COST ESTIMATING WORKSHEET

Project Title: Date Prepared:

Parametric Estimates
Number of
WBS ID Cost Variable Cost per Unit Units Cost Estimate

Analogous Estimates
Previous Current
WBS ID Activity Previous Cost Activity Multiplier Cost Estimate

Three Point Estimates

Optimistic Most Likely Pessimistic Weighting Expected Cost


WBS ID Cost Cost Cost Equation Estimate
Parametric Estimates
Resource Performance
WBS ID Effort Hours Quantity % available factor
1.1 150 2 75% 80%

Analogous Estimates
Prior Current
WBS ID Prior activity Variable Duration variable

1.1 Build deck 160 sq. ft. 10 days 200 sq. ft.

Three Point Estimates

Most
Optimistic likely Pessimistic Weighting
WBS ID estimate estimate estimate factor
1.1 20 25 36 (o+4m+p)/6
Duration
Estimate
125

Duration
Multiplier Estimate

1.25 12.5

Expected
Duration
Estimate
26