Training Manual
Developed by
1|P a g e © www.gaeaglobal.com
Primavera P6 Essentials Training manual
Table of Contents
2|P a g e © www.gaeaglobal.com
1. Introduction to Oracle Primavera
Oracle Primavera P6 Enterprise Project Portfolio Management (P6 EPPM) is a robust and easy-
to-use integrated solution for globally prioritizing, planning, managing, and executing projects,
programs, and portfolios. It optimizes role-specific functionality to satisfy each team member's
needs, responsibilities, and skills. It provides a single solution for managing projects of any size,
adapts to various levels of complexities within a project, and intelligently scales to meet the
needs of various roles, functions, or skill levels in your organization and on your project team.
Share data with human capital, financial management, and enterprise resource planning
systems
P6 EPPM also integrates with many other optional Oracle solutions such as Contract
Management, Oracle Risk Analysis, Oracle PPM, and Cost Manager.
3|P a g e © www.gaeaglobal.com
1.1 Working with Oracle Primavera P6 Enterprise Project Portfolio
Management Solutions
Depending on your organization's specific deployment, P6 EPPM generally consists of the
applications, functions, and databases depicted below.
Applications:
P6: Most users will rely almost exclusively on the P6 web application running in a standard web
browser. Simply termed P6, it is the primary interface for administering and managing projects.
P6 Professional for EPPM: The P6 web application is the main interface for all project
management functionality; however, you can also use the optional P6 Professional software to
take advantage of its core project planning and scheduling functionality. The P6 Professional
application and its features, including the built-in TSLD viewer, run on the Microsoft Windows
operating system.
4|P a g e © www.gaeaglobal.com
P6 Team Member Applications: Optional applications for team members to use to provide
status on their tasks.
P6 Team Member Web: This web application allows team members to provide status on
their tasks using a web browser.
P6 Team Member for iPhone app: This iPhone app allows team members to provide
status on their tasks while working "on the go".
E-mail Statusing Service: This method allows team members to provide status on their
tasks using any HTML or plain text e-mail application.
P6 Progress Reporter: P6 EPPM includes the P6 Progress Reporter integrated timesheet entry
software. Resources use P6 Progress Reporter to record their time spent working on
assignments via electronic timesheets, and approving managers use P6 to review and approve
them.
P6 Analytics: An optional integrated dynamic reporting tool with advanced visual features,
including dashboards.
P6 is the main web application of the P6 EPPM solution. P6 provides enterprise-wide web
access to features arranged into the following main sections:
Dashboards
5|P a g e © www.gaeaglobal.com
Portfolios
Projects
Resources
Reports
Administration
P6 is a complete Enterprise Project Portfolio Management application with a powerful but easy-
to-use interface. It completely tracks projects, portfolios, and resources across their full project
lifecycles capturing all related costs, issues, risks, and performance metrics along the way. It
also supports project templates, allowing you to reuse projects in full or in part. It is designed
for organizations that need to simultaneously manage multiple projects and support multi-user
access across job sites and throughout the entire organization.
The user interface provides structured menus where you can access a wide range of data views
and features that enable you to manage your projects from initial concept review and approval
through to completion. You can customize your own web pages, called dashboards, to create a
custom view of the specific projects and categories of project data that are most relevant to
your role in managing projects and resources. Project workspaces and workgroups extend the
model of customizable, focused data views by enabling designated project members to create a
uniform view of data that relates to one specific project or to a subset of activities within a
project.
6|P a g e © www.gaeaglobal.com
Finally, P6 is the single source for administrative functions, including centralized enterprise
data, user accounts, application settings, and security for all users in P6 EPPM.
Project Management: Project Management is the application of knowledge, skills, tools and
techniques to protect activities to meet the project requirements. It is the process of achieving
set goals within the constraints of time, budget, and staffing restrictions. Project Management
is accomplished through the appropriate application and integration of different project
management processes comprising the 5 process groups.
7|P a g e © www.gaeaglobal.com
•Collect Project Information (like project statement of
work)
Initiation •Obtain organizational commitment
•Initiate project request
•Develop the project team
•Distribute information
Executing •Track work in progress and actual costs
8|P a g e © www.gaeaglobal.com
Notes
9|P a g e © www.gaeaglobal.com
2. Logging in and Web Access navigations
View of P6R8.2 Web access with different option tabs such as Dashboards, Portfolios,
Projects, etc available in the navigation bar.
In the upper right corner, logged in username appears
10 | P a g e ©
www.gaeaglobal.com
2.2 Basic Navigation
P6 title bar: Located in the P6 title bar, the Administer menu provides links to related pages
based on your view settings and personal preferences. The Help menu items are standard and
cannot be changed.
P6 navigation bar: Located in the P6 navigation bar, each menu opens up additional pages
within the section it represents. The Dashboards, Portfolios, Projects, and Resources menus
provide links to related pages based on your view settings and personal preferences. The
menus for portfolios and projects also display links to your most recently used items.
Portfolios menu: Provides links to open and manage portfolios, views, and scenarios. This
example also shows two recently used portfolios, Key Projects over $500K and Engineering &
Construction.
Projects menu: Provides links to open one or more projects, adjust specific enterprise data for
projects, and schedule services. This example also shows a recently used project, Harbour
Pointe Assisted Living Center.
Resources menu: Contains a single link to adjust resource-specific enterprise data without
navigating away from the current page.
Administer menu: Assuming all its menu items are configured, this menu provides links to
adjust your own calendar and personal preferences. In addition, it can also display links to the
Application Settings, Enterprise Data, Global Scheduled Services, User Access, and User
Interface Views pages.
11 | P a g e ©
www.gaeaglobal.com
Help menu: A fixed menu providing links to the Online Help, P6 Library of documents available
online, and the Oracle Primavera Customer Support website.
Project Workspace:
Provides information specific to each project, that includes information on project management and
project performance. With the proper configuration, you can also communicate and share information
and documents with other project members in this workspace
12 | P a g e ©
www.gaeaglobal.com
13 | P a g e ©
www.gaeaglobal.com
Multiple windows can be opened at a time
14 | P a g e ©
www.gaeaglobal.com
3. Understanding and customizing Layouts
3.1 Open an existing project/template
By default, if no projects are open when you log on to P6 or if you are a new user,
clicking Projects in the P6 navigation bar will take you directly to the EPS page as long as this
page is available in your user interface view. If you do not have access to the EPS page or you
navigate to another page in the Projects section, the Open Projects dialog box appears when
you click Projects.
15 | P a g e ©
www.gaeaglobal.com
You can also right-click on any of the project and select Open Project .
16 | P a g e ©
www.gaeaglobal.com
3.2 Opening an Existing Activity Layout
A variety of layout are available that provides different views of activity data. You can create
user – specific layout and project – specific layouts or use global layout provided by your
company.
Apply – Displays the selected layout but keeps the open layout dialog box open.
Open – Displays the selected layout and closes the Open layout dialog box.
17 | P a g e ©
www.gaeaglobal.com
3.3 Customizing a layout
The Activities window can be customized and saved as a layout. Saving layouts for future use
allows you to retrieve information quickly. Use the layout options bar as your centralized menu
for layout customizing.
Selecting Columns
The columns dialog box enables you to select columns to display in the activity table and
specify the order in which they appear.
18 | P a g e ©
www.gaeaglobal.com
Click Edit column to change the selected items title and choose the titles alignment in the
display.
Add a column to the activity table and reorder the items displayed.
Views (same as layout as in Client) can be shared, customized and are an element that
combine what columns you want to see, how to group them, how to sort them and how
to hide/show graphical elements.
19 | P a g e ©
www.gaeaglobal.com
End of this Chapter
20 | P a g e ©
www.gaeaglobal.com
Notes
21 | P a g e ©
www.gaeaglobal.com
4. Formatting Data
Schedule data can be formatted in project management tool using Grouping, sorting or by
applying filters.
Grouping & Filtering temporarily limits the projects or activities that appear on layout,
according to criteria you establish.
To simplify the display of complex tables of data, you can group rows of similar data and sort
the grouped bands as well as the data under them. Grouping helps you block distracting data
and focus only on the information you need. It also permits you to collapse and expand
hierarchical arrangements of your data rather than navigate large flat lists.
22 | P a g e ©
www.gaeaglobal.com
activities for Phase II that fall under the Planning stage. To see activities grouped
by all ten levels, choose 10 or All.
d. For each field, in the Sort Order list, select how you want the grouped
data bands to be sorted when your grouping options are applied.
e. Click OK to close the dialog box and apply your grouping options to the
page you selected in step 1.
Group By: Lists grouping data items for the current display. To select or
change a data item, double-click it.
o Indent: Automatically marked if the item selected in the Group By
column is hierarchical. Each level of the hierarchy is indented.
o To Level: Indicates the number of levels to indent when grouping by a
hierarchical code.
o Group Interval: Indicates the group interval when grouping by fields.
For example, group by Remaining Duration. Type 5d in the Group
23 | P a g e ©
www.gaeaglobal.com
Interval field. The data items are grouped according to the length of
their remaining durations — 0.0d to 5.0d, 5.0d to 10.0d, etc. For date
fields, choose from Day, Week, Month, Quarter, and Year.
o Font & Color: Lists each grouping's display color and font. To change a
color or font, double-click it.
Hide if empty: Mark to hide group title bands that do not contain data items
within the group. Mark if you are grouping by a hierarchical field, such as EPS
or WBS, and the project has empty EPS or WBS bands. For example, mark this
checkbox if you are grouping by WBS in the Activities window and the project
has empty WBS bands. Hiding the empty bands ensures that the rolled up
data is accurate.
Sort bands alphabetically: Mark to sort the grouping bands alphabetically
rather than their order in their respective hierarchy. This checkbox is disabled
for any grouping that is not hierarchical.
Show Title: Mark to display the field name on the grouping band.
Show ID/Code: Mark to display the ID or Code value on the grouping band.
Show Name/Description: Mark to display the Name or Description on the
grouping band.
You can click a column header in the actual table you just customized later to change the
column used to sort the data rows under each band, but the sort order for the grouping bands
themselves is only determined by your selections in the Sort Order list on the Customize
Groupings dialog box.
Most groupings support up to ten (10) levels with some pages such as the Activities, EPS,
and Resource Assignments pages supporting up to twenty (20) levels of grouping by one or
more fields.
24 | P a g e ©
www.gaeaglobal.com
4.2 Apply a filter
A filter is a set of instructions that determines which activities or projects display. You can apply
a filter at any time to focus on specific areas of a project. For example, you might want to see
only critical activities, activities that are underway, or completed activities.
Filtering Data
Filters use logical rules you define to hide the data that you don't want to display. This allows
you to work with only the "good" data you want. Filters help reduce visual clutter and improve
performance.
To use filters:
Navigate to a page that supports filtering.
Define and save your filter criteria.
Enable or apply the filter.
Apply filters to a project to specify the data you want to display. You can add user-created filters or
select from the list of standard filters.
To apply filters:
1) Open one or more projects in the Projects section using one of the following methods:
Click Projects to open the last project or group of projects you were working with.
Click the Projects menu and choose one of the most-recently used projects or group of
projects.
Click the Projects menu and choose Open Projects to select a project or group of
projects by portfolio type, EPS node, or project code.
25 | P a g e ©
www.gaeaglobal.com
a. Click the Activity View or EPS View list and select a view to which you will add the
filters.
4) In the Customize Activity View or Customize Project View dialog box, click the Filters tab.
b. In the Apply to View column, select the option for each filter you want to apply.
c. Click OK.
To create filters:
1) Open one or more projects in the Projects section using one of the following methods:
Click Projects to open the last project or group of projects you were working with.
26 | P a g e ©
www.gaeaglobal.com
Click the Projects menu and choose one of the most-recently used projects or group of
projects.
Click the Projects menu and choose Open Projects to select a project or group of
projects by portfolio type, EPS node, or project code.
2) On the Project navigation bar, click Activities or EPS.
3) On the Activities or EPS page:
a. Click the Activity or EPS View list and select a view to which you will add the filters.
b. Click the View menu and select Customize View....
4) In the Customize Activity View or Customize Project View dialog box, click the Filters tab.
5) On the Filters tab, click Add Filter.
6) In the Create Filter dialog box:
a. Click the Definition tab and configure the fields and lists for one or more filter
statements.
b. Click the Access tab and define user access.
c. Click OK.
27 | P a g e ©
www.gaeaglobal.com
To add more criteria statements, click . To remove a criteria statements, click . To nest
a criteria statement inside another, click . You can add up to ten levels of nesting.
Calendars enable you to define available workdays and workhours in a day. You can also specify
national holidays, recognized holidays, project-specific work/nonworkdays, and resource
vacation days. You can establish an unlimited number of calendars to accommodate different
work patterns.
1. Global: Global calendars can be defined and applied to all projects and
resources in the database.
Assign global or resource calendars to resources, and global or project calendars to activities.
You can establish an unlimited number of calendars to accommodate different work patterns.
For example, if some activities require a five day workweek, while others are performed part-
time (such as Monday, Wednesday, and Friday), you can create different calendars and assign
them to the activities and resources in your projects.
An activity’s Activity Type field value determines whether the activity uses the calendar of an
assigned resource or its project calendar.
28 | P a g e ©
www.gaeaglobal.com
• Right click on that and select View Calender
29 | P a g e ©
www.gaeaglobal.com
4.4.2 To make changes or add new Global calendar:
30 | P a g e ©
www.gaeaglobal.com
4.4.3 Impact on scheduling: Changes in the Dates and criticality of activities
Initially, 5 day calendar has been assigned to the activities of the selected project
Now let us change the assigned 5 day calendar to 7-day Workweek calendar for some
activities as highlighted below.
31 | P a g e ©
www.gaeaglobal.com
After scheduling, the dates were changed and some activities became critical as well
Assigned Calendar drives the dates of the activities and the project as a whole.
32 | P a g e ©
www.gaeaglobal.com
4.5.1 Projects Code
Project codes help you track different projects based on characteristics they share.
If you have many projects in the hierarchy, project codes help you group and filter potentially
vast amounts of information spanning different areas of the organization.
The application supports an almost unlimited number of hierarchical project codes and values;
you can establish as many as you need to meet the filtering, sorting, and reporting
requirements of your organization.
Use this procedure to assign resource codes to resources. Once assigned, you can categorize
resources using codes.
Activity codes represent broad categories of information, a department or project manager for
instance. You can create multiple activity codes according to specific categories, then assign
different values for each code. For example, assume your organization has many departments and
you want to review activities within each department. You can first create an activity code
"department," then assign different values such as quality assurance, finance, and sales. You can
then associate activities with specific departments.
A key characteristic of an activity code as opposed to an activity user defined field is that activity
codes will only allow entries from a predefined list of values. After you create activity codes, users
can assign activity code values to activities to group, sort, and filter project data based on these
values.
33 | P a g e ©
www.gaeaglobal.com
Notes
34 | P a g e ©
www.gaeaglobal.com
5. Understand Project structure in Primavera
Enterprise Data
Enterprise data provides the global structure needed to manage multiple projects. It is available
to all projects across the organization and provides the structure necessary for centralized
35 | P a g e ©
www.gaeaglobal.com
project and resource management. Enterprise data is usually defined and maintained by a
system administrator.
Project-Specific Data
Project-specific data is only available to the project in which it is defined. Project managers define
project-specific data to further control their projects.
Dates
Work Breakdown Structure (WBS)
Activities
Activity relationships
Baselines
Expenses
Risks
Thresholds and issues
Work products and documents
Project Web site
Enterprise/Project-Specific Data
Calendars
Reports
Activity codes
36 | P a g e ©
www.gaeaglobal.com
The Enterprise Project Structure (EPS) provides the foundation for enterprise project
management. EPS represents the hierarchical structure of all projects in the database. The EPS
can be subdivided into as many levels or nodes as needed to represent work at your
organization. Nodes at the highest, or root, level might represent divisions within your
company, project phases, site locations, or other major groupings that meet the needs of your
organization; projects always represent the lowest level of the hierarchy. Every project must be
included in an EPS node.
The number of EPS levels and their structure depend on the scope of your projects and how
you want to summarize data. For example, you might want to define increasingly lower levels
of EPS nodes, similar to an outline, to represent broad areas of work that expand into more
detailed projects. Specify as many projects as needed to fulfill the requirements of your
operations executives and program managers.
Multiple levels enable you to manage projects separately while retaining the ability to roll up
and summarize data to higher levels. For example, you can summarize information for each
node in the EPS. Conversely, you can use top-down budgeting from higher-level EPS nodes
down through their lower-level projects for cost control.
37 | P a g e ©
www.gaeaglobal.com
User access and privileges to nodes within the EPS hierarchy are implemented through a global
organizational breakdown structure (OBS) that represents the management responsible for the
projects in the EPS. Each manager in the OBS is associated with an area of the EPS, either by
node or by project, and the WBS of the particular level of the hierarchy.
Once you have added users and associated them with OBS elements and project profiles, you
can define the EPS and assign a responsible manager (OBS element) to each level. You must
specify a responsible manager for each node of the EPS.
EPS toolbars: Customize the toolbars to include icons that you use most often.
EPS View toolbar: Determines how you see data on the EPS page.
EPS/Project table: Displays each project within the EPS. In this example, the data is grouped
by EPS, then by Portfolio, and then by a project code calledFinancial Rating. The table is
sorted by Project Name.
38 | P a g e ©
www.gaeaglobal.com
EPS Gantt chart: Displays project and EPS data in a Gantt chart format.
Detail Windows: The Funding detail window for the project selected in the table. Additional
detail windows appear along the bottom of the table.
You can also right-click an EPS on the table and select Add Child EPS or Add Sibling EPS to
create an EPS.
You might find it helpful to apply the EPS Only standard filter when creating an EPS
element. This will remove all projects and templates from the view so you can easily see where
your new EPS fits into the EPS hierarchy as a whole.
39 | P a g e ©
www.gaeaglobal.com
User access and privileges to nodes within the EPS hierarchy are implemented through a global
OBS that represents the management responsible for each project. Each manager in the OBS is
associated with an area of the EPS, either by node or by project, and the WBS of the particular
level of the hierarchy.
Creating OBS
Elements
40 | P a g e ©
www.gaeaglobal.com
a. Click Add.
Note: The OBS is automatically added as a child of another OBS.
b. Move the OBS to the correct location in the list and hierarchical position by
clicking the Move Up, Move Down, Move Left, or Move
Right arrows.
c. In the OBS Name field, double-click and type a unique name.
d. Click the Users detail window.
4. In the Users detail window, remove or assign users to the OBS.
To remove a user from the OBS, select a user and click the Delete icon.
To assign a user to the OBS, click the Add icon.
In the Select Users dialog box, select a user and click OK.
On the OBS page, click Save.
41 | P a g e ©
www.gaeaglobal.com
Assigning Users to an OBS
Except for a project owner or a Team Member user, a user must have permission to access an
organizational breakdown structure (OBS) to access a project assigned to that OBS. If you have
appropriate privileges, you can assign users to OBS elements using their login names.
Caution: Users assigned to an OBS that is assigned to the root EPS have access to all nodes
beneath the root.
3) On the OBS page, select an OBS and click the Users detail window.
Note: The default project security profile will automatically be assigned when the User is
selected.
6) In the Users detail window, select a different project security profile for each user, if needed.
42 | P a g e ©
www.gaeaglobal.com
End of this Chapter
43 | P a g e ©
www.gaeaglobal.com
Notes
44 | P a g e ©
www.gaeaglobal.com
6. Creating a project
Create a new
Importing a file
Copy/Paste (Copying an existing project)
To create a project:
1) Click Projects.
a. Select the EPS element to which you want to add the new project.
a. Click the General tab and select an option or enter a value in each required field.
Note: You can add a description or a Must Finish By date. You can also copy the project from an
existing project or template.
b. Click Create.
45 | P a g e ©
www.gaeaglobal.com
Note:
To configure advanced options, you must select a project to copy. This will enable the
Advancedtab. If you select to copy a template, the Advancedtab will not be enabled.
You can also right-click the table and select Add Project to create a project.
46 | P a g e ©
www.gaeaglobal.com
To create a project from an existing project or template:
1) Click Projects.
a. Select the EPS element to which you want to add the new project.
b. In the Copy from existing project or template field, click Select Project or Template to Copy
and select an option from the dialog box.
Note: Click Select Project Type and select Projects or Templates to open the list of projects or
templates.
c. Click Create.
47 | P a g e ©
www.gaeaglobal.com
To configure advanced options, you must select a project to copy. This will enable
the Advanced tab. If you select to copy a template, the Advanced tab will not be enabled.
48 | P a g e ©
www.gaeaglobal.com
1. The Layout options bar enables you to format data and open layouts.
2. The Project Table displays project information in spreadsheet format.
3. Use the vertical split bar to alter the balance between left and right panes of
the Projects window.
4. Use the horizontal split bar to hide/show more information – for example, to
display more Project Details and less of the Project Table
5. Tabs in Project Details display detailed information about a project selected in
the Projects Table.
In order to provide additional information to the Project, you need to use Project Detail window. In
order to display the project detail window, click View Show on Bottom Details.
49 | P a g e ©
www.gaeaglobal.com
General tab - Project Details
Use this tab to view or modify general information for the selected project or node.
EPS ID/Project ID: The node/project identifier. You can type a new unique ID in this field
or directly in the ID cell within the hierarchy display.
EPS Name/Project Name: The node/project name. You can type a new name in this field
or directly in the name cell within the hierarchy display.
Status: The status of the selected project (not applicable for EPS nodes). Use status to
identify active or inactive projects. You can also select What If status for analysis before
establishing a more permanent project schedule, or Planned status for use during the
project planning phase.
50 | P a g e ©
www.gaeaglobal.com
Note: To change the responsible manager for a project, a user must have Project
Superuser access rights.
Project Leveling Priority: A user-defined rank of the project among other projects used
during leveling. P6 Optional Client uses this number to determine which assignments
from other projects to consider within the leveling run. For example, if you specify 5 in
the Consider Assignments in Other Projects With Priority Equal/Higher Than field of the
Level Resources dialog box, P6 Optional Client considers all projects with a project
leveling priority of 1, 2, 3, 4, and 5.
Check Out Status: Indicates whether a project is being used remotely. This feature
enables version-control of projects. You can also change the status of the project to
"checked in" or "checked out". For example, if a project was checked out, no changes
were made, and you would like to work with the project from the live database without
having to import the project, change the status to "checked in."
Checked Out By: The name of the user that checked out the project. This field is blank
when the Check Out Status is Checked In.
Date Checked Out: The date and time the user checked out the project. This field is
blank when the Check Out Status is Checked In.
Project Web Site URL: The project’s Web site address, if applicable.
Launch: Launches the Web site specified in the Project Web Site URL field.
51 | P a g e ©
www.gaeaglobal.com
Dates tab - Project Details
Use this tab to view or modify dates for the selected project.
Schedule Dates
Project Planned Start: The start date of the project.
Must Finish By: A date constraint placed on the project end date.
When you add a must finish by date, the calendar defaults to the date and time of the
project's finish date. When the Finish is blank, the calendar defaults to the current
system date and time.
When you edit the must finish by date, the calendar defaults to the date and time
currently in the Must Finish By field.
Data Date: The date used as the starting point to calculate the schedule.
Finish: The latest early finish date calculated when P6 Optional Client last scheduled
the project.
Actual Start: The actual start date of the project, if the project has started.
Actual Finish: The actual finish date of the project, if the project has finished—all
activities in the project have actual finish dates.
Anticipated Dates
Anticipated Start: The user-defined date the project is expected to start; used during
the project planning stage, and set at the WBS, EPS, or project level.
Anticipated Finish: The user-defined date the project is expected to finish; used during
the project planning stage, and set at the WBS, EPS, or project level.
Note: The following applies only to a project that has no activities: The application uses
the Project Planned Start date as the Start date if no Anticipated Start is defined; if
Anticipated Start is defined, then it is used as the Start date. The Finish date is blank if
no Anticipated Finish is defined; if Anticipated Finish is defined, then it is used as the
Finish date.
52 | P a g e ©
www.gaeaglobal.com
Notebook tab - Project Details
Use this tab to view or modify project details, such as the project’s purpose, core
requirements, tools or techniques, or any other project-specific information.
Notebook Topic:
A list of topics assigned to the selected node/project. Notebook topics (or categories)
are defined in P6. Mark the checkboxes to make a topic accessible to projects, EPS
nodes, WBS elements, and/or activities. To assign a topic, click Add, select a topic, and
then click Assign.
Detail: Project-specific details for the selected topic. The title of the Detail area is the
notebook topic name. You can only view the notes in this field; to add or edit notes, you
must use the HTML editor.
Modify: Click to add or edit the notes for the selected notebook topic in an HTML
editor. In the editor, you can format text, insert pictures and tables, copy and paste
information from other document files (while retaining formatting), and add hyperlinks.
This button is enabled only when a notebook topic is assigned to the selected project.
Copy: Click to copy the selected text. After copying text, you can paste it into the HTML
editor or into another application. This button is enabled only when a notebook topic is
assigned to the selected project.
Print: Click to print the displayed notes. This button is enabled only when a notebook
topic is assigned to the selected project.
53 | P a g e ©
www.gaeaglobal.com
Codes tab: Project Details
In order to Assign Project Codes, Select the Project and click Code tab in the Project Detail
window(Bottom Layout).
Click Assign Tab to display Assign Project Codes dialogue box. Use the control tab on the
keyboard and select:
Thus the Projects codes are assigned to the Project as shown below.
54 | P a g e ©
www.gaeaglobal.com
Defaults tab – Project Details
55 | P a g e ©
www.gaeaglobal.com
Notes
56 | P a g e ©
www.gaeaglobal.com
7. Creating a Work Breakdown Structure (WBS)
This enables you to divide a project into logical pieces for the purpose of planning and
control.
Note: Child/parent relationships between elements enable lower levels to be rolled up and
summarized.
57 | P a g e ©
www.gaeaglobal.com
To view a WBS for your project(s):
1) Click the Projects menu and choose Open Projects to select a project or group of projects by
EPS node or project code.
a. Select a WBS or project. The WBS can act as a sibling or a parent. The project will
always act as a parent.
c. Double-click in the WBS/Activity field to enter a name for the new WBS.
58 | P a g e ©
www.gaeaglobal.com
3. Click Add in the WBS window
4. Define WBS Code & WBS Name in the WBS Details or in the WBS window as
shown above.
59 | P a g e ©
www.gaeaglobal.com
03 Engineering
01 Structural Drawings
04 Procurement
05 Construction
01 Substructure
01 Basement
02 Ground Floor
02 Superstructure
01 Floor
03 Envelop
04 Finish
05 Services
Configure WBS information to account for any updates or changes made to the WBS.
60 | P a g e ©
www.gaeaglobal.com
1) Open one or more projects in the Projects section using one of the following methods:
Click Projects to open the last project or group of projects you were working with.
Click the Projects menu and choose one of the most-recently used projects or group of
projects.
Click the Projects menu and choose Open Projects to select a project or group of
projects by portfolio type, EPS node, or project code.
3) On the Activities page, select a WBS and click the General detail window.
a. Add the columns you need to configure to the detail window. See Showing and
Hiding Columns in a Table.
5) On the Activities page, click the Actions menu and select Save (Ctrl+S).
61 | P a g e ©
www.gaeaglobal.com
Notes
62 | P a g e ©
www.gaeaglobal.com
8. Adding Activities
Activities are also known as tasks, events, or work packages, activities are the lowest level
manageable work elements in a project or WBS. Activities typically have expected durations,
costs, and resource or role requirements. Milestone activities, however, have no duration or
cost. Collectively, all activities form the foundation of the entire project, driving resource
assignments, relationships, constraints, expenses, and durations. Activities are sometimes
further divided into any number of discrete steps.
The Activity definition includes the identifier and a scope of work description in sufficient
detail to ensure that project team members understand what work is required to be
completed.
63 | P a g e ©
www.gaeaglobal.com
8.1.1 Mandatory Components
WBS & OBS
Activity ID & Description
Activity Type
Duration
Dates
Calendar Assignment
Duration & Percent complete types
It depends on the activity’s function in the project and the calendar used for the activity during
scheduling.
Task Dependent: This type of activity indicates that assigned resources should be scheduled
based on the activity's calendar, rather than the calendars of the resources.
Resource Dependent: This type of activity indicates that resources should be scheduled based
on their assigned calendars. Use this type when the activity duration may be affected by
resource availability.
Level of Effort: This type of activity indicates that it is ongoing with a duration determined by its
dependent activities. The duration is calculated based on the schedule dates of its predecessors
and successors. Administrative activities are typically designated as Level of Effort.
Start Milestone: This type of activity indicates the beginning of a major project phase. Activities
of this type have a duration of zero (0) with no resource assignments.
64 | P a g e ©
www.gaeaglobal.com
Finish Milestone: This type of activity indicates the end of a major project phase. Activities of
this type have duration of zero (0) with no resource assignments.
WBS Summary: A WBS summary activity type represents a group of activities that share a
common work breakdown structure (WBS) level. The summary-level WBS activity enables
the rollup of dates for the activity group. Rollup values for a WBS summary activity are
calculated when the project is scheduled. The duration of a WBS summary activity extends
from the start of the earliest activity in a group to the finish of the latest activity.
To create activities:
1) Open one or more projects in the Projects section using one of the following methods:
Click Projects to open the last project or group of projects you were working
with.
Click the Projects menu and choose one of the most recently used projects or
group of projects.
Click the Projects menu and choose Open Projects to select a project or group of
projects by portfolio type, EPS node, or project code.
65 | P a g e ©
www.gaeaglobal.com
8.4 Add a Notebook topic to an activity
A notebook is another name for a log or binder of electronic details about an activity, WBS,
project, or EPS element. All the notes users enter or paste into the notebook, including e-
mail messages, web links, tables, and other entries, share a single common theme called a
notebook topic.
Notebook topics are typically instructions or descriptions that further describe the activity
according to specific categories of information.
Notebook topics help multiple users apply a common theme or label to shared information
about an activity, WBS, project, or EPS element such as its purpose, completion instructions,
or other helpful notes.
For example, you might copy an e-mail message, a web link, a table of observations, and a
series of text notes into a notebook topic called Budget Recommendations to capture the
ongoing cost impacts of a recurring project
66 | P a g e ©
www.gaeaglobal.com
Assigning Notebook Topics
67 | P a g e ©
www.gaeaglobal.com
8.5 Adding Steps to an Activity
Activity steps allow you create a checklist for the activity, and then track the completion of
each step. Often, steps provide a list of procedures required to complete the activity and
provide extra guidance to resources assigned to the activity.
For example: Three steps are assigned to an activity; the first step has a weight of 2, and the
second and third steps each have a weight of 1. When you mark the first step (weight of 2) as
complete, the percent complete is 50. When you mark the first and second steps complete,
the percent complete is 75. When all three steps are marked complete, the percent
complete is 100.
Step Weights - The higher the value you enter, the greater the importance of the step in the
activity. Based on the total weight for all steps in the activity, the percent for each step is
calculated and displayed in the Step Weight Percent column. Select Physical as the percent
68 | P a g e ©
www.gaeaglobal.com
complete type on the General tab of Activity Details to calculate the percent for each
weighted step.
To create steps:
1) Open one or more projects in the Projects section using one of the following methods:
Click Projects to open the last project or group of projects you were working with.
Click the Projects menu and choose one of the most recently used projects or group of
projects.
Click the Projects menu and choose Open Projects to select a project or group of
projects by portfolio type, EPS node, or project code.
2) On the Projects navigation bar, click Activities.
3) On the Activities page, select an activity you want to break down into smaller parts and click
the Steps detail window.
4) In the Steps detail window, repeat the following for each step you want to add to the
activity:
a. Click Add Activity Step (Insert).
b. Enter a value in the Step Name, Step % Complete, and Step Weight fields.
5) On the Activities page, click the Actions menu and select Save (Ctrl+S).
69 | P a g e ©
www.gaeaglobal.com
Choose Physical as the activity’s percent complete type in the General tab in the
Activities window
Add steps from a step template to add a group of predefined steps to an activity.
1) Open one or more projects in the Projects section using one of the following methods:
Click Projects to open the last project or group of projects you were working with.
Click the Projects menu and choose one of the most recently used projects or group
of projects.
Click the Projects menu and choose Open Projects to select a project or group of
projects by portfolio type, EPS node, or project code.
3) On the Activities page, select an activity and click the Steps detail window.
5) In the Select Activity Step Template dialog box, assign templates and click Close.
6) On the Activities page, click the Actions menu and select Save (Ctrl+S).
70 | P a g e ©
www.gaeaglobal.com
Step templates are created on the Enterprise Data or Enterprise Project Data page.
71 | P a g e ©
www.gaeaglobal.com
For example, assume your organization has many departments and you want to review
activities within each department. You can first create an activity code "department," then
assign different values such as quality assurance, finance, and sales. You can then associate
activities with specific departments.
A key characteristic of an activity code as opposed to an activity user defined field is that
activity codes will only allow entries from a predefined list of values. After you create activity
codes, users can assign activity code values to activities to group, sort, and filter project data
based on these values.
72 | P a g e ©
www.gaeaglobal.com
Notes
73 | P a g e ©
www.gaeaglobal.com
9. Assigning Codes
Project codes help you track different projects based on characteristics they share.
If you have many projects in the hierarchy, project codes help you group and filter potentially
vast amounts of information spanning different areas of the organization.
The application supports an almost unlimited number of hierarchical project codes and values;
you can establish as many as you need to meet the filtering, sorting, and reporting
requirements of your organization.
74 | P a g e ©
www.gaeaglobal.com
9.2 Assign resource code values to resources
With potentially hundreds of resources in use across the enterprise, resource codes provide an
efficient means for tracking and sorting resources for reporting or analysis.
Use this procedure to assign resource codes to resources. Once assigned, you can categorize
resources using codes.
1. Click Resources.
2. On the Resources navigation bar, click Administration.
3. On the Administration page, click the Resources tab.
4. On the Resources tab:
a. Click a resource.
b. Click the Codes detail window.
5. On the Codes detail window, click Add (Insert).
6. On the Select Resource Code dialog:
a. Choose a resource code and click Assign.
75 | P a g e ©
www.gaeaglobal.com
b. Select additional resource codes, if necessary, and click Assign.
Note: You can only select one value from each code name category. If you try to
assign a second value from the same category, the first value will be replaced
with the new value.
c. Click Close.
7. On the Resources tab, click Save (Ctrl+S).
76 | P a g e ©
www.gaeaglobal.com
Project activity codes categorize activities based on specific features within a project.
Activity codes represent broad categories of information, a department or project manager for
instance. You can create multiple activity codes according to specific categories, then assign
different values for each code.
Steps to create project based activity codes:
1. Click the Projects menu and select Enterprise Project Data, or click
the Administer menu and select Enterprise Data.
2. In the Enterprise Data pane, expand Activities and click Activity Codes - Project.
1. Open one or more projects in the Projects section using one of the following
methods:
Click Projects to open the last project or group of projects you were
working with.
Click the Projects menu and choose one of the most recently used
projects or group of projects.
Click the Projects menu and choose Open Projects to select a project
or group of projects by portfolio type, EPS node, or project code.
2. On the Projects navigation bar, click Activities.
3. On the Activities page, select an activity and click the Codes detail window.
4. In the Codes detail window, click Assign (Insert).
5. In the Select Code Value dialog box, assign code values and click Close.
6. On the Activities page, click the Actions menu and select Save (Ctrl+S).
77 | P a g e ©
www.gaeaglobal.com
End of this Chapter
78 | P a g e ©
www.gaeaglobal.com
Notes
79 | P a g e ©
www.gaeaglobal.com
10. Creating Relationships
Relationships define how an activity relates to the start or finish of another activity or
assignment. Sequence Activities is the process of identifying and documenting
relationships among the project activities.
Activities are sequenced using logical relationships. An activity can have as many
relationships as necessary to model the work that must be done.
Every activity and milestone except the first and last are connected to at least one
predecessor and one successor. It may be necessary to use lead or lag time between
activities to support a realistic and achievable project schedule.
80 | P a g e ©
www.gaeaglobal.com
An Activity Network is a graphical display of activities and their logical relationships according
to the WBS. You can use an Activity Network to view activity relationship paths and the flow of
work through a project.
Activity Networks also allow you to examine and edit an activity and its predecessors and
successors.
You can customize the content and arrangement of the boxes that represent your activities in
the network. If you select the Show progress option on the Customize Activity Network dialog
81 | P a g e ©
www.gaeaglobal.com
box or on the Activity Network tab of the Customize Activity View dialog box, you can view
activity progress in the Activity Network. Completed activities are marked with an X across the
activity box. Activities in progress are marked with a slash (\) across the activity box.
82 | P a g e ©
www.gaeaglobal.com
b. Click the View menu and select Show Relationship Lines.
c. Right-click the bar to which you want to assign a relationship and
click Create Relationship.
d. With the cross, click the beginning or end of the bar and then click the
beginning or end of the bar you want to relate.
e. Click the Actions menu and select Save (Ctrl+S).
83 | P a g e ©
www.gaeaglobal.com
Notes
84 | P a g e ©
www.gaeaglobal.com
11. Scheduling the Project
Scheduling is done through critical path method to determine the amount of duration
flexibility (the amount of float) on various logical network paths in the project schedule
network, and to determine the minimum total project duration.
Early start and finish dates are calculated by means of a forward pass, using a specified
start date. Late start and finish dates are calculated by means of a backward pass, starting
from a specified completion date, which sometimes is the project early finish date
determined during the forward pass calculation.
Before scheduling the project, you should confirm the data date. The data date reflects
the date used as a starting point for scheduling the project plan.
When you schedule a project, activity dates are calculated according to durations and
logic.
The Critical Path Method (CPM) scheduling technique is utilized to calculate project schedules. CPM uses
activity durations and relationships between activities to calculate schedule dates. This calculation is
done in two passes through the activities in a project.
85 | P a g e ©
www.gaeaglobal.com
The duration of the activities on the critical path controls the duration of the entire project; a delay to
any of these activities will delay the finish date of the entire project.
Critical activities are defined by either the total float or the longest path in the project network.
86 | P a g e ©
www.gaeaglobal.com
9.2 Float
Free Float (FF): The amount of time a task can be delayed without delaying the early start date
of its successor
Total Float (TF): The amount of time a task can be delayed without affecting a project’s
required due date.
An activity's Total Float is automatically calculated each time you schedule the
project. You cannot edit an activity's float values directly.
87 | P a g e ©
www.gaeaglobal.com
Notes
88 | P a g e ©
www.gaeaglobal.com
12. Understanding Constraints
To apply constraints activate Activity Details. In Activity Details enable Status / Constraints
menu, select the constraint and apply appropriate constraint date. Schedule the project using
Schedule button.
89 | P a g e ©
www.gaeaglobal.com
Start On: Imposes the specific start date you select. The Start On constraint can delay an
activity's early start or move forward an activity's late start to satisfy the constraint date.
Start On or Before: Defines the latest date an activity can start. This constraint only affects late
dates and can decrease total float. When calculating a schedule, P6 imposes the start on or
before constraint in the backward pass only if the calculated late start date will be later than
the imposed date.
Start On or After: Defines the earliest date an activity can begin. This constraint affects only
early dates. When calculating a schedule, P6 imposes the start on or after constraint in the
forward pass only if the calculated early start date will be earlier than the imposed date.
Finish On: Imposes the specific finish date you select. The Finish On constraint can delay an
activity's early finish or move forward an activity's late finish to satisfy the constraint date.
Finish On or Before: Defines the latest time an activity can finish. The finish on or before
constraint affects only late dates.
Finish On or After: Defines the earliest date an activity can finish. The finish on or after
constraint reduces float to coordinate parallel activities, ensuring that the finish of an activity is
not scheduled before the specified date. It is usually applied to activities with few predecessors
that must finish before the next phase of a project.
As Late As Possible: Imposes a restriction on an activity with positive float to allow it to start as
late as possible without delaying its successors. When calculating a schedule, P6 sets the
activity's early dates as late as possible without affecting successor activities. This option
disables the calendar icon.
Mandatory Start: Imposes the early and late start dates you select. P6 uses the mandatory
early start date regardless of its effect on network logic. A mandatory early start date could
affect the late dates for all activities that lead to the constrained activity and all early dates for
the activities that lead from the constrained activity.
Mandatory Finish: Imposes the early and late finish dates you select. P6 uses the mandatory
finish date regardless of its effect on network logic. This constraint affects the late dates for all
activities that lead to the constrained activity and all early dates for the activities that lead from
the constrained activity.
90 | P a g e ©
www.gaeaglobal.com
Notes
91 | P a g e ©
www.gaeaglobal.com
13. Duration Types
Duration type is the basis for estimating an activity's completion time. It determines whether
the schedule, resource availability, or costs are most important when updating activities. The
duration type applies only when you have at least one resource assigned to the activity. Select
one of the following duration types based on which factor is most important (least flexible) in
planning your project: Fixed Duration & Units/Time, Fixed Duration & Units, Fixed Units/Time,
or Fixed Units.
The setting which allows to control how P6 synchronizes the Duration, Labor / Non-Labor
Units and Resource Units / Time for activities so that the following equation is always true :
Duration x Unit / Time = Units
Duration type determines whether the schedule, resource availability, or cost is most inflexible
when calculations are performed to reflect activity progress. Duration type affects update
calculations only when resources are assigned to an activity.
Choose a duration type based on which factor is the most important, or least flexible, in
planning your project.
92 | P a g e ©
www.gaeaglobal.com
When you When you change When you
Activity change Units, Duration, change
Duration Type Units/Time,
P6 changes… P6 changes… P6 changes…
Fixed Units/
Time Duration Units Duration
Fixed duration
& Units / Time Units / Time Units Units
Fixed Duration
& Units Units / Time Units / Time Units
93 | P a g e ©
www.gaeaglobal.com
Notes
94 | P a g e ©
www.gaeaglobal.com
14. Calculating Percent Complete
It determines the way in which the application calculates the percent complete for the activity.
The type can be Units, Duration, or Physical.
If the Percent Complete Type is Units, percent complete is calculated from the actual and
remaining units. If the Percent Complete Type is Duration, the percent complete is calculated
from the actual and remaining duration. If the Percent Complete Type is Physical, the user will
enter the percent complete for the activity.
Establishes the link between Duration %, Remaining duration and Actual resource units.
Physical Type :
95 | P a g e ©
www.gaeaglobal.com
No link is established between Physical %, Remaining duration and Actual Resource units
Units Type :
To indicate the portion of activity work that a single step represents, you can assign it a
numerical value, or weight. Once work for a step is underway, Primavera can use the step
weight and the reported progress of step work (Step Percent Complete) to calculate the
percentage of total work that has been completed for the activity (Activity Percent Complete).
Determines if Activity % Complete is calculated from activity steps or from manual input.
This option is cleared by default. If the option is selected, you must also set Percent Complete
Type to Physical on the Activities page to view the calculation in the Activity % Complete field.
This option also sets the Physical % Complete field calculation to calculate from activity steps
instead of manual input.
For example, if 3 of 4 steps are marked complete, and the steps are weighted equally, the
Activity % Complete and the Physical % Complete is 75%.
96 | P a g e ©
www.gaeaglobal.com
End of this Chapter
97 | P a g e ©
www.gaeaglobal.com
Notes
98 | P a g e ©
www.gaeaglobal.com
15. Roles and Resources
Roles represent personnel job titles or skills needed to execute projects. Architect, general
laborer, quality assurance tester, and engineer are all examples of possible roles. You can
create a standard set of roles that you then assign to labor and non-labor resources and
activities for all projects in the organization. You can establish an unlimited number of roles and
organize them in a hierarchy for easier management and assignment. The set of roles you
assign to an activity defines the activity’s skill requirements. You can also define multiple price
per unit rates and unit per time limits for each role to accurately plan future costs and
allocation.
You can assign one or more roles to individual resources. When you assign roles to a resource,
you also indicate their proficiency in that role and identify which role is their primary role. A
primary role is the main role the resource is currently performing. The proficiency level
describes the resource's skill level in that role. For example, Joe is a resource and fills the role of
both software engineer and manager. He has been a software engineer for 20 years and is 1 -
Master in that role; however, his primary role is manager, which he has been for 5 years and his
proficiency level is 3- Skilled.
Assign roles to activities as you would resources during project schedule and cost planning.
When your plans are finalized, you can replace roles with resources, based on each activity’s
role and skill requirements.
Create a standard set of roles that you can assign to labor and nonlabor resources and
activities.
To create roles:
1) Click Resources.
99 | P a g e ©
www.gaeaglobal.com
2) On the Resources navigation bar, click Administration.
a. Click Add (Insert), or click an existing role and click Add Child to add a role in a
hierarchy. A new row is added to the Roles table.
b. In the ID field, click and type a unique identifier for the new role.
d. To create or modify a hierarchy of roles, use the arrows on the toolbar to position the
new row.
For example, if a Project Manager role exists in the system and you just created a Design
Manager role, which is a type of Project Manager, use the up/down arrows to position
the new Design Manager role under Project Manager, and then click the right arrow to
indent the new row.
7) In the Prices detail window, click in a rate type field and enter the rate. Repeat for all
applicable rate fields.
a. Click Add (Insert) to define the units/time for the role over time.
b. In the Effective Date field, double-click and select the effective date on the calendar.
c. In the Max Units/Time field, click and type the maximum work units per time for this
role.
100 | P a g e ©
www.gaeaglobal.com
10) On the Roles tab, click Save (Ctrl+S).
A resource is any quantifiable item in limited supply and of sufficient value to justify tracking
and assigning to specific activities for a project. Resources include general or specialized labor,
non-labor items such as equipment, and material items such as bricks.
Resources perform roles, if defined. Resources are indirectly assigned to activities by first
planning the role required. It is also possible to directly assign resources to activities. For
example, Chris, a level 2 contractor with the confirmed skills and status, is directly assigned to
activity 01. However, a technician level 4 role is assigned to activity 02. The project will proceed
while management determines the best available resource to fulfill this role.
Resource Details
Indicates the resource is Labor, Non-labor or Material.
Utilized for material resources. Select to determine what unit
the resource utilizes.
Indicates the currency associated with the resource's costs.
Calendar used to identify resource availability.
101 | P a g e ©
www.gaeaglobal.com
Indicates the units/time that will be applied when the
resource is assigned to an activity.
Mark to automatically calculate the resource's actual
quantity of work according to the project plan.
Mark to calculate the cost of an activity based on
the assigned units.
The effective start date for price and availability.
A numeric value or percentage the resource can perform in a
single work period, according to effective date, e.g., 8 hid (100%) full-time or 4
hid (50%) part-time. Setting this limit allows you to quickly identify areas of
resource over allocation in resource profiles spreadsheets.
Set the resource's price for a single work unit, according to the
effective date.
Use this task to add resources to the resource pool. Resources include the personnel and
equipment that perform work on activities across all projects. Resources are generally reused
between activities and/or projects. Resources can be distinguished as either labor, material, or
nonlabor. Labor and nonlabor resources are always time-based, and material resources, such as
consumable items, use a unit of measure you can specify.
To add a resource:
1) Click Resources.
a. Click Add (Insert), or click an existing resource and click Add Child to add a resource in
a hierarchy. A new row is added to the table.
102 | P a g e ©
www.gaeaglobal.com
6) On the Resources tab:
a. Click Select Columns and select any additional column headings that you need in your
view.
7) In the Notes detail window, type any notes you want to capture for the resource.
103 | P a g e ©
www.gaeaglobal.com
Use the Settings detail window available from the Administration Resources tab to define
settings for the resource, such as the resource calendar and default units/time, as well as P6
Progress Reporter settings.
1) Click Resources.
4) On the Resources tab, select the resource for which you want to define general settings.
5) Click the Settings detail window, review the following options and make selections based on
your project needs.
Default Units/Time: Use the default value or change the default units/time value. Enter these
values as units per duration or as a percentage, depending on your choice in the Units/Time
Format area of the My Preferences page.
Overtime Allowed: Select to enable the labor resource to record overtime hours for activities.
Overtime Factor: Type the number by which the resource's standard price should be multiplied
to determine the resource's overtime price.
Auto Compute Actuals: Select to automatically calculate the selected resource's actual quantity
of work according to the project plan rather than reported hours in P6 Progress Reporter. Clear
this option if you plan to select Uses Timesheets.
Currency: Click to select a currency that is different from the default currency, and click OK.
Calculate Costs from Units: Select this option to indicate that any new assignment for this
resource will have its cost recalculated whenever any quantity changes occur, such as changing
an activity's remaining duration.
104 | P a g e ©
www.gaeaglobal.com
Progress Reporting Settings: Applicable when progress reporter is configured.
105 | P a g e ©
www.gaeaglobal.com
Notes
106 | P a g e ©
www.gaeaglobal.com
16. Assigning Roles
Assign roles to an activity to show which roles are needed to perform the work required for an
activity. Perform these steps to assign one or more roles to an activity.
The Assignments detail window enables you to see all resources and roles assigned to
any activity. You can also assign roles to an activity from the Actions menu on
the Activities page.
107 | P a g e ©
www.gaeaglobal.com
16.2 Assigning Rates to Roles
Use this procedure to assign rates to the roles you created. Assigning rates to roles enables you
to more accurately determine total resource (and activity) costs. You can assign up to five rate
types depending on number of rate types set up by your administrator.
108 | P a g e ©
www.gaeaglobal.com
End of this Chapter
109 | P a g e ©
www.gaeaglobal.com
Notes
110 | P a g e ©
www.gaeaglobal.com
17. Assigning Resources and Cost assignment
111 | P a g e ©
www.gaeaglobal.com
17.2 Assign Resources to Activities
1. Click Projects.
2. On the Projects navigation bar, click Activities.
3. On the Activities page, select the activity to which you want to assign one or
more resources and click the Assignments detail window.
4. In the Assignments detail window, click Assign Resource and
Save (Ctrl+Alt+R).
5. In the Select Resource dialog box:
a. Select the resource and click Assign.
b. Select any additional resources needed for the activity and click Assign.
c. Click Close when you are finished.
112 | P a g e ©
www.gaeaglobal.com
When you assign a resource to an activity that does not have any resource
assignments, the resource is identified as the primary resource.
113 | P a g e ©
www.gaeaglobal.com
4) On the Resources tab:
a. Click a resource.
b. Click the Units and Prices detail window.
5) In the Units and Prices detail window:
a. Click Add (Insert).
b. In the Effective Date field, double-click to open the calendar and choose a date to
start the new rate.
c. In the Max Units/Time field, double-click and type the maximum work units per time
for this resource.
d. In the appropriate price fields, double-click and type an amount. The default time
period is price per hour unless you specify another time period.
6) On the Resources tab, click Save (Ctrl+S).
114 | P a g e ©
www.gaeaglobal.com
17.4 Assign Expenses to activities
About Expenses
Expenses are non-resource costs associated with a project and assigned to a project’s activities.
An expense is typically a one-time expenditure for non-reusable items. Expenses are project-
specific and not time-based. Some examples include facilities, travel, consulting, and training.
Each expense has an actual, remaining, and at completion value for both cost and units that is
either budgeted or planned.
Expense categories classify and standardize expenses, and organize and maintain your expense
information.
Create expenses to show costs that you expect each activity to accrue.
To create expenses:
1) Open one or more projects in the Projects section using one of the following methods:
Click Projects to open the last project or group of projects you were working with.
Click the Projects menu and choose one of the most-recently used projects or group of
projects.
Click the Projects menu and choose Open Projects to select a project or group of
projects by portfolio type, EPS node, or project code.
3) On the Activities page, select an activity and click the Expenses detail window.
5) On the Activities page, click the Actions menu and select Save (Ctrl+S).
115 | P a g e ©
www.gaeaglobal.com
End of this Chapter
116 | P a g e ©
www.gaeaglobal.com
Notes
117 | P a g e ©
www.gaeaglobal.com
18. Analyzing Resources
The Resources Analysis section enables you to compare resource utilization and analyze
resource allocations.
Define the profile to specify whether you want to display cost or quantity information and set
the timescale for displaying data values. Choose to display past period actual or actual to date
values in bars and curves. Choose to display vertical bars to represent costs or units allocated to
your resources for each time period, and include cumulative curves to represent accumulated
units and costs over time.
118 | P a g e ©
www.gaeaglobal.com
Determine resource usage by late dates
Display a "banana" curve to compare early and late dates
Display different colors or patterns on the histogram bars when showing the stacked
histogram
In addition to customizing data, you can customize the look of the profile by specifying display
options, for example, bar color, background line type, or averaging. You can also save a
customized profile so that you can always access the same set of activity information or share
the Resource Usage Profile with someone else.
The Resource Usage Profile is available only in the bottom layout of the Activities window. The
bottom layout window is divided into two panes.
The left pane lists all the resources or roles stored in the hierarchy, depending on your
current view. In the stacked histogram view, the left pane lists all the resource or role
filter/group names in the hierarchy.
The right pane displays the values for the activities assigned to each resource or role in
the histogram, or resource or role filter/group name in the stacked histogram.
When displaying units, bars do not display for summary rows if your selection contains
mixed units of measure or a mixture of labor/ nonlabor and material type resources.
Bars and cumulative curves with negative values do not display in the profile. You can
view the negative values.
The Resource Usage/Role Profile Options dialog box contains the following tabs:
Data tab - Resource Usage/Role Profile Options dialog box - for regular
histograms
Graph tab - Resource Usage/Role Profile Options dialog box
119 | P a g e ©
www.gaeaglobal.com
In addition, the following buttons are available in the Resource Usage/Role Profile Options
dialog box:
Apply: Applies the selected Resource Usage/Role Profile settings without closing this dialog
box.
Preferences: Opens the Resource Analysis tab in the User Preferences dialog box so you can set
preferences for the Resource Usage/Role Profile
18.2.1 Data tab - Resource Usage/Role Profile Options dialog box - for regular
histograms
Use the Resource Usage/Role Profile Options Data tab for regular histograms to specify the
information to include in a resource profile when viewing allocation for projects by resource or
by role. To specify whether you want to view the resource profile by role or by resource, in the
Resource Explorer window, click the Display Options bar, then choose Select View and the
option you want.
Display
Units: Choose to display the resource profile bars in terms of project units.
Cost: Choose to display the resource profile bars in terms of project costs.
120 | P a g e ©
www.gaeaglobal.com
Display Actual using Financial Period data: Mark to display past period actuals stored in
financial period intervals for the actual bar and curve. When you choose this option, stored
financial period actuals are distributed evenly, within each financial period, from the financial
period start date to the financial period end date.
If you do not choose this option, the profile spreads actual to date values evenly from the
actual start to the data date or actual finish date of the activity or assignment
Show Bars/Curves
Budgeted or Planned: Mark to show budgeted or planned values by date for each time unit in
the current layout, or show values cumulatively, as a horizontal curve. Click the Color button to
select the color used to display budgeted or planned values.
Actual: Mark to show actual values for each time unit in the current layout, or show values
cumulatively, as a horizontal curve. Click the Color button to select the color used to display
actual values.
Remaining Early: Mark to show remaining early values for each time unit in the current layout,
or show values cumulatively, as a horizontal curve. In the Show Remaining Bars As section,
select the option and bar color you want to use to show remaining units.
Remaining Late: Mark to show remaining late values for each time unit in the current layout, or
show values cumulatively, as a horizontal curve. In the Show Remaining Bars As section, select
the option and bar color you want to use to show remaining units.
Total Remaining: Choose this option to show remaining values for all projects as a single bar. To
select the color used to display total remaining early and late values, click the Color button. The
selected color will also display for the remaining early and late bar/curve.
Staffed vs. Unstaffed: (Role view only) Choose this option to use different bar colors to
represent remaining values for staffed versus unstaffed projects. To select colors, click each
Color button for the early and late values. The left button represents the staffed projects
bar/curve color and the right button represents the unstaffed projects bar/curve color.
Open vs. Closed Projects: Choose this option to use different bar colors to represent remaining
values for open versus closed status projects. To select colors, click each Color button for the
early and late values. The left button represents the open project bar/curve color and the right
button represents the closed projects bar/curve color.
121 | P a g e ©
www.gaeaglobal.com
Additional Data Options
Show Limit: Mark to display the resource's maximum units for each time unit in the current
layout. This option is available only if you choose to display Units.
Show Overallocation: Mark to display overallocated values in the current layout. This option is
available only if you choose to display Units and select Show Limit. If you select the option to
Display Actual using Financial Period data, the displayed overallocation represents past period
actual values.
ShowAvailable Units: Mark to display a horizontal line that indicates the resource's available
units. This option is available only if you choose to display All Projects. If you select the option
to Display Actual using Financial Period data, the displayed available units represent past period
actual values.
Show Overtime: Mark to show the resource's overtime units for each time unit in the current
layout. This option is available if you choose to display open projects only.
Use the Resource Usage/Role Profile Options Graph tab to specify how information is presented
in a resource profile when viewing resource allocation for projects by role or by resource. To
specify how you want to view resources in a resource profile, in the Resource Explorer window,
click the Display Options bar, then choose Select View and the option you want.
122 | P a g e ©
www.gaeaglobal.com
Vertical Lines
Major: Mark to display vertical lines to indicate major time units in the current layout.
Minor: Mark to display vertical lines to indicate minor time units in the current layout.
Horizontal Lines
Dotted: Choose to display horizontal lines as dotted lines in the current layout.
Solid: Choose to display horizontal lines as continuous lines in the current layout.
LineColor: Click to change the display color of horizontal lines in the current layout.
123 | P a g e ©
www.gaeaglobal.com
Calculate Average: Mark to specify the values you want to use to divide the timescale interval
totals.
Divide Interval Totals By: To divide the timescale interval totals by an increment you specify,
type it in this field.
Base on Hours Per Timeperiod: To divide the timescale interval totals by automatic increments,
based on the date interval selected, mark this checkbox. When you choose this option, the
Divide Interval Totals By field displays the division increment based on the division increment
specified in User Preferences for the corresponding date interval: 1h for Hour date interval, 2h
for Shift date interval, 8h for Day date interval, 40h for week date interval, and so on.
Unit of Measure: Specify the unit of measure for the timescale intervals.
124 | P a g e ©
www.gaeaglobal.com
manually enter values for budgeted or planned and remaining (early) units in the spreadsheet.
When you choose to display information for all projects, the bottom layout is divided into two
panes.
The left pane lists all the resources or roles stored in the hierarchy, depending on your
current view.
The right pane displays the values for the activities assigned to each resource or role.
When you choose to display information only for a specific project, the bottom layout is
divided into three panes.
The left pane lists all the resources or roles stored in the hierarchy, depending on you
current view.
125 | P a g e ©
www.gaeaglobal.com
The middle pane displays all of the activity assignments for the resource or role
currently selected in the left pane.
The right pane displays the values for the activities assigned to the resource or role
currently selected in the left pane.
In the Resource Assignments window, the Resource Usage Spreadsheet is available in the right
pane.
You can group, sort, or filter the resources or roles displayed in the Resource Usage
Spreadsheet.
Use the Spreadsheet Options dialog box in the Activity Usage Spreadsheet and Resource Usage
Spreadsheet to display the timescale based on an average value you specify.
Calculate Average: Mark to specify the values you want to use to divide the timescale interval
totals.
Divide Interval Totals By: To divide the timescale interval totals by an increment you specify,
type it in this field.
Base on Hours Per Time period: To divide the timescale interval totals by automatic
increments, based on the date interval selected, mark this checkbox. When you choose this
option, the Divide Interval Totals By field displays the division increment based on the division
increment specified in User Preferences for the corresponding date interval: 1h for Hour date
interval, 2h for Shift date interval, 8h for Day date interval, 40h for week date interval, and so
on.
Unit of Measure: Specify the unit of measure for the timescale intervals.
126 | P a g e ©
www.gaeaglobal.com
Notes
127 | P a g e ©
www.gaeaglobal.com
19. Baselining the Project Plan
A baseline is a copy, or snapshot, of project data at a given time. Because a baseline is a static
representation of a project plan, it can be used as a benchmark against which to measure
performance as a project progresses.
You can create multiple baselines to establish metrics throughout the project life cycle.
Typically, you would want to create an initial baseline once the project plan is approved, then
you would create additional baselines according to your organization's requirements. For
example, you could create new baselines at specific reporting intervals.
Although many baselines can be created for a project, only two baselines can be used at any
given time to display and compare data. These are known as the Project Baseline and User's
Primary Baseline. The current project can also be used as the baseline, for example, in
situations where no other baseline yet exists.
The Project Baseline is a single metric for comparison that enables all members of a team to
have a shared and consistent set of data against which to evaluate project progress. There is
only one Project Baseline at any time. All pages that display summarized data compare and
display data against the Project Baseline.
The User's Primary Baseline is an optional personal baseline that is used to evaluate project
progress.
128 | P a g e ©
www.gaeaglobal.com
To help categorize, or track, multiple baselines for a single project, you can assign each baseline
a type that reflects its purpose, for example, initial planning baseline, What-if project baseline,
customer sign-off, or midproject baseline.
Regardless of the number of baselines you store for a project, at any given time you can only
select at most two baselines for use in making comparisons in P6. The project-level baseline is
used for project/activity usage spreadsheets and profiles, as well as for earned value
calculations.
You can convert another project in the EPS hierarchy to a baseline for use in comparisons with
the current project. Before converting a project to a baseline, if you still want to have access to
the original project, you should make a copy of it. Once you convert a project to a baseline, it is
no longer available in the project hierarchy. You can restore a baseline, making it available
again as a separate project in the project hierarchy, in order to modify it or update it.
Note: You must have the Edit Project Details Except Costs/Financials and Assign Project Baseline
project privileges to set the project baseline.
Add Baselines: When you add a baseline, give it a name, assign it a type, and decide if
you want to make it the Project Baseline or User's Primary Baseline for the currently
129 | P a g e ©
www.gaeaglobal.com
selected project. Baseline designations are made in the projects rows of the table
highlighted in blue.
Convert a Project to Baseline: Save a copy of the baseline before you convert it.
Convert a project to use it as a baseline for a current project.
Restore a Baseline: Use restore a baseline to modify a baseline project. You must first
unlink a baseline from its current project by restoring it as a separate project. You can
then work with this restored baseline project as you would any other project in the
EPS.
Baseline Type: Assign baseline types to baselines to help categorize multiple baselines
for a single project. Configure the available baseline types along with your other
Enterprise Data settings.
Project Baseline: Lists the available baselines for the selected project. Select the
baseline to use as the project baseline. If a baseline does not exist, the current project
is the default value.
User's Primary Baseline: Select the user's primary baseline from the list of available
baselines. If a baseline does not exist, the current project is the default value.
To create a baseline:
1) Open the project or projects for which you want to create a baseline using one of the
following methods:
Click Projects to open the last project or group of projects you were working with.
Click the Projects menu and select one of the most-recently used projects or group of
projects.
Click the Projects menu and select Open Projects to select a project or group of projects
by portfolio type, EPS node, or project code.
130 | P a g e ©
www.gaeaglobal.com
2) On the Project Navigation bar, click Activities or EPS.
3) On the Activities or EPS page, click the Actions menu and select Define Baselines....
Note:
The application automatically assigns the baseline a name based on the selected
project. For example, if you select Project A, the application will name the newly
created baseline A - B1.
Specify the default Project Baseline and User's Primary Baseline by selecting from the
list of available baselines for each project in the table on the Baselines dialog box.
131 | P a g e ©
www.gaeaglobal.com
Click Convert a Project to Baseline and select a project to convert a project into a
baseline.
Select a baseline and click Restore a Baseline to remove the baseline and make it a
project.
To restore a baseline
132 | P a g e ©
www.gaeaglobal.com
The project-level baseline is used for project/activity usage spreadsheets and profiles, as well as
for earned value calculations.
133 | P a g e ©
www.gaeaglobal.com
Notes
134 | P a g e ©
www.gaeaglobal.com
20. Updating Baseline
Use the Update Baseline dialog box to update project- and activity-level data types for the
baseline you selected in the Maintain Baselines dialog box.
Specify the type(s) of project data to update for the baseline. You do not have to select any of
the available options.
Note: For added control and flexibility as well as enhanced system performance while updating
project baselines, you can select to update specific User Defined Fields (UDFs) rather than
updating all UDFs simultaneously.
Project UDFs: Mark to update and include project UDFs in the updated baseline.
Work products and documents: Mark to include, in the updated baseline, data related to
products and documents developed as part of the project.
Work products and document UDFs: Mark to update and include UDFs of project-related
products and documents in the updated baseline.
WBS UDFs: Mark to update and include WBS UDFs in the updated baseline.
135 | P a g e ©
www.gaeaglobal.com
Project risks, issues and thresholds: Mark to update and include, in the updated baseline, UDFs
related to risks, issues, and thresholds. For example, selecting this option causes a UDF that
describes an issue triggered by a deviation in a cost variance threshold to be updated and
included in the baseline update.
Risk UDFs: Mark to update and include risk UDFs in the updated baseline. This option isolates
and updates risk UDFs only.
Issue UDFs: Mark to update and include issue UDFs in the updated baseline. This option isolates
and updates issue UDFs only.
Choose to update data for all activities or activities that meet a filter's criteria.
Activities within the following filter: Updates filtered activities. Click the browse button to
select a filter.
Add new activities and activity data (except actuals): Mark to add new project activities and
activity data (except actual units and costs) to the baseline. If you apply a filter, the module will
add only new activities that meet the selected filter's criteria.
Delete from baseline any activities no longer in the current project: Mark to delete activities
from the baseline that have been removed from the current project.
Update existing activities already in the baseline: Mark to update activities in the baseline with
activity data that has been modified or added in the current project. If you select this option,
click Update Options to select the types of activity and resource/role assignment data to
update.
Update Options: If you choose to update existing activities already in the baseline, click this
button to open the Update Baseline Options dialog box. In the Update Baseline Options dialog
box, you can select the types of activity and resource/role assignment data you want to update.
This button is disabled unless you choose to update existing activities.
136 | P a g e ©
www.gaeaglobal.com
Notes
137 | P a g e ©
www.gaeaglobal.com
21. Activity Usage Profile and Spreadsheet
The Activity Usage Profile can display labor, nonlabor, material, and expense costs and labor
and nonlabor units allocated to the activities in your project over time. Costs and units
allocated to activities for each period in the timescale are represented as vertical bars. You can
also display curves for charting cumulative costs or units over time.
138 | P a g e ©
www.gaeaglobal.com
Save any of these changes so that you can always access the same set of activity
information, or share your Activity Usage Profile with someone else.
You can filter the Activity Usage Profile to include all activities displayed in the top layout, or to
include only the activities you select in the top layout. You can also filter the top layout to
display only those activities that correspond to the timeperiod you select in the bottom layout.
If you apply activity filters to the Activity Table, Gantt Chart, Activity Usage Spreadsheet,
or the Activity Network, these filters also apply to the Activity Usage Profile.
Use the Project/Activity Usage Profile Options dialog box to view and edit the data in a Project
Profile or Activity Usage Profile.
In addition, the following button is available in the Project/Activity Usage Profile Options dialog
box:
Apply: Applies the selected Project/Activity Usage Profile settings without closing this dialog
box.
139 | P a g e ©
www.gaeaglobal.com
21.2.1 Data tab - Project/Activity Usage Profile Options dialog box
Display
Display actual and earned value using financial period data: Mark to display past period actual
values (rather than actual to date values) stored in financial period intervals for the Actual bar
and curve, Planned Value curve, Earned Value curve, and Estimate at Completion curve. When
you choose this option, stored past period actuals are distributed evenly, within each financial
period, from the financial period start date to the financial period end date, and earned value
calculations are based on these stored period quantities.
140 | P a g e ©
www.gaeaglobal.com
If you do not choose this option, the profile spreads actual to date values evenly from the
actual start to the data date or actual finish date of the activity or assignment.
Labor: Mark to display labor units or costs, depending on the selected display option, then
select the fill pattern for displaying labor information.
Nonlabor: Mark to display nonlabor units or costs, depending on the selected display option,
then select the fill pattern for displaying nonlabor information. You can select a new fill pattern.
Material: Mark to display material costs, depending on the selected display option, then select
the fill pattern for displaying material information.
Expenses: Mark to display expense costs, then select the fill pattern for displaying expense
information. The Expenses checkbox is available only if the selected display option is Cost.
Total: Mark to display total costs (Total = Labor + Nonlabor + Expenses). The Total checkbox is
available only if the selected display option is Cost.
Show Bars/Curves
Baseline: Mark to show primary baseline values by date for each time unit in the current layout,
or show values cumulatively, as a horizontal curve. Click the Color button to select the color
used to display baseline information.
Budgeted or Planned: (Activity Usage Profile only) Mark to show budgeted or planned values
by date for each time unit in the current layout, or show values cumulatively, as a horizontal
curve. Click the Color button to select the color used to display budgeted or planned values.
Actual: Mark to show actual values by date for each time unit in the current layout, or show
values cumulatively, as a horizontal curve. Click the Color button to select the color used to
display actual values.
Remaining Early: (Activity Usage Profile and Activity Profile only) Mark to show remaining early
values by date for each time unit in the current layout, or show values cumulatively, as a
horizontal curve. Click the Color button to select the color used to display remaining early
values.
Remaining Late: (Activity Usage Profile and Activity Profile only) Mark to show remaining late
values by date for each time unit in the current layout, or show values cumulatively, as a
horizontal curve. Click the Color button to select the color used to display remaining late values.
141 | P a g e ©
www.gaeaglobal.com
Show Earned Value Curves
Planned Value Cost / Labor Units: Mark to show, as a curve, the portion of the budgeted or
planned total cost or units scheduled to be completed as of the project data date.
Earned Value Cost / Labor Units: Mark to show, as a curve, the portion of the budgeted or
planned total cost or units actually completed as of the project data date.
Estimate at Completion Cost (EAC) / Labor Units: Mark to show, as a curve, the estimated cost
or units at completion.
Vertical Lines
Major: Mark to display vertical lines to indicate major time units in the current layout.
Minor: Mark to display vertical lines to indicate minor time units in the current layout.
Horizontal Lines
142 | P a g e ©
www.gaeaglobal.com
Dotted: Choose to display horizontal lines as dotted lines in the current layout.
Solid: Choose to display horizontal lines as continuous lines in the current layout.
LineColor: Click to change the display color of horizontal lines in the current layout.
ShowLegend: Mark to display a box containing definitions of each color in the current layout.
Calculate Average: Mark to specify the values you want to use to divide the timescale interval
totals.
Divide Interval Totals By: To divide the timescale interval totals by an increment you specify,
type it in this field.
Base on Hours Per Timeperiod: To divide the timescale interval totals by automatic increments,
based on the date interval selected, mark this checkbox. When you choose this option, the
Divide Interval Totals By field displays the division increment based on the division increment
specified in Admin Preferences for the corresponding date interval: 1h for Hour date interval,
2h for Shift date interval, 8h for Day date interval, 40h for week date interval, and so on.
Unit of Measure: Specify the unit of measure for the timescale intervals.
143 | P a g e ©
www.gaeaglobal.com
The Activity Usage Spreadsheet displays activity data in a spreadsheet format. View baseline,
budgeted or planned, actual, remaining, and at completion values or review information such
as earned value cost, actual labor and nonlabor units, and remaining total cost for the activities
in your project.
Display the Activity Usage Spreadsheet in the top or bottom layout of the Activities
window.
Use the Activity Usage Spreadsheet to
Quickly analyze activity data
Filter activities
Group and sort activity data
The Activity Usage Spreadsheet is split into two panes. The left pane displays the Activity Table,
including all the columns, grouping, sorting, and filtering options defined for the Activity Table.
The right pane displays timescaled spreadsheet data for each activity; you can specify the data
fields you want to include.
Use the Spreadsheet Options dialog box in the Activity Usage Spreadsheet and Resource Usage
Spreadsheet to display the timescale based on an average value you specify.
144 | P a g e ©
www.gaeaglobal.com
Calculate Average: Mark to specify the values you want to use to divide the timescale interval
totals.
Divide Interval Totals By: To divide the timescale interval totals by an increment you specify,
type it in this field.
Base on Hours Per Timeperiod: To divide the timescale interval totals by automatic increments,
based on the date interval selected, mark this checkbox. When you choose this option, the
Divide Interval Totals By field displays the division increment based on the division increment
specified in User Preferences for the corresponding date interval: 1h for Hour date interval, 2h
for Shift date interval, 8h for Day date interval, 40h for week date interval, and so on.
Unit of Measure: Specify the unit of measure for the timescale intervals.
145 | P a g e ©
www.gaeaglobal.com
Notes
146 | P a g e ©
www.gaeaglobal.com
22. Advanced Scheduling and other Schedule related features
Schedule projects to keep track of activities, actual durations, and costs. Knowing where these
stands will help you when making decisions and predictions about the project.
147 | P a g e ©
www.gaeaglobal.com
Calculate multiple float paths option
Determines whether to calculate multiple critical float paths (sequences of activities) in the
project schedule.
Calculate multiple paths using options
Determines whether to calculate multiple paths using Total Float or Free Float.
Total Float: Based on the activity you want the paths to end on, P6 determines which
predecessor activity has the most critical Relationship Total Float on the backward pass. This
process repeats until an activity is reached that has no relationship. P6 begins the forward
pass from this activity and determines which successor activity has the most critical
Relationship Successor Total Float. These activities represent the most critical float path.
The process begins again until the remaining sub-critical paths are calculated.
Free Float: Defines critical float paths based on longest path. The most critical path will be
identical to the critical path that is derived when you select Define critical activities as:
Longest Path on the General tab. In a multi-calendar project, the longest path is calculated
by identifying the activities that have an early finish equal to the latest calculated early
finish for the project and tracing all driving relationships for those activities back to the
project start date. After the most critical path is identified, P6 will calculate the remaining
sub-critical paths.
148 | P a g e ©
www.gaeaglobal.com
These options are applied to all open projects; close or open projects to control which
projects are configured. You can select any activity in the Display Multiple Float Paths ending
with activity dialog box; however, typically this activity is a milestone or some other major
activity in the project schedule.
To optimize performance, type a low number (10 or less) in the Specify the number of paths to
calculate field.
149 | P a g e ©
www.gaeaglobal.com
P6 stores your selection at the user-level and applies it to all projects you open and
schedule.
When scheduling progressed activities use option
Determines the type of logic used to schedule dependent activities with out-of-sequence
progress. For example, a Finish to Start relationship in which the predecessor has not
finished but the successor has started.
Retained Logic: In this logic, the remaining duration of a progressed activity is not scheduled
unless and until all of its predecessors are completed.
Progress Override: The schedule ignores network logic and allows the activity to progress
without delay.
Actual Dates: Backward and forward passes are calculated using actual dates
150 | P a g e ©
www.gaeaglobal.com
22.3 Schedule Preview .
After modifying activity, relationship, and assignment data, but before deciding to formally
schedule a project, use the optional Schedule Preview feature to estimate schedule changes
without actually committing them to the project.
Schedule Preview automatically recalculates the schedule for activities that have changed or
were affected by a change to a relationship, resource assignment, or another activity.
You can then decide to commit these changes to the schedule or, if the preview produces
unwanted results, discard them.
If Schedule Preview is disabled, changes to activities are not reflected in the schedule until you
manually calculate the schedule again.
The Schedule Preview icon is disabled if more than one project is open, or if you do
not have the Schedule Project privilege for the open project.
To turn Schedule Preview mode off, click the Actions menu and select Run Schedule
Preview again so it is not highlighted on the Run menu.
1) Click Projects.
2) On the Projects navigation bar, click Activities.
3) On the Activities page, click the Actions menu and select Run Check Schedule
151 | P a g e ©
www.gaeaglobal.com
It checks the current schedule for any unrealistic scenarios and provides a detailed Output
Schedule Checker Report
152 | P a g e ©
www.gaeaglobal.com
Notes
153 | P a g e ©
www.gaeaglobal.com
23 Adding Notebook Topics and Cost accounts
Notebook topics are created by the administrator on the Enterprise Data page of the
Administer menu. These topics are then assigned to activity, WBS, project, or EPS node
notebooks.
Notebook topics help multiple users apply a common theme or label to shared information
about an activity, WBS, project, or EPS element such as its purpose, completion instructions, or
other helpful notes. For example, you might place an e-mail message, a web link, a table of
observations, and a series of text notes into a notebook topic called Budget Recommendations
to capture the ongoing cost impacts of a recurring project.
1) Click Projects.
3) On the EPS page, select a project or EPS node and click the Notebooks detail window.
5) In the Select Notebook Topic dialog box, select a notebook topic, click Assign, then Close.
6) On the EPS page, click the Actions menu and select Save (Ctrl+S).
154 | P a g e ©
www.gaeaglobal.com
Notebook Topic assigned to projects
155 | P a g e ©
www.gaeaglobal.com
Notebook Topic assigned to activities
You can also create notebook topic descriptions. In the Notebooks detail window,
double-click the Description field and click (browse). Enter a description in the dialog box. You
can also assign notebook topics to activities from the Notebooks detail window of the Activities
page or the Activity Details page of the Open Requests for Resources portlet of the Dashboards
page.
156 | P a g e ©
www.gaeaglobal.com
23.2 About Cost Accounts
Cost accounts enable you to monitor project expenses, activity costs, and earned value
throughout the project life cycle. Costs are attached to activities and resources so you can track
the amount of work accomplished against the amount of money spent. You can assign default
or created cost accounts to any project.
Cost accounts are established in a hierarchy. For example, if you created a cost account for a
project component such as hardware, you would create other cost accounts beneath this
component to show its parts such as coding and installation.
1) Click the Projects menu and select Enterprise Project Data, or click the Administer menu and
select Enterprise Data.
2) In the Enterprise Data pane, expand Activities and click Cost Accounts.
157 | P a g e ©
www.gaeaglobal.com
b. Move the cost account to the correct location in the list and hierarchical position by
clicking the Move Up (Ctrl+Alt+Up), Move Down (Ctrl+Alt+Down), Move Left
(Ctrl+Alt+Left), and Move Right (Ctrl+Alt+Right) arrows.
4) In the Description detail window, type a brief narrative about the cost account.
Click the Projects menu and select Enterprise Project Data, or click the Administer menu
and select Enterprise Data.
In the Enterprise Data pane, expand Activities and click Expense Categories.
1) Click the Projects menu and select Enterprise Project Data, or click the Administer menu and
select Enterprise Data.
2) In the Enterprise Data pane, expand Activities and click Expense Categories.
158 | P a g e ©
www.gaeaglobal.com
To change an expense category, double-click it, then type a new name. The change
applies to all projects to which the expense item is assigned.
159 | P a g e ©
www.gaeaglobal.com
Notes
160 | P a g e ©
www.gaeaglobal.com
24. User-Defined Fields and Global Change
User defined fields allow you to create and maintain data specific to your organization. For
example, you can track additional activity data, such as delivery dates and purchase order
numbers. You can also track additional resource data or project cost-related data, such as
profit, variances, and revised budgets. User defined fields are global, so they can be used across
all projects in your organization.
You can also create project user defined fields. Project user defined fields track information
specific to projects. For example, your organization might require a custom field to track project
profit. Project user defined fields are unique in that you can define a formula or statement to
automatically calculate field values, and identify graphical indicators to display for a field, based
on its value.
Projects
WBS elements
Activities
Steps
Expenses
Issues
Resources
Resource Assignments
Risks
Documents
The majority of the custom fields you create will have only two main properties: a name and a
data type. Project and activity UDFs will also support custom formulas and graphical indicators
based on calculations.
161 | P a g e ©
www.gaeaglobal.com
162 | P a g e ©
www.gaeaglobal.com
24.1.1 Creating Activity UDFs
Create activity user defined fields (UDFs) if the predefined fields do not meet your needs.
1) Click the Projects menu and select Enterprise Project Data, or click the Administer menu and
select Enterprise Data.
2) In the Enterprise Data pane, expand Activities and click Activity UDFs.
c. In the Data Type field, double-click and choose a type from the list.
163 | P a g e ©
www.gaeaglobal.com
1) Click the Resources menu and select Enterprise Resource Data, or click the Administer menu
and select Enterprise Data.
2) In the Enterprise Data pane, expand Resources and click Assignment UDFs.
c. In the Data Type field, double-click and choose a type from the list.
Create document user defined fields (UDFs) if the predefined fields do not meet your needs.
1) Click the Projects menu and select Enterprise Project Data, or click the Administer menu and
select Enterprise Data.
2) In the Enterprise Data pane, expand Documents and click Document UDFs.
c. In the Data Type field, double-click and choose a type from the list.
Create expense user defined fields (UDFs) if the predefined fields do not meet your needs.
164 | P a g e ©
www.gaeaglobal.com
1) Click the Projects menu and select Enterprise Project Data, or click the Administer menu and
select Enterprise Data.
2) In the Enterprise Data pane, expand Activities and click Expense UDFs.
c. In the Data Type field, double-click and choose a type from the list.
Create issue user defined fields (UDFs) if the predefined fields do not meet your needs.
1) Click the Projects menu and select Enterprise Project Data, or click the Administer menu and
select Enterprise Data.
2) In the Enterprise Data pane, expand Issues and click Issue UDFs.
c. In the Data Type field, double-click and choose a type from the list.
Create project user defined fields (UDFs) if the predefined fields do not meet your needs.
Project UDFs have formulas that automatically calculate values for the field.
165 | P a g e ©
www.gaeaglobal.com
1) Click the Projects menu and select Enterprise Project Data, or click the Administer menu and
select Enterprise Data.
2) In the Enterprise Data pane, expand Projects and click Project UDFs.
c. In the Data Type field, double-click and choose a type from the list.
d. In the UDF Type field, double-click and choose Manual or Formula from the list.
Note: Choosing Formula enables the fields in the Formula detail window, allowing you to
define a formula or statement to calculate the value of the field. If no calculation is required,
choose Manual.
4) In the Formula detail window, define a formula or statement. See Defining Formulas for
User Defined Fields or Defining Statements for User Defined Fields.
5) In the Indicators detail window, define a graphical indicator. See Defining Indicators for User
Defined Fields.
You cannot define a formula for fields with 'Indicator' marked. If you define an
indicator, a checkmark will appear in the Indicator field. You can edit the Indicator detail
window only if you select Integer, Cost, and Number.
166 | P a g e ©
www.gaeaglobal.com
1) Click the Resources menu and select Enterprise Resource Data, or click the Administer menu
and select Enterprise Data.
2) In the Enterprise Data pane, expand Resources and click Resource UDFs.
User-defined fields can be of many types: text, start date, finish date, cost, number, integer, or
indicator. Data from UDFs is not used in scoring calculations.
1) Click the Projects menu and select Enterprise Project Data, or click the Administer menu and
select Enterprise Data.
2) In the Enterprise Data pane, expand Risks and click Risk UDFs.
c. In the Data Type field, double-click and choose a data type from the list.
167 | P a g e ©
www.gaeaglobal.com
24.1.9 Creating Step UDFs
Create step user defined fields (UDFs) if the predefined fields do not meet your needs.
1) Click the Projects menu and select Enterprise Project Data, or click the Administer menu and
select Enterprise Data.
2) In the Enterprise Data pane, expand Activities and click Step UDFs.
c. In the Data Type field, double-click and choose a type from the list.
1) Click the Projects menu and select Enterprise Project Data, or click the Administer menu and
select Enterprise Data.
2) In the Enterprise Data pane, expand Projects and click WBS UDFs.
c. In the Data Type field, double-click and choose a type from the list.
168 | P a g e ©
www.gaeaglobal.com
Before defining a formula, you need to first create a project user defined field. To create a
project user defined field see Creating Project UDFs.
1) Click the Projects menu and select Enterprise Project Data, or click the Administer menu and
select Enterprise Data.
2) In the Enterprise Data pane, expand Projects and click Project UDFs.
3) On the Project UDFs page, select a UDF and click the Formula detail window.
Note: The UDF Type must be set to Formula to access the Formula detail window.
Note: You can select any existing project-related field defined in the project
management database, including project codes, or any other user defined field that
exists for your organization.
c. Continue to build your formula by inserting fields and using the operator buttons.
Before defining an indicator, you need to first create a project user defined field. To create a
project user defined field see Creating Project UDFs
169 | P a g e ©
www.gaeaglobal.com
Note: You can identify graphical indicators only for fields with a 'Cost', 'Integer', or 'Number'
Data Type.
1) Click the Projects menu and select Enterprise Project Data, or click the Administer menu and
select Enterprise Data.
2) In the Enterprise Data pane, expand Projects and click Project UDFs.
3) On the Project UDFs page, select a UDF and click the Indicators detail window.
Note: You can also follow these steps for the Summary Indicators detail window
4) In the Indicators detail window repeat the following for each parameter statement:
1. If you mark the Value option, double-click the field and type a value.
2. If you mark the Field option, click the list and select a field.
Note: If you select a "is within the range of" or "is not in the range of" condition, use the Value
field to specify the lower range value and the High Value field to specify the upper range value.
170 | P a g e ©
www.gaeaglobal.com
1) Click the Projects menu and select Enterprise Project Data, or click the Administer menu and
select Enterprise Data.
2) In the Enterprise Data pane, expand Projects and click Project UDFs.
3) On the Project UDFs page, select a UDF and click the Formula detail window.
Note: The UDF Type must be set to Formula to access the Formula detail window.
4) In the Formula detail window:
a. Click Advanced .
b. Click IF/THEN/ELSE.
Note: The default statement 'IF (condition) THEN (expression) ELSE (expression)' is
displayed in the detail window.
c. Highlight a (condition) or (expression) entry and its parentheses.
d. Click the Fields list and choose a field.
Note: You can select any existing project-related field defined in the project
management database, including project codes, or any other user defined field that
exists for your organization.
e. Click Insert Field.
Note: The selected field will replace the highlighted (condition) or (expression) entry.
f. Continue to replace fields and use the operator, relational operator, and expression
buttons to build your statement.
Note: Relational operators (<, >, =, <>) are only valid for the 'IF' condition statement.
4) On the Project UDFs page, click Save (Ctrl+S).
171 | P a g e ©
www.gaeaglobal.com
Operator buttons include: +, -, *, /, (, and ). Expression buttons include: AND, OR, and
IF/THEN/ELSE.
You can also replace (condition) and (expression) entries by deleting the entries and their
parentheses, placing the cursor in the appropriate location in the statement, and
following steps 4.d. through 4.f.
When you run Global change, data exclusively locked by another user does not change. To
obtain exclusive access, before opening the project, choose Exclusive in the Access Mode
section of the Open Project dialog box.
You must have access to the activities, resource assignments, and expenses to which
you want to make global changes. If your security profile does not enable you to access all of
these items, you will not be able to commit the changes you make.
If you manually plan future period resource/role allocation, changing data globally
may change or delete manual future period values.
172 | P a g e ©
www.gaeaglobal.com
5. Define If, Then, Else and statements to specify the data you want to change.
6. Click Add to define additional If, Then, or Else statements.
7. Click Change
8. To accept the changes, click Commit Changes; to cancel the global change and return
the data to its original state, click Cancel Changes.
All global change specifications require at least one Then statement. If statements are optional.
A Then statement with no If statement is applied to all activities in the current filter.
Multiple instances of global change specifications are not stored. When you choose Tools,
Global Change, the last set of conditions you specified are the only ones available.
If statements
If statements define the conditions used to make changes to project data. When you define
multiple If statements, link them by selecting All of the Following or Any of the Following. When
you select All of the Following, data changes only if all If statement conditions are true. When
you select Any of the Following, data changes if at least one of the If statement conditions are
true.
173 | P a g e ©
www.gaeaglobal.com
Then statements
Then statements specify the changes to make to project data when the If conditions are
satisfied. Multiple Then statements are executed in the sequence you list them. If you want to
set the Parameter/Value equal to a user-entered number, the second Parameter/Value field
and the Operator field must be left blank.
Else statements
Else statements specify the changes to make to project data when the If conditions are not met.
To specify an Else statement, you must define at least one If statement. If you want to set the
Parameter/Value equal to a user-entered number, the second Parameter/Value field and the
Operator field must be left blank.
Name: Lists global change specifications. Click to edit the name of the global change.
Available To: Choose to make the selected global change specification global or available only
to specified users. Choose All Users to make the global change specification global, available to
all users. Choose Current User to make the specification available only to the user currently
logged in. New global changes are automatically assigned to Current User. Choose Another User
to make the specification available to a selected user.
User: Click and select a user name to make the specification available to this user.
Apply Change: Allows you to preview the selected specification's changes in a report before
applying them to the project.
174 | P a g e ©
www.gaeaglobal.com
Paste: Adds a copied specification.
2. Click New.
3. Define If, Then, and Else statements to specify the data you want to change.
4. Click Change.
A Global Change Report displays in the Global Change Report dialog box.
5. To save the report, click Save to File and type a name for the report.
6. To accept the changes, click Commit Changes; to cancel the Global Change and return
the data to its original state, click Cancel Changes.
175 | P a g e ©
www.gaeaglobal.com
End of this Chapter
176 | P a g e ©
www.gaeaglobal.com
Notes
177 | P a g e ©
www.gaeaglobal.com
25 Risks and Issues
Once you add a risk to the risk register, you can perform further analysis on the risk and create
one or more risk response plans which include activities to reduce the negative impact of the
risk.
1. Risks toolbar.
178 | P a g e ©
www.gaeaglobal.com
2. Risks work area: Risks for all the projects you have open display in the risk
register. You can group by field name, such as project name to view all risks
organized by project, or create a filter to view only the risks that interest you.
When adding a risk to the risk register, you supply a name for the risk, identify
the risk as a threat or an opportunity, identify the current status of the risk,
identify the owner of the risk, and then assign the values for probability,
schedule, cost, and any other applicable user-defined impacts. The values for
probability, schedule, cost, and additional user-defined impacts are used to
calculate the risk score.
Response Plans: The area where you add response plans and response plan action items.
Activities: The area where you associate scheduled activities in your project to an identified
risk. Refer to the example above to see a list of the project activities impacted by risk R001:
Concrete supply constrained.
Effect: The area used to describe the impact this risk has on this project.
Notes: The area used to capture any additional information regarding the risk.
Probability and Impact Diagram: The Probability and Impact Diagram (PID) is a graphical
representation of the probability and impact thresholds assigned to the risk scoring matrix
associated with the project.
If the Probability, Cost, and Schedule fields are disabled, a risk scorning matrix has not
been assigned to the project. You can still use the risk register to track your risks; however, you
cannot use the qualitative risk analysis features in the application until you create a risk scoring
matrix and assign it to the project.
179 | P a g e ©
www.gaeaglobal.com
25.1.2 Assigning a Risk to an Activity
Assign a risk to an activity to explicitly identify the activity impacted by the risk.
You can assign a risk to an activity while you are adding project risks on the Risks page or while
managing your activities on the Activities page.
1) Click Projects.
3) Click on a risk.
b. Select any additional activities impacted by the risk and click Assign.
c. Click Close.
Click Projects.
On the Projects navigation bar, click Activities.
On the Activities page, select the activity you want to assign a risk.
On the Risks detail window, click Assign Risk.
On the Select Risk dialog box, select a risk and click OK.
On the Activities page, click Save (Ctrl+S).
180 | P a g e ©
www.gaeaglobal.com
1) Click the Projects menu and select Enterprise Project Data, or click the Administer menu and
select Enterprise Data.
2) In the Enterprise Data pane, expand Risks and click Risk Categories.
To display the Category field on the Projects Risks page, click Select Columns on the
Risks toolbar and select Category.
You can also think of issues as impediments, action items, open items, punch lists, logs, or
concerns. Over time, if you do not resolve or close open issues or issues placed on hold, they
can become risks.
Issue codes enable you to organize and categorize issues in a way that is meaningful to you. For
example, you can create an issue code titled Severity, and subsequently create issue code
values: High, Medium, and Low. You can assign each of these code values to issues across
multiple projects, enabling you to categorize each issue according to how severe it is. Similarly,
you can create codes to categorize issues by responsibility, subproject, or any other
181 | P a g e ©
www.gaeaglobal.com
classification you require to organize issues. Assigning issue codes enables you to quickly search
for and view issues according to specific criteria.
1) Open one or more projects in the Projects section using one of the following methods:
Click Projects to open the last project or group of projects you were working with.
Click the Projects menu and choose one of the most-recently used projects or group of
projects.
Click the Projects menu and choose Open Projects to select a project or group of
projects by portfolio type, EPS node, or project code.
4) On the Details of page, expand the Issue Codes section and click Assign Issue Codes.
5) In the Select Issue Codes detail window, select a code and click Assign.
You can only assign one issue code at a time. Click Assign Issue Codes again to
assign another code.
You can also assign issue codes from the Project Issues portlet on the
Workspace page or the My Issues portlet on the Dashboards page.
182 | P a g e ©
www.gaeaglobal.com
25.2.2 Creating Activity Issues
Create activity issues to identify problems that must be addressed before a project can be
completed.
1) Open one or more projects in the Projects section using one of the following methods:
Click Projects to open the last project or group of projects you were working with.
Click the Projects menu and choose one of the most-recently used projects or group of
projects.
Click the Projects menu and choose Open Projects to select a project or group of
projects by portfolio type, EPS node, or project code.
183 | P a g e ©
www.gaeaglobal.com
3) On the Activities page, select an activity and click the Issues detail window.
b. Enter or select a value for the Issue Name, Priority, Status, and Responsible Manager
fields.
5) On the Activities page, click the Actions menu and select Save (Ctrl+S).
The application automatically names the issue New Issue. Update the issue so it
has a unique name.
184 | P a g e ©
www.gaeaglobal.com
Notes
185 | P a g e ©
www.gaeaglobal.com
26 Monitor Thresholds
Use thresholds as a project management technique. You can create a threshold by selecting a
parameter, such as start date variance; setting lower and upper values for the threshold; and
applying the threshold to a specific work breakdown structure (WBS) element, or area, of your
project plan.
When you define a threshold for a WBS element, you can specify the level of detail by which
you want to monitor the WBS element. You can monitor the threshold at the activity level, and
you can monitor the threshold at the WBS level. If you monitor a threshold at the activity level,
issues are generated for each activity that violates the threshold. If you monitor a threshold at
the WBS level, each activity contained in the specified WBS element is tested, and then all
issues are summarized to the WBS element, rather than each activity.
After you define a threshold, you can monitor it to identify any issues associated with it. For
example, you may set a threshold using the Total Float parameter. If the lower threshold value
is 1d and the upper threshold value is 10d, an issue is generated for any activities that have a
total float less than or equal to 1d or more than or equal to 10d. You can assign a person to be
responsible for issues generated by the threshold. You can also specify threshold tracking
layouts and assign priority levels to thresholds. A threshold's tracking layout assignment
identifies the tracking layout that best displays the threshold problem area.
Use the Project Thresholds window to create, view, edit, and monitor thresholds for the open
project. You can monitor a threshold at the work breakdown structure (WBS) level or the
activity level to identify issues. You can customize the columns that display in the threshold
table, and you can group, sort, and filter thresholds.
Use the Edit menu on the Menu bar or the Edit toolbar to add, delete, cut, copy, and
paste thresholds. See Edit Toolbar.
Use the Display Options bar, the View menu on the Menu bar, or the Layout toolbar to
customize the threshold table. See Layout Toolbar.
186 | P a g e ©
www.gaeaglobal.com
On the Edit toolbar, click to monitor the selected threshold to identify issues. See Edit
Toolbar.
Use Project Threshold Details or the threshold table to define general and detailed
information for each threshold. To show or hide Threshold Details, click on the
Bottom Layout toolbar. See Bottom Layout Toolbar.
You can monitor an individual threshold or all thresholds at once. See Monitor a
threshold for more information.
After opening the Project Thresholds window, the window remains open until you
close all open projects or you close the window; if you open or navigate to another
window without closing the Project Thresholds window, click the Project Thresholds tab
to return to the window at any time.
You can assign thresholds to WBS elements at the activity or WBS level. If you monitor a project
at the WBS activity level, the module reviews and reports issues for each activity that violates
the threshold. If you monitor a project at the WBS level, the module reviews and reports the
WBS summary level data rather than at the activity level. For example, if an activity within a
particular WBS level has a start date variance of –1, but the start date variance at the WBS level
is 0, an issue is not generated even though you may be monitoring for a lower threshold of –1.
187 | P a g e ©
www.gaeaglobal.com
Choose Project, Thresholds. Click Add, then click the General tab. Select a threshold parameter.
If you enter a lower and upper threshold limit, an issue is generated for any WBS
element/activity that falls outside the specified range. For example, enter –2 days as the lower
limit and 10 days as the upper limit for a total float threshold. You are notified when any WBS
element/activity has a total float less than or equal to –2 days and greater than or equal to 10
days. The module automatically enters the type of value that corresponds to the selected
threshold. Select the WBS element you want the threshold to monitor, then select whether to
monitor it at the WBS or activity level. If you select activity, the threshold will review activities
in the specified WBS and in lower-level elements of that WBS. The manager responsible for
addressing the issues generated by the threshold is automatically assigned when you select a
WBS element. Responsible managers are defined in the OBS. Click the Browse button in the
Tracking Layout field to select the layout that best displays the threshold problem area.
188 | P a g e ©
www.gaeaglobal.com
Once you define a threshold parameter, you need to monitor it to generate any applicable
issues. In the Project Monitor Thresholds. Thresholds window, select the threshold you want to
monitor, and then click Monitor. A list of any issues generated is displayed in the Details tab.
You can specify a threshold parameter and a lower and/or upper threshold value against which
project data can be evaluated to identify issues that you want to track.
An issue is automatically generated when a threshold parameter is equal to or less than the
lower threshold value, or equal to or greater than the upper threshold value.
189 | P a g e ©
www.gaeaglobal.com
Cost % of Budget Cost % of Budget threshold values are expressed as a percentage. An
issue is generated if the ratio of the activity’s actual cost to its budgeted cost (actual
cost / budgeted cost * 100) falls beyond the threshold values. Actual cost is the same as
Actual Cost, and budgeted cost is the same as Budget at Completion (BAC).
The Cost % of Budget will reach 100 percent when the actual cost reaches the budgeted
cost. The Cost % of Budget may be greater than 100 percent.
CPI – Cost Performance Index a Cost Performance Index (CPI) threshold value is
expressed as a ratio. An issue is generated if the CPI falls beyond the threshold values.
The Cost Performance Index is computed as CPI = Earned Value Cost /Actual Cost. A
value less than one indicate that actual costs have exceeded the value of work
performed. If the lower threshold value is one, an issue is generated whenever the
actual costs exceed the value of the work performed.
Cost Variance (CV) A Cost Variance (CV) threshold value is expressed as a monetary
value. An issue is generated if the CV (the difference between the activity’s earned value
and the actual cost of performing the activity) falls beyond the threshold values. Cost
Variance is computed as CV = Earned Value Cost – Actual Cost.
A negative value indicates that actual costs have exceeded the value of work
performed, which may be considered a cost overrun. If the lower threshold value is
zero, an issue is generated as soon as actual cost of the work is greater than the value of
the work. A larger negative value for the threshold indicates that a certain amount of
cost overrun may be tolerated before an issue is generated.
Cost Variance Index (CVI) A Cost Variance Index (CVI) threshold value is expressed as a
ratio. An issue is generated if the CVI (the ratio of the cost variance to the earned value
of work performed) falls beyond the threshold values. The Cost Variance Index is
computed as CVI = Cost Variance (CV) / Earned Value Cost. A value less than zero
indicate that actual costs have exceeded the value of work performed. If the lower
threshold value is zero, an issue is generated whenever the actual costs exceed the
value of the work performed.
190 | P a g e ©
www.gaeaglobal.com
Duration % of Original A Duration % of original threshold value is expressed as a
percentage. An issue is generated if the ratio of the activity’s actual duration to its
original duration (actual duration / original duration * 100) falls beyond the threshold
values. The ratio of actual duration to original duration may be greater than 100.
Finish Date Variance A Finish Date Variance threshold value is a specified number of
days. An issue is generated if the difference between the activity’s planned and current
finish date (calculated as Planned Finish Date – Finish Date) falls beyond the threshold
values.
If an activity’s status is Not Started or Active, then the Finish date will be the Planned
Finish date, and the finish date variance is always zero. If an activity’s status is
completed, then Finish date is the actual finish date. A negative value for Finish Date
Variance indicates that the current finish date is later than the planned finish date.
Free Float A Free Float threshold value is a specified number of days. An issue is
generated if an activity’s free float (the amount of time the activity can be delayed
without delaying the Early Start of any successor activity) falls beyond the threshold
values. Free Float threshold monitoring can only be applied at the activity level, not at
the WBS level.
Schedule Performance Index (SPI) A Schedule Performance Index (SPI) threshold value is
expressed as a ratio. An issue is generated if the Schedule Performance Index (the ratio
of the earned value of work performed to the budgeted cost of work that was
scheduled) falls beyond the threshold values.
The Schedule Performance Index is computed as SPI = Earned Value Cost / Planned
Value Cost. A value less than one indicate that less work was actually performed than
was scheduled. If the threshold value is one, an issue is generated whenever the value
of the work performed falls below the expected cost of performing that work, according
to the schedule.
Start Date Variance A Start Date Variance threshold value is a specified number of days.
An issue is generated if the difference between the activities planned and current start
191 | P a g e ©
www.gaeaglobal.com
dates (calculated as Planned Start Date – Start Date) falls beyond the threshold values. If
an activity’s status is Not Started, then the Start date will be the Planned Start date, and
the start date variance is always zero. If an activity’s status is Started or Completed, then
Start date is the actual start date.
Schedule Variance (SV) A Schedule Variance (SV) threshold value is expressed as a
monetary value. An issue is generated if the Schedule Variance (the difference between
the activity’s earned value and the planned value) falls beyond the threshold values.
Schedule Variance is computed as SV = Earned Value Cost – Planned Value Cost. A
negative value indicates that less work was actually performed than was scheduled.
The activity may be considered behind schedule. If the threshold value is zero, an issue
is generated as soon as the earned value of the work performed falls below the amount
of work that was supposed to be performed, according to the schedule. A larger
negative value for a Schedule Variance threshold indicates that an activity may be
behind schedule by that amount before an issue is generated.
Schedule Variance Index (SVI) A Schedule Variance Index (SVI) threshold value is
expressed as a ratio. An issue is generated if the Schedule Variance Index (the ratio of
the schedule variance to the planned value) falls beyond the threshold values.
The Schedule Variance Index is computed as SVI = Schedule Variance (SV) / Planned
Value Cost. A value less than zero indicate that the value of the work performed is less
than what was scheduled. If the threshold value is zero, an issue is generated whenever
the value of the work performed falls below the expected cost of performing that work,
according to the schedule.
Total Float a Total Float threshold value is a specified number of days. An issue is
generated if an activity’s total float (the amount of time the activity can be delayed
without delaying the project finish date) falls beyond the threshold values.
Variance at Completion (VAC) A Variance at Completion (VAC) threshold value is
expressed as a monetary value. An issue is generated if the Variance at Completion (the
budgeted total cost – latest total cost estimate) falls beyond the threshold values.
192 | P a g e ©
www.gaeaglobal.com
Variance at Completion may also be expressed as VAC = Budget at Completion (BAC) –
Estimate at Completion (EAC).
A negative value indicates an estimated total cost overrun. If the threshold value is
zero, an issue is generated as soon as the latest estimate for total cost exceeds the
planned total cost. A larger negative value for a Variance at Completion threshold
indicates that a certain amount of estimated total cost overrun may be tolerated before
an issue is generated.
You can run all the thresholds assigned to a project at one time, or you can run only
individual thresholds as needed.
Monitor all thresholds at once When the project is open, choose Tools, Monitor
Thresholds.
To use the timeperiod specified for each threshold, choose Use Original Threshold
Monitor Windows.
To specify a new timeperiod that will apply to all thresholds, choose Use New Threshold
Monitor Window, then click the Browse buttons in the From Date and To Date fields to
select a new set of dates.
Click Monitor.
193 | P a g e ©
www.gaeaglobal.com
Monitor a specific threshold Choose Project, Thresholds. Select the threshold you want to
monitor. Click Monitor.
You cannot monitor a threshold whose status is Disabled. To change a threshold’s status,
double-click the status you want to change in the Project Thresholds window.
194 | P a g e ©
www.gaeaglobal.com
Notes
195 | P a g e ©
www.gaeaglobal.com
27 Importing and Exporting Data
Import/Export features allow you to bring data into P6 as well as export data to other tools
when needed.
Use import/export dialog box to import and export information to and from this database
using external files and then share this information with other P6 Professional users, Oracle
Primavera Contractor users, other project management tools (such as Microsoft Project
2007 and Microsoft® Excel), and your organization's human resource and accounting
systems. You can also use external files to archive your projects or create a backup of your
database.
You can import and export between P6 and other applications using the following file
formats:
Oracle Primavera's P6 Professional XML format, which enables you to share project
information between Project Management databases.
Microsoft Project XML format enables you to share information with Microsoft Project 2007
or Microsoft Project 2010.
Export Projects
Export Activities
Export Resources
Export Resource Allocation and Cost
Export Project Data to an ERP System
196 | P a g e ©
www.gaeaglobal.com
27.1 Export Projects
Steps:
1) Click Projects.
2) On the Projects navigation bar, click EPS.
3) On the EPS page, click the Actions menu and select Import/Export XML Project
Import/Export.
4) In the Import/Export Project dialog box, click the Export tab.
To export activities:
1) Open one or more projects in the Projects section using one of the following methods:
Click Projects to open the last project or group of projects you were working with.
Click the Projects menu and choose one of the most-recently used projects or group of
projects.
Click the Projects menu and choose Open Projects to select a project or group of
projects by portfolio type, EPS node, or project code.
197 | P a g e ©
www.gaeaglobal.com
2) On the Projects navigation bar, click Activities.
b. Configure the activity view to determine what data are exported. See Configuring Activity
Views .
4) In the File Download dialog box, click Open to open the Excel spreadsheet or Save to save
the file to your computer.
Note: All data, except grouping row information, are exported as they appear in the current
activity view.
198 | P a g e ©
www.gaeaglobal.com
27.1 Import Projects
Steps:
1) Click Projects.
2) On the Projects navigation bar, click EPS.
3) On the EPS page, click the Actions menu and select Import/Export XML Project
Import/Export.
4) In the Import/Export Project dialog box, click the Import tab.
199 | P a g e ©
www.gaeaglobal.com
27.3 Importing Activities from Excel or Exporting Activities to Excel
To import activities:
You can import new activities into a P6 project from a Microsoft® Excel® (.xls) file.
1) Open one or more projects in the Projects section using one of the following methods:
Click Projects to open the last project or group of projects you were working with.
Click the Projects menu and choose one of the most-recently used projects or group of
projects.
Click the Projects menu and choose Open Projects to select a project or group of
projects by portfolio type, EPS node, or project code.
3) On the Activities page, click the Actions menu and select Import/Export Import from Excel.
200 | P a g e ©
www.gaeaglobal.com
a. Click Import File and select a file from the dialog box.
b. Click Select Project and select a project from the dialog box.
c. Click Import.
5) On the Activities page, click the Actions menu and select Save (Ctrl+S).
201 | P a g e ©
www.gaeaglobal.com
Notes
202 | P a g e ©
www.gaeaglobal.com
28 Reports and Publish Layouts
Navigation – Use tool menu on the menu bar, go to report wizard to generate report
203 | P a g e ©
www.gaeaglobal.com
Publish a Project Website
Publish project website, will save the project information in specified HTML files, So it can be publish
these files as a website on an intranet or internet.
204 | P a g e ©
www.gaeaglobal.com
Printing and print preview
User can define pages and print settings, publish the content of the selected window to an
HTML file, and print the content of the selected window.
205 | P a g e ©
www.gaeaglobal.com
Page Tab:-
Page tab to specify the page orientation, scaling and paper size for the layout or report
currently displayed
Header Tab:-
Use Header tab to create a custom header for the displayed layout or report
Footer Tab:-
Footer tab to create a custom header for the displayed layout or report
Option Tab:-
206 | P a g e ©
www.gaeaglobal.com
Options tab to specify date range, content, and pagination options when you print window data
or layouts. The available options on this tab vary according to the current view displayed when
you select the Page Setup option.