CoilCAT Customer Report

Company: SLB
Prepared for: GPC
Date Prepared: 05-26-2017

Well Name: SE Alhamad 2X


Well Location:
Field: AL HAMAD
Formation: LOWER MIOCENE

County: Egypt
State:
Country: Egypt

Comments:

Service District: EGWD


Prepared by: Mohamed Hussieny
Phone: 01063633316
Email: Mamin11@slb.com
Version:

Disclaimer Notice:
This information is presented in good faith, but no warranty is given by and Schlumberger assumes no liability for
advice or recommendations made concerning the use of any product or service. The results given are estimates based on
calculations produced by a computer model including various assumptions on the well, reservoir and treatment. The
results depend on input data provided by the Customer and estimates as to unknown data and can no more accurate than
the model, the assumptions and such input data. The information presented is Schlumberger's best estimate of the
results that may be achieved and should be used for comparison purposes rather than absolute values. The quality of
input data, and hence results, may be improved through the use of certain tests and procedures which Schlumberger can
assist in selecting. Freedoms from infringement of patents of Schlumberger or others is not to be inferred nor are any
such rights granted unless expressly agreed to in writing.
Client : SLB
Well : SE Alhamad 2X
Formation : LOWER MIOCENE
Country : Egypt

Section 1: Job Messages


Total
Corr Circ Wellhead Total N2
Pump
Time Message Depth Pres Pres Rate
Rate
(ft) (psi) (psi) (scf/min)
(bbl/min)
8th May 2017
Standby for crew and equipment
Equipment at the Jetty , Crew standby in Ghareb
Equipment on Board :
1. 1 ½” Coiled Tubing Unit.
2. N2 Pump
3. Liquid N2. (25000 gal) in 5 N2 Tanks
4. Fluid Pump + Iron Basket
5. Centrifugal pump
6. Chemical transfer pump
7. 2 Mixing Tank
8. Batch Mixer
9. Tool box container
10. Chemical as per design recipe
9th May 2017
Standby for crew and equipment
10th May 2017
Standby for crew and equipment
16:00:00 Start spot CT equipment on cantilever
20:30:00 Rig up Fluid pump and Batch mixer on main deck
22:00:00 Continue Rig Up
11th May 2017
Operation Day for crew and equipment
1:30:00 Rig up surface lines
6:30:00 Rig up WH x-over & BOP
10:00:00 Function Test BOP
10:30:00 Lift I.H to Rig floor
13:45:00 Stab in CT pipe into I.H
15:15:00 Start Make up end connector
17:39:15 Start Pull test on End connector 0.0 -144 42 0.0 0
17:44:33 Pull test completed 0.0 -143 43 0.0 0
19:00:48 Start Flushing CT reel 47.5 55 41 0.7 0
19:13:55 Flush completed 47.5 56 38 0.0 0
19:14:55 Start Pressure test against choke 47.5 55 44 0.0 0
19:22:40 Pressure test against choke completed 66.0 3189 3164 0.0 0
19:29:56 Start Pressure test on down stream 66.0 56 39 0.0 0
19:40:43 done with pressure test down stream 65.9 518 634 0.0 0
19:56:33 open the well 66.2 3 32 0.0 0
19:57:49 start RIH 68.3 5 32 0.0 0
20:02:45 start Cool down 1 109.7 4 32 0.0 0
20:42:38 start pumping N2 @ 400 scf/m 1076.8 1197 34 0.0 384
20:59:28 stop pumping N2 1646.5 908 124 0.0 237
21:03:17 resume pumping N2 @ 400 scf/m 1646.5 489 87 0.0 336
21:08:19 Pull Test at Feet 1723.1 660 92 0.0 414
21:09:11 Recommence RIH CT 1700.2 666 101 0.0 380
21:51:55 Pull Test at Feet 3144.3 737 106 0.0 388
21:53:07 Recommence RIH CT 3132.1 742 107 0.0 401
22:21:46 Pull Test at Feet 4217.5 692 69 0.0 401
12th May 2017
Operation Day for crew and equipment
5:01:25 stop pumping 4316.1 608 161 0.0 0
11:27:20 Pull Test at Feet 4316.3 600 243 0.0 0
15:32:48 POOH to surface 4317.5 610 42 0.0 0
Client : SLB
Well : SE Alhamad 2X
Formation : LOWER MIOCENE
Country : Egypt
Total
Corr Circ Wellhead Total N2
Pump
Time Message Depth Pres Pres Rate
Rate
(ft) (psi) (psi) (scf/min)
(bbl/min)
16:51:23 CT Back at Surface 46.0 317 353 0.0 0
16:55:00 Bad weather , waiting for chemicals
13th May 2017
Standby for crew and equipment
I.H rigged up , observing WH pressure until chemicals
6:00:00
arrive to the rig
12:30:00 Start loading chemicals to the rig
17:30:00 Stop loading due to bad weather
14th May 2017
Standby for crew and equipment
6:00:00 I.H rigged up , observing WH pressure
13:00:00 Weather still windy to load the chemicals
15th May 2017
Operation Day for crew and equipment
15:31:44 start mixing 445 bbl brine 0.0 0 0 0.0 0
18:15:07 start mix 10 bbls pickling -8.0 -138 45 0.0 0
19:21:43 start pumping 10 bbls of brine to displace Expro lines -8.0 39 41 0.7 0
19:31:33 switch to pump 10 bbls of pickling -8.0 -13 41 0.1 0
19:50:00 start pumping 20 bbls of brine to displace CT string -8.0 1669 37 1.0 0
20:09:51 stop pumping brine -8.0 -9 32 0.0 0
21:02:48 open the well -8.1 5 41 0.0 0
21:05:25 start RIH -3.7 26 41 0.0 0
21:08:48 Reset Volume 40.5 1 41 0.0 0
21:16:41 start pumping brine with min rate to fil the well 314.3 141 41 0.2 0
21:48:16 Pull Test at Feet 2058.5 154 45 0.3 0
21:49:11 Recommence RIH CT 2050.7 143 45 0.3 0
21:56:14 stop pumping 2449.5 45 52 0.1 0
22:24:39 Pull Test at Feet 3865.6 -14 50 0.0 0
22:25:47 Recommence RIH CT 3838.7 -16 48 0.0 0
23:26:41 Reset Volume 4788.5 59 40 0.6 0
23:26:45 start pumping Brine to confirm well is full 4788.5 68 41 0.7 0
16th May 2017
Operation Day for crew and equipment
0:41:20 Brine at surface stop pumping and switch to pre flush 4789.0 51 50 0.0 0
0:44:35 Start pumping pre flush till tip of nozzle 4789.0 4 45 0.0 0
0:56:33 pre flush at tip of nozzle 4788.8 3 46 0.0 0
0:57:43 shut in the well and start squeezing 4788.8 3 45 0.0 0
1:16:46 Sec. interval 4649.4 0 35 0.0 0
1:36:22 third perf 4479.2 -2 34 0.1 0
2:07:57 Injectivity completed 4362.8 257 284 0.0 0
2:12:56 Waiting for decision 4380.0 3 40 0.0 0
2:39:13 Continue squeezing pre flush with rate 1 bbl 4347.4 549 33 0.8 0
2:57:39 Decrease rate to .75 bbl/m 4507.5 2264 732 1.0 0
5:17:56 increase rate to 0.9 bbl/m 4694.4 1510 520 0.8 0
6:40:58 increase rate to 1 bbl/m 4759.2 2273 681 1.1 0
6:44:36 decrease rate to 0.9 bbl/m 4784.0 2384 747 1.0 0
7:00:49 Switch to brine to displace CT reel 4609.4 2064 684 1.0 0
7:06:02 loose prime from Derick c-pump 4586.1 -10 120 0.0 0
7:16:54 Stop Pumping 4371.1 2270 662 1.0 0
7:17:21 POOH to surface waiting on chemicals to arrive 4361.4 413 435 0.0 0
8:30:09 CT Back at Surface 7.7 -19 37 0.0 0
17th May 2017
Operation Day for crew and equipment
weather is good now , start receiving clean sweep
9:56:35 0.0 0 0 0.0 0
chemicals
Client : SLB
Well : SE Alhamad 2X
Formation : LOWER MIOCENE
Country : Egypt
Total
Corr Circ Wellhead Total N2
Pump
Time Message Depth Pres Pres Rate
Rate
(ft) (psi) (psi) (scf/min)
(bbl/min)
12:50:35 start Mixing clean sweep 0.0 0 0 0.0 0
15:54:31 open the well 0.0 0 0 0.0 0
15:55:33 start RIH 0.0 0 0 0.0 0
16:07:46 Started Recording 0.0 0 0 0.0 0
16:25:28 Pull Test at Feet 1124.0 -157 35 0.0 0
16:26:33 Recommence RIH CT 1095.6 -158 35 0.0 0
16:58:41 Pull Test at Feet 2779.5 2 37 0.0 0
17:00:18 Recommence RIH CT 2757.5 1 36 0.0 0
17:23:50 Pull Test at Feet 4109.8 24 38 0.0 0
17:32:47 Pull Test at Feet 4397.1 27 37 0.0 0
17:45:45 finish mixing clean sweep 4348.1 15 36 0.0 0
17:54:42 open the well 4348.1 15 39 0.0 0
17:58:37 start pumping brine to confirm well is full 4348.1 115 39 0.4 0
18:03:20 return found on surface 4348.1 278 39 0.5 0
18:03:32 stop pumping brine 4348.1 284 39 0.5 0
18:04:02 Reset Volume 4348.1 90 39 0.0 0
18:06:16 start pumping 12 bbls clean sweep , well is open 4348.1 155 39 0.6 0
18:20:58 Clean sweep @ nozzle, stop pumping 4348.2 1286 44 0.9 0
18:21:25 close the well 4348.2 22 42 0.0 0
18:22:04 start RIH to bottom perf 4349.7 21 40 0.0 0
18:43:53 Reset Volume 4791.0 20 31 0.0 0
18:46:14 start squeeze 78 bbls clean sweep to lower perf 4791.0 373 31 0.6 0
18:52:15 increase pump rate to 0.9 bpm 4721.7 1443 34 0.9 0
19:16:24 increase pump rate to 1.2 bpm 4769.8 2046 272 1.1 0
19:42:40 increase pump rate to 1.5 bpm 4740.5 3416 451 1.5 0
19:54:09 increase pump rate to 1.75 bpm 4779.2 4677 595 1.8 0
19:56:50 POOH to lower middle perf 4793.3 4770 644 1.8 0
20:12:16 decrease pump rate to 1.5 bpm 4596.6 3531 699 1.6 0
20:21:56 decrease pump rate to 1.25 bpm 4623.8 3007 700 1.3 0
20:50:37 POOH to upper Middle perf 4580.2 2610 688 1.2 0
20:57:25 Decrease rate to 1 bbl/m 4451.5 2301 694 1.1 0
22:45:40 Stop pumping 4353 1656 466 0 0
23:23:12 Start POOH to surface 4192 277 64 0 0
18th May 2017
Operation Day for crew and equipment
0:48:14 CT back at surface 3.7 3 39 0.0 0
16:29:16 open the well -8.0 -161 53 0.0 0
16:31:35 start RIH -0.8 -159 53 0.0 0
17:04:57 Pull Test at Feet 1352.2 5 106 0.0 0
17:05:50 Recommence RIH CT 1338.5 5 90 0.0 0
17:24:13 Pull Test at Feet 2131.6 29 123 0.0 0
17:53:30 Pull Test at Feet 3617.7 15 129 0.0 0
17:55:24 Recommence RIH CT 3567.0 5 92 0.0 0
18:55:49 open the well 4349.4 36 61 0.0 0
19:00:11 start pumping 12 bbls MSR to displace the reel 4349.4 28 43 0.0 0
19:12:34 stop pumping 4349.4 30 41 0.1 0
19:13:04 shut in the well 4349.4 25 40 0.0 0
19:13:18 RIH to bottom perf 4349.4 25 43 0.0 0
19:23:39 Reset Volume 4791.5 23 131 0.0 0
19:26:00 start squeeze 62 bbl of MSR into bottom perf 4791.5 898 155 1.0 0
19:55:42 increase pump rate to 1.1 bpm 4779.4 2104 596 1.1 0
20:10:57 switch to pump 8 bbl MSR WT U66 4722.9 2540 612 1.2 0
20:17:56 switch to pump 55 bbls VDA 4764.2 2488 592 1.2 0
20:20:42 MSR WT U66 @ nozzle 4724.6 2567 590 1.2 0
20:27:25 VDA @ Nozzle 4790.2 3063 580 1.2 0
Client : SLB
Well : SE Alhamad 2X
Formation : LOWER MIOCENE
Country : Egypt
Total
Corr Circ Wellhead Total N2
Pump
Time Message Depth Pres Pres Rate
Rate
(ft) (psi) (psi) (scf/min)
(bbl/min)
20:27:28 Reset Volume 4790.2 3063 580 1.2 0
21:02:27 Switch to 4.5bbl MSR W/O U066 4725.9 2735 524 1.2 0
21:06:07 Switch to MSR of the Next zone to displace the reel 4736.8 2498 520 1.2 0
21:12:14 Reset Volume 4788.8 2708 511 1.2 0
21:12:14 MSR W/O U066 @ nozzle 4.5bbl 4788.8 2708 511 1.2 0
21:17:25 Reset Volume 4678.1 26 388 0.0 0
21:31:21 Increase Rate to 1.5bbl/Min. 4620.7 3671 449 1.6 0
22:00:27 Switch to 8 bbl MSR W/O U066 4563.6 4299 429 1.7 0
22:05:00 Switch to 55bbl VDA 4601.0 4352 445 1.7 0
22:08:03 MSR W/O U66 @ Nozzle 4649.2 3937 443 1.7 0
22:12:20 VDA @ Nozzle 4605.6 4317 432 1.7 0
22:38:32 Switch to MSR W/O U066 4.5bbl 4583.9 5192 401 1.6 0
22:41:12 Switch to MSR for the Next zone to displace the reel 4598.9 4995 403 1.6 0
22:45:55 MSR W/O U66 @ Nozzle 4645.7 4243 404 1.6 0
Start Squeezing for the next zone MSR @
22:51:38 4473.9 11 295 0.0 0
Nozzle(1345m-1365m)
22:51:47 Reset Volume 4473.9 11 292 0.0 0
23:21:51 Switch to 8bbl MSR W/O U066 4462.2 4252 397 1.7 0
23:26:30 Switch to 55bbl VDA 4425.6 4272 391 1.7 0
23:29:24 MSR W/O U66@ Nozzle now 4427.3 4401 390 1.7 0
23:33:49 VDA @ Nozzle 4416.3 5264 379 1.7 0
19th May 2017
Operation Day for crew and equipment
0:01:48 Switch to 4.5 bbl MSR w/O U066 4421.8 4794 326 1.5 0
0:05:22 Switch to MSR to displace the Reel 4440.8 4313 325 1.5 0
0:08:57 MSR w/o @ nozzle 4479.3 4317 331 1.6 0
0:13:45 Reset Volume 4379.2 14 285 0.0 0
0:17:39 Automatic Message: Start Pumping 4379.2 554 233 0.7 0
0:17:45 Start Squeezing MSR to the last perf (1335m-1325m) 4379.2 553 232 0.7 0
0:29:16 Switch to MSR W/O U066 6.5bbl 4359.4 4094 305 1.7 0
0:33:00 Switch to VDA 4380.1 4088 314 1.7 0
0:36:35 MSR W/O @ nozzle 4351.8 4442 319 1.7 0
0:39:59 VDA @ Nozzle 4380.6 5079 321 1.7 0
0:49:44 switch to MSR w/) U066 4356.5 4945 313 1.6 0
CT @ EOT & waiting for Soaking time & mixing the rest
1:00:11 4290.4 28 251 0.0 0
of the treatment
6:04:37 End of mixing rest of MSR & MSR W/O U066 4290.4 16 35 0.0 0
6:05:02 Start RIH to Top of Perf. 4290.4 21 34 0.0 0
6:06:02 Reset Volume 4310.0 23 34 0.0 0
6:09:08 Start Pumping MSR W/O U066 4350.3 846 35 1.0 0
6:18:03 MSR W/O U066 @ 2nd perf. 4421.7 2088 82 1.2 0
6:29:00 MSR W/O U066 @ 3ed perf. 4587.2 1996 122 1.6 0
6:39:33 MSR W/O @ Bottom perf. 4734.4 4251 201 1.8 0
6:44:06 Switch to MSR to displace MSR W/O from the reel 4768.6 4264 215 1.8 0
6:44:22 Reset Volume 4770.4 4133 215 1.8 0
6:51:21 Reset Volume 4748.3 4274 226 1.8 0
6:51:56 MSR @ Nozzle & start by the bottom perf. 4742.8 4425 227 1.8 0
7:28:52 Squeezing MSR @ perf.1397m-1417m 4645.0 4266 252 1.8 0
8:06:27 Squeezing MSR to perf. (4412ft-4478ft) 4423.6 4114 260 1.8 0
8:37:23 Squeezing MSR @ perf.1325m-1335m 4377.0 3954 261 1.8 0
8:52:49 done with MSR , stop pumping 4356.8 3350 260 1.8 0
8:58:31 start mix 547 bbls post flush 4272.1 122 203 0.0 0
13:12:49 start pumping Post flush @ 1.75 bpm 4351.6 1541 35 1.4 0
13:19:07 Reset Volume 4456.2 3457 67 1.7 0
14:15:16 increase pump rate to 2 bpm 4358.7 4805 177 2.0 0
15:22:03 Stop Pumping 4463.8 37 215 0.0 0
Client : SLB
Well : SE Alhamad 2X
Formation : LOWER MIOCENE
Country : Egypt
Total
Corr Circ Wellhead Total N2
Pump
Time Message Depth Pres Pres Rate
Rate
(ft) (psi) (psi) (scf/min)
(bbl/min)
15:49:42 resume pumping @ 2 bpm 4342.5 1773 104 1.6 0
18:23:53 start cool down 2 4356.7 4260 242 1.9 0
18:28:14 switch to pump 12 bbls brine to displace the reel 4356.7 4306 243 1.9 0
18:40:07 Start POOH to 500 m 4308.0 15 229 0.0 0
18:43:09 Open swap valve 4171.1 10 190 0.0 0
18:54:07 start pumping N2 @ 400 scf/m 3713.3 58 76 0.0 0
19:31:03 RIH to 1270 m & continue lifting 1897.4 969 222 0.0 440
20:26:39 CT @ 1270 m 4167.9 1084 123 0.0 423
22:21:13 Pumping 3bbl H2S Scavenger 4168.0 1016 220 0.0 388
20th May 2017
Operation Day for crew and equipment
1:05:38 CT @ 1000m 3282.0 993 275 0.0 401
1:32:31 CT @ 1270m 4168.8 996 165 0.0 375
4:05:29 Pumping 2nd 3 bbl H2S scavenger 4168.9 1383 194 0.8 410
6:35:38 Stop Pumping N2 while keeping the cool down 4169.0 881 119 0.0 0
8:57:34 Start pumping N2 Rate 400 SCAF 4169.0 843 42 0.0 410
10:50:48 Pumping 3rd 3 bbl H2S scavenger 4169.0 1203 150 1.1 405
11:28:12 stop pumping N2 4169.0 931 146 0.0 0
14:05:28 start cool down 3 4169.0 703 42 0.0 0
14:38:17 start pumping N2 @ 400 scf/m 4169.0 700 42 0.0 380
16:14:36 Pumping 4th 3 bbl H2S scavenger 4169.0 1727 146 0.9 354
17:49:32 stop pumping N2 4169.0 900 188 0.0 0
18:35:11 start POOH to surface 4161.6 843 41 0.0 0
19:51:35 CT Back at Surface 22.2 14 344 0.0 0
19:51:48 waiting for decision 22.2 15 344 0.0 0
22:33:07 waiting for the boat to back load crude oil 15.0 14 41 0.0 0
21st May 2017
Operation Day for crew and equipment
11:36:22 Open swap valve -7.8 -146 43 0.0 0
11:40:37 Start RIH to 1270m -7.8 1 50 0.0 0
12:02:28 Pull Test at Feet 1014.5 -2 44 0.0 0
12:29:39 Pull Test at Feet 2514.8 0 43 0.0 0
12:43:50 Start Cool down N2 4 3270.2 3 43 0.0 0
13:21:05 start pumping N2 @ 400 scf/m 4171.7 155 43 0.0 448
15:50:40 Stop pumping N2 4171.7 895 197 0.0 0
19:27:58 5000 gal of liquid Nitrogen arrived to the rig 4171.6 835 41 0.0 0
19:37:47 Start cool down 5 4171.6 835 41 0.0 0
20:15:21 Pumping 5th 3 bbl H2S scavenger 4171.6 909 41 1.0 0
20:21:35 start pumping N2 @ 400 scf/m 4171.6 1869 41 0.1 466
23:56:27 stop pumping N2 4171.6 869 172 0.0 0
22nd May 2017
Operation Day for crew and equipment
2:21:35 Start POOH & waiting for the new oil tank 4171.6 861 43 0.0 0
3:45:22 CT Tagged @ surface & waiting for any update -7.4 390 425 0.0 0
8:03:02 start transfer oil from EXPRO tanks to the boat -7.3 1 42 0.0 0
10:07:23 All Tanks are ready & Start RIH to 1270m -7.4 0 42 0.0 0
10:40:06 Pull Test at Feet 1520.3 1 41 0.0 0
10:57:24 Pumping 6th 3 bbl H2S scavenger 2441.4 1 41 0.0 0
11:08:46 Pull Test at Feet 3084.4 7 41 0.0 0
11:13:48 Start Cool down 6 3374.1 261 41 0.8 0
11:29:41 Pull Test at Feet 4168.1 28 40 0.0 0
11:30:30 CT @ 1270m 4168.2 36 40 0.0 0
11:30:48 Start Pumping N2 @ rate 400 SCF/Min. 4168.2 37 41 0.0 0
17:05:30 stop pumping N2 4168.2 858 156 0.0 0
17:06:37 POOH to surface 4168.2 854 145 0.0 0
Client : SLB
Well : SE Alhamad 2X
Formation : LOWER MIOCENE
Country : Egypt
Total
Corr Circ Wellhead Total N2
Pump
Time Message Depth Pres Pres Rate
Rate
(ft) (psi) (psi) (scf/min)
(bbl/min)
18:35:17 CT Back at surface -7.2 2 41 0.0 0
18:43:23 close swap valve -7.2 2 41 0.0 0
18:45:34 waiting for decision -7.2 1 41 0.0 0
23rd May 2017
Operation Day for crew and equipment
4:25:00 Open swap valve
4:30:05 Start RIH to 1270m -8.0 -146 43 0.0 0
5:02:38 Pull Test at Feet 1506.8 2 43 0.0 0
5:34:29 Pull Test at Feet 3032.9 2 43 0.0 0
5:47:17 Start Cool down 7 3758.5 1 43 0.0 0
5:55:14 Pull Test at Feet 4180.7 2 42 0.0 0
5:56:05 CT @ 1270m 4169.6 1 43 0.0 0
6:04:10 Start Pumping N2 @ rate 350 SCF/Min. 4169.6 22 43 0.0 0
12:59:41 stop pumping N2 , and wait for Nitrogen suppy 4169.4 867 96 0.0 0
15:50:42 5000 GL of liquid Nitrogen recieved 4169.4 852 177 0.0 0
16:43:55 Pumping 7th 3 bbl H2S scavenger 4169.3 897 182 1.0 0
16:50:12 start cool down 8 4169.3 959 234 0.0 0
17:05:07 Start pumping N2 @ 350 scf/m 4169.3 1214 77 0.0 336
22:03:14 Pumping 8th 3 bbl H2S scavenger 4169.2 1151 167 0.4 336
24th May 2017
Operation Day for crew and equipment
2:27:03 Pumping 9th 3 bbl H2S scavenger 4169.2 973 164 0.0 375
9:29:12 Stop pumping N2 till the boat take the N2 Tanks 4169.1 882 142 0.0 0
9:54:54 Pumping 10th 3 bbl H2S scavenger 4169.1 850 349 0.0 0
10:02:02 Continue pumping N2 with same rate 350SCF/Min. 4169.1 846 48 0.0 285
10:49:04 All N2 at rig finished waiting for the new 5000Gal 4169.1 866 101 0.0 0
10:49:16 stop pumping N2 4169.1 866 104 0.0 0
16:27:44 extra 5000 GL of liquid Nitrogen arrived to the rig 4169.0 801 134 0.0 0
16:35:03 start cool down 9 4169.0 798 134 0.0 0
16:47:04 Pumping 11th 3 bbl H2S scavenger 4169.0 840 135 1.0 0
17:31:30 start N2 pumping @ 350 scf/m 4169.0 1189 94 0.0 349
22:25:09 Pumping 12th 3 bbl H2S scavenger 4168.9 1215 138 1.1 349
25th May 2017
Operation Day for crew and equipment
8:22:49 Pumping 13th 3 bbl H2S scavenger 4167.9 916 121 0.0 362
9:23:37 Stop Pumping N2 & wait for new update 4167.9 739 142 0.0 0
10:52:00 Start killing the well by brine from the Rig 80bbl 4167.8 716 43 0.0 0
11:59:42 Stop pumping brine & wait observing the well 4167.8 -89 44 0.2 0
13:02:12 Continue POOH to surface 4167.8 -104 44 0.0 0
14:21:31 CT Back at Surface -10.9 -165 44 0.0 0
14:35:07 close swap valve -10.9 -149 -3750 0.0 0
14:39:50 start Lay down I.H. -10.9 -148 -3750 0.0 0
23:35:00 Complete R/D
26th May 2017
Standby Day for crew and equipment
08:00:00 Back load CT equipment

GPC Representative Schlumberger Representative


……………………………….. ……………………………………………