Sunteți pe pagina 1din 4

Submitted to:

Engr. Ken
Noblezada

Submitted by:

Bragat, Cyndrille John A.

PROPOSED 3-STOREY HOTEL

3-7 POST AND COLUMN REINFORCEMENT


Note: Using 20 mm ø, 6 m long steel bars

Column (30 columns)

Calculate the total length of the main steel bar reinforcements.


A. Bend at the base footing = 0.20m
B. Length from footing to ground floor = 1.20m
C. Height from ground line to beam = 10.20 m
D. Depth of beam in Ground Floor = 0.45m
E. Depth of beam in 2nd floor = 0.45m
F. Depth of beam in 3rd floor = 0.45m
G. Thickness of the floor slab(3 floors) = 0.30m
H. Dowel for 2nd floor = 0.40m
I. Dowel for 3rd floor = 0.40m

Total length of the Reinforcement = 14.05m

Number of Steel Bars:

No. of Steel Bars =()(Number of TotalLengt hof Re inf orcement


bars in one post)(Number of post) LengthofSteelBar

14.05
 x8 x13
6.00
No. of Steel Bars = 243.533pieces of 6ms eel bars
t

3-8 BEAM AND GIRDER REINFORCEMENT


Note: 20 mm ø, 6 m long steel bars

With a span of 5.8 meters (4pcs.) (2 floors)

No. of Steel Bars = x number of bars x lengthofspan


number of beams x number of floors 6meters

No. of Steel Bars = x 6 x 16x 2 = With a span of 5.8m


3.6 meters (12pcs.) (2 floors) 6meters
No. of Steel Bars = x number of bars x lengthofspan
number of beams x number of floors 6meters
No. of Steel Bars = x 6 x 16x2 = 115.2 pieces 3.6m
6meters

With a span of 2.5 meters (12pcs.) (2 floors)

No. of Steel Bars = x number of bars x lengthofspan


number of beams x number of floors 6meters
No. of Steel Bars = x 6 x 10 x 2 =50 pieces 2.5m
6meters
With a span of 1.5 meters (12pcs.) (3 floors)

No. of Steel Bars = x number of bars x lengthofspan


number of beams x number of floors 6meters
No. of Steel Bars = x 6 x 8 x 2=24 pieces 1.5m
6meters

Total number of steel bars = 189.2 pieces

3-9 LATERAL TIES


Note: Diameter of longitudinal bar: 20mm

Diameter of Lateral Ties: 10mm

Column Dimensions: 0.30m x 0.30m

The ACI Code (Lateral Ties Spacing):

1. 16 x the longitudinal bar diameter


2. 48 x the lateral tie bar diameter
3. The least dimension of the column

Determine the spacing of the lateral ties:

16 x 20mm = 320mm or 32.00cm

48 x 10mm = 480mm or 48cm

The least dimension of the column is 30cm

Note: Use 30cm spacing

Spacing = = 20 6.00m
0.30m
No. of Lateral Ties = 20 + 1 = 21 pieces

Total Ties = 21 x 13 columns = 273 pieces

Note: By inspection, the tie is 100cm or 1.00m long. Using 6.0 m long steel bar
No. of ties that can be derived = = 6 6.00m
ties in every 6m long steel bar 1.00m
No. of steel bars = = 105 pieces of 6m 630ties
long steel bars 6ties

Tie wire (Note: each tie is 40cm long, In every one kilogram of No.16 G.I. wire there is approximately 53
meters)

Kilograms of G.I. wire = = 39 kg of G.I. 0.40 x8 x 21x30


wire 53

3-10 STIRRUPS FOR BEAMS AND GIRDERS


Note: No. of stirrups per 1m span beam = 7 pieces

From the design, Total beam span (3 floors) = 343.20 m

343.20m x 7 pieces = 2403 pieces

For a 0.29m x 0.39m beam (beams have the same dimensions)

From table D-3 (Estimating Bill of materials by Vicente A. Tagayun)

5 pcs of closed stirrups available from 6m long steel bars

= 481 pieces of steel bars 2403 pcs


5
Tire wire (Note: each tie is 40cm long, In every
one kilogram of No.16 G.I. wire there is approximately 53 meters)

Kilograms of G.I. wire = = 109 kg of G.I. 0.4 x 6 x 2403


wire 53

S-ar putea să vă placă și