Documente Academic
Documente Profesional
Documente Cultură
VENUGOPAL
DILEMMA
BID
INVITATION
PREPARATION
Critical Success Optimum utilisation of funds for effective bidding of the IT solution for growth and
Factors enhancing the profits of the company
(What needs to
go right?)
Risk The Technical risk to be avoided for efficient bidding of the right IT solutions. The
(What can go budgeted risk and the schedule risk should be mitigated to avoid additional cost to
wrong?) the company. Qualitative risk to be reduced by using Monte Carlo Simulation in case
of default probability
Causes High cost and not following the budget estimation while bidding. Wrong system
(What could design. Installation defaults. Improper resources allocation and inefficient risk
cause that to management
happen?)
Consequence if (Maximum Probable Loss – to avoid keep reserves and contingency plans). When
risk occurs analysing the consequences of a risk event, an authority incharge needs to consider
(consider the the level of impact (1 to 5) in relation to each of the consequence categories defined
worst/largest $ in the Public Authority’s in this case Venugopal’s own consequence rating table.
impact)
1. RISK IDENTIFICATION
Bidding Risk - They have to bid for the IT package which would cost
Rs.300000 per day which requires 100 workers (labour cost)
Legal and compliance risk involved with software design and bidding.
Scheduling risk – specified Time period - 8 weeks.
Other risks - Document review, interviews with key project players, , wrong
risk brainstorms to secure team buy-in, unaware of specific requirements or
even can be people are unknown about software application
Wrong estimated Budgeting and over incurrence of costs
Preparation of Bid (12 million could go up to 24 million)-
External risk- from competitors –
Business risk – business process failure , people, lack of information, reports
could be biased, input issues
Environmental and contingency risk
Quantitative risk - degree of confidence for preparing the bid within the
estimated budget
2. RISK ASSESSMENT
Monte Carlo technique - Applying a Monte Carlo approach which integrates risks and
uncertainties provides a clear view of their impact on timelines and costs. This defines
the extremes of the range, as well as the probability of a particular outcomes.
Prioritize risks by their impact on the project – how much time, money, and effort does
each risk require
It is critical to carefully think through each risk, so that they can be managed (step three)
strategically, rather than just haphazardly dealing with the first risk on the list.
SEVERITY
LITTLE TO NO EFFECT ON EFFECTS ARE FELT, BUT SERIOUS IMPACT TO THE COULD RESULT IN
EVENT NOT CRITICAL TO COURSE OF ACTION DISASTER
OUTCOME AND OUTCOME
LIKELIHOOD
REF/ID PRE-MITIGATION
RISK RISK
RISK RISK LEVEL
SEVERITY LIKELIHOOD
Funding or Cash
6 ACCEPTABLE POSSIBLE EXTREME
management risk
Software and
Hardware installation UNDESIRABLE PROBABLE LOW YES
checks
Abide by
compliance related
bidding
TOLERABLE POSSIBLE MEDIUM NO
requirements. Pay
bidding legal
charges
Follow budget
estimation plan,
schedule and keep TOLERABLE IMPROBABLE MEDIUM YES
backup costing
remedies
Reserves and
Contingency plans
INTOLERABLE POSSIBLE LOW NO
for controllable part
of this risk
Internal awareness
and use of
techniques like
ACCEPTABLE PROBABLE LOW NO
probability of default
and loss given
default
By submitting a bid price that realistically reflects the level of uncertainty and risk
Taking a strategic decision to proceed with the bid knowing the risk exposure, and
where the company ensures that is has the contingency funds to support it.
The company officials can decide to “No-bid” in the case of high risk projects that
without a change to the scope have a low probability of making a profit – with the
result that you can focus on winning good, profitable business
Once Venu Gopal and team wins the bid the project has a starting point in terms
of risks and the above matrix shows the levels and means to mitigate.