Documente Academic
Documente Profesional
Documente Cultură
LTRO-1B Project
1.2 Objective
The objectives of this document are:
To describe the process control and operating philosophy for New LTRO-1B process
facilities at Rawa Station.
To describe the shutdown philosophy for New LTRO-1B process facilities at Rawa Station.
To fully understand the operating control narrative of overall Rawa Station facilities, this
document shall be read in conjunction with Doc. No. C-84524-RW-PP0-PHY-ST-00-0004
"Operating and Control Philosophy - LTRO-1A Project" [Ref. 2].
2 ABBREVIATIONS
BPD Barrel per Day
CCR Central Control Room
CGP Central Gas Plant
COPI ConocoPhillips Indonesia
CPGL ConocoPhillips (Grissik) Ltd.
DCS Distributed Control System
EDP Emergency Shutdown and Depressurize
ESD Emergency Shutdown
ESDV Emergency Shutdown Valve
FEL Front End Loading
FIC Flow Indicating Controller
HP High Pressure
HMI Human Machine Interface
LCP Local Control Panel
LI Level Indicator
LP Low Pressure
LTR Letang Tengah Rawa
LTRO Letang Tengah Rawa Optimization
MCC Motor Control Center
MMScfd Millions Standard Cubic Feet per Day
MP Medium Pressure
PCS Process Control System
PI Pressure Indicator
PIC Pressure Indicating Controller
PLC Programmable Logic Controller
PSD Process Shut-Down
PSHH Pressure Switch High-High
PSLL Pressure Switch Low-Low
P&ID Piping and Instrumentation Diagram
PSC Production Sharing Contract
PV Process Value
S/D Shutdown
SCFM Standard Cubic Feet per Minute
SDV Shutdown Valve
SIL Safety Integrity Level
SIS Safety Instrumented System
SP Set Point
TEG Triethylene Glycol
TI Temperature Indicator
USD Unit Shutdown
3 PROCESS DESCRIPTION
3.1 Brief Description for Rawa Station Facilities
The existing Rawa Station Facilities will be modified by LTRO Project in order to maximize the
gas recovery from Letang, Tengah and Rawa wells. The LTRO Project was planned to be
implemented in two phases, Phase-1A with Rawa Station inlet pressure of 450 psig and
Phase-1B with Rawa Station inlet pressure of 215 psig. Currently, the LTRO-1A Project have
been placed in service in April, 2013. The following Table 3.1 summarizes the Rawa Station
facilities after the completion of LTRO-1A and LTRO-1B Project.
Table 3.1 Rawa Station Facilities Summary
Capacity design of the existing facilities can be seen in following Table 3.2.
Table 3.2 Design Capacity of Existing Rawa Station Facilities
Equipment Tag
Equipment Designed Capacity
Number
Existing Facilities (Before LTRO-1A Project)
HP Production Separator 5000-V-70 38 MMscfd, 1575 BPD (estimated)
23 MMscfd, 1200 BOPD, 6000
MP (LP) Production Separator 3033-V-60
BWPD (estimated)
LP Compressor Package 5000-PK-101 10-15 MMscfd
Gas Injection Compressor 46 MMscfd
5000-V-80
Suction Scrubber
Gas Injection Compressor 46 MMscfd,
5000-PK-100
Package Suct : 500 psig, Disch : 1450 psig
Equipment Tag
Equipment Designed Capacity
Number
Gas Injection Compressor After
5000-E-110 12.4 MMBTU/hr
Cooler
Glycol Contactor 5000-C-100 46 MMscfd
Glycol Regeneration Package 5000-C-100 TEG circulation rate 8 USgpm
Test Tank 5000-T-10 500 bbl
Produced Water Tank 5000-T-11/16 2 x 500 bbl
120 USGPM and 60 USGPM,
Test Tank Transfer Pump 5000-P-007/034
diff head 100 psi
135 USGPM,
Produced Water Transfer Pump 5000-P-001A/B
diff head 50 psi
Additional Facilities by LTRO-1A Project
Condensate Stabilization
20-SZZ-001 600 BPD Crude/Cond
Package
Crude /Condensate Tank 21-ABJ-001 1520 BBLS (Net Working Capacity)
Flare K.O. Drum 43-MBD-001 72 MMSCFD
Flare K.O. Drum Pump 43-PBA-001 A/B 26.4 USGPM (rated)
Closed Drain Drum 62-MBD-001 124 bbls
Closed Drain Pump 62-PBA-001 A/B 17.6 USGPM (rated)
Portable Pit Pump 43-PBA-002 17.5 USGPM
Diesel Fire Water Pump + Day
71-PBA-011/12 1000 USGPM
Tank
Electrical Jockey Pump 71-PBA-013 125 USGPM
Well Water Pump 71-PBA -014 100 USGPM
Instrument Gas K.O. POT 3M-MAK-100~106 0.86 SCFM
Corrosion Inhibitor Injection 3M-PBE-100~106 /
Tank = 1000 L
Package 42-SZZ-001
Instrument Air Receiver 67-MBF-100 72 SCFM
Instrument air Compressor and
67-CA-001 100 SCFM
Drier package
Glycol Contactor 27-MAF-201 46 MMSCFD
Glycol Regeneration Package 27-SZZ-001 TEG Circulation rate of 15 USGPM
Capacity design of the new LTRO-1B facilities can be seen in following Table 3.3.
Table 3.3 Design Capacity of LTRO-1B Facilities
Equipment Tag
Equipment Designed Capacity
Number
equipped with an internal heater (20-ZAP-001) to further heat up the pre-heated condensate.
The additional heat is intended to vaporize light components to achieve the required condensate
product shipping specification with the maximum RVP of 12 psia and TVP of 13 psia. This heater
consists of 2 (two) stage, with the 1st stage automatically handle the normal duty and the 2nd
stage is manually adjustable to handle the peak duty during pre-heater maintenance.
The 1st Stage Condensate Separator (20-MBD-001) is a three phase separator. The flash gas
from this separator is sent to the existing Flare System, the hot condensate is routed to the 2nd
Stage Condensate Separator (20-MBD-002), and the produced water is sent to the existing
Produced Water Tanks. The 2nd Stage Condensate Separator (20-MBD-002) is two phase
separator. The flash gas from this vessel is also sent to the existing Flare System and the hot
condensate is intended to be diverted to the Condensate Pre-Heater (20-HBG-001) for cooling
while additional cooling is further achieved in the Condensate Cooler (20-HAL-001). Stabilized
condensate product is pumped by the Condensate Pumps (20-PBA-001A/B) for storage in new
Crude/Condensate Tank (21-ABJ-001) or the existing Test Tank (5000-T-10).
3.3.4 Grissik CGP
The incoming gases from Rawa Station are combined with the gas from Gelam Station and
routed to the existing GLT Slug Catcher (15-M-101). This slug catcher provides gas and liquid
separation. The existing slug catcher is an above ground finger type designed with hydrocarbon
liquid capacity of 241 barrels.
The LTR Pig Receiver was installed at the downstream of Rawa Station gas trunkline and used
during pigging operations from the Rawa Station to Grissik CGP. Flare and drain lines from the
Pig Receiver is routed to the existing Grissik CGP flare and drain systems.
Control
No. System Description Remarks
Equipment
Pneumatic Majority of the process control
Local Control uses Local Pneumatic Control
Pneumatic Local Panel for the
control of the Glycol Contactor
Pneumatic and Regeneration Package.
1.
Control Pneumatic This Pneumatic Local Panel is
Local Panel used for local pneumatic
alarms and common
shutdown signals to the
package.
Local Control LP Compressor Package is
Panel for LP controlled by Local Control
Compressor Panel located near
Package compressor using Allen
(5000-PK-101). Bradley PLC.
Electronic
2. Unit Control Gas Injection Compressor
Control
Panel for Gas Package is controlled by Unit
Injection Control Panel using Allen
Compressor Bradley PLC located in the
Package Control Room with a panel
(5000-PK-100). mounted HMI.
No integrated and automated safety and control system is available in the existing Rawa control
system before LTRO-1A Project.
The following control systems have been applied to Letang and Tengah Wells.
System Description