Documente Academic
Documente Profesional
Documente Cultură
1. Plan, organise and manage more efficiently the construction processes using
industry standard software and effective coordination of information
modelling using Asta Powerproject BIM.
2. Critically analyse the roles of the project manager within the production
process and working in collaboration with other roles within the project.
You are a newly employed planning manager for the project. Using ASTA
Powerproject BIM programming tool, you are assigned to produce an effective
construction programme of the project to allow the following functions: Gantt chart
and CPM Networks, Work Breakdown Structure (WBS), resources analysis diagram,
progress tracking, risk simulation and produce a critical evaluative report including all
tasks below for the approval from the project manager.
b. Critically evaluate the significance of the critical path method (CPM) and WBS
at the planning stage for the successful delivery of a project. Also, discuss the
Page 1 of 9
7435BEPG_Coursework Assignment
b. Carry out resource levelling for equipment resource and discuss how the
activities might be delayed beyond Latest Start Date (LST) to cater for the
limits on equipment resources because of levelling. Consider the resource
pool for equipment resources is 7 units per day. Critically evaluate the
significance for a project manager of resource management in project
delivery in time and cost. (200 words)
a. Track the project progress at the end of week 16 from the project start date.
Assume that the practical site progress of all tasks before week 16 and take
into account the following exceptional events that occurred in the project.
The steelwork contractor suffered labour resource problems and
started the structural steel frame 3 weeks late.
The client changed the specification to the service duct, which caused
the service duct to commence 2 weeks later than the planned date on
the programme and take 1 week longer.
Due to adverse weather, the duration of the sub-structure brick walls
increased by 3 weeks, although the task started on schedule.
b. Critically evaluate the impact of these delays on other activities and overall
project delivery. Also, discuss the possible measures considered by a project
manager to reduce the consequential impact on the possible liquated
damage and variation claim of time and cost (400 words).
a. Conduct a sensitivity analysis using Monte Carlo simulation (assume max 20%
higher and min 20% lower than the estimated duration of the selected tasks
due to the influence of risk factors in the project) and present the results in
your report. Tables and/or graphs are likely to be useful in helping to present
the results clearly.
Page 2 of 9
7435BEPG_Coursework Assignment
Project Information
Clarification of the assignment and demonstration of the software tool will be given
in the module assignment briefing session and within IT tutorial workshops.
Page 3 of 9
7435BEPG_Coursework Assignment
Page 4 of 9
Level 1 Work Ref Activity Immediate Type of Lag Duration Equipmen Skilled Unskilled
Packages No Description Predecessor Relatio (Days) (days) t /day Worker / Worker/
(Level 2) (Level 3 nship day day
7435BEPG_Coursework Assignment
B + -
U 1 Start on site 0 0 - -- -
I 2 Site 1 10 3 3 3
L preparation
D 3 Piling 2 15 2 2 3
I 4 Pile caps & 3 5 20 2 2 4
N Structure ground beams
G 5 Structural steel 4 3 30 2 3 3
frame
P 6 PCC floors 9 25 3 2 2
R level
O 7 Drainage 6 5 30 2 1 2
J under slab
E 8 Service Ducts 7 5 20 2 2 4
C 9 Concrete 5 5 25 3 2 2
T column
casements
Project 10 Sub structure 4 20 2 1 2
Start date brickwork
07/10/2019
11 Insulation and 8 15 1 1 2
sacred to
ground floor
Activity Means Looks like this in the Lead (-) Lag (+)
relationship Gantt chart
Finish-to-start (FS) The finish date of the predecessor task determines Lead-time causes the Lag time causes a
the start date of the successor task. successor activity to delay of (n) days
Start-to-Start (SS) The start date of the predecessor task determines start (n) number of days to start the
the start date of the successor task. before the predecessor successor
activity, irrespective of activity,
Finish-to-finish (FF) The finish date of the predecessor task determines
the relationship irrespective of
the finish date of the successor task.
between the two the relationship
Start-to-finish (SF) The start date of the predecessor task determines
activities. between the two
the finish date of the successor task.
activities.
Page 6 of 9
7435BEPG_Coursework Assignment
Appendix 3
Note: please assume reasonable progress in the rest of work activities (tasks) that
look logical according to the progress period at End of week 16.
Structural framing-5
Substructure- the part of the structural system that is below the ground level
Page 7 of 9
7435BEPG_Coursework Assignment
Consists of the foundations for the building and column, and walls below the
ground level.
Basement for multi-storey buildings are also considered to be substructure
Substructure supports and anchors the superstructure into the earth.
Excavation
Column footing and tie beam- pouring of concrete mix on footing and tie beam
Poured column below tie beam
Tie beam rebar preparation
Column formwork from footing to tie beam
Tie beam rebar reinforcement
Poured tie beam
Column formwork
Poured column
Page 8 of 9
7435BEPG_Coursework Assignment
Page 9 of 9