1. Objective
To outline the work methodology for Priming, Waterproofing and Concrete Topping works to exposed
RC slabs for the Project by means of provision of clear sequences of works in order to achieve a quality
finished works.
METHOD STATEMENT
In overall, to achieve the objective outlined, we propose to segregate the works in following stages for
ease of monitoring:
3. Concrete casting -
- Trial mix shall be conducted at least 30 days before the actual waterproofing concrete is cast.
- Check that the maximum free water/cement ratio is not greater that 0.45(free water-fine aggregate
moisture + admixture)
- Determine the quantity of concrete that to be treated with Pentens T-308. Prepare and measure the
appropriate amount of Pentens T-308.
- Dosage rate: Pentens T-308 - 0.8% by weight of cementitious content.
TAIWAN / CHINA / MALAYSIA / VIETNAM / THAILAND / PHILIPPINES / MYANMAR / DUBAI Tel: +603 8060 4396 Fax: +603 8060 4394 URL: www.pentens.com E-mail: dongji@tm.net.my
PENTENS Waterproofing System
Method Statement for RC Water Tank Waterproofing Works –
Pentens T-308 + T-305
- Ensure works of stage 5 completed with uniform level and duly verified.
- Proceed to concreting.
METHOD STATEMENT
Prepare Pentens T-308, Pour mixture into the Concreting For water retaining structure
measure and mix with drum of the ready-mix i.e. swimming pool and
water. truck. water tank.
In overall, to achieve the objective outlined, we propose to segregate the works in following stages for
ease of monitoring:
5. Ponding Test -
The works for each of the above stages are clarified in the following pages.
TAIWAN / CHINA / MALAYSIA / VIETNAM / THAILAND / PHILIPPINES / MYANMAR / DUBAI Tel: +603 8060 4396 Fax: +603 8060 4394 URL: www.pentens.com E-mail: dongji@tm.net.my
PENTENS Waterproofing System
Method Statement for RC Water Tank Waterproofing Works –
Pentens T-308 + T-305
5. Work Methodology
- Check for defects on RC slab i.e. cracks, oil patches, foreign materials, cracks etc and inform Main
Contractor on rectification required.
METHOD STATEMENT
- Apply Pentens T-805 non-shrink grout to holes and hollow surfaces to achieve uniform level of RC
substrate.
- Apply Pentens T-805 angle fillet at 45 degrees (25mm x 25mm) consistently throughout perimeter of
work area
- Ensure area is dust free and thoroughly cleaned to receive primer material as per manufacturer’s
instructions.
- Treatment to all inlet and outlet must be coated with two layers of Pentens T-305 at least 50mm deep
and shall extend 50mm up all horizontal or vertical faces.
- Ensure work area applied with waterproofing membrane (stage 4) is fully cured and application
verified/approved.
- Carry out ponding test to work area (minimum ponding of 48-72hrs).
- Proceed with next stage if ponding test approved.
- Note: repeat Stage 4 should ponding test fail.
TAIWAN / CHINA / MALAYSIA / VIETNAM / THAILAND / PHILIPPINES / MYANMAR / DUBAI Tel: +603 8060 4396 Fax: +603 8060 4394 URL: www.pentens.com E-mail: dongji@tm.net.my
PENTENS Waterproofing System
Method Statement for RC Water Tank Waterproofing Works –
Pentens T-308 + T-305
Photo of Application:
METHOD STATEMENT
Surface Preparation Angle Fillet Apply Pentens T-007 as Mix Pentens T-305
primer thoroughly. (can add 3-5%
clean water to mix container)
TAIWAN / CHINA / MALAYSIA / VIETNAM / THAILAND / PHILIPPINES / MYANMAR / DUBAI Tel: +603 8060 4396 Fax: +603 8060 4394 URL: www.pentens.com E-mail: dongji@tm.net.my
PENTENS Waterproofing System
Method Statement for RC Water Tank Waterproofing Works –