MATERIALES
Arena Gruesa m3
Cemento portland tipo I (42.5kg) bls
Piedra chancada de 1/2" m3
EQUIPOS
MATERIALES
Acero Corrugado Fy=4200 kg/cm2 grado 60 m3
Alambre negro recocido # 16 (5% acero) bls
EQUIPOS
Herramientas manuales %Mo
COSTOS
ITEM
DESCRIPCION UNIDAD CANTIDAD PU
OBRAS DE CONCRETO ARMADO
CONCRETO F´C= 175 KG/CM2 m3 S/. 1,000.05 507
ACERO ESTRUCTURAL F´Y = 4200 KG/CM2 kg S/. 79,000.99 5.96
5% 169.67 8.48 37
Jornada 8
Costo unitario directo por: KG 5.96
cantidad precio parcial IU
5% 2.31 0.12 37
COSTOS
PARCIAL SUBTOTAL
S/. 507,025.35
S/. 470,845.90
977,871.25
63,500.03
78,229.70
1,119,600.98
201,528.18
1,321,129.15
COSTO DIRECTO S/. 977,871.25
PLAZO DE EJECUCION 90 dias
IU TOTAL
47 352180.771
5 141317.066
21 187,539.38
37 17960.5428
3 270183.386
39 141729.73
2 8690.1089
COSTO TOTAL 1119600.98
IU DESCRIPCION MONTO INCIDENCIA MONTOS INCIDE AGRU
47 mano de obra 352180.77 0.3146 352180.77 0.315 1
5 arena gruesa 141317.07 0.1262 141317.07 0.126 2
21 cemento portland tipo I 187539.38 0.1675 187539.38 0.168 3
37 herramientas manuales 17960.54 0.0160 0
3 acero corrugado grado 60 270183.39 0.2413 296834.04 0.265 4
2 alambre negro recocido #16 8690.11 0.0078 0
39 indice de precios al consumidor 141729.73 0.1266 141729.73 0.127 5
1119600.98 1 1119600.98 1
AC 0.265
GGU 0.127