This run was done after new volume probe which shows that
Gas Filling:
1. Check all venting closed after venting! (one for reactor one for gas storage vessel)
2. Chiller Temperature is set at 15 degrees
3. According to calculation (volume probe), a total of 4930.0g of sand is required to fill up
3270 ml reactor. Sand need to be reduced.
1st fill 2nd fill 3rd fill 4rd fill 5rd fill Final Mass
1540.1 g 1475.0 g 1725.1 g 201.0 40.5 4981.7
Time 3:04 pm
Total Water Injection at first time 435.0 mL
To start a new file with name “hydrate formation
11. 2nd water injection when Ptop = 3478 MPa Pbot = 3482 MPa, at 30ml/min.
12. 3rd water injection when Ptop = 3.336 MPa, Pbot=6.543MPa, at 30ml/min.
Duration time Start volume Rate*time (ml/min*min) End Pressure
X min XX s 237.06 mL 178.5 ml 9.058 MPa
flowrate End volume Δ Volume (mL) Stable Pressure
30 mL/min 68.02ml 169.04 Top=4.414MPa,
Bot=5.116MPa
13. Increase T from 1 C to 5 C to 6 C and stabilize at Ptop = 7370 kPa Pbot = 7379 kPa.
Depressurization
Final Pressure: Ptop = 3036.33 kPa Pbot = 2995.7 kPa PGR = 2054.47 kPa Water mass = 355.9 g
Purge Step:
Learning: Gas cylinder pressure is set as 3.5 MPa and this is believed lead to CV open more than
usual, thus the final pressure attained is at 2.0 Mpa and is less than 4.0 Mpa. Thus, the data cannot
be used for production profile. Learning is that we need to control gas cylinder pressure around 1.0
bar (not more than 2,0 bar) to supply air to CV. Otherwise, CV is not controlling at the later part. In
addition, try dissociation during the day instead of night. If anything went wrong, we can still fix it.