Practitioner Exam Questions

® 8
PRINCE2 Practitioner Resource Book

Question Part 2
4 C Answer
When designing and appointing the project management team,
consideration should be given to whether or not separate Team
Managers are needed, or whether the Project Manager will be filling
1a incorrect this role. If appropriate, role descriptions should be created. Ref.
12.4.3. It is the responsibility of the Project Manager and the
Executives to produce project management team role descriptions. Ref
12.4.3
If selected as a Team Manager, the professional photographer will
become a member of the project management team. Both internal and
1b incorrect
external resources can be members of the project management team.
Ref. 5.3.2.2
Consideration should be given to whether or not separate Team
Managers are needed, or whether the Project Manager will be filling
1c correct
this role. If appropriate, role descriptions should be created. Ref.
12.4.3.
The Executive is responsible for preparing a role description for the
1d incorrect
Project Manager. Ref. 12.4.1.
Question Part

4 C Answer
The Business Case should contain the reasons for undertaking the
project and explain how the project will enable the achievement of
2a incorrect corporate strategies and objectives. Ref. A.2.2. The production of a
new company logo by another project is not the reason for the
Calendar project. Ref. Project Scenario.
Internal dependences are those under the control of the Project
Manager. The new company logo is being produced by another project
2b incorrect
and is therefore an external dependency. Ref. Glossary / Project
Scenario.
When creating the Project Plan, the Project Brief should be checked for
understanding of any prerequisites, external dependences, constraints
and assumptions. Ref. 14.4.6. / A.16.2. External dependences are
2c correct
those dependencies outside the control of the Project Manager - for
example, the delivery of a product required by this project from another
project. Ref. Glossary / Project Scenario.
External dependences are those dependences outside the control of
2d incorrect the Project Manager - for example, the delivery of a product required by
this project from another project. Ref. Glossary / Project Scenario.

© 2009 ILX Group plc 219