Documente Academic
Documente Profesional
Documente Cultură
3. In this papa stated that the contractor was advised verbally and in writing for a
number of occasions to deploy adequate resources on work so that they may
be able to complete the work at earliest. The claimant did not respond to the
Railway and executed the work as per their own convenience. Last extension
was granted to them from 01.04.2011 to 31.07.2011. The penalty was
imposed as the merit of the case as the applicant was not able to accelerate
the progress considering the merit of the case now they are taking the benefit
of the lenient view of the department. Even after various correspondence
progress was not up to the required pace. One meeting was also conducted
with the contractor on 15.07.2011, but no solution on the poor progress was
found.
4. In this para it is stated that 7 days notice was issued to the contractor on
22.07.2011 due to slow progress of the work and they were also advised to
accelerate the satisfactory progress otherwise initiative will be taken as per
clause no. 62 of GCC which is legally applicable on the subject contract.
Noting has been done wrong by the way of issuing of 7 days notice as the
same was issued in the admit of GCC and not threat was extended a asked
by the notice issue authority. It is again started that the notice was issued
without any prejudice in the interest of the work.
5. Further the applicant statement that the intention of the notice was to cancel
without any power of reasons in false and fabricated and very far from the
facts. Lots of correspondence was made with the claimant to accelerate the
progress as can be seen 6 extensions have been granted o complete the
work. It is further stated that the extension of time was granted of time was
granted to the contractor up to 31.07.2011 after going through the reasons put
forth by them and not up to 31.10.2011 as mentioned by the claimant. Only
Rs 410.97 lakhs was paid to the contractor against the agreement value of
Rs. 629.78 lakhs. The statement of the applicant that the work was in extreme
progress stage is not true. A leg of 4 years was too much for completion of
subject work but considering the requirement of the user department no stern
steps were taken and now the applicant is taking the ground of the lenient
attitude and blaming the administrative for such adverse situation. It is again
state that due to failure of the applicant 7 days notice followed by 48 hrs
notice was issued to the claimant and finally the contract, so nothing has been
done wrong by the railway administrative. Ultimately due to failure of the
claimant the contract was terminated under clause no. 62 of GCC and as per
condition of the agreement.