Width Clearing & Excavation Embankment ABC Asphalt/ Gravel Road Shoulder
Local Road Length Pavement Remarks
No (m) Type Grubbing Concrete Finish
CW SH
SUB SECTION 1
27 B275 430 9.00 1.00 Asphalt 100% 100% 100% 100% n/a 67%
28 20 150 4.50 1.00 Asphalt 100% 100% 100% n/a 50%
29 21 691 9.00 1.00 Asphalt 100% 60% 60% n/a 37%
30 21A 158 4.50 0.60 Concrete 0% n/a 0%
31 22 320 4.50 1.00 Asphalt 100% 100% 100% 100% 31% n/a 72%
32 22A 173 3.00 0.60 Gravel 100% 100% 100% n/a 100% 100%
33 22B 84 3.00 0.60 Gravel 100% 100% 100% n/a 100% 100%
SUB SECTION 4
34 23 347 4.50 1.00 Asphalt 10% 80% 80% 60% n/a 38%
35 23A 44 3.00 1.00 Gravel 20% 25% 25% n/a 18%
36 23B 32 3.00 1.00 Gravel 0% n/a 0%
37 23C 79 3.00 0.60 Concrete 0% n/a 0%
38 24 111 4.50 1.00 Concrete 0% n/a 0%
39 24A 43 3.00 0.60 Concrete 0% n/a 0%
40 25 128 4.50 1.00 Asphalt 0% n/a 0%
41 26A 309 3.00 0.60 Gravel 0% n/a 0%
42 26B 40 3.00 0.60 Gravel 0% n/a 0%
43 27 285 4.00 0.60 Asphalt 100% 100% 100% 100% 100% n/a 30% 88%
PRIORITY LOCAL ROAD CONSTRUCTION
Width Clearing & Excavation Embankment ABC Asphalt/ Gravel Road Shoulder
Local Road Length Pavement Remarks
No (m) Type Grubbing Concrete Finish
CW SH
44 28 520 4.50 1.00 Asphalt 100% 40% 40% n/a 30%
45 28A 123 3.00 0.60 Concrete 0% n/a 0%
46 29 213 4.50 1.00 Concrete 0% n/a 0%
47 29A 215 3.00 Gravel 0% n/a 0%
48 B284 770 9.00 1.00 Asphalt 100% 80% 80% n/a 43%
SUB SECTION 5
49 30 162 3.00 0.60 Gravel 100% 100% 100% n/a 100% 100%
50 31 381 4.50 1.00 Gravel 100% 80% 80% n/a 65%
51 32 190 6.40 1.00 Asphalt 100% 80% 80% n/a 43%
52 33 152 3.00 0.60 Gravel 100% 100% 100% n/a 75%
53 33A 100 2.00 Gravel n/a 0%
54 34 358 4.50 1.00 Asphalt 100% 100% 100% 100% 100% n/a 100% 100%
55 35 897 4.50 1.00 Asphalt 100% 100% 100% 100% 100% n/a 100% 100%
56 36 122 4.50 1.00 Concrete 100% 100% 100% 100% 100% n/a 100% 100%
57 37 74 4.50 1.00 Gravel 100% 5% 5% n/a 28%
58 38 1,039 6.40 1.00 Asphalt 100% 70% 50% 25% 20% n/a 20% 48%
59 39 830 4.50 1.00 Asphalt 100% 95% 50% n/a 41%
60 39A 440 3.00 - Concrete 100% n/a 17%
61 40 102 4.50 1.00 Asphalt 100% 50% 90% n/a 40%
62 40A 77 4.50 1.00 Asphalt 100% 90% 90% n/a 47%
63 41 73 4.50 1.00 Asphalt 100% 0% 0% n/a 17%
64 42 151 4.50 1.00 Asphalt 100% 80% 50% n/a 38%
65 43 214 4.50 1.00 Asphalt 100% 50% 50% n/a 33%
PRIORITY LOCAL ROAD CONSTRUCTION
Width Clearing & Excavation Embankment ABC Asphalt/ Gravel Road Shoulder
Local Road Length Pavement Remarks
No (m) Type Grubbing Concrete Finish
CW SH
66 43A 315 4.50 1.00 Asphalt 100% 75% 60% n/a 39%
67 44 601 4.50 1.00 Asphalt 100% 60% 60% n/a 37%
68 45 380 4.50 1.00 Asphalt 100% 0% 0% n/a 17%
69 46 292 4.50 1.00 Concrete 100% 70% 70% n/a 40%
70 47 1,450 4.50 1.00 Asphalt 80% 68% 30% 36% 36% n/a 42%
71 47A 135 3.00 0.60 Asphalt 100% 100% 100% 100% 85% n/a 90% 96%
72 48 105 4.50 1.00 Asphalt 0% n/a 0%
73 50 882 4.50 1.00 Concrete 20% 20% 20% n/a 10%
74 50A 286 3.00 Concrete 100% 20% 20% n/a 23%
75 52 327 4.50 1.00 Concrete 90% 50% 50% 40% 40% n/a 45%
76 52A 209 4.50 1.00 Concrete 100% 100% 100% 100% 100% n/a 100%
77 54 864 4.50 1.00 Asphalt 0% n/a 0%
78 54A 451 3.00 0.60 Concrete 80% 70% 50% n/a 33%
79 55 277 6.40 1.00 Asphalt 0% n/a 0%
80 56 195 3.00 0.60 Asphalt 100% 100% 100% 50% n/a 58%
81 57 319 4.50 1.00 Concrete 100% 50% 80% n/a 38%
82 59 235 4.50 1.00 Concrete 90% 40% 30% n/a 27%
83 59A 100 4.50 1.00 Asphalt 80% n/a 13%
84 61 292 3.00 0.60 Gravel 100% 40% 0% 0% n/a 35%
85 62 180 4.50 1.00 Asphalt 100% 100% 100% 100% 100% n/a 80% 97%
86 62A 110 3.00 Concrete 30% 30% n/a 10%
87 63 603 4.50 1.00 Concrete 40% n/a 7%
88 64 400 4.50 1.00 Concrete 70% 70% 20% 20% n/a 30%
PRIORITY LOCAL ROAD CONSTRUCTION
Width Clearing & Excavation Embankment ABC Asphalt/ Gravel Road Shoulder
Local Road Length Pavement Remarks
No (m) Type Grubbing Concrete Finish
CW SH
89 65 197 4.50 1.00 Concrete 20% n/a 3%
90 65A 65 3.00 0.60 Gravel 20% n/a 5%
91 B630 370 9.00 1.00 Asphalt 60% 70% 30% 25% 25% n/a 25% 39%
SUB SECTION 6
92 66 310 4.50 1.00 Concrete 100% 100% 100% 100% 100% n/a 90% 98%
93 67 242 3.00 0.60 Concrete 20% 20% 20% n/a 10%
94 68 185 4.50 1.00 Concrete 75% 75% 75% 75% 75% n/a 70% 74%
95 69 177 4.50 1.00 Concrete 10% 10% 10% n/a 5%
96 69A 148 3.00 0.60 Concrete 100% 90% 90% 90% n/a 62%
97 70 214 4.50 1.00 Concrete 80% 50% 50% 30% n/a 35%
98 70A 117 3.00 0.60 Concrete 10% 10% 10% n/a 5%
99 71 882 8.00 1.00 Asphalt 50% 10% 10% n/a 12%
100 72 378 4.50 1.00 Asphalt 70% 70% 70% 70% 65% n/a 58%
101 72A 136 3.00 0.60 Gravel 90% 75% 75% n/a 60%
102 73 313 4.50 1.00 Concrete 50% n/a 8%
103 73A 285 3.00 0.60 Gravel 75% 40% 40% n/a 39%
104 73B 210 3.00 Gravel 100% n/a 25%
105 74 222 4.50 1.00 Asphalt 0% n/a 0%
106 75 170 3.00 0.60 Concrete 0% n/a 0%
107 76 230 4.50 1.00 Asphalt 100% 70% 70% 25% n/a 44%
108 77 331 3.00 0.60 Gravel 100% 80% 80% n/a 65%
109 RDA B141 593 9.00 1.00 Asphalt 0% n/a 0%
110 RDA B054 1,380 9.00 1.00 Asphalt 75% 20% 20% 15% 15% n/a 24%
PRIORITY LOCAL ROAD CONSTRUCTION
Width Clearing & Excavation Embankment ABC Asphalt/ Gravel Road Shoulder
Local Road Length Pavement Remarks
No (m) Type Grubbing Concrete Finish
CW SH
35,694 40%
Total Number of Roads with Asphalt 46Nos
No of roads Asphalt Completed 5 Nos
TOTAL NO OF ESSENTIAL LR COMPLETED BALANCE TO BE DONE
SS1 11.00 0 11.00
SS3 7.00 0 7.00
SS4 2.00 0 2.00
SS 4.00 3 1.00
SS6 9.00 0 9.00
33 3 30
PRIORITY Target
ROADS Completion
yes 20-Dec-19
Completed
yes 31-Jan-20
yes 31-Dec-19
Completed
Completed
15-Dec-19
Completed
yes 15-Dec-19
5-Dec-19
Completed
28-Feb-20
Completed
yes 31-Dec-19
yes 31-Dec-19
yes 31-Jan-20
yes 31-Jan-20
yes 31-Jan-20
yes 15-Dec-19
yes 10-Dec-19
PRIORITY Target
ROADS Completion
yes 31-Jan-20
yes 31-Jan-20
yes 31-Jan-20
yes 31-Jan-20
yes 31-Jan-20
yes 31-Jan-20
yes 31-Jan-20
30-Dec-19
30-Dec-19
30-Dec-19
30-Dec-19
20-Dec-19
20-Dec-19
30-Dec-19
30-Jan-20
30-Jan-20
30-Jan-20
PRIORITY Target
ROADS Completion
yes 31-Jan-20
30-Jan-20
30-Jan-20
30-Jan-20
yes 31-Jan-20
Completed
31-Mar-20
31-Jan-20
31-Jan-20
31-Jan-20
yes Completed
Completed
Completed
31-Dec-19
31-Mar-20
31-Dec-19
31-Dec-19
31-Dec-19
31-Dec-19
31-Jan-19
31-Dec-19
31-Jan-19
PRIORITY Target
ROADS Completion
15-Feb-20
15-Feb-20
15-Feb-20
31-Dec-19
31-Mar-20
31-Dec-19
31-Mar-20
31-Mar-20
31-Mar-20
31-Mar-20
yes Completed
31-Mar-20
31-Jan-20
29-Feb-20
31-Jan-20
31-Mar-20
29-Feb-20
29-Feb-20
31-Mar-20
yes Completed
31-Dec-19
31-Mar-20
31-Dec-19
PRIORITY Target
ROADS Completion
31-Mar-20
31-Dec-19
yes 31-Jan-20
yes 31/Jan/20
yes 31-Jan-20
yes 20-Jan-20
yes 31-Jan-20
yes 31-Jan-20
yes 31-Jan-20
yes 31-Jan-20
yes 31-Jan-20
yes 31-Jan-20
EXTENSION OF SOUTHERN EXPRESSWAY PROJECT (ESEP 1)ROM MATARA TO HAMBANTHOTA Contract No: RDA/SEEP/CONT-S1
1 Asphlat 5 2,082
SS1 7,230
2 Concrete 9 3,110
3 Gravel 7 2,038
4 Asphlat 8 3,010
SS3 3,673
5 Concrete 2 406
6 Gravel 2 257
7 Asphlat 5 2,050
SS4 3,259
8 Concrete 5 569
9 Gravel 5 640
10 Asphlat 22 8,905
SS5 15,005
11 Concrete 14 4,874
12 Gravel 7 1,226
13 Asphlat 6 3,686
SS6 6,525
14 Concrete 9 1,877
15 Gravel 4 962
ASPHALT 46 19,733
ESEP 1 35,692
CONCRETE 39 10,836
GRAVEL 25 5,123