Documente Academic
Documente Profesional
Documente Cultură
1. PURPOSE
It is the vertical wall at the end of most bridges that extend up from the abutment seats
and support the expansion joint. A small retaining wall which also supports the
approach slabs and hold back embankment under the approach slabs.
This covers the installation of a backwall and the specifications of the materials. Backwall
play an important role in bridge construction and other structure. The backwall supports
In Bridge/Road construction surveying the area is a necessity to determine the plan for
the structure and the location and other information that can help the design. A location
survey is done to lay out the bridge according to the plans. A preliminary survey is made
at the best site to establish horizontal and vertical control and to obtain information for
The required labor and equipment of constructing a backwall are carpenters, steel
fixers, masons, labors and the equipment that are needed are concrete mixer and
vibrator.
While shoring, form of prop or support, usually temporary, that is used during the repair
required, for example, to relieve the load on a masonry wall while it is repaired or
reinforced.
6. POURING OF CONCRETE
When pouring of concrete just like the wing wall the back wall is also the same., the
contractor must prepare their transit or concrete mixer from the batching plant for the
pouring procedures. Prepare the following equipment and manpower. Just like wing wall
reinforced poured concrete is typically the material of choice for backwalls attached to
bridges or buildings.
7. REMOVAL OF FORMWORK
should be carried out only after the time when concrete has gained sufficient strength, at
least twice the stress to which the concrete may be subjected to when the formworks
are removed. It is also necessary to ensure the stability of the remaining formwork
during formwork removal. With that said there are some issues to consider. The single
biggest issue with forms is whether the concrete will support itself, so beams, especially
beam bottom forms, high wall forms, and other structures that don’t allow for concrete to
support itself until it has cured require leaving forms in place for 3 to 7 days for side
Curing is another concern. If you pour a 12 inch thick wall, 12 feet tall, for instance, the
concrete would support itself the next day, but would not cure as well since moisture
would be lost when the forms are removed. This means a curing compound or another
8. RISK ASSESSMENT
The most common problem associated with backwalls occurs when the backwall gets
pushed into the ends of the beams due to pavement pressure (or pavement growth).
This most commonly occurs on bridges that are on highways constructed of several
miles of concrete pavement. The concrete approach pavement expands in the summer
months, but then in the winter, the pavement contracts. As the pavement contracts, the
joints between the pavement slabs open up and dirt, sand, and other incompressible get
Report : (30%)_________
Total: (100%)
Date Submitted
Instructor