates to the CIL tails pump hopper. Discharge from the hopper is pumped
to the CIL tails storage facility by the variable speed CIL tails pump (one duty/one standby).
Pump speed is adjusted to maintain a specified level in the pump hopper. Each pump has
actuated valves for isolation of suction, discharge and gland water.
Water is reclaimed from the CIL tails storage facility by the CIL tails decant pump (one duty) and
returned to the CIL water tank for re-use.
A thermal flow switch is installed on each decant pump delivery. If a no flow situation is detected
by the switch, due to the CIL water tank being full and the outlet float valve being closed, or the
TSF being dry, the switch stops the decant pump. The switch is linked to a timer and the pump
will restart after a 20 minute delay.
5.1 General
Interlocks and permissives are programmed into the control system consistent with the
control philosophy.
Permissives need to be satisfied prior to starting equipment to ensure that equipment is not
damaged and that operational hazards are prevented. Similarly, interlocks have been
programmed into the control system to stop and protect equipment, or equipment around it,
under circumstances where associated equipment stops or process conditions dictate it.
The following sections list the permissives and interlocks required to operate the equipment
in the respective areas.
257422914.doc Page 33
5.2 Crushing
Drive Drive Permissive to Start Running Interlock
Description Number
Primary crusher 10-FE-001 Primary jaw crusher running Primary jaw crusher stops
feeder
Crusher product conveyor running Crusher product conveyor stops
LAH1003 not activated LAH1003 activated
LAH1015 not activated LAH1015 activated
LALL1079 activated
Primary jaw 10-CR-001 Primary crusher healthy Primary crusher lubrication system
crusher OFF for a set time
Lubrication system selected to ON
Lubrication system running
Crusher product 10-CV-001 Secondary screen running Secondary screen stops
conveyor
Pull-wire switch not activated Pull-wire switch activated XA1006
XA1006
Belt drift switch activated ZA1007
Belt drift switch not activated
ZA1007 Conveyor underspeed switch
activated SAL1005
Secondary screen 10-SC-001 Secondary crusher feed bin feed Secondary crusher feed bin feed
conveyor running conveyor stops
Fine ore bin feed conveyor running Fine ore bin feed conveyor stops
Secondary 10-CV-002 LAHH1015 not activated OR LAHH1015 activated
crusher feed bin ZSC1076 activated (bin bypassed)
feed conveyor Pull-wire switch activated XA1011
Pull-wire switch not activated
XA1011 Belt drift switch activated ZS1012
Fine ore bin feed 10-CV-003 LAHH1023 not activated LAHH1023 activated
conveyor
Pull-wire switch not activated Pull-wire switch activated XA1019
XA1019
Belt drift switch activated ZS1020
Belt drift switch not activated
ZS1020 Conveyor underspeed switch
activated SAL1018
HPGR magnet switched on
HPGR magnet switched off
Secondary 10-FE-002 Secondary cone crusher running Crusher product conveyor stops
crusher feeder
LAH1016 not activated Secondary cone crusher stops
LAH1016 activated
Secondary cone 10-CR-002 Crusher product conveyor running Secondary crusher lubrication system
crusher OFF for a set time
Secondary cone crusher healthy
Lubrication system selected to ON
Lubrication system running
Crusher spillage 10-PU-001 LAHH1051 not activated LAHH1051 activated
pump
Stormwater 10-PU-054 LAH7008 not activated LAH7008 activated
collection pump
257422914.doc Page 34
5.3 Fine Ore Bin, HPGR, Grinding and Gravity
257422914.doc Page 35
Drive Drive Permissive to Start Running Interlock
Description Number
Fine ore bin belt 10-FE-003 HPGR feed conveyor running HPGR feed conveyor stops
feeder
LAL1023 not activated LAL1023 activated
Pull-wire switch not activated Pull-wire switch activated XA1025
XA1025
Belt drift switch activated ZS1026
Belt drift switch not activated
ZS1026 Conveyor underspeed switch
activated SAL1024
HPGR feed 10-CV-004 HPGR running HPGR stops
conveyor
LAHH1044 not activated OR Mill feed conveyor stops
ZSC1042 activated
LAHH1044 activated
Pull-wire switch not activated
XA1030 Pull-wire switch activated XA1030
Belt drift switch activated ZS1031 Belt drift switch activated ZS1031
Ball mill screen 20-SC-002 Mill screen oversize conveyor Mill screen oversize conveyor stops
running
Mill pump stops
Mill pump running
HPGR 20-CR-003 Mill feed conveyor running Mill feed conveyor stops
HPGR healthy HPGR not healthy
Mill pump 20-PU-003 XV2017 or XV2018 or XV2019 open XV2017 & XV2018 & XV2019 all
closed
Process water pump running
FAL2006/08 not activated
257422914.doc Page 36
Drive Drive Permissive to Start Running Interlock
Description Number
Primary jig no.1 XV2017 Primary jig no.1 running Primary jig no.1 stops (valve closes)
feed valve open
Primary jig no.2 XV2018 Primary jig no.2 running Primary jig no.2 stops (valve closes)
feed valve open
Primary jig no.3 XV2019 Primary jig no.3 running Primary jig no.3 stops (valve closes)
feed valve open
Cyclone pump 20-PU-004 Flotation feed thickener running
Process water pump running
FAL2057/59 not activated
Primary jig no.1 20-GC-001 Process water pump running
Primary jig no.2 20-GC-002 Process water pump running
Primary jig no.2 20-GC-003 Process water pump running
Centrifugal 20-GC-004A Process water pump running
concentrator No 1
Ball mill 20-ML-001 Refer Outokumpu design document Refer Outokumpu design document
7330-DD01 Rev0 7330-DD01 Rev0
257422914.doc Page 37
5.4 Flotation
Drive Drive Permissive to Start Running Interlock
Description Number
Flotation feed 30-PU-006 FAL3006/09 not activated
thickener
underflow pump
Flotation tail 30-PU-007 Flotation tail thickener running LAH4023 activated
pump
LAH4023 not activated
FAL3026/61 not activated
Flotation 30-PU-008 Concentrate thickener running
concentrate pump
Flotation tails 30-PU-081 Flotation tail thickener running
sampler transfer
pump
Flotation 30-PU-010 Trash screen running LAHH8319 activated
concentrate
thickener LAHH8319 not activated
underflow pump
Flotation tail 40-PU-013 FAL4007/09 not activated
thickener
underflow pump
Sand pump 1 40-PU-072 FAL4031/33 not activated
257422914.doc Page 38
5.5 Reagents and Consumables
Drive Drive Permissive to Start Running Interlock
Description Number
Collector dosing 60-PU-038 LAL6001 not activated Flotation feed thickener underflow
pump pump stops for longer than 60
seconds
Frother pump 60-PU-041 LAL6003 not activated Flotation feed thickener underflow
pump stops for longer than 60
seconds
Copper sulphate 60-PU-039A LALL6047 not activated Flotation feed thickener underflow
dosing pump A pump stops for longer than 60
LAL6023 not activated seconds
Copper sulphate 60-PU-039B LALL6047 not activated XC6051 selected for flotation &
dosing pump B flotation feed thickener underflow
LAL6023 not activated pump stops for longer than 60
seconds
XC6051 selected for Detox & CIL tails
pump stops for longer than 60
seconds
Copper sulphate 60-PU-039C LALL6047 not activated CIL tails pump stops for longer than
dosing pump C 60 seconds
LAL6023 not activated
Flocculant dosing 60-PU-043A LALL6005 not activated LALL6005 activated
pump A
Cyclone pump stops
Flocculant dosing 60-PU-043B LALL6005 not activated LALL6005 activated
pump B
XC6052 selected for flotation feed &
cyclone pump stops
XC6052 selected for Flotation tails &
flotation tail pump stops
Flocculant dosing 60-PU-043C LALL6005 not activated LALL6005 activated
pump c
Flotation tail pump stops
Flocculant dosing 60-PU-043D LALL6005 not activated LALL6005 activated
pump d
Flotation concentrate pump stops
Flocculant dosing 60-PU-043E LALL6005 not activated LALL6005 activated
pump e
Flotation concentrate pump stops
Cyanide pump 60-PU-047 LAL6014 not activated LAL6014 activated
LALL6012 not activated LALL6012 activated
Cyanide tank XV6013 LAHH6012 not activated LAHH6012 activated
water addition
valve open
Sodium hydroxide 60-PU-044A LALL6034 not activated LALL6034 activated
pump A
Sodium hydroxide 60-PU-044B LALL6034 not activated LALL6034 activated
pump B
SMBS pump 60-PU-067 LAL6021 not activated LAL6021 activated
LALL6019 not activated LALL6019 activated
SMBS tank water XV6020 LAH6019 not activated LAH6019 activated
addition valve
open
257422914.doc Page 39
5.6 Gravity and Flotation Concentrate Leaching
Drive Drive Permissive to Start Running Interlock
Description Number
Trash screen 80-SC-005 Trash screen underflow pump
running
Trash screen 83-PU-079 CIL agitator No 1 running
underflow pump
Flotation 83-SA-003 Flotation concentrate thickener Flotation concentrate thickener
concentrate underflow pump running underflow pump stops
sampler
CIL tails sampler 83-SA-005 Trash screen underflow pump Trash screen underflow pump stops
airlift running
Detox tails 90-SA-004 Trash screen underflow pump Trash screen underflow pump stops
sampler running
Final CIL tail 90-SA-008 CIL tails pump running CIL tails pump stops
sampler
Loaded carbon 83-SC-006 LAH8702 not activated LAH8702 activated
screen
5.8 Electrowinning
Drive Drive Permissive to Start Running Interlock
Description Number
Pan filter vacuum 85-VP-001 LAH8504 not activated LAH8504 activated
pump
Refer to vendor manual Refer to vendor manual
257422914.doc Page 40
5.9 Cyanide Detoxification
Drive Drive Permissive to Start Running Interlock
Description Number
CIL tails pump 90-PU-022 FAL9011/13 not activated Nil
LAL9007 not activated
257422914.doc Page 41
6 PROCESS CONTROL LOOPS
6.1 Crushing
b) Remote Manual - the operator selects the speed of the feeder through the bin level
controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote LIC1015 Auto Set-point for LIC1015 To secondary crusher feeder VVVF
drive SC1089
Process variable for LIC1015
LIC1015 Manual Nil To secondary crusher feeder VVVF
drive SC1089
257422914.doc Page 42
6.2 Fine Ore Bin, HPGR, Grinding and Gravity
b) Remote Auto (Override) - the output of the HPGR feed rate controller is driven to a
minimum while the HPGR feed bin high level alarm condition is active.
c) Remote Manual - the operator selects the speed of the feeder through the HPGR feed
rate controller.
d) Remote Manual (Override) - the output of the HPGR feed rate controller is driven to a
minimum while the HPGR feed bin high level alarm condition is active.
Control Controlle Controller Controller Input Controller Output
Mode r Mode
Tag
Remote WIC1033 Auto Set-point for WIC1033 To fine ore bin belt feeder VVVF
drive SC1033
Process variable for WIC1033
LIC1044 Auto(Override) LAH1044 Fine ore bin belt feeder VVVF drive
SC1033 to minimum
WIC1033 Manual Nil To fine ore bin belt feeder VVVF
drive SC1033
LIC1044 Manual LAH1044 To fine ore bin belt feeder VVVF
(Override) drive SC1033 to minimum
b) Remote Manual - the operator selects the speed of the HPGR rolls through the HPGR
feed bin level controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote WIC1033 Auto Set-point for LIC1044 To HPGR VVVF drive SC1090A/B
Process variable for LIC1044
WIC1033 Manual Nil To HPGR VVVF drive SC1090A/B
257422914.doc Page 43
6.2.3 Mill Pump Hopper Level
Objective:
Level of the mill pump hopper is controlled to maintain required throughput.
Modes of Operation:
a) Remote Auto - the operator selects a mill pump hopper level set-point and the level
controller adjusts the speed of the mill pump.
b) Remote Auto (Override) - the output of the mill pump hopper level controller is driven to
a minimum while the cyclone underflow launder high-level alarm condition is active.
c) Remote Manual - the operator selects the speed of the mill pump through the mill pump
hopper level controller.
d) Remote Manual (Override) - the output of the mill pump hopper level controller is driven
to a minimum while the cyclone underflow launder high-level alarm condition is active.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote LIC2009 Auto Set-point for LIC2009 To mill pump VVVF drive SC2089A/B
Process variable for LIC2009
LIC2009 Auto LAH2067 Mill pump VVVF drive SC2089A/B to
(Override) minimum
LIC2009 Manual Nil To mill pump VVVF drive SC2089A/B
LIC2009 Manual LAH2067 Mill pump VVVF drive SC2089A/B to
(Override) minimum
b) Remote Manual - the operator selects the position of the flow control valve through the
mill pump delivery density controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote DIC2016 Auto Set-point for DIC2016 To FCV-2003 positioner
Process variable for DIC2016
DIC2016 Manual Nil To FCV-2003 positioner
257422914.doc Page 44
6.2.5 Mill Feed End Water Addition
Objective:
Flowrate of mill feed end water addition is controlled to maintain mill operating slurry
density.
Modes of Operation:
a) Remote Auto - the operator selects a mill feed end water addition flow set-point and the
flow controller adjusts the position of the flow control valve.
b) Remote Manual - the operator selects the position of the flow control valve through the
mill feed end water addition flow controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote FIC2097 Auto Set-point for FIC2097 To FCV-2092 positioner
Process variable for FIC2097
FIC2097 Manual Nil To FCV-2092 positioner
b) Remote Manual - the operator selects the position of the flow control valve through the
mill screen gold trap feed water addition flow controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote FIC2091 Auto Set-point for FIC2091 To FCV-2091 positioner
Process variable for FIC2091
FIC2091 Manual Nil To FCV-2091 positioner
257422914.doc Page 45
6.2.7 Cyclone Pump Hopper Level
Objective:
Level of the cyclone pump hopper is controlled to maintain required throughput.
Modes of Operation:
a) Remote Auto - the operator selects a cyclone pump hopper level set-point and the level
controller adjusts the speed of the cyclone pump.
b) Remote Auto (Override) - the output of the cyclone pump hopper level controller is
driven to a minimum while the cyclone underflow launder high-level alarm condition is
active.
c) Remote Manual - the operator selects the speed of the cyclone pump through the
cyclone pump hopper level controller.
d) Remote Manual (Override) - the output of the cyclone pump hopper level controller is
driven to a minimum while the cyclone underflow launder high-level alarm condition is
active.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote LIC2048 Auto Set-point for LIC2048 To cyclone pump VVVF drive
SC2090A/B
Process variable for LIC2048
LIC2048 Auto LAH2067 Cyclone pump VVVF drive
(Override) SC2090A/B to minimum
LIC2048 Manual Nil To cyclone pump VVVF drive
SC2090A/B
LIC2048 Manual LAH2067 Cyclone pump VVVF drive
(Override) SC2090A/B to minimum
b) Remote Manual - the operator selects the position of the water dilution valve through the
cyclone pump hopper water addition valve controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote XV2072 Auto LAL2048 XV2072 positioner to open
XV2072 Manual Nil XV2072 positioner to open
257422914.doc Page 46
6.2.9 Gravity Concentrate Surge Tank Level
Objective:
Level of the gravity concentrate surge tank is controlled to prevent overfilling with
concentrate by successive concentrate flushing from the spinners and centrifugal
concentrator.
Modes of Operation:
a) Remote Auto - the supervisor selects a high-level alarm set-point. At high-level, the
PLC opens the actuated valve feeding slurry to the concentrate tank and inhibits any
unit from flushing.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote LIC2061 Auto LAH Set-point for LI2061 XV2066 positioner to open at LAH
LAHH Set-point for LI2061 LAHH inhibit flush signal (order of
priority):
Process variable for LI2061
Centrifugal concentrator
Spinner No 1
Spinner No 2
Spinner No 3
Spinner No 4
b) Remote Manual - the operator selects a purge cycle through the controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote KC2002 Auto running time set-point for Timer expires
KC2002
XV2001 open for set time
open time set-point for XV2001
XV2001 to close
open time set-point for XV2002
XV2002 open for set time
XV2002 to close
KC2002 Manual open time set-point for XV2001 XV2001 open for set time
open time set-point for XV 2002 XV2001 to close
XV2002 open for set time
XV2002 to close
257422914.doc Page 47
6.3 Flotation
b) Remote Manual - the operator selects the speed of the flotation feed thickener
underflow pump through the flotation feed thickener underflow slurry density controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote DIC3012 Auto Set-point for DIC3012 To flotation feed thickener underflow
pump VVVF drive SC3074A/B
Process variable for DIC3012
DIC3012 Manual Nil To flotation feed thickener underflow
pump VVVF drive SC3074A/B
b) Remote Auto 2 - the operator selects a conditioning tank dilution water flow set-point
and the flow rate controller adjusts the position of the flow control valve.
c) Remote Manual - the operator selects the position of the flow control valve through the
conditioning tank dilution water flow controller.
257422914.doc Page 48
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote FIC3001 Auto 1 Set-point for FIC3001 from To FCV-3011 positioner
FY3012
FY3012 inputs:
Process variable from WIC3012
Process variable from DIC3012
Set-point from HX3012
Solids SG (t/m³) (Supervisor
level access only)
FIC3001 Auto 2 Set-point for FIC3001 To FCV-3011 positioner
FIC3001 Manual Nil To FCV-3011 positioner
b) Remote Manual - the operator selects the speed of the flotation tails pump through the
flotation tails hopper level controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote LIC3020 Auto Set-point for LIC3020 To flotation tails pump VVVF drive
SC3075A/B
Process variable for LIC3020
LIC3020 Manual Nil To flotation tails pump VVVF drive
SC3075A/B
257422914.doc Page 49
6.3.4 Flotation Concentrate Thickener Underflow Slurry Density
Objective:
Density of flotation concentrate thickener underflow slurry is controlled to maintain
required throughput, optimum thickener performance and optimum CIL feed slurry
density.
Modes of Operation:
a) Remote Auto - the operator selects a flotation concentrate thickener underflow slurry
density set-point and the density controller adjusts the speed of the flotation concentrate
thickener underflow pump.
b) Remote Manual - the operator selects the speed of the flotation concentrate thickener
underflow pump through the flotation concentrate thickener underflow slurry density
controller.
b) Remote Manual - the operator selects the speed of the flotation tailings thickener
underflow pump through the flotation tailings thickener underflow slurry density
controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote DIC4010 Auto Set-point for DIC4010 To flotation tailings thickener
underflow pump VVVF drive
Process variable for DIC4010 SC4055A/B
DIC4010 Manual Nil To flotation tailings thickener
underflow pump VVVF drive
SC4055A/B
257422914.doc Page 50
6.3.6 Sand Pump Delivery Slurry Density
Objective:
Density of the sand pump delivery slurry is controlled to maintain required throughput,
optimum and correct TSF feed slurry density.
Modes of Operation:
a) Remote Auto - the operator selects a sand pump delivery slurry density set-point and
the density controller adjusts the position of the sand pump hopper dilution water flow
control valve.
b) Remote Manual - the operator selects the position of the sand pump hopper dilution
water flow control valve through the sand pump delivery density controller.
Control Controlle Controller Controller Input Controller Output
Mode r Mode
Tag
Remote DIC4038 Auto Select DIC4038 A or B To FCV-4039 positioner
Set-point for DIC4038
Process variable for DIC4038
DIC4038 Manual Nil To FCV-4039 positioner
b) Remote Auto (Override) - the sand pump hopper water dilution valve is opened fully
while the alarm condition is active.
c) Remote Manual - the operator selects the speed of sand pump 2 through the sand
pump hopper level controller.
d) Remote Manual (Override) - the sand pump hopper water dilution valve is opened fully
while the alarm condition is active.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote LIC4023 Auto Set-point for LIC4023 To sand pump 2 VVVF drive
SC4056A/B
Process variable for LIC4023
LIC4023 Auto LAL4023 activated FCV-4039 positioner to open
(Override)
LIC4023 Manual Nil To sand pump 2 VVVF drive
SC4056A/B
LIC4023 Manual LAL4023 activated FCV-4039 positioner to open
(Override)
257422914.doc Page 51
6.3.8 Flotation Tails Decant Pump
Objective:
The flotation tails decant pump is stopped if the process water tank is full and the float
valve closes.
Modes of Operation:
a) Local Auto
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Local FAL4017 Auto FAL4017 activated Flotation tails decant pump stop
Initiate restart timer
257422914.doc Page 52
6.4 Reagents and Consumables
b) Remote Manual - the operator selects the speed of the collector dosing pump through
the collector addition rate controller.
257422914.doc Page 53
6.4.2 Frother Dosing Pump Speed
Objective:
Frother addition is ratio controlled to the flotation feed rate measured by the flotation feed
thickener underflow mass flow system. Both pumps may be operated at the same time if
required.
Modes of Operation:
a) Remote Auto - the operator selects a ratio of pump speed to the flotation feed thickener
integrated dry tonnage flow rate and the frother addition rate controller adjusts the
speed of the frother dosing pump.
b) Remote Manual - the operator selects the speed of the frother dosing pump through the
frother addition rate controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote SIC6004 Auto Frother solution concentration To frother dosing pump VVVF drive
(Supervisor level access only) SC6004A/B
Pump flowrate at 100% output
(Supervisor level access only)
Operator entered ratio (g/t)
Process variable from WIC3012
SIC6004 Manual Nil To frother dosing pump VVVF drive
SC6004A/B
b) Remote Manual - the operator selects the speed of the flotation copper sulphate dosing
pump through the copper sulphate addition rate controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote SIC6045 Auto CuSO4 mix strength (Supervisor To copper sulphate dosing pump
level access only) VVVF drive SC6024/25
Pump flowrate at 100% output
(Supervisor level access only)
Operator entered ratio (g/t)
Process variable from WIC3012
SIC6045 Manual Nil To copper sulphate dosing pump
VVVF drive SC6024/25
257422914.doc Page 54
6.4.4 Copper Sulphate (Detox) Dosing Pump Speed
Objective:
Detox copper sulphate addition is ratio controlled to the detoxified CIL tails flow rate. As
copper sulphate dosing pump B is a common standby, a selection (XC6051) must be
made to ensure the correct controller output is fed to the pump.
A fixed adjustment is made to the CIL tails volumetric flowrate as measured by the
flowmeter to account for the volume of carbon safety screen sprays and dilution water
into the CIL tails pump hopper.
The speed of the copper sulphate dosing pump adding solution to the detox tank is ratio
controlled from the adjusted CIL tails volumetric flowrate and a manually input CIL tails
slurry density and the copper addition rate set point in grams Cu2+ per cubic metre of
solution.
Modes of Operation:
a) Remote Auto - the operator selects the copper sulphate mix concentration, copper
addition rate set point and estimated average CIL tails slurry density. The ratio is
applied to the adjusted CIL tails volumetric flow rate and the detox copper sulphate
addition rate controller adjusts the speed of the detox copper sulphate dosing pump.
b) Remote Manual - the operator selects the speed of the detox copper sulphate dosing
pump through the detox copper sulphate addition rate controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote SIC6040 Auto Operator entered of Cu2+ To copper sulphate dosing pump
addition per m³ (Supervisor level VVVF drive SC6026/25
access only)
CuSO4 mix strength input
(Supervisor level access only)
CIL tails slurry density
(Supervisor level access only)
FIC9018 adjustment for dilution
(Supervisor level access only)
Pump flowrate at 100% output
(Supervisor level access only)
Process variable from FIC9018
SIC6040 Manual Nil To copper sulphate dosing pump
VVVF drive SC6026/25
257422914.doc Page 55
6.4.5 Flotation Feed Thickener Flocculant Dosing Pump Speed
Objective:
Flotation feed thickener flocculant addition is controlled based on the flotation feed
thickener bed level. As flocculant dosing pump B is a common standby, a selection
(XC6052) must be made to ensure the correct controller output is fed to the pump.
Modes of Operation:
a) Remote Auto - the operator selects a set point for the flotation feed thickener bed level
and the flotation feed thickener bed level controller adjusts the speed of the flocculant
dosing pump.
b) Remote Manual - the operator selects the speed of the flotation feed thickener
flocculant dosing pump through the flotation feed thickener bed level controller.
Control Controller Controlle Controller Input Controller Output
Mode Tag r
Mode
Remote LIC3044 Auto Set-point for LIC3044 To flocculant dosing pump VVVF
drive SC6031A/B
Process variable for LIC3044
LIC3044 Manual Nil To flocculant dosing pump VVVF
drive SC6031A/B
b) Remote Manual - the operator selects the speed of the flocculant dosing pump through
the flotation tail thickener bed level controller.
Control Controller Controlle Controller Input Controller Output
Mode Tag r
Mode
Remote LIC4013 Auto Set-point for LIC4013 To flocculant dosing pump VVVF
drive SC6031E/B
Process variable for LIC4013
LIC4013 Manual Nil To flocculant dosing pump VVVF
drive SC6031E/B
257422914.doc Page 56
6.4.7 Concentrate Thickener Flocculant Dosing Pump Speed
Objective:
Concentrate thickener flocculant addition is controlled based on the concentrate
thickener bed level.
Modes of Operation:
a) Remote Auto - the operator selects a set point for the concentrate thickener bed level
and the concentrate thickener bed level controller adjusts the speed of the flocculant
dosing pump.
b) Remote Manual - the operator selects the speed of the flocculant dosing pump through
the concentrate thickener bed level controller.
Control Controller Controlle Controller Input Controller Output
Mode Tag r
Mode
Remote LIC3039 Auto Set-point for LIC3039 To flocculant dosing pump VVVF
drive SC6031C/D
Process variable for LIC3039
LIC3039 Manual Nil To flocculant dosing pump VVVF
drive SC6031C/D
b) Remote Manual - the operator selects the speed of the SMBS dosing pump through the
SMBS addition rate controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote SIC9018 Auto Operator entered ratio of SMBS To SMBS dosing pump VVVF drive
addition to CNwad level SC6039A/B
SMBS mix strength input
(Supervisor level access only)
CNfree level input (Supervisor
level access only)
CNwad to CNfree ratio input
(Supervisor level access only)
FIC9018 adjustment for dilution
(Supervisor level access only)
Pump flowrate at 100% output
(Supervisor level access only)
Process variable from FIC9018
SIC9018 Manual Nil To SMBS dosing pump VVVF drive
SC6039A/B
257422914.doc Page 57
6.4.9 Lime Make-Up
Objective:
Lime and water addition to the lime tank controlled to maintain the lime slurry level in the
tank. The relative feedrate of lime and make up water are set to produce the required
lime slurry density.
Modes of Operation:
a) Remote Auto
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote LI6017 Auto LAL6017 active Lime feeder drive on
Lime silo vibrated fluidiser air open
(XV6053)
XV6018 open
LAH6017 active Lime feeder drive off
Lime silo vibrated fluidiser air closed
(XV6053)
XV6018 close
257422914.doc Page 58
6.5 Gravity and Flotation Concentrate Leaching
b) Remote Manual - the operator selects the open position time (seconds) of the pulsing
CIL lime addition valve through the CIL tank 1 pH controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote AIC8301 Auto Selection (XC8301) of AIC8301A To KC8301 to XV8301 pulse rate
or B
Set-point for AIC8301A/B
Process variable from
AIC8301A/B
AIC8301 Manual Nil KC8301 To XV8301 pulse rate
b) Remote Auto 2 - the operator selects a flow set-point and the CIL cyanide addition flow
rate controller adjusts the position of the CIL cyanide flow control valve.
c) Remote Manual - the operator selects the position of the CIL cyanide flow control valve
through the CIL cyanide addition flow rate controller.
257422914.doc Page 59
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote FIC8303 Auto 1 Cyanide solution concentration To FCV-8303 positioner
(Supervisor level access only)
Operator entered ratio (g/t)
Set-point for FIC8303 from
WIC3035
FIC8303 Auto 1 Set-point for FIC8303 To FCV-8303 positioner
FIC8303 Manual Nil To FCV-8303 positioner
b) Remote Manual - the operator selects heater burner output through the elution
temperature controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote TIC8708 Auto Set-point for TIC8708 To elution heater burner controller
(vendor supply)
Process variable for TIC8708
TIC8708 Manual Nil To elution heater burner controller
(vendor supply)
6.7 Electrowinning
257422914.doc Page 60
6.8 Cyanide Detoxification
b) Remote Manual - the operator selects the speed of the CIL tails pump through the CIL
tails pump hopper level controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote LIC9007 Auto Set-point for LIC9007 To CIL tails pump VVVF drive
SC9022A/B
Process variable for LIC9007
LIC9007 Manual Nil To CIL tails pump VVVF drive
SC9022A/B
b) Remote Manual - the operator selects the open position time (seconds) of the pulsing
detox lime addition valve through the detox tank pH controller.
Control Controlle Controlle Controller Input Controller Output
Mode r r
Tag Mode
Remote AIC9001 Auto Selection (XC9001) of AIC9001A To KC9001 to XV9001 pulse rate
or B
Set-point for AIC9001A/B
Process variable from
AIC9001A/B
AIC9001 Manual Nil To KC9001 to XV9001 pulse rate
257422914.doc Page 61
7 SEQUENCES AND PROCEDURES
Selected automated sequences and manually controlled procedures for start-up and shutdown
of the plant are listed below. Note that for an automated sequence or manually controlled
procedure to progress permissives and interlocks as detailed above must be satisfied.
Sequences and procedures assume normally continuously running equipment e.g. thickeners,
the conditioning tank, Detox and CIL tank agitators are left operating.
Start or stop of a pump with actuated suction and delivery valves automatically opens or closes
the valves after the pump running indication is received by the PLC.
Flotation cell mechanisms are started and stopped locally at the field stop/start station located
adjacent to the cell.
The compressors are only able to be started and stopped locally at the field stop/start station
and are under the control of the vendor controller package, which senses load and starts the
second unit or puts the compressor on idle, as required.
7.1 Crushing
Start-up and shut-down of the crushing section is split into two PLC controlled group sequences.
One covers services such as dust collection equipment and the other covers the crushing
equipment (conveyors, screens and feeders).
257422914.doc Page 62
7.1.2 Crusher Plant Start-up Sequence
This PLC controlled group sequence covers start up of crushing equipment feeding the fine ore
bin. The sequence will be initiated from the SCADA screen by the operator clicking on the
Crusher Plant sequence start button.
The primary jaw crusher and secondary cone crusher must be stopped individually when the
area operator confirms they are clear.
257422914.doc Page 63
7.1.4 Crusher Plant Services Shut-down Sequence
The PLC controlled function group shut-down sequence will be initiated from the SCADA screen
by the operator clicking on the Crusher Plant Services sequence stop button.
Drive Description Drive Number Sequence Comment
Step Delay
(sec)
Crusher dust collector ID fan 10-FA-017 n/a Stopped simultaneously
Crusher dust collector 10-BH-001
Crusher dust collector rotary valve 10-VV-001
Crusher area fan 10-FA-003
HPGR & secondary screen dust 10-FA-018
collector ID fan
HPGR & secondary screen dust 10-BH-001
collector
HPGR & secondary screen dust 10-VV-002
collector rotary valve
HPGR & secondary screen dust screw 10-FE-010
feeder
HPGR & secondary screen area fan 10-FA-007
The Crusher Plant Services shut-down sequence should not be used if the Grinding and Gravity
circuit is operating as the HPGR & secondary screen area fan and HPGR & secondary screen
dust collector equipment is required to operate while the HPGR is running. The Crusher dust
collection equipment may be stopped individually by the control room operator in “Manual” mode
257422914.doc Page 64
7.2.2 Gravity Circuit Start-up Procedure
This PLC controlled group sequence covers start up of equipment in the Gravity circuit. The
sequence will be initiated from the SCADA screen by the operator clicking on the Gravity
sequence start button.
Drive Description Drive Number Sequence Comment
Step Delay
(sec)
Gravity concentrate transfer pump 20-PU-065 5 Select duty/standby
Ensure suction and delivery
pipes correctly connected in
field.
XV2066 closed
Spinner tails pump 20-PU-080 5
Spinner no 1 20-GC-005A 5 Simultaneous start
Spinner no 2 20-GC-005B
Spinner no 3 20-GC-006A
Spinner no 4 20-GC-006B
Primary jig no 1 20-GC-001 5 Field operator intervention
required to open hutch water
Primary jig no 2 20-GC-002 5 valves and bleed air
Primary jig no 3 20-GC-003 5
Gravity screen 20-SC-003 5 Field operator intervention
required to open spray valves
Primary jig no 1 feed valve open XV2017 0 Simultaneous open
Primary jig no 2 feed valve open XV2018
Primary jig no 3 feed valve open XV2019
Mill pump 20-PU-003 5 Select duty/standby
Cyclone pump 20-PU-004 5 Select duty/standby
Centrifugal concentrator no 1 20-GC-004 5 Start with XV2046 closed.
Open XV2046 manually after
completion of HPGR sequence
start.
257422914.doc Page 65
7.2.3 HPGR Start-up Procedure
This PLC controlled group sequence covers start up of equipment in the HPGR circuit. The
sequence will be initiated from the SCADA screen by the operator clicking on the HPGR
sequence start button.
Drive Description Drive Number Sequence Comment
Step Delay
(sec)
Mill feed, seal & trommel spray water XV2093 n/a Actuated valve opened
valve
Ball mill 20-ML-001 5 Refer Outokumpu design
document 7330-DD01 Rev0
Ball mill screen 20-SC-002 5 Open spray valves in field
Mill screen oversize conveyor 10-CV-006 5
Mill feed conveyor 10-CV-005 5
HPGR 10-CR-003 n/a
HPGR feed conveyor 10-CV-004 10
Fine ore bin belt feeder 10-FE-003 5 Start in manual mode -
minimum output
Flocculant dosing pump A/B 60-PU-043A/B 30 Select duty/standby
Feeds float feed thickener
257422914.doc Page 66
7.2.5 Gravity Shut-down Procedure
The procedure covers shut-down of the Gravity section.
The PLC controlled function group shut-down sequence will be initiated from the SCADA screen
by the operator clicking on the Gravity sequence stop button.
Drive Description Drive Number Sequence Comment
Step Delay
(sec)
Purge Mill Screen Gold Trap XV2001 & 2 n/a The operator selects a purge
cycle through the controller
Ball mill screen 20-SC-002 15 Close spray valves in field
Primary jig no 1 feed valve close XV2017 0 Simultaneous closure
Primary jig no 2 feed valve close XV2018
Primary jig no 3 feed valve close XV2019
Mill pump 20-PU-003 0
Primary jig no 1 20-GC-001 120 Simultaneous shut-down after
jigs flushed.
Primary jig no 2 20-GC-002
Field operator intervention
Primary jig no 3 20-GC-003 required to close hutch water
valves
Spinner no 1 20-GC-005A 20 Simultaneous shut-down
Spinner no 2 20-GC-005B
Spinner no 3 20-GC-006A
Spinner no 4 20-GC-006B
Spinner tails pump 20-PU-080 5
Gravity screen 20-SC-003 5 Close spray valves in field
Centrifugal concentrator no 1 feed XV2046 30 Delay to empty screen
valve closed underpan
Centrifugal concentrator no 1 20-GC-004 30 Stop initiates a controlled
shutdown and timed rinse
Ball mill 20-ML-001 5 Refer Outokumpu design
document 7330-DD01 Rev0
Mill feed, seal and trommel spray water XV2093 n/a
valve close
Flocculant dosing pump A/B 60-PU-043A/B 5
Cyclone pump 20-PU-004 5
257422914.doc Page 67
7.3 Flotation
257422914.doc Page 68
Drive Description Drive Number Comment
Open flotation cell launder sprays n/a Field operator action
water valves
Flotation cell no 1 30-FC-001 Field operator action
Flotation cell no 2 30-FC-002 Field operator action
Flotation cell no 3 30-FC-003 Field operator action
Flotation cell no 4 30-FC-004 Field operator action
Flotation cell no 5 30-FC-005 Field operator action
Flotation concentrate pump 30-PU-008 Select duty/standby
Flotation feed thickener underflow 30-PU-006 Select duty/standby
pump
Start in recirculation mode
(XV3013 open & XV3014) then
reset valves if underflow density
acceptable
May have been left running on
circuit shutdown in recirculation
mode (i.e. XV3013 open &
XV3014 closed)
Frother pump 60-PU-041 Select duty/standby
Start in manual mode -
minimum output
Collector dosing pump 60-PU-038 Select duty/standby
Start in manual mode -
minimum output
Copper sulphate dosing pump A/B 60-PU-039A/B Select duty/standby
Start in manual mode -
minimum output
Flotation tail thickener underflow pump 40-PU-013 Select duty/standby
Start in recirculation mode
(XV4011 open & XV4013) then
reset valves if underflow density
acceptable
May have been left running on
circuit shutdown in recirculation
mode (i.e. XV4011 open &
XV4013 closed)
Sand pump hopper dilution water valve FCV4039 Place Sand Pump Delivery
Slurry Density control loop in
Remote Manual mode and fully
open the sand pump hopper
dilution water flow control valve
Sand pump 1 40-PU-072 Select duty/standby
Sand pump 2 40-PU-073 Select duty/standby
Flotation tail pump 30-PU-007 Select duty/standby
Flotation tails concentrator 50-GC-009
Flocculant dosing pump B/E 60-PU-043B/E Select duty/standby
Feeds float tail thickener
257422914.doc Page 69
Drive Description Drive Number Comment
Flocculant dosing pump C/D 60-PU-043C/D Select duty/standby
Feeds Concentrate thickener
257422914.doc Page 70
7.3.4 Flotation Plant Services Shut-down
The flotation blower (70-CP-002) is stopped after the flotation cells are stopped, if a prolonged
shut down (longer than 15 minutes) is anticipated.
If the grinding and gravity circuit or CIL circuits are not running, the following services equipment
items are also stopped individually during the shut-down procedure:
Process water pump (70-PU-035)
Raw water pump (70-PU-033)
Gland water pump (70-PU-032)
257422914.doc Page 71
Drive Description Drive Number Comment
CIL tails pump 90-PU-022 Dilution water valve must be
opened manually by field
operator
Carbon safety screen 90-SC-014 Screen spray water must be
opened manually by field
operator
Trash screen underflow pump 83-PU-079 Select duty/standby
Trash screen 80-SC-005 Screen spray water must be
opened manually by field
operator
SMBS pump 60-PU-067 Select duty/standby
Start in manual mode -
minimum output
Copper sulphate dosing pump B/C 60-PU-039B/C Select duty/standby
Start in manual mode -
minimum output
Flotation concentrate thickener 30-PU-010 Select duty/standby
underflow pump
ILR n/a System stopped or left in
internal recycle
257422914.doc Page 72
7.4.4 CIL and Detox Services Shut-down
The following equipment items are stopped individually at the relevant point, during the shut-
down procedure, if a prolonged shut down (longer than 15 minutes) is anticipated:
CIL LP blower (70-CP-003)
CIL water pump (70-PU-028)
Cyanide pump (60-PU-047)
The lime pump (60-PU-066) is normally left operating to avoid choking the ringmain pipeline.
The CIL lime addition control loop is set to “Remote Manual” mode and the operator selects the
open position time (seconds) of the pulsing CIL lime addition valve as zero.
257422914.doc Page 73
7.5 Acid Wash Procedures
The acid wash system is not automated and operator monitoring and intervention is required at
various times during the acid wash sequence.
The extent of calcium scaling of the carbon will dictate the required acid strength and acid wash
period. It may be necessary to increase acid wash solution acid strength or extend the acid
wash time if the carbon is badly fouled. If it is required to complete as many elutions as fast as
possible to meet gold production targets, the acid wash time may be reduced or the acid wash
step maybe omitted completely on occasion.
Once a complete batch of carbon is ready in the acid wash column, the operator can perform the
acid wash procedure.
257422914.doc Page 74
7.5.4 Carbon Transfer to Elution Column
Close acid wash column solution inlet valve and acid wash strainer inlet valves.
Open elution column carbon filling valve
Open selected elution column strainer inlet and outlet valves.
Ensure elution column carbon outlet valve is closed.
Close eluate to electrowinning cell valve at the inlet to the heat exchanger.
Open transfer water recycle valve at the inlet to the heat exchanger.
Open transfer water valves to acid wash column and carbon outlet...
Start transfer water pump.
Open acid wash column carbon outlet valve.
Allow carbon to transfer for the required period (i.e. until all carbon is transferred).
Close acid wash column carbon outlet valve.
Close transfer water valves to acid wash column and carbon outlet.
Stop transfer water pump.
Close elution column carbon filling valve.
Close transfer water recycle valve at the inlet to the heat exchanger.
Open eluate to electrowinning cell valve at the inlet to the heat exchanger.
Open acid wash column floor drain valve and allow transfer water in the column to drain to the
spillage sump.
257422914.doc Page 75
7.5.6 Dilute Acid Make up
Check acid wash tank is empty.
Open acid wash tank raw water addition valve and partially fill the tank.
Close acid wash tank raw water addition valve.
Start hydrochloric acid offload pump and run for the required period.
Stop hydrochloric acid offload pump.
Re-open the acid wash tank raw water addition valve and fill the tank.
Check acid wash tank level and dilute acid concentration.
257422914.doc Page 76
Monitor column pressure using the column pressure gauge and adjust pressure regulation valve
at the outlet of the recovery heat exchanger if required.
Approximately 1-2 hours prior to the end of the allotted elution time, switch off the elution heater
to allow column to cool.
Stop elution pump.
257422914.doc Page 77
7.6.4 Eluted Carbon Transfer Procedure
Close elution heater outlet isolation valve.
Close elution strainer inlet valve.
If carbon is to bypass the regeneration kiln, open eluted carbon screen bypass valve, close the
eluted carbon screen feed valve and switch on the regen carbon screen and open the carbon
quench pan water valve.
If carbon is to be regenerated ensure eluted carbon screen feed valve is open and eluted carbon
screen bypass valve is closed and check availability of space in the kiln feed hopper.
Open transfer water valves to elution column and carbon outlet.
Start transfer water pump.
Open elution column carbon outlet valve.
Allow carbon to transfer for the required period (i.e. until all carbon is transferred)
Close elution column carbon outlet valve.
Close transfer water valves to elution column and carbon outlet.
Stop transfer water pump.
257422914.doc Page 78
ERROR: REFERENCE SOURCE NOT FOUND ERROR: REFERENCE SOURCE NOT FOUND
ERROR: REFERENCE SOURCE NOT FOUND APPENDICES
APPENDIX 1
SCHEDULE OF ALARMS
Description Alarm
Category
BH-001 crushing area dust collector ID fan failure 3
BN-001 ROM bin high level 3
BN-001 ROM bin low-low level 2
BN-002 fine ore bin high level 3
BN-002 fine ore bin high-high level 2
BN-002 secondary crusher feed bin high level 2
BN-002 secondary crusher feed bin high-high level 2
BN-005 HPGR feed bin diverter gate valve 1 closed 3
BN-005 HPGR feed bin diverter gate valve 1 open 3
BN-005 HPGR feed bin high level 3
BN-005 HPGR feed bin high-high level 2
CR-001 primary jaw crusher high level 2
CR-001 primary jaw crusher motor current high 3
CR-002 secondary cone crusher high level 2
CR-002 secondary cone crusher motor current low 3
Crusher spillage sump flood warning 3
Crusher spillage sump high level 2
CV-001 crusher product conveyor belt drift switch A (head lhs) 3
CV-001 crusher product conveyor belt drift switch B (head rhs) 3
CV-001 crusher product conveyor belt drift switch C (tail lhs) 3
CV-001 crusher product conveyor belt drift switch D (tail rhs) 3
CV-001 crusher product conveyor belt rip detector A 3
CV-001 crusher product conveyor belt rip detector B 3
CV-001 crusher product conveyor pull wire switch A (walkway side) 2
CV-001 crusher product conveyor pull wire switch B (non-walkway side) 2
CV-001 crusher product conveyor start-up warning system 3
CV-001 crusher product conveyor underspeed switch 3
CV-002 secondary crusher bin feed conveyor belt drift switch A (head lhs) 3
CV-002 secondary crusher bin feed conveyor belt drift switch B (head rhs) 3
CV-002 secondary crusher bin feed conveyor belt drift switch C (tail lhs) 3
CV-002 secondary crusher bin feed conveyor belt drift switch D (tail rhs) 3
CV-002 secondary crusher bin feed conveyor pull wire switch A (walkway side) 2
CV-002 secondary crusher bin feed conveyor pull wire switch B (non-walkway side) 2
CV-002 secondary crusher bin feed conveyor start-up warning system 3
CV-002 secondary crusher bin feed conveyor underspeed switch 3
CV-003 fine ore bin feed conveyor belt drift switch A (head lhs) 3
CV-003 fine ore bin feed conveyor belt drift switch B (head lhs) 3
CV-003 fine ore bin feed conveyor belt drift switch B (head rhs) 3
CV-003 fine ore bin feed conveyor belt drift switch B (tail rhs) 3
CV-003 fine ore bin feed conveyor pull wire switch A (walkway side) 2
Description Alarm
Category
CV-003 fine ore bin feed conveyor pull wire switch B (non-walkway side) 2
CV-003 fine ore bin feed conveyor start-up warning system 3
CV-003 fine ore bin feed conveyor underspeed switch 3
CV-004 HPGR feed conveyor belt drift switch A (head lhs) 3
CV-004 HPGR feed conveyor belt drift switch B (head rhs) 3
CV-004 HPGR feed conveyor belt drift switch C (tail lhs) 3
CV-004 HPGR feed conveyor belt drift switch D (tail rhs) 3
CV-004 HPGR feed conveyor pull wire switch A (walkway side) 2
CV-004 HPGR feed conveyor pull wire switch B (non-walkway side) 2
CV-004 HPGR feed conveyor start-up warning system 3
CV-004 HPGR feed conveyor underspeed switch 3
FA-003 crusher area fan low air flow switch 1
MA-002 HPGR magnet hoist down limit switch 3
MA-002 HPGR magnet hoist up limit switch 3
MA-002 HPGR magnet trolley in limit switch 3
MA-002 HPGR magnet trolley out limit switch 3
MD-002 HPGR metal detector 1 metal detected 2
MD-003 HPGR metal detector 2 metal detected 2
Secondary crusher metal detector metal detected 2
Stormwater collection pond flood warning 3
Stormwater collection pond high level 2
CH-030 Ball Mill Screen feed box high 2
CV-005 mill feed conveyor belt drift switch A (head lhs) 3
CV-005 mill feed conveyor belt drift switch B (head rhs) 3
CV-005 mill feed conveyor belt drift switch C (tail lhs) 3
CV-005 mill feed conveyor belt drift switch D (tail rhs) 3
CV-005 mill feed conveyor pull wire switch A (walkway side) 2
CV-005 mill feed conveyor pull wire switch B (non-walkway side) 2
CV-005 mill feed conveyor start-up warning system 3
CV-005 mill feed conveyor underspeed switch 3
CV-006 mill screen oversize conveyor belt drift switch A (head lhs) 3
CV-006 mill screen oversize conveyor belt drift switch B (head rhs) 3
CV-006 mill screen oversize conveyor belt drift switch C (tail lhs) 3
CV-006 mill screen oversize conveyor belt drift switch D (tail rhs) 3
CV-006 mill screen oversize conveyor pull wire switch (non-walkway side) 2
CV-006 mill screen oversize conveyor pull wire switch (walkway side) 2
CV-006 mill screen oversize conveyor start-up warning system 3
CV-006 mill screen oversize conveyor underspeed switch 3
FE-003 fine ore bin belt feeder belt drift switch A (head lhs) 3
FE-003 fine ore bin belt feeder belt drift switch B (head rhs) 3
Description Alarm
Category
FE-003 fine ore bin belt feeder belt drift switch C (tail lhs) 3
FE-003 fine ore bin belt feeder belt drift switch D (tail rhs) 3
FE-003 fine ore bin belt feeder pull wire switch A (lhs) 2
FE-003 fine ore bin belt feeder pull wire switch B (rhs) 2
FE-003 fine ore bin belt feeder start-up warning system 3
FE-003 fine ore bin belt feeder underspeed switch 3
HP-001 mill pump hopper high level 3
HP-001 mill pump hopper low level 3
HP-002 cyclone pump hopper high level 3
HP-002 cyclone pump hopper high-high level 3
HP-002 cyclone pump hopper low level 2
HP-010 gravity concentrate surge tank high level 2
HP-010 gravity concentrate surge tank high-high level 2
HP-010 gravity concentrate surge tank low level 2
Jig feed distributor density high 3
Jig feed distributor density low 3
Primary cyclone feed density high 3
Primary cyclone feed density low 3
PU-003A mill pump A gland water low flow 3
PU-003B mill pump B gland water low flow 3
PU-004A cyclone pump A gland water low flow 3
PU-004B cyclone pump B gland water low flow 3
PU-005 mill spillage sump high level 2
PU-074 mill spillage sump 2 high level 2
XM-001 ball mill screen gold trap discharge valve 1 closed 3
XM-001 ball mill screen gold trap discharge valve 1 open 3
XM-001 ball mill screen gold trap discharge valve 2 closed 3
XM-001 ball mill screen gold trap discharge valve 2 open 3
Concentrate thickener underflow density high 3
Concentrate thickener underflow density low 3
Concentrate thickener bed level high 3
Concentrate thickener bed level low 3
CY-001 mill cyclone pressure high 3
CY-001 mill cyclone pressure low 3
CY-002 sand cyclone inlet pressure high 3
CY-002 sand cyclone inlet pressure low 3
CY-001 cyclone underflow launder high level 2
DB-001 jig feed distributor pressure high 3
DB-001 jig feed distributor pressure low 3
Flotation feed thickener underflow density high 3
Description Alarm
Category
Flotation feed thickener underflow density low 3
Flotation feed thickener bed level high 3
Flotation feed thickener bed level low 3
PU-006A float feed thickener underflow pump A gland water low flow 3
PU-006B float feed thickener underflow pump B gland water low flow 3
PU-007A flotation tail pump 1 gland water low flow 3
PU-007B flotation tail pump 2 gland water low flow 3
PU-009 flotation spillage sump 1 high level 2
PU-011 float concentrate spillage sump high level 2
PU-055 float feed thickener spillage sump high level 2
PU-077 flotation spillage sump 2 high level 2
PU-081 flotation tails sampler transfer sump high level 3
SC-003 gravity screen underflow chute discharge valve closed 3
SC-003 gravity screen underflow chute discharge valve open 3
Flotation tails thickener underflow density high 3
Flotation tails thickener underflow density low 3
Flotation tails thickener bed level high 3
Flotation tails thickener bed level low 3
Flotation tails to east flotation TSF dam pipeline pressure high 3
Flotation tails to east flotation TSF dam pipeline pressure low 3
HP-003 flotation tail pump hopper high level 3
HP-003 flotation tail pump hopper high-high level 3
HP-003 flotation tail pump hopper low level 3
HP-018 sand pump hopper low level 3
HP-018 sand pump hopper low-low level 2
PU-012 flotation tails thickener spillage sump high level 2
PU-013A float tails thickener underflow pump A gland water low flow 3
PU-013B float tails thickener underflow pump B gland water low flow 3
PU-072A sand pump 1A gland water low flow 3
PU-072B sand pump 1B gland water low flow 3
PU-073A sand pump 2A gland water low flow 3
PU-073B sand pump 2B gland water low flow 3
Sand pump discharge pipeline pressure A high 3
Sand pump discharge pipeline pressure A low 3
Sand pump discharge pipeline pressure B high 3
Sand pump discharge pipeline pressure B low 3
PU-015 goldroom spillage sump high level 2
PV-001 pan filtrate receiver high level 2
Smelting furnace hood high differential pressure high 3
CM-001 acid wash column high level 3
Description Alarm
Category
Flocculant system fault 2
HP-019 collector stand pipe low level 3
HP-020 frother stand pipe low level 3
HP-021 sodium hydroxide stand pipe high level 3
HP-022 hydrochloric acid stand pipe high level 3
HP-024 trash screen underflow hopper low level 3
HP-024 trash screen underflow hopper high level 3
HP-024 trash screen underflow hopper high-high level 2
hydrochloric acid sump high level 3
PU-048 reagents spillage sump 1 high level 2
PU-049 reagents spillage sump 2 high level 2
PU-075 flocculant spillage sump high level 3
TK-023 copper sulphate tank low level 3
Flotation blower low pressure air pressure low 3
Potable water jockey pump low flow 3
PU-032 gland water pressure low 2
PU-076 CIL water tank spillage sump high level 2
PV-003 plant air receiver pressure low 3
PV-004 mill air receiver pressure low 3
TK-019 raw water tank low level 3
TK-020 process water tank high level 2
TK-020 process water tank low level 2
TK-020 process water tank low-low level 3
PU-016 ILR spillage sump high level 2
CIL differential pH high 3
PU-018 CIL spillage sump high level 2
HP-017 ILR cell tail pump hopper high level 2
PU-030 electrowinning spillage sump high level 2
CIL tanks area HCN gas high 1
FA-012/013 CIL tanks area vent failure 1
FA-014/015/016 CIL tanks area vent failure 1
HE-001 elution heater discharge temperature high 3
Kiln package fault 2
PU-026 acid wash spillage sump high level 3
TK-013 elution tank high level 3
TK-013 elution tank low level 2
TK-013 elution tank low-low level 2
TK-014 acid wash tank high level 2
TK-014 acid wash tank low level 2
CIL/Detox area HCN gas high 1
Description Alarm
Category
Detox differential pH high 3
Detox differential pH low 3
HP-007 CIL tails pump hopper low level 2
PU-021 detox spillage sump high level 2
PU-022A CIL tails pump A gland water low flow 3
PU-022B CIL tails pump B gland water low flow 3
APPENDIX 2
PIPING & INSTRUMENTATION DIAGRAMS